Вы находитесь на странице: 1из 36

BILL OF QUANTITY

Project
Works
Owner
Location
No.
I.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang
DESCRIPTION

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

PREPARATORY WORK
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10

II

Survey and Marking


Temporary Site Office ( Direksi keet & Storage )
Temporary Water
Temporary Power
Safety & Protection
Design Fee
Mobilization & Demobilization
Cleaning During Construction
Unloading fee, coordination & security
Reporting

2.2
2.2.1
2.2.2
2.2.3
2.3
2.3.1
2.3.1.1
2.3.1.2
2.3.1.3
2.3.1.4
2.3.1.5
2.3.1.6

PILING WORKS
Concrete spun pile 300mm, L= 10 m' ( P1 )
Driving Pile
Cuting Pile
FOUNDATION & COLUMN WORK
Pile Cap
Excavation, Backfill, diaposal & compaction base soil
Sand gravel, t - 10cm
Lean concrete, t - 5cm
Formwork for pile cap
Steel bars for pile cap
Concrete work for pile cap ( 70*70*80cm )

REMARKS

199,230,000

Heavy equip, piling machine, others tools

ls
ls
ls
ls
ls
ls
ls
ls
ls
ls

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

5,250,000
40,500,000
12,000,000
26,000,000
15,000,000
24,480,000
22,000,000
12,000,000
38,000,000
4,000,000

CONSTRUCTION WORKS

2.1 SITE CLEARING


2.1.1 Site Clearing / Stripping
2.1.2 Disposal

AMOUNT
( Rp. )

5,250,000
40,500,000
12,000,000
26,000,000
15,000,000
24,480,000
22,000,000
12,000,000
38,000,000
4,000,000

###

4,318,893,059

outside area

m2
m3

1,560.00
234.00

3,500
30,000

12,480,000
5,460,000
7,020,000

Incl disposal

m'
m'
nos

550.00
550.00
55.00

195,000
75,000
60,000

151,800,000
107,250,000
41,250,000
3,300,000

60,000
20,000
35,250
75,000
13,000
770,250

412,139,757
95,477,578
18,120,600
891,000
1,570,388
9,240,000
49,049,000
16,606,590

used brick/bataco
D-16, D-13
K 250 kg/cm2

m3
m2
m2
m2
kg
m3

302.01
44.55
44.55
123.20
3,773.00
21.56

###
###
###

BILL OF QUANTITY
Project
Works
Owner
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang
DESCRIPTION

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

AMOUNT
( Rp. )

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang
DESCRIPTION

AMOUNT
( Rp. )

UNIT

516.56
19.58
9.79
435.00
90.60
10,704.75
61.17

60,000
20,000
35,250
75,000
105,000
13,000
770,250

260,146,241
30,993,600
391,600
345,098
32,625,000
9,513,000
139,161,750
47,116,193

110.00
2,475.00
13.75

125,000
13,000
770,250

56,515,938
13,750,000
32,175,000
10,590,938

2.3.2
2.3.2.1
2.3.2.2
2.3.2.3
2.3.2.4
2.3.2.5
2.3.2.6
2.3.2.7

Tie Beam
Excavation, Backfill, diaposal & compaction base soil
Sand gravel, t - 10cm
Lean concrete, t - 5cm
Formwork for tie beam
Formwork for tie beam
Steel bars for tie beam
Concrete work for tie beam ( 25cm*50cm )

used brick/bataco
used plywood 12mm & wooden frame
D-16, D-8
K 250 kg/cm2

m3
m2
m2
m2
m2
kg
m3

2.3.3
2.3.3.1
2.3.3.2
2.3.3.3

Column Concrete ( C-1 )


Formwork for column
Steel bars for tie beam
Concrete work for tie beam ( 50cm*50cm* 100cm )

used plywood 12mm & wooden frame


D-16, D-8
K 250 kg/cm2

m2
kg
m3

2.4
2.4.1
2.4.1.1
2.4.1.2
2.4.1.3
2.4.1.4
2.4.1.5
2.4.1.6
2.4.1.7
2.4.1.8

CONCRETE SLAB & STAIR WORK


Concrete Ground Slab ( 1st Floor )
Excavation, Backfill, diaposal & compaction base soil
Lime stone, t = 40cm
Sand gravel, t - 10cm
Plastic sheet
Formwork / stop cor, h - 20cm
Wiremesh, 1 layer ( incl spacer block )
Concrete work, t - 15cm ( w/ pump or bucket )
Surface finishing & curing

2.4.2
2.4.2.1
2.4.2.2
2.4.2.3
2.4.2.4
2.4.2.5

Concrete Slab ( 2nd Floor )


Bondex sheet, t - 0,75mm ( incl screw )
Formwork / stop cor, h - 15cm
Wiremesh, 1 layer ( incl spacer block )
Concrete work, t - 15cm ( w/pump or bucket)
Surface finishing by trowel & curing

used plywood 12mm & wooden frame


M8 @ 150, D-8
K 250 kg/cm2

type KF 1000
used plywood 12mm & wooden frame
M8 @ 150, D-8
K 250 kg/cm2

QTY

UNIT PRICE
( Rp. )

SPESIFICATION

m3
m3
m3
m2
m'
m2
m3
m2

932.40
532.80
133.20
1,296.00
342.00
1,296.00
199.80
1,332.00

60,000
180,000
200,000
3,500
17,500
65,000
785,250
7,500

820,890,621
440,131,950
55,944,000
95,904,000
26,640,000
4,536,000
5,985,000
84,240,000
156,892,950
9,990,000

m2
m'
m2
m3
m2

998.20
342.00
998.20
149.73
998.20

125,000
15,000
65,000
785,250
15,000

327,336,483
124,775,000
5,130,000
64,883,000
117,575,483
14,973,000

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

2.4.3
2.4.3.1
2.4.3.2
2.4.3.3

Stair Work
Formwork
Steel bars
Concrete work

2.5
2.5.1
2.5.2
2.5.3
2.5.7
2.5.8
2.5.9
2.5.10
2.5.11

STEEL STRUCTURE WORK


Anchor bolt, L - 60cm
Base plate, size 35cm*35cm*12mm
Steel main beam & ring beam 2nd floor
Steel structure for roofing ( truss, gording, etc )
Steel plate for joint & others
Steel structure for bracket gutter
Bolt & Nut
Painting for steel structure

2.6
2.6.1
2.6.1.1
2.6.1.2
2.6.1.3

ROOFING WORK
Roof of Finishes
Roof metal w/ colour
Insulation
Nok/ridge

AMOUNT
( Rp. )

UNIT

used plywood 12mm & wooden frame


D-16, D-13
K 250 kg/cm2

m2
m'
m3

55.00
2,750.00
13.75

125,000
13,000
785,250

53,422,188
6,875,000
35,750,000
10,797,188

M-22

nos
kg
kg
kg
kg
kg
lot
kg

204.00
588.51
60,451.60
25,574.38
1,209.03
925.00
1.00
88,748.52

85,000
16,250
16,250
16,250
16,250
16,250
14,421,600
1,500

1,607,047,831
17,340,000
9,563,288
982,338,500
415,583,675
19,646,738
15,031,250
14,421,600
133,122,780

