CSE170/ COGS 120

Gantt Chart 2012-2014 by Vertex42.com: Licensed for private use only. Do not publish on the inter

Team HANA

Project Start Date: 2/2/2015 (Monday)


Today's Date: [1] 1/31/2015 (Saturday)
Display Week:

End [6]

Week 7

Week 8

3 / 2 / 15

3 / 9 / 15

3 / 16 / 15

3 / 23 / 15

Cal
%
Work Days Days
Da [7] Done [8] Day [9] D [10] Le [11] M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su
7

100%

1.1

Set up Gitup Version Control

Max

Mon 2/02/15

Mon 2/02/15

100%

1.2

Create Development plan

Daniel

Mon 2/02/15

Tue 2/03/15

100%

1.3

Design mockup for Login page Max

Mon 2/02/15

Tue 2/03/15

100%

1.7

Design mockup for main user p Alex

Mon 2/02/15

Tue 2/03/15

100%

1.8

Design mockup for main postin Everyone

Mon 2/02/15

Tue 2/03/15

100%

1.9

Add 4 lessons into content

Everyone

Mon 2/02/15

Wed 2/04/15

100%

1.10

Max

Mon 2/02/15

Thu 2/05/15

100%

1.11

Set up navigation skeleton


Create Mongo database
collections for Users, Posts

Mon 2/02/15

Sun 2/08/15

57%

x x x

1.12

Set up signin/signup

Alex
Alex, Max,
Daniel

Mon 2/02/15

Tue 2/10/15

44%

x x x

Week6 - Functionality

Mon 2/09/15

Sun 2/15/15

100%

All

Mon 2/09/15

Tue 2/10/15

100%

Max, Daniel,
Alex

Mon 2/09/15

Tue 2/10/15

100%

All

Mon 2/09/15

Wed 2/11/15

100%

All

Mon 2/09/15

Thu 2/12/15

100%

Alex, Daniel

Mon 2/09/15

Thu 2/12/15

100%

Alex, Max,
Daniel

Mon 2/09/15

Thu 2/12/15

100%

Max, Daniel

Mon 2/09/15

Thu 2/12/15

100%

Alex, Isabelle

Mon 2/09/15

Thu 2/12/15

100%

Alex, Isabelle

Mon 2/09/15

Thu 2/12/15

100%

Daniel, Max

Mon 2/09/15

Thu 2/12/15

100%

All
Alex, Max,
Daniel

Mon 2/09/15

Thu 2/12/15

100%

Mon 2/09/15

Thu 2/12/15

100%

2.13

Fix scrolling CSS bug


Rework CSS header so fonts
are constant across all pages
Split post elements into picture
on left then content on right
Add more divisions for storing
lessons
In addition to set up Mongo DB,
put lessons in JSON database
Fixing style and margins for the
webstie
Add Facebook login(Debugging
errors and setting up correctly)

Max, Isabelle

Mon 2/09/15

Thu 2/12/15

100%

2.14

Create database for the posts

All

Mon 2/09/15

Thu 2/12/15

100%

2.15

Mon 2/09/15

Thu 2/12/15

100%

2.16

Update development plans


All
Revisit inspiration for 5 relevant
projects; competitive analysis All

2/9/2015

Fri 2/13/15

100%

Week7 - Ready for testing

Mon 2/16/15

Sun 2/22/15

0%

Alex, Max

Mon 2/16/15

Tue 2/17/15

100%

Isabelle

Mon 2/16/15

Tue 2/17/15

100%

Daniel

Mon 2/16/15

Wed 2/18/15

100%

All

Mon 2/16/15

Wed 2/18/15

100%

Isabelle, Alex

Mon 2/16/15

Wed 2/18/15

100%

Isabelle, Alex

Mon 2/16/15

Thu 2/19/15

100%

Max

Mon 2/16/15

Thu 2/19/15

100%

Daniel

Mon 2/16/15

Thu 2/19/15

100%

2.9
2.1
2.11
2.12

3.1
3.2
3.3
3.4
3.5
3.6

3.7
3.8

Set up Admin functionality to


add/remove users
Identifty UI / appearance
breakdowns
First pass on friend
engagement feature
Add sharing features to
Facebook
Revisit UX with two testers to
identify critical UX pain points
Discuss UX feedback, plan
modifications
Rework Meteor subscriptions
so users can only access their
own posts
Add description field to Posts
Mongo collection

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

2 / 23 / 15

Sun 2/08/15

2.8

2 / 16 / 15

Start [5]

2.7

2 / 9 / 15

Mon 2/02/15

2.6

2 / 2 / 15

Everyone

2.5

Week 6

Lead [4]

2.4

Week 5

Week5 - Skeleton

2.3

Week 4

Task [3]

2.2

Week 3

Add 6 lessons with detailed


description and images
Set up a page that the admin
can just add image/content into
the database
Brainstorm how to encourage
friend engagement
Figure out how to route pages
using Meteor
Add buttons for Home Page
lessons to route to Wellness
Index
Add .js script to add post to
Wellness Index and route page
to Wellness Index

