Вы находитесь на странице: 1из 4

System Commissioning Specifications, doc. No.: SCS_rA_dated15.04.

2012

Valid from 15th of April 2012 until further notice

1. System Commissioning Specifications


Rolls-Royce will provide a Commissioning Project Manager (CPM) and an optional Site
Commissioning Co-ordinator (SCC) for system commissioning support to allow an
efficient commissioning schedule to be developed and managed through to the
successful completion of sea trial.
The CPM shall manage all technical aspects of the commissioning and sea trial on
behalf of the contract manager. As part of this the CPM shall be accountable for the
following:

Point of Contact (PoC) for the Aftermarket Product Centers (APCs)


Interface to the shipyard
Managing the SCC
Liasing with the Contract Manager
Reporting out of scope work / delays
Monitoring and reporting project status internally and externally
Follow up of HSE issues within the project
Follow up of RCI and Non-Conformance (NC) reporting
Creating final commissioning report with red mark drawings and software as installed,
commissioning certificates and outstanding issues
Handover of contract (commissioning) to the Contract Manager

The optional SCC, reporting to the CPM, shall co-ordinate the commissioning and sea trials
on-site at the shipyard. They shall be accountable for the following:

Pre-commissioning
o Verifying equipment is correctly fitted according to specifications
o Reporting missing parts or damages
o Checking commissioning prequisites are met and reporting readiness for Service
Engineer attendance
Commissioning & Sea Trial
o PoC and co-ordination of Service Engineers
o Daily activities interface to the shipyard
o Participate in commissioning and sea trial work where applicable
o Manage site log
o Collecting and ensuring customer signed timesheets are delivered weekly
o Support the raising of RCI and NC actions
o Support of HSE issues on-site
Post Commissioning
o Gather red mark drawings and software as installed and certificates
o Return damaged and unused parts

2. System Commissioning Process


2.1 Organisation
A typical system commissioning organisation structure is shown in Figure 1 below.
The Contract Manager shall retain all commercial aspects of the project with the
Shipyard / customer and the CPM shall work on behalf of the Contract Manager for
all technical aspects of the commissioning. The optional SCC who will remain at the shipyard
during the course of the commissioning reports into CPM, dealing with the daily
activities on the shipyard.

-1-

System Commissioning Specifications, doc. No.: SCS_rA_dated15.04.2012

Valid from 15th of April 2012 until further notice

For all technical commissioning aspects of the project the CPM and SCC shall act as
the PoC to the shipyard, removing the need for the shipyard to deal with multiple
product centers and methods of working. On-site, the SCC shall co-ordinate RollsRoyce Service Engineers.

Figure 1: Typical organization structure

2.2 Pre-Commissioning
As part of the system commissioning activity, the CPM shall have an introductory
meeting with the Shipyard / Customer and Contract Manager 3 months prior to
estimated start-up of commissioning activities. At the meeting the CPM will accept
responsibility for the technical project management of all commissioning activities
related to Rolls-Royce Marine product deliveries. From this point the shipyard /
customer shall bring all technical installation and commissioning issues to System
Commissioning.
The CPM shall, in conjunction with the Shipyard, create an integrated commissioning
and sea trial plan for Rolls-Royce deliveries. The plan will break down equipment
commissioning into significant tasks with realistic timeframes for completion,
identifying task dependencies so that the shipyard can schedule installation and
commissioning of the vessel correctly and efficiently. Timeframes provided in the
System Commissioning plan are based on the assumption that all installation tasks
have been completed correctly in accordance with the installation manual.
The SCC shall attend the shipyard 2 weeks before commissioning is scheduled to
begin. The SCC shall support the yard during this period by checking that RollsRoyce equipment has been installed according to specifications. They shall also
report any missing parts or equipment damages, so that they maybe replaced /
repaired prior to commissioning as to avoid any delay to the completion of the vessel.
-2-

System Commissioning Specifications, doc. No.: SCS_rA_dated15.04.2012

Valid from 15th of April 2012 until further notice

This reduces the probability that Rolls-Royce will need to rectify any external nonconformance work during commissioning, which is invoiced to the purchaser.
Once equipment installation has been completed the SCC shall check that all
commissioning pre-requisites have been met for the equipment to ensure that the
product is ready to be commissioned. This will minimize the potential idle / waiting
time that the Service Engineer could face when arriving to commission a product that
is not ready. Waiting / idle time that is caused by others will be invoiced to the
purchaser and is not included as part of the commissioning hours sold in the
contract.

2.3 Commissioning
When an equipments readiness for commissioning has been established the CPM
shall call off the Service Engineer(s) to complete commissioning. The SCC shall
ensure that the Shipyard is briefed on any support that the Service Engineer
requires, such as lifting equipment or technicians, so that the Shipyard can prepare.
Throughout the commissioning the optional SCC shall remain present at the Shipyard
supporting commissioning activities. The SCC will co-ordinate the Service Engineers
onsite ensuring timesheets and commissioning reports are delivered and signed
regularly, support of HSE issues, support of NCs and RCIs, and participate in
commissioning and sea trial activities with the Service Engineers where relevant.
Additionally they will act as the interface to the Shipyard for commissioning activities
on a daily basis during the commissioning.
The CPM shall follow-up and manage technical issues arising from the
commissioning and provide regular reports to the customer. The CPM will generally
not be based at the Shipyard, although they will attend as and when required, but will
follow-up issues / actions raised during commissioning with the Rolls-Royce product
centers and Contract Management.
The CPM will regularly report to the Shipyard and Contract Manager with the status
of the commissioning. This report will cover but not be limited to the following:

Status of equipment installation and commissioning tasks


Recommendations / advice towards the successful completion of outstanding installation or
commissioning tasks as efficiently as possible
The Rolls-Royce Commissioning & Sea Trial plans, including an estimation of hours required
to complete remaining commissioning activities
Identification of potential issues / problems that could affect the commissioning and supporting
recommendations to mitigate these
Status of NC and RCI actions
Summary of commissioning hours used and remaining in the contract

2.4 Post Commissioning


The CPM shall take a close out meeting with the shipyard to reveiw the
commissioning and identify any outstanding issues. Once all work towards the
shipyard has been completed the CPM will take a commissioning handover meeting
with Contract Management to reveiw the project and hand responsibility back to
Contract Management.
-3-

System Commissioning Specifications, doc. No.: SCS_rA_dated15.04.2012

Valid from 15th of April 2012 until further notice

Upon the satisfactory completion of commissioning and sea trial System


Commissioning shall create and deliver a final commissioning report containing:

Red mark drawings and software as installed


Commissioning Certificates, per equipment and system
Punch list of outstanding issues
Overview of commissioning hours used versus contract
A lessons learnt summary

Document revision
Rev
Date
Sign
1
02.05.2012 KSH

Change pg

-4-

Description
System Commissioning Work
Methods

Вам также может понравиться