WF 400, WF 300, WF 250, WF 200


WF 350, CNP 125, trackstang, turnbukcle
PL 12mm
CNP, L
HTB
Zincromate & finish paint Ftalit

QTY

UNIT PRICE
( Rp. )

SPESIFICATION

Alm sheet, t - 0.30mm


Glass wool t-50, alm foil & wiremesh
Alm sheet, t - 0.30mm

m2
m2
m'

2,045.95
2,045.95
75.00

105,000
85,000
73,500

432,073,000
394,243,000
214,824,750
173,905,750
5,512,500

2.6.2 Gutter
2.6.2.1 Gutter metal
2.6.2.2 Down spout PVC dia 4", incl accessories

Alm sheet, t - 0.50mm


PVC, Wavin type AW

m'
m'

185.00
72.00

150,000
140,000

37,830,000
27,750,000
10,080,000

2.7 WALL WORKS


2.7.1 Brick wall + practical column, 1st floor
2.7.2 Plaster board

used heble 20*40*12cm


GRC, t - 6mm

m2
m2

1,060.80
2,121.60

175,000
37,500

132,600,000
185,640,000
79,560,000

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang
DESCRIPTION

2.8
2.8.1
2.8.1.1
2.8.1.2
2.8.1.3
2.8.1.4

DOOR AND WINDOW WORKS


Doors
Alm door type AD1, single swing door 800*2100
Alm door type AD2, double swing door 1600*2100
Alm door type AD3, double swing door 1200*2100
Alm door type AD4, double swing door 1600*2100

2.8.2
2.8.2.1
2.8.2.2
2.8.2.3
2.8.2.4
2.8.2.5

Windows
Aluminium window type AW1, size 800*2100
Aluminium window type AW2, size 1600*1200
Aluminium window type AW3, size 2400*1200
Aluminium window type AW4, size 3200*1200
Alum window (Bouvenlight), size 500*1200

2.9
2.9.1
2.9.2
2.9.3
2.9.4

FLOOR FINISH WORKS


Ceramic tile 1st floor & stair
Scriting ceramic, h - 100mm
Epoxy floor, 2nd floor ( half of area 2nd floor )
Floor harderner, 2nd floor ( half of area 2nd floor )

2.10
2.10.1
2.10.2
2.10.3

WALL FINISHES
Painting wall exterior
Painting wall Interior
Ceramic tile 200 x 250, H=2m for wall of toilet

2.11
2.11.1
2.11.2
2.11.3

CEILING FINISHES
Gypsum, t = 9mm + hollow frame + hanger
Cornice, w = 10cm x 10cm
Painting work

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

AMOUNT
( Rp. )

nos
nos
nos
nos

13.00
2.00
1.00
1.00

2,772,000
5,544,000
4,158,000
5,880,000

99,042,000
57,162,000
36,036,000
11,088,000
4,158,000
5,880,000

Al Clear anodize Ex. Alexindo, fix , Glass 5 mm

nos
nos
nos
nos
nos

4.00
1.00
6.00
1.00
4.00

2,520,000
2,400,000
3,600,000
4,800,000
750,000

41,880,000
10,080,000
2,400,000
21,600,000
4,800,000
3,000,000

size 30*30 ex. Roman


ex. Roman
t = 500 micron, ex. maxiFloor
fosroc

m2
m'
m2
m2

1,332.00
500.00
499.10
499.10

140,000
32,500
125,000
87,500

308,788,750
186,480,000
16,250,000
62,387,500
43,671,250

weathersield ex. Dulux


ex. Dulux
ex. Roman

m2
m2
m2

536.00
1,585.60
108.00

35,000
31,000
150,000

84,113,600
18,760,000
49,153,600
16,200,000

ex. Jayaboard, galvanized hollow


ex. Jayaboard
ex. Vinilex

m2
m'
m2

240.00
210.00
240.00

127,500
27,500
31,000

43,815,000
30,600,000
5,775,000
7,440,000

Al Clear anodize Ex. Alexindo, fix , Glass 5 mm


Al Clear anodize Ex. Alexindo, fix , Glass 5 mm
Al Clear anodize Ex. Alexindo, fix , Glass 5 mm
Al Clear anodize Ex. Alexindo, fix , Glass 5 mm

Al Clear anodize Ex. Alexindo, fix , Glass 5 mm


Al Clear anodize Ex. Alexindo, fix , Glass 5 mm
Al Clear anodize Ex. Alexindo, fix , Glass 5 mm
Al Clear anodize Ex. Alexindo, fix , Glass 5 mm

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location
No.
2.12
2.12.1
2.12.2
2.12.3
2.12.4
2.12.5
2.12.6
2.12.7
2.12.8
2.12.9

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang
DESCRIPTION
OTHERS WORK
Roster wall ventilation (near ablution area)
Concrete table for canteen, w - 50cm
Hand washing for canteen, size 50cm*50cm
Ablution, w - 60cm
Path foot around building, w - 100cm
Drainage u-ditch around building
Concrete table for wastafel at toilet, w - 50cm
Cubical toilet partition (incl door)
Partition urinoir, 35cm*76cm

SPESIFICATION

concrete & ceramic


concrete & ceramic
concrete & ceramic
excav, sand gravel, concrete, bars, etc
size 30cm*50cm
PVC
PVC ex. Toto

UNIT

m2
m'
m'
m'
m2
m'
m'
m2
nos

QTY

13.00
37.00
12.00
7.00
160.00
164.00
12.00
89.60
8.00

UNIT PRICE
( Rp. )

175,000
187,500
900,000
500,000
225,000
185,000
187,500
1,250,000
1,250,000

AMOUNT
( Rp. )

214,102,500
2,275,000
6,937,500
10,800,000
3,500,000
36,000,000
30,340,000
2,250,000
112,000,000
10,000,000

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

I.

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

PREPARATORY WORK
1.1
1.2
1.3
1.4
1.5
1.6
1.7

II.

AMOUNT
( Rp. )

50,000,000

Survey, marking & setting out


Unloading fee
Mobilization & Demobilization
Cleaning During Construction
Safety & Protection
Coordination & security
Reporting

ls
ls
ls
ls
ls
ls
ls

1.00
1.00
1.00
1.00
1.00
1.00
1.00

3,000,000
5,000,000
10,000,000
10,000,000
10,000,000
10,000,000
2,000,000

3,000,000
5,000,000
10,000,000
10,000,000
10,000,000
10,000,000
2,000,000

CONSTRUCTION OF WORKSHOP BUILDING


2.1 FOUNDATION WORKS

2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6

Bouwplank
Excavation
Lean concrete, t - 50mm
Concrete foundation pile cap , 400*400*800mm
Backfill
Disposal exist soil

15,161,600

steel bars, formwork, concrete, etc

m'
m3
m2
m3
m3
m3

32.00
12.00
7.20
2.56
9.44
2.56

22,000
60,000
56,700
5,000,000
45,500
39,000

2.2 SUB BASE WORK FOR FLOOR


2.2.1 Excavation
2.2.2 Limestone (t = 40 cm)
2.2.3 Base course, t - 10cm

704,000
720,000
408,240
12,800,000
429,520
99,840
84,175,500

m3
m3
m3

255.00
204.00
51.00

60,000
243,000
378,500

15,300,000
49,572,000
19,303,500

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

2.3 FLOOR FINISH WORKS


2.3.1 Lean concrete, t - 50mm
2.3.2 Ceramic tile

52,931,540

size 30*30

m2
m2

206.20
206.20

56,700
200,000

2.4 BUILDING MAINTENANCE


2.4.1 Building

AMOUNT
( Rp. )

11,691,540
41,240,000
105,000,000

lot

1.00

105,000,000

105,000,000

2.5 MECHANICAL WORK

lot

1.00

43,140,000

43,140,000

2.6 ELECTRICAL WORK

lot

1.00

57,610,000

57,610,000

III.

