Академический Документы
Профессиональный Документы
Культура Документы
P)
Aditya College of Technology & Science
Satna (M.P)
CERTIFICATE
This is to certify that the project entitled as
national HIGHWAY CONSTRUCTIONS which has
been completed & submitted by CHANDRADEEP
SHUKLA , ABHINAV JAISWAL, AMAR DEEP GAUTAM ,
PRAKASH NARAYAN MISHRA
, PAWAN GAUTAM in
H.O.D
Principal
Guided By
Er.S.K.Gupta
Dr.J.S. Parihar
Er.S.K.GUPTA
(Civil Engg)
CERTIFICATE
This is to certify that the Project
entitled as
CHANDRADEEP
MISHRA
PAWAN GAUTAM
in
2013.
(External
Examiner)
(Internal Examiner)
ACKNOWLEDGEMENT
A Project report like this one involves many
people and would be incomplete without the
mention of all those people whose guidance and
encouragement
helped
in
the
successful
for
CHANDRADEEP SHUKLA
(0307CE091017)
ABHINAV JAISWAL
(0307CE091001)
AMAR DEEP GAUTAM
(0307CE091006)
DECLARATION
of
Engineering
4
in
CIVIL
CHANDRADEEP SHUKLA
(0307CE091017)
ABHINAV JAISWAL
(0307CE091001)
AMAR DEEP GAUTAM
(0307CE091006)
INTRODUCTION
NATIONAL HIGHWAY
PROJECT
DEFINITIONS
(ii) A BYEPASS
and
the bypass
may eventually
become as
motorist
from
driving
into
the
shoulder,
median,
sidewalk, or pavement.
in
title
to
such
person.
But
not
any
means
the
conditions,
the
10
manuals
means
the
priced
and
by
the
other
places
as
may
be
specifically
11
SETTING OUT
12
if
any,
shall
13
be
maintained
by
the
of
the
highway
must
be
accurately
satisfactory
to
the
engineer,
every
50m
in
or
near
the
fence
line,
and
schedule
of
commenced
until
the
centre
line
has
been
referenced.
The contractor will be the sole responsible party for
safeguarding all survey monuments, bench marks, etc.
The Engineer will provide the Contractor necessary for
setting out of the centre line. All dimensions and levels
shown on the drawing or mentioned in documents
forming part of the or issued under the contract shall
be verified by the Contractor on the site and he shall
immediately inform the engineer of any apparent error
in such dimensions. The Contractor shall in connection
with the staking out of the canter line, survey the
terrain along the road and shall submit the engineer
for his approval, a profile along the road centre line
and cross section at intervals as required by the
Engineer.
15
16
17
the
result
of
gradation
test
are
used
to
frost
etc.also
capacity
approximately
and
action,
pumping
permeability
some
estimated
other
based
of
rigid
characteristics,
properties,
on
grain
are
size
which are
19
measured
quantity
sieves.
The
weight
of
material
through
retain
on
each
sieve
is
greater than
APPARATUS:
Various apparatus set of standard sieves of different
sieves
size,
balance,
and
rubber
covered
pestle
CALCULATION:
The weight of dry soil fraction retained on each sieve
is calculated as a percentage of the total dry weight of
21
RESULT:
The gravel, silt sand clay contents are marked as
result.
22
or
may
content.
be
very
stiff
Plasticity
23
depending
is
on
the
property
of
shearing
force.
The
liquid
limit
is
usually
and
determined
in
the
laboratory
by
Hence
properties
are
generally
24
used
in
the
standardized
dimension
cut
in
the
sample
by
APPARATUS:
Mechanical liquid limit device consists of a cup and
arrangement
specified
for
height,
raising
and
grooving
dropping
tool.
Other
through
apparatus
PROCEDURE:
About 120 g of dry pulverized soil sample passing 425
micron sieve is weighted, and mixed thoroughly with
distilled
water
in the evaporating
dish
to
from
25
the
paste
is
placed
above
the
lowest
spot,
and
in
dried
in
oven
and
the
dry
weight
26
CALCULATION:
the flow index The flow cure is plotted by taking the
number of blows in the log scale on the x-axis, and the
water content in arithmetic scale on the y-axis, of
format sheet .the flow curve is straight line drawn on
semi-logrithmetic
plot.
The
moisture
content
For
index,
If=
W 1W 2
W 10W 100
log n2Logn1 = log10 100/10
=w
W 10W 100
27
APPARATUS:
Evaporating
dish,
spatula,
glass
plate,
moisture
PROCEDURE:
28
is
CALCULATION:
29
(III)
COMPACTION TEST
30
causes
decreases
ia
air
void
and
APPARATUS:
(a)
(b)
heavy
compaction,
the
rammer
has
cm
weight 4.89
container,
PROCEDURE:
In case of soil sample has particle bigger than 4075
mm sieve, about 20 kg of the representstive soil is air
dried, mixed pulerized and sieved through 20 mm and
4.75 m sieve is not use in the test the percentage
passing 20 mm sieve and retained on 4075 mm sieve
is noted and if this is less than 20 percen this sample
is used as such. It is more than this phenomenon is
repeated. In case the sample passes 4075 sieves, than
the bdry pulverized sample is sieved through 4.75 mm
sieve and the portion passing this sievesis only used
32
33
(2) For
heavy
compaction
the
wet
soil
mix
is
CALCULATION:
Let weight of mould copacted soil be = W1 g
Weight of empty mould =W2 g
34
Volume of mould = W
Wet density =
W 1W 2
W
g/cc
Wet Density
( 100+ M . C )100
RESULT:
The result are dry density and wet density.
35
is
desired.
The
CBR
test
may
be
laboratory.