Week 2

W [2]

2.1

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Week 1

x x x x x x x

x x
x x x x x x x

CSE170/ COGS 120

Gantt Chart 2012-2014 by Vertex42.com: Licensed for private use only. Do not publish on the inter

Team HANA

Project Start Date: 2/2/2015 (Monday)


Today's Date: [1] 1/31/2015 (Saturday)
Display Week:

W [2]

Task [3]

End [6]

Lead [4]

Start [5]

Alex, Max

Mon 2/16/15

Thu 2/19/15

100%

Isabelle

Mon 2/16/15

Thu 2/19/15

100%

All

Mon 2/16/15

Thu 2/19/15

100%

Mon 2/16/15

Thu 2/19/15

100%

Mon 2/16/15

Thu 2/19/15

100%

Mon 2/16/15

Thu 2/19/15

100%

3.12

3.13

Update development plan

Daniel
Alex, Max,
Daniel,
Isabelle

3.14

debugging

All

Week8 - User testing result

Mon 2/23/15

Sun 3/01/15

0%

4.1

Set up online test for the beta


version

Mon 2/23/15

Tue 2/24/15

0%

Mon 2/23/15

Tue 2/24/15

0%

Mon 2/23/15

Wed 2/25/15

0%

4.4

Publicize our app in public


All
Create a video demonstration
for our platform
Alex
Summarize feedbacks to action
item
Max

Mon 2/23/15

Thu 2/26/15

0%

4.5

updating devleopment plans

Mon 2/23/15

Thu 2/26/15

0%

Week9 - Fit & Finish

Mon 3/02/15

Sun 3/08/15

0%

5.1

All

Mon 3/02/15

Tue 3/03/15

0%

5.2

Marketing and post it on


facebook, twitter and other
social networking sites
Set up more online testing for
our beta verson

Alex

Mon 3/02/15

Tue 3/03/15

0%

5.3

Fix final bugs

All

Mon 3/02/15

Wed 3/04/15

0%

5.4

Mon 3/02/15

Wed 3/04/15

0%

5.5

Work on screen transitions


Isabelle
add setting menu to the setting
place
Max

Mon 3/02/15

Wed 3/04/15

0%

Week10 - Results

Mon 3/09/15

Sun 3/15/15

0%

6.1

Collect data from test

Isabelle

Mon 3/09/15

Tue 3/10/15

0%

6.2

Reskin some pages with css.

Max

Mon 3/09/15

Wed 3/11/15

0%

1.3

Analyze from the test

Daniel

Mon 3/09/15

Wed 3/11/15

0%

1.4

Fix final bugs

Alex

Mon 3/09/15

Thu 3/12/15

0%

1.5

Practice for presentation/pitchi

All

Mon 3/09/15

Thu 3/12/15

0%

1.6

Double check for the functionali

All

Mon 3/09/15

Thu 3/12/15

0%

3.1
3.11

4.2
4.3

All

All

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Week 2

Week 3

Week 4

Week 5

Week 6

Week 7

Week 8

2 / 2 / 15

2 / 9 / 15

2 / 16 / 15

2 / 23 / 15

3 / 2 / 15

3 / 9 / 15

3 / 16 / 15

3 / 23 / 15

Cal
%
Work Days Days
Da [7] Done [8] Day [9] D [10] Le [11] M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su M T W Th F Sa Su

Add colored circle to Wellness


Report
Add .js backend to change
circle color of Wellness Report
based on num posts
Add descriptions to available
lessons on home page
Perform stress testing to
observe load times and max
users

3.9

Week 1

[1] Today's Date:


Use the formula =TODAY() to make the red line in the gantt chart display the current day, or enter the date manually..
[2] Work Breakdown Structure:
Level 1: 1, 2, 3, ...
Level 2: 1.1, 1.2, 1.3,
Level 3: 1.1.1, 1.1.2,
The WBS uses a formula to control the numbering, but the formulas are different for different levels..
[3] Task:
Enter the name of each task and sub-task. Use spaces to indent sub-tasks..
[4] Task Lead
Enter the name of the Task Lead in this column..
[5] Task Start Date:
You can manually enter the Start Date for each task or use a formula to create a dependency on a Predecessor. For example, you
could enter =enddate+1 to set the Start date to the next calendar day, or =WORKDAY(enddate,1) to set the Start date to the next work
day (excluding weekends), where enddate is the cell reference for the End date of the Predecessor task..
[6] End Date:
Calculated based on the Start Date and the duration of the task..
[7] Duration:
The duration is the number of calendar days for the given task..
[8] Percent Complete:
Update the status of this task by entering the percent complete (between 0% and 100%)..
[9] Work Days:
Work Days exclude Saturday and Sunday. The Pro version allows you to use this column as an input..
[10] Calendar Days Complete:
This column is calculated by multiplying the Duration by the %Complete and rounding down to the nearest integer.
Note: This column is required, but may be hidden prior to printing..
[11] Calendar Days Remaining:
This column is calculated by subtracting the Days Complete from the Duration.
Note: This column is required, but may be hidden prior to printing..