Ex Site office KUJA

CONSTRUCTION OF WASTE AREA


3.1 FOUNDATION WORKS

3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6

Bouwplank
Excavation
Lean concrete, t - 50mm
Concrete foundation pile cap , 400*400*800mm
Backfill
Disposal exist soil

10,613,120

steel bars, formwork, concrete, etc

m'
m3
m2
m3
m3
m3

22.40
8.40
5.04
1.79
6.61
1.79

22,000
60,000
56,700
5,000,000
45,500
39,000

3.2 SUB BASE FLOOR WORKS 17 m x 35 m


3.2.1 Excavation
3.2.2 Limestone (t = 40 cm)
3.2.3 Base course, t - 10cm

492,800
504,000
285,768
8,960,000
300,664
69,888
60,325,775

m3
m3
m3

182.75
146.20
36.55

60,000
243,000
378,500

10,965,000
35,526,600
13,834,175

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

3.3 FLOOR FINISH WORKS

9,366,840

3.3.1 Lean concrete, t - 50mm

m2

165.20

56,700

3.4 WALL WORKS


3.4.1 Brickwall
3.4.2 Wiremesh M6 + Polycarbonate 6mm

Hebel + Plester, Height = 1.2 m

m2
m2

279.96
68.64

278,250
55,000

77,898,870
3,775,200
11,019,000

frame alm 4", glasess 5mm

nos
nos
nos

1.00
1.00
1.00

5,544,000
3,075,000
2,400,000

3.6 ROOFING WORK


3.6.1 Roofing zincalume, t - 0.5mm

9,366,840
81,674,070

3.5 DOORS & WINDOWS


3.5.1 Alm door , double swing door 1600*2100
3.5.2 Alm door, single swing door 800*2100
3.5.3 Aluminium window, size 1600*1200

AMOUNT
( Rp. )

5,544,000
3,075,000
2,400,000
70,434,000

m2

270.90

260,000

70,434,000

3.7 MECHANICAL WORK

lot

1.00

46,620,000

46,620,000

3.8 ELECTRICAL WORK

lot

1.00

63,260,000

63,260,000

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

AMOUNT
( Rp. )

UNIT

by excavator

m3
m3
m2

80.00
80.00
80.00

60,000
39,000
5,000

8,320,000
4,800,000
3,120,000
400,000

4.2 LIMESTONE & BASE COURSE


4.2.1 Limestone, t - 40cm
4.2.2 Base course, t - 10cm

m3
m3

32.00
8.00

243,000
378,500

10,804,000
7,776,000
3,028,000

4.3
4.3.1
4.3.2
4.3.3

m2
m2
m3

33.76
33.76
1.54

35,400
56,700
5,000,000

10,789,296
1,195,104
1,914,192
7,680,000

incl. wiremesh M6, conc K-175, etc

m2
m'

80.00
54.00

306,800
39,000

26,650,000
24,544,000
2,106,000

incl. formwork, steel bars, concrete K-300

m3
nos

0.36
16.00

6,000,000
125,000

4,160,000
2,160,000
2,000,000

PL 20mm, WF 250

kg
kg
kg
lot
kg

1,752.06
163.80
191.59
1.00
2,107.45

21,000
21,000
21,000
885,127
3,500

52,517,554
36,793,260
3,439,800
4,023,306
885,127
7,376,061

4.1
4.1.1
4.1.2
4.1.3

CONSTRUCTION GASOLINE TANK WORKS


EARTH WORK
Excavation
Disposal
Subgrade preparation

FOUNDATION WORK
Gravel bedding, t - 10cm
Lean concrete, t - 5cm
Pile cap, size 80cm*80cm*60cm

4.4 FLOOR WORK


4.4.1 Concrete floor, t - 12cm
4.4.2 Cutter concrete + joint sealan
4.5 COLUMN / PEDESTAL
4.5.1 Column / Pedestal, size 30cm*30cm*h
4.5.2 Anchor bolt M20, L - 65cm
4.6
4.6.1
4.6.2
4.6.3
4.6.4
4.6.5

QTY

UNIT PRICE
( Rp. )

SPESIFICATION

IV.

DESCRIPTION

STEEL STRUCTURE
Base plate, Column, beam
Steel structure for Gording
Steel plate for joint & others
Bolt & Nut
Painting for steel structure

outside area
compaction base soil by vibro roller

incl. formwork, steel bars, concrete K-300

CNP 125, trackstang, turnbukcle


PL 12mm
HTB
Zincromate & finish paint Ftalit

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang
AMOUNT
( Rp. )

UNIT

ex. Lysaght, type clip lock, roll on site

m2
nos
m2
m'

80.00
240.00
18.00
36.00

260,000
1,500
260,000
90,000

29,080,000
20,800,000
360,000
4,680,000
3,240,000

4.8 FOUNDATION FUEL TANK


4.8.1 Concrete foundation
4.8.2 Steel structure

m3
kg

2.50
1,250.00

5,800,000
21,000

40,750,000
14,500,000
26,250,000

4.9 MECHANICAL & ELECTRICAL WORK


4.9.1 Mechanical Work
4.9.2 Electrical Work

lot
lot

1.00
1.00

18,190,000
20,380,000

38,570,000
18,190,000
20,380,000

m2

2,027.92

113,100

229,357,752

V.

ROOFING WORK
Roofing zincalume, t - 0.5mm
Self drilling
Fascia, spandeck color, t - 0.45mm, H - 500mm
Flashing, t - 0.45mm

QTY

UNIT PRICE
( Rp. )

SPESIFICATION

4.7
4.7.1
4.7.2
4.7.3
4.7.4

DESCRIPTION

CONSTRUCTION SIGNAGE BUILDING WORKS

5.1 SIGNAGE BUILDING


5.1.1 -. Retaining Wall Dock Leveller
-. Retaining Wall Loading Area
-. Wall Exterior Loading Area
-. Wall Interior Loading Area
-. Column Marking
-. Parking Marking

REMARKS

SUMMARY
PROGRESS REPORT
Period : 15 February 2013 ~ 21 February 2013
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: Karawang International Industrial City (KIIC) - Karawang

ITEM
No.

Weighting
(%)

DESCRIPTION

Planing
Progress
(%)

REPORT No. : 2
Previous Progress
On Site
Weight
(%)
(%)

This time Progress


On Site
Weight
(%)
(%)

To Date Progress
On Site
Weight
(%)
(%)

Deviation
(%)

I.

PREPARATORY WORK

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

#REF!

II

CONSTRUCTION WORKS
SITE CLEARING
PILING WORKS
FOUNDATION & COLUMN WORK
CONCRETE SLAB & STAIR WORK
STEEL STRUCTURE WORK
ROOFING WORK
WALL WORKS
DOOR AND WINDOW WORKS
FLOOR FINISH WORKS
WALL FINISHES
CEILING FINISHES
OTHERS WORK

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12

TOTAL

Evaluation of Progress :
Accumulation of Planing Progress :
#REF!
Accumulation of actual Progress :
#REF!
----------------------------------#REF!
#REF!

#REF!

#REF!

Approved by;
PT. Sharp Indonesia

Karawang, 15 February 2013


Prepared by;
PT. Karya Utama Jaya Abadi

( Nanang Prakosa Budianto )

( Gunawan )

Project Manager

Site Manager

RENCANA KERJA MINGGU DEPAN


( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013

Project
Works
Owner
Contractor
Location
No.
I.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: PT. Karya Utama Jaya Abadi
: Karawang International Industrial City (KIIC) - Karawang
Description

Contract
Weighting
Quantity
(%)

Planing Progress for Next week


Progress Weighting
Quantity
(%)
(%)

Target Progress for Next Week


Progress Weighting
Quantity
(%)
(%)

Planing
until
Previous

Actual
until
Previous

Deviation
until
Previous

ls
ls
ls
ls
ls
ls
ls
ls
ls
ls

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

4.410%
0.116%
0.896%
0.266%
0.575%
0.332%
0.542%
0.487%
0.266%
0.841%
0.089%

0.09
0.05
0.02
0.03
0.03
0.03
0.02
0.04

0.00%
8.50%
5.00%
2.00%
3.00%
2.50%
0.00%
3.00%
2.00%
4.46%

0.153%
0.000%
0.076%
0.013%
0.012%
0.010%
0.014%
0.000%
0.008%
0.017%
0.004%

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

CONSTRUCTION WORKS
2.1 SITE CLEARING
2.1.1 Site Clearing / Stripping
2.1.2 Disposal

m2
m3

1,560.00
234.00

0.276%
0.121%
0.155%

0.00%
0.00%

0.000%
0.000%
0.000%

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

2.2
2.2.1
2.2.2
2.2.3

m'
m'
nos

550.00
550.00
55.00

3.360%
2.374%
0.913%
0.073%

45.00%
45.00%
275.00%

1.680%
1.068%
0.411%
0.201%

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

302.01
44.55
44.55
123.20
3,773.00
21.56

9.122%
2.113%
0.401%
0.020%
0.035%
0.205%
1.086%
0.368%

35.13%
0.00%
0.00%
0.00%
0.00%
0.00%

0.141%
0.141%
0.141%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10

PREPARATORY WORK
Survey and Marking
Temporary Site Office ( Direksi keet & Storage )
Temporary Water
Temporary Power
Safety & Protection
Design Fee
Mobilization & Demobilization
Cleaning During Construction
Unloading fee, coordination & security
Reporting

Unit

REPORT No. : 2

II.

2.3
2.3.1
2.3.1.1
2.3.1.2
2.3.1.3
2.3.1.4
2.3.1.5
2.3.1.6

PILING WORKS
Concrete spun pile 300mm, L= 10 m' ( P1 )
Driving Pile
Cuting Pile
FOUNDATION & COLUMN WORK
Pile Cap
Excavation, Backfill, diaposal & compaction base soil
Sand gravel, t - 10cm
Lean concrete, t - 5cm
Formwork for pile cap
Steel bars for pile cap
Concrete work for pile cap ( 70*70*80cm )

m3
m2
m2
m2
kg
m3

247.50
247.50
151.25

106.09
0.00

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

RENCANA KERJA MINGGU DEPAN


( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013

Project
Works
Owner
Contractor
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: PT. Karya Utama Jaya Abadi
: Karawang International Industrial City (KIIC) - Karawang

REPORT No. : 2

Contract
Weighting
Quantity
(%)

Planing Progress for Next week


Progress Weighting
Quantity
(%)
(%)

Target Progress for Next Week


Progress Weighting
Quantity
(%)
(%)

Planing
until
Previous

Actual
until
Previous

Deviation
until
Previous

Description

Unit

2.3.2
2.3.2.1
2.3.2.2
2.3.2.3
2.3.2.4
2.3.2.5
2.3.2.6
2.3.2.7

Tie Beam
Excavation, Backfill, diaposal & compaction base soil
Sand gravel, t - 10cm
Lean concrete, t - 5cm
Formwork for tie beam
Formwork for tie beam
Steel bars for tie beam
Concrete work for tie beam ( 25cm*50cm )

m3
m2
m2
m2
m2
kg
m3

516.56
19.58
9.79
435.00
90.60
10,704.75
61.17

5.758%
0.686%
0.009%
0.008%
0.722%
0.211%
3.080%
1.043%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

2.3.3
2.3.3.1
2.3.3.2
2.3.3.3

Column Concrete ( C-1 )


Formwork for column
Steel bars for tie beam
Concrete work for tie beam ( 50cm*50cm* 100cm )

m2
kg
m3

110.00
2,475.00
13.75

1.251%
0.304%
0.712%
0.234%

0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

2.4
2.4.1
2.4.1.1
2.4.1.2
2.4.1.3
2.4.1.4
2.4.1.5
2.4.1.6
2.4.1.7
2.4.1.8

CONCRETE SLAB & STAIR WORK


Concrete Ground Slab ( 1st Floor )
Excavation, Backfill, diaposal & compaction base soil
Lime stone, t = 40cm
Sand gravel, t - 10cm
Plastic sheet
Formwork / stop cor, h - 20cm
Wiremesh, 1 layer ( incl spacer block )
Concrete work, t - 15cm ( w/ pump or bucket )
Surface finishing & curing

m3
m3
m3
m2
m'
m2
m3
m2

932.40
532.80
133.20
1,296.00
342.00
1,296.00
199.80
1,332.00

18.169%
9.741%
1.238%
2.123%
0.590%
0.100%
0.132%
1.864%
3.473%
0.221%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

m2
m'
m2
m3
m2

998.20
342.00
998.20
149.73
998.20

7.245%
2.762%
0.114%
1.436%
2.602%
0.331%

0.00%
0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

2.4.2 Concrete Slab ( 2nd Floor )


Bondex sheet, t - 0,75mm ( incl screw )
Formwork / stop cor, h - 15cm
Wiremesh, 1 layer ( incl spacer block )
Concrete work, t - 15cm ( w/pump or bucket)
Surface finishing by trowel & curing

2.4.2.1
2.4.2.2
2.4.2.3
2.4.2.4
2.4.2.5

RENCANA KERJA MINGGU DEPAN


( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013

Project
Works
Owner
Contractor
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: PT. Karya Utama Jaya Abadi
: Karawang International Industrial City (KIIC) - Karawang
Description

Unit

Contract
Weighting
Quantity
(%)

REPORT No. : 2
Planing Progress for Next week
Progress Weighting
Quantity
(%)
(%)

Target Progress for Next Week


Progress Weighting
Quantity
(%)
(%)

Planing
until
Previous

Actual
until
Previous

Deviation
until
Previous

RENCANA KERJA MINGGU DEPAN


( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013

Project
Works
Owner
Contractor
Location

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: PT. Karya Utama Jaya Abadi
: Karawang International Industrial City (KIIC) - Karawang

No.

Description

Unit

REPORT No. : 2

Contract
Weighting
Quantity
(%)

Planing Progress for Next week


Progress Weighting
Quantity
(%)
(%)

Target Progress for Next Week


Progress Weighting
Quantity
(%)
(%)

Planing
until
Previous

Actual
until
Previous

Deviation
until
Previous

2.4.3
2.4.3.1
2.4.3.2
2.4.3.3

Stair Work
Formwork
Steel bars
Concrete work

m2
m'
m3

55.00
2,750.00
13.75

1.182%
0.152%
0.791%
0.239%

0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

2.5
2.5.1
2.5.2
2.5.3
2.5.7
2.5.8
2.5.9
2.5.10
2.5.11

STEEL STRUCTURE WORK


Anchor bolt, L - 60cm
Base plate, size 35cm*35cm*12mm
Steel main beam & ring beam 2nd floor
Steel structure for roofing ( truss, gording, etc )
Steel plate for joint & others
Steel structure for bracket gutter
Bolt & Nut
Painting for steel structure

nos
kg
kg
kg
kg
kg
lot
kg

204.00
588.51
60,451.60
25,574.38
1,209.03
925.00
1.00
88,748.52

35.569%
0.384%
0.212%
21.742%
9.198%
0.435%
0.333%
0.319%
2.946%

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

2.6
2.6.1
2.6.1.1
2.6.1.2
2.6.1.3

ROOFING WORK
Roof of Finishes
Roof metal w/ colour
Insulation
Nok/ridge

m2
m2
m'

2,045.95
2,045.95
75.00

9.563%
8.726%
4.755%
3.849%
0.122%

0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

m'
m'

185.00
72.00

0.837%
0.614%
0.223%

0.00%
0.00%

0.000%
0.000%
0.000%

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

m2
m2

1,060.80
2,121.60

2.935%
2.054%
0.880%

0.00%
0.00%

0.000%
0.000%
0.000%

#REF!
#REF!

#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

2.6.2 Gutter
2.6.2.1 Gutter metal
2.6.2.2 Down spout PVC dia 4", incl accessories
2.7 WALL WORKS
2.7.1 Brick wall + practical column, 1st floor
2.7.2 Plaster board

RENCANA KERJA MINGGU DEPAN


( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013

Project
Works
Owner
Contractor
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: PT. Karya Utama Jaya Abadi
: Karawang International Industrial City (KIIC) - Karawang
Description

Unit

REPORT No. : 2

Contract
Weighting
Quantity
(%)

Planing Progress for Next week


Progress Weighting
Quantity
(%)
(%)

Target Progress for Next Week


Progress Weighting
Quantity
(%)
(%)

0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Planing
until
Previous

Actual
until
Previous

Deviation
until
Previous

2.8
2.8.1
2.8.1.1
2.8.1.2
2.8.1.3
2.8.1.4

DOOR AND WINDOW WORKS


Doors
Alm door type AD1, single swing door 800*2100
Alm door type AD2, double swing door 1600*2100
Alm door type AD3, double swing door 1200*2100
Alm door type AD4, double swing door 1600*2100

nos
nos
nos
nos

13.00
2.00
1.00
1.00

2.192%
1.265%
0.798%
0.245%
0.092%
0.130%

2.8.2
2.8.2.1
2.8.2.2
2.8.2.3
2.8.2.4
2.8.2.5

Windows
Aluminium window type AW1, size 800*2100
Aluminium window type AW2, size 1600*1200
Aluminium window type AW3, size 2400*1200
Aluminium window type AW4, size 3200*1200
Alum window (Bouvenlight), size 500*1200

nos
nos
nos
nos
nos

4.00
1.00
6.00
1.00
4.00

0.927%
0.223%
0.053%
0.478%
0.106%
0.066%

0.00%
0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

FLOOR FINISH WORKS


Ceramic tile 1st floor & stair
Scriting ceramic, h - 100mm
Epoxy floor, 2nd floor ( half of area 2nd floor )
Floor harderner, 2nd floor ( half of area 2nd floor )

m2
m'
m2
m2

1,332.00
500.00
499.10
499.10

6.834%
4.127%
0.360%
1.381%
0.967%

0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!

WALL FINISHES
Painting wall exterior
Painting wall Interior
Ceramic tile 200 x 250, H=2m for wall of toilet

m2
m2
m2

536.00
1,585.60
108.00

1.862%
0.415%
1.088%
0.359%

0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

m2
m'
m2

240.00
210.00
240.00

0.970%
0.677%
0.128%
0.165%

0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

2.9
2.9.1
2.9.2
2.9.3
2.9.4
2.10
2.10.1
2.10.1
2.10.1

2.11 CEILING FINISHES


2.11.1 Gypsum, t = 9mm + hollow frame + hanger
2.11.2 Cornice, w = 10cm x 10cm
2.11.3 Painting work

RENCANA KERJA MINGGU DEPAN


( Minggu Ke - 3 )
Periode : 22 February 2013 ~ 28 February 2013

Project
Works
Owner
Contractor
Location
No.
2.12
2.10.1
2.10.1
2.10.1
2.10.1
2.10.1
2.10.1
2.10.1
2.10.1
2.10.1

: Sharp Electronic Indonesia New Factory Project


: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )
: PT. Sharp Indonesia
: PT. Karya Utama Jaya Abadi
: Karawang International Industrial City (KIIC) - Karawang
Description
OTHERS WORK
Roster wall ventilation (near ablution area)
Concrete table for canteen, w - 50cm
Hand washing for canteen, size 50cm*50cm
Ablution, w - 60cm
Path foot around building, w - 100cm
Drainage u-ditch around building
Concrete table for wastafel at toilet, w - 50cm
Cubical toilet partition (incl door)
Partition urinoir, 35cm*76cm
TOTAL

Unit

m2
m'
m'
m'
m2
m'
m'
m2
nos

REPORT No. : 2

Contract
Weighting
Quantity
(%)

13.00
37.00
12.00
7.00
160.00
164.00
12.00
89.60
8.00

4.739%
0.050%
0.154%
0.239%
0.077%
0.797%
0.672%
0.050%
2.479%
0.221%
100.00%

Planing Progress for Next week


Progress Weighting
Quantity
(%)
(%)

0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%

0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
0.000%
1.974%

Target Progress for Next Week


Progress Weighting
Quantity
(%)
(%)

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Planing
until
Previous

Actual
until
Previous

Deviation
until
Previous

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!

#REF!

#REF!

#REF!

Karawang, 15 February 2013


PT. KaryaUtama Jaya Abadi

Gunawan
Site Manager

Next
Week
Deviation
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Next
Week
Deviation
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Next
Week
Deviation

Next
Week
Deviation
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Next
Week
Deviation
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

Next
Week
Deviation
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

0.590%

SCHEDULE OF WORK
Project

: Sharp Electronic Indonesia New Factory Project

Works

: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )

Owner

: PT. Sharp Indonesia

Location

: Karawang International Industrial City (KIIC) - Karawang


-2
-1
January 2013
Description

6
7
March 2013

10

11
April 2013

12

13

14

15
May 2013

16

17

18

19
20
June 2013

21

22

23

24
July 2013

25

26

27

28
August 2013

29

30

18 ~ 24

25 ~ 31

01 ~ 07

08 ~ 14

15 ~ 21

22 ~ 28

01 ~ 07

08 ~ 14

15 ~ 21

22 ~ 28

29 ~ 04

05 ~ 11

12 ~ 18

19 ~ 25

26 ~ 02

03 ~ 09

10 ~ 16

17 ~ 23

24 ~ 30

31 ~ 06

07 ~ 13

14 ~ 20

21 ~ 27

28 ~ 04

05 ~ 11

12 ~ 18

19 ~ 25

26 ~ 01

02 ~ 08

09 ~ 15

16 ~ 22

23 ~ 29

-14dy

-7dy

7dy

14dy

21dy

28dy

35dy

42dy

49dy

56dy

63dy

70dy

77dy

84dy

91dy

98dy

105dy

112dy

119dy

126dy

133dy

140dy

147dy

154dy

161dy

168dy

175dy

182dy

189dy

196dy

203dy

210dy

0.0028

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0026

0.0001

lot

1.00

4.41%

2.1 SITE CLEARING

m2

1,560.00

0.28%

2.2 PILING WORKS

m'

550.00

3.36%

2.3.1 Pile Cap

m3

21.56

2.11%

2.3.2 Tie Beam

m3

61.17

5.76%

2.3.3 Column Concrete ( C-1 )

m3

13.75

1.25%

2.4.1 Concrete Ground Slab ( 1st Floor )

m3

199.80

9.74%

2.4.2 Concrete Slab ( 2nd Floor )

m3

149.73

7.24%

2.4.3 Stair Work

m3

13.75

1.18%

kg

88,748.52

35.57%

m2

2,045.95

9.56%

m2

1,060.80

2.93%

2.8.1 Doors

unit

17.00

2.8.2 Windows

unit

16.00

2.9.1 Ceramic tile 1st floor & stair

m2

1,332.00

4.49%

2.9.3 Epoxy floor, 2nd floor ( half of area 2nd floor )

m2

499.10

1.38%

2.9.4 Floor harderner, 2nd floor ( half of area 2nd floor )

m2

499.10

0.97%

II

(%)

Volume

PREPARATORY WORK

2
3
February 2013

Weighting
Unit

START --->

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

0.0015

100%

0.0014

CONSTRUCTION WORKS

0.0101

90%

0.0168

0.0067

0.0014

0.0070

0.0127

0.0096

0.0120

0.0264

0.0096

0.0042

0.0042

0.0042

0.0032

0.0271

2.3 FOUNDATION & COLUMN WORK


80%

2.4 CONCRETE SLAB & STAIR WORK


0.0150

0.0150

0.0070

70%

0.0116

0.0116

0.0116

0.0116

0.0261
0.0020

2.5 STEEL STRUCTURE WORK


2.5.1~11 Fabrication & Erection of Steel Structure

0.0301

0.0013

0.0049

Erection

Fabrication
0.0013

0.0049

0.0013

0.0013

0.0133

0.0333

0.0333

0.0476

0.0501

0.0358

0.0341

0.0341

0.0239

0.0095

0.0352

60%

2.6 ROOFING WORK


2.6.1~2 Roof of Finishes & Gutter

0.0048

0.0239

0.0311

0.0311

0.0048

2.7 WALL WORKS

50%

2.7.1~2 Brick wall + practical column & plaster board

0.0037

0.0037

0.0037

0.0037

0.0037

0.0037

0.0037

0.0037

1.27%

0.0013

0.0013

0.0013

0.0089

0.93%

0.0023

0.0023

0.0023

0.0023

2.8 DOOR AND WINDOW WORKS

40%

2.9 FLOOR FINISH WORKS


0.0015

0.0015

0.0187

0.0150

0.0075

0.0007
0.0069

0.0048

0.0069

0.0048

30%

2.10 WALL FINISHES


2.10.1 Painting wall exterior

m2

536.00

0.42%

2.10.2 Painting wall Interior

m2

1,585.60

1.09%

2.10.3 Ceramic tile 200 x 250, H=2m for wall of toilet

m2

108.00

0.36%

m2

240.00

0.97%

lot

1.00

0.57%

2.12.5 Path foot around building, w - 100cm

m2

160.00

0.80%

2.12.6 Drainage u-ditch around building

m'

164.00

0.67%

2.12.8~9 Cubical toilet & partition urinoir

lot

1.00

2.70%

0.0010
0.0036
0.0018

0.0036

0.0031

0.0036

0.0018

20%

2.11 CEILING FINISHES


2.11.1~3 Gypsum , cornice & painting

0.0048

0.0048

2.12 OTHERS WORK

10%

2.12.1~4 Conc table, hand washing, ablution

0.0010

0.0022

0.0022

0.0010

0.0010

0.0010

0.0027

0.0027

0.0027

0.0010

0.0010

0.0090

0.0090

0.0022
0.0090

0%

100.00%

0.000%

0.000%

0.546%

1.175%

1.974%

2.623%

3.171%

3.667%

4.369%

4.494%

4.991%

4.991%

5.614%

5.531%

5.258%

5.088%

5.088%

4.907%

4.924%

5.076%

5.006%

4.568%

3.590%

3.087%

2.330%

1.952%

0.900%

1.414%

1.839%

1.828%

0.000%

0.000%

ACCUMULATION

TOTAL

0.00%

0.000%

0.000%

0.546%

1.721%

3.695%

6.317%

9.489%

13.156%

17.525%

22.019%

27.010%

32.001%

37.615%

43.146%

48.404%

53.492%

58.580%

63.486%

68.411%

73.486%

78.492%

83.060%

86.650%

89.737%

92.068%

94.020%

94.920%

96.334%

98.172%

100.000%

100.000%

100.000%

ACTUAL

0.00%

0.000%

0.000%

0.000%

#REF!

#REF!

0.000%

0.000%

-0.546%

#REF!

#REF!

DEVIASI

Karawang, 15 February 2013


PT. Suryacipta Swadaya

PT. Karya Utama Jaya Abadi

( Gunawan )

SCHEDULE OF WORK
Project

: Sharp Electronic Indonesia New Factory Project

Works

: Employee Facility Building ( Canteen, Musholla, Clinic, Toilet, etc )

Owner

: PT. Sharp Indonesia

Location

: Karawang International Industrial City (KIIC) - Karawang


-2

-1

January 2013
Description

Unit

Volume

Weighting
(%)

18 ~ 24
-14dy

25 ~ 31
-7dy

February 2013
01 ~ 07
7dy

08 ~ 14
14dy

15 ~ 21
21dy

10

March 2013
22 ~ 28
28dy

01 ~ 07
35dy

08 ~ 14
42dy

15 ~ 21
49dy

11

12

13

14

April 2013
22 ~ 28
56dy

29 ~ 04
63dy

05 ~ 11
70dy

12 ~ 18
77dy

15

16

17

18

May 2013
19 ~ 25
84dy

26 ~ 02
91dy

03 ~ 09
98dy

10 ~ 16
105dy

19

20

21

22

23

June 2013
17 ~ 23
112dy

24 ~ 30
119dy

31 ~ 06
126dy

07 ~ 13
133dy

14 ~ 20
140dy

24

25

26

27

July 2013
21 ~ 27
147dy

28 ~ 04
05 ~ 11
154dy
161dy
Site Manager

12 ~ 18
168dy

28

29

30

16 ~ 22
203dy

23 ~ 29
210dy

August 2013
19 ~ 25
175dy

26 ~ 01
182dy

02 ~ 08
189dy

09 ~ 15
196dy

100%

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

I.

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

PREPARATORY WORK
1.1
1.2
1.3
1.4
1.5
1.6
1.7

II.

AMOUNT
( Rp. )

50,000,000

Survey, marking & setting out


Unloading fee
Mobilization & Demobilization
Cleaning During Construction
Safety & Protection
Coordination & security
Reporting

ls
ls
ls
ls
ls
ls
ls

1.00
1.00
1.00
1.00
1.00
1.00
1.00

3,000,000
5,000,000
10,000,000
10,000,000
10,000,000
10,000,000
2,000,000

3,000,000
5,000,000
10,000,000
10,000,000
10,000,000
10,000,000
2,000,000

CONSTRUCTION OF WORKSHOP BUILDING


2.1 FOUNDATION WORKS

2.1.1
2.1.2
2.1.3
2.1.4
2.1.5
2.1.6

Bouwplank
Excavation
Lean concrete, t - 50mm
Concrete foundation pile cap , 400*400*800mm
Backfill
Disposal exist soil

15,161,600

steel bars, formwork, concrete, etc

m'
m3
m2
m3
m3
m3

32.00
12.00
7.20
2.56
9.44
2.56

22,000
60,000
56,700
5,000,000
45,500
39,000

2.2 SUB BASE WORK FOR FLOOR


2.2.1 Excavation
2.2.2 Limestone (t = 40 cm)
2.2.3 Base course, t - 10cm

704,000
720,000
408,240
12,800,000
429,520
99,840
84,175,500

m3
m3
m3

255.00
204.00
51.00

60,000
243,000
378,500

15,300,000
49,572,000
19,303,500

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

2.3 FLOOR FINISH WORKS


2.3.1 Lean concrete, t - 50mm
2.3.2 Ceramic tile

52,931,540

size 30*30

m2
m2

206.20
206.20

56,700
200,000

2.4 BUILDING MAINTENANCE


2.4.1 Building

AMOUNT
( Rp. )

11,691,540
41,240,000
105,000,000

lot

1.00

105,000,000

105,000,000

2.5 MECHANICAL WORK

lot

1.00

43,140,000

43,140,000

2.6 ELECTRICAL WORK

lot

1.00

57,610,000

57,610,000

III.

Ex Site office KUJA

CONSTRUCTION OF WASTE AREA


3.1 FOUNDATION WORKS

3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6

Bouwplank
Excavation
Lean concrete, t - 50mm
Concrete foundation pile cap , 400*400*800mm
Backfill
Disposal exist soil

10,613,120

steel bars, formwork, concrete, etc

m'
m3
m2
m3
m3
m3

22.40
8.40
5.04
1.79
6.61
1.79

22,000
60,000
56,700
5,000,000
45,500
39,000

3.2 SUB BASE FLOOR WORKS 17 m x 35 m


3.2.1 Excavation
3.2.2 Limestone (t = 40 cm)
3.2.3 Base course, t - 10cm

492,800
504,000
285,768
8,960,000
300,664
69,888
60,325,775

m3
m3
m3

182.75
146.20
36.55

60,000
243,000
378,500

10,965,000
35,526,600
13,834,175

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

DESCRIPTION

SPESIFICATION

UNIT

QTY

UNIT PRICE
( Rp. )

3.3 FLOOR FINISH WORKS

9,366,840

3.3.1 Lean concrete, t - 50mm

m2

165.20

56,700

3.4 WALL WORKS


3.4.1 Brickwall
3.4.2 Wiremesh M6 + Polycarbonate 6mm

Hebel + Plester, Height = 1.2 m

m2
m2

279.96
68.64

278,250
55,000

77,898,870
3,775,200
11,019,000

frame alm 4", glasess 5mm

nos
nos
nos

1.00
1.00
1.00

5,544,000
3,075,000
2,400,000

3.6 ROOFING WORK


3.6.1 Roofing zincalume, t - 0.5mm

9,366,840
81,674,070

3.5 DOORS & WINDOWS


3.5.1 Alm door , double swing door 1600*2100
3.5.2 Alm door, single swing door 800*2100
3.5.3 Aluminium window, size 1600*1200

AMOUNT
( Rp. )

5,544,000
3,075,000
2,400,000
70,434,000

m2

270.90

260,000

70,434,000

3.7 MECHANICAL WORK

lot

1.00

46,620,000

46,620,000

3.8 ELECTRICAL WORK

lot

1.00

63,260,000

63,260,000

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang

No.

AMOUNT
( Rp. )

UNIT

by excavator

m3
m3
m2

80.00
80.00
80.00

60,000
39,000
5,000

8,320,000
4,800,000
3,120,000
400,000

4.2 LIMESTONE & BASE COURSE


4.2.1 Limestone, t - 40cm
4.2.2 Base course, t - 10cm

m3
m3

32.00
8.00

243,000
378,500

10,804,000
7,776,000
3,028,000

4.3
4.3.1
4.3.2
4.3.3

m2
m2
m3

33.76
33.76
1.54

35,400
56,700
5,000,000

10,789,296
1,195,104
1,914,192
7,680,000

incl. wiremesh M6, conc K-175, etc

m2
m'

80.00
54.00

306,800
39,000

26,650,000
24,544,000
2,106,000

incl. formwork, steel bars, concrete K-300

m3
nos

0.36
16.00

6,000,000
125,000

4,160,000
2,160,000
2,000,000

PL 20mm, WF 250

kg
kg
kg
lot
kg

1,752.06
163.80
191.59
1.00
2,107.45

21,000
21,000
21,000
885,127
3,500

52,517,554
36,793,260
3,439,800
4,023,306
885,127
7,376,061

4.1
4.1.1
4.1.2
4.1.3

CONSTRUCTION GASOLINE TANK WORKS


EARTH WORK
Excavation
Disposal
Subgrade preparation

FOUNDATION WORK
Gravel bedding, t - 10cm
Lean concrete, t - 5cm
Pile cap, size 80cm*80cm*60cm

4.4 FLOOR WORK


4.4.1 Concrete floor, t - 12cm
4.4.2 Cutter concrete + joint sealan
4.5 COLUMN / PEDESTAL
4.5.1 Column / Pedestal, size 30cm*30cm*h
4.5.2 Anchor bolt M20, L - 65cm
4.6
4.6.1
4.6.2
4.6.3
4.6.4
4.6.5

QTY

UNIT PRICE
( Rp. )

SPESIFICATION

IV.

DESCRIPTION

STEEL STRUCTURE
Base plate, Column, beam
Steel structure for Gording
Steel plate for joint & others
Bolt & Nut
Painting for steel structure

outside area
compaction base soil by vibro roller

incl. formwork, steel bars, concrete K-300

CNP 125, trackstang, turnbukcle


PL 12mm
HTB
Zincromate & finish paint Ftalit

REMARKS

BILL OF QUANTITY
Project
Works
Owner
Location
No.

: Sharp Electronic Indonesia New Factory Project


: Workshop, Waste area, Gasoline Tank & Signage Building
: PT. Sharp Electronic Indonesia
: Karawang International Industrial City (KIIC) - Karawang
AMOUNT
( Rp. )

UNIT

ex. Lysaght, type clip lock, roll on site

m2
nos
m2
m'

80.00
240.00
18.00
36.00

260,000
1,500
260,000
90,000

29,080,000
20,800,000
360,000
4,680,000
3,240,000

4.8 FOUNDATION FUEL TANK


4.8.1 Concrete foundation
4.8.2 Steel structure

m3
kg

2.50
1,250.00

5,800,000
21,000

40,750,000
14,500,000
26,250,000

4.9 MECHANICAL & ELECTRICAL WORK


4.9.1 Mechanical Work
4.9.2 Electrical Work

lot
lot

1.00
1.00

18,190,000
20,380,000

38,570,000
18,190,000
20,380,000

m2

2,027.92

113,100

229,357,752
229,357,752

V.

ROOFING WORK
Roofing zincalume, t - 0.5mm
Self drilling
Fascia, spandeck color, t - 0.45mm, H - 500mm
Flashing, t - 0.45mm

QTY

UNIT PRICE
( Rp. )

SPESIFICATION

4.7
4.7.1
4.7.2
4.7.3
4.7.4

DESCRIPTION

CONSTRUCTION SIGNAGE BUILDING WORKS

5.1 SIGNAGE BUILDING


5.1.1 -. Retaining Wall Dock Leveller
-. Retaining Wall Loading Area
-. Wall Exterior Loading Area
-. Wall Interior Loading Area
-. Column Marking
-. Parking Marking

REMARKS

SCHEDULE OF WORK
Project

: Sharp Electronic Indonesia New Factory Project

Works

: Canopy Parking Manager

Owner

: PT. Sharp Indonesia

Location

: Karawang International Industrial City (KIIC) - Karawang

Description

Start

Finish

Duration

(Date)

(Date)

( days )

JULI 2014
01/06/2014

02/06/2014

03/06/2014

04/06/2014

05/06/2014

06/06/2014

07/06/2014

08/06/2014

09/06/2014

10/06/2014

11/06/2014

12/06/2014

13/06/2014

14/06/2014

15/06/2014

16/06/2014

17/06/2014

18/06/2014

19/06/2014

20/06/2014

21/06/2014

22/06/2014###

##
I

PREPARATORY WORK

##
###

1.1 PREPARATION

II

1-Jun-14

11-Jun-14

11

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

CONSTRUCTION

##

2.1 EXCAVATION

1-Jun-14

15-Jun-14

15

2.2 BOR PILE & CONCRETE PILE CAP

4-Jun-14

16-Jun-14

13

2.3 FOUNDATION 1M X 1M & CONCRETE COLUM

6-Jun-14

16-Jun-14

11

2.4 STEEL TRUCTURE FOR CANOPY

9-Jun-14

21-Jun-14

13

0.0108

0.0108

0.0108

2.5 ROOFING WORK

17-Jun-14

23-Jun-14

0.0104

0.0104

0.0104

2.6 DRAINAGE WORK

8-Jun-14

21-Jun-14

14

0.0031

0.0031

0.0031

0.0031

0.0347

0.0347

##
###

##

0.0146

0.0146

0.0146

0.0108

0.0108

0.0108

0.0108

0.0108

##

0.0104

0.0104

0.0104

0.0104

0.0104

###

RE-SCHEDULE OF WORK
Project

: Sharp Electronic Indonesia New Factory Project

Works

: Canopy Parking Manager

Owner

: PT. Sharp Indonesia

Location

: Karawang International Industrial City (KIIC) - Karawang

Description

Start

Finish

Duration

(Date)

(Date)

( days )

JUNI 2014
21/06/2014

22/06/2014

23/06/2014

24/06/2014

25/06/2014

JULI 2014

26/06/2014

27/06/2014

28/06/2014

29/06/2014

30/06/2014

01/07/2014

02/07/2014

03/07/2014

04/07/2014

05/07/2014

06/07/2014

07/07/2014###

##
I

PREPARATORY WORK

##
###

1.1 PREPARATION

II

1-Jun-14

28-Jun-14

28

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

0.0041

CONSTRUCTION

##

2.1 EXCAVATION ( FOR FOUNDATION )

1-Jun-14

15-Jun-14

15

FINISH

2.2 BOR PILE & CONCRETE PILE CAP

4-Jun-14

16-Jun-14

13

FINISH

2.3 FOUNDATION 1M X 1M & CONCRETE COLUM

6-Jun-14

16-Jun-14

11

FINISH

2.4 STEEL STRUCTURE FOR CANOPY

25-Jun-14

1-Jul-14

0.0108

0.0108

0.0108

1-Jul-14

6-Jul-14

0.0104

0.0104

0.0104

2.6 EXCAVATION ( FOR DRAINASE )

26-Jun-14

2-Jul-14

2.7 DRAINAGE WORK

29-Jun-14

5-Jul-14

2.8 REMOVAL CONCRETE STOPER & CURB STONE

26-Jun-14

1-Jul-14

4-Jul-14

6-Jul-14

1-Jun-14

7-Jul-14

37

2.5 ROOFING WORK

2.9

CONCRETE FOR STOPER

2.10 REALIGMNET CURB STONE

III

CLEANING AREA

0.0031

ERECTION CANOPY IDLE

0.0031

0.0031

0.0031

0.0347

0.0347

##
###

0.0146

0.0146

0.0146

##

0.0108

0.0108

0.0108

0.0108

##
0.0108

0.0104

0.0104

0.0104

0.0104

###
0.0104

PROGRESS PHOTOGRAPH
Project
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Waste Area 1
: Karawang International Industrial City (KIIC) - Karawang

PROGRESS PHOTOGRAPH
Project
Owner
Location

: Sharp Electronic Indonesia New Factory Project


: Waste Area 1
: Karawang International Industrial City (KIIC) - Karawang

Вам также может понравиться