U.S.
crops
of
engineers
have
also
APPARATUS:
Loading machine: Any compression machine which
can operate at a constant rate of 1.25 mm/minute can
be used for this purpose. If such machine is not
available then a calibrate hydraulic press with proving
ring to measure load can be used. A metal penetration
piston or plunger of a diameter 50 mm is attached to
the loading machine.
Cylindrical moulds: Mould of 150 mm diameter and
175 mm height provided with a collar of about 50
37
material
is
usually
NUMBER
WEIGHT
FALL,
NUMBER
COMPACTION
OF
OF
cm
OF
LAYERS
HAMMER,
Light
Kg
2.6
31
56
compaction
Heavy
4.89
45
56
BLOWS
compaction
Adjustable stem, perforated plate, tripod and dial
gauge: the standard procedure require that the soil
sample before testing should be soaked in water to
measure swelling.
Annular weight: in order to stimulate the effect of
the overlying pavement weight, annular weight each
of 2.5 kg and 147 mm diameter are placed on the
top of the specimen, both at the time of soaking and
testing the sample, as surcharge.
38
Beside
above
equipment,
coarse
39
filte
paper,
TEST ON
CEMENT
INTRODUCTION:
40
By drying sieving.
1. Blaine air permeability method.
2. By wet sieving.
41
43
OF
CEMENT
INTRODUCTION:
This test determines the quantity of water required to
produce a cement paste of standard consistency for
the use of other test. The vicat apparatus is used for
44
PROCEDURE:
Take 400g cement and add to it 30% water on a glass
plate or any non porous surface. Mix thoroughly and fill
the mould of vicat apparatus. The interval from the
time of adding water to the dry cement until
commencing to fill the mould is known as the time of
gauging and must be not less than 3 minutes and not
more than 5 minutes. Lower plunger gently to touch
the surface of test block and quickly release it,
45
46
47
INTRODUCTION:
The change of the cement paste from fluid to rigid
state may be referred to as setting. The gaining of
strength of a cement of a set cement paste is known
as hardening. During the setting, cement acquires
some strength, however it is not considered in
definition to distinguished setting from hardening,
where hardening is gain of strength of a set cement
paste.
48
49
PROCEDURE:
50
concrete.
The transportation of concrete from the place where
concrete is prepared to the placing of concrete
requires some finite time.
The maximum limits of the final setting time are
specified because the concrete should achieve the
desired strength as early as possible so that the
shuttering can be remove and reused.
INTRODUCTION:
Toughness is the property of the materials to resist
impact. Due to traffic loads, the load stones are
subjected to the pounding action or impacts and there
possibility of stones breaking into smaller pieces. The
road stones should therefore be tough enough to resist
fracture under impact. A test designed to evaluate the
toughness of the stones therefore the resistance of the
two fractures under repeated impacts may be called
52
APPARATUS:
54
PROCEDURE:
The test sample consist of aggregates passing
12.5mm sieves and retained on 10mm sieve and dried
in an oven 4 hours at a temperature 100oC to 110oC
and cooled. The aggregates are filled up to about one
third full in the cylindrical measure and tamped 25
times with rounded and of the tampering rod. Further
quantity of aggregates is then added up to about two
third full in the cylinder and 25 strokes of the tamping
rod are given. The measure is now filled with the
aggregates to over flow, tamped 25 times. The surplus
aggregates are stuck off using the tamping rod as
55
METHODOLOGY OF PQC.
SCOPE:
The work shall consist of construction of un-reinforced,
dowel jointed plain cement concrete pavements in
accordance with the requirements of MOST
specification and in conformity with the lines grades
and cross sections as shown on the approved
drawings. The work shall include furnishing of all plant
and equipment, materials and labour as directed by
the Engineer.
MATERIALS:
CEMENT:
Ordinary part land cement 43 grade confirming IS:
8112.
ADMIXTURES:
Admixtures used conforming to IS: 9625 and IS: 9103.
57
COARSE AGGREGATE:
The maximum size of aggregate is 20 mm. the coarse
aggregate complying with IS: 383
FINE AGGREGATE:
As approved in mix design confirm to IS: 383.
WATER:
It shall meet the requirement as stipulated in IS: 456.
58
Bitumen testing
59
61
REPORTING OF RESULTS
Bitumen content = [(A-B)/B]100 %
Repeat the test thrice and average the results.
Determining the Ductility Of Bitumen
This test is done to determine the ductility of distillation
residue of cutback bitumen, blown type bitumen and
other bituminous products as per IS: 1208 1978. The
principle is : The ductility of a bituminous material is
measured by the distance in cm to which it will
elongate before breaking when a standard briquette
specimen of the material is pulled apart at a specified
speed and a specified temperature.
The apparatus required for this test:
i) Standard mould
62
softening
point
until
it
becomes
of
the
specified
temperature.
REPORTING OF RESULTS
A normal test is one in which the material between the
two clips pulls out to a point or to a thread and rupture
64
The
apparatus
needed
penetration of bitumen is
i) Penetrometer
ii) Water bath
65
to
determine
the
SAMPLE
Bitumen should be just sufficient to fill the container to
a depth of at least 15mm in excess of the expected
penetration.
Procedure
to
determine
the
penetration
of
bitumen
i) Soften the bitumen above the softening point
(between 75 and 100oC). Stir it thoroughly to remove
air bubbles and water.
ii) Pour it into a container to a depth of at least 15mm
in excess of the expected penetration.
66
67
MACHINERY USED IN
CONSTRUCTION
68
Needle Vibrator
Water Pump
Bitumen Spryer
Welding set with Generator 8KVA
Mechanical Boomer
Vehicles
Water Tanks
70
71
72
73
74
75
SUGGESTION AND
CONCLUSION
1. Civil engineer should perform the work at their
level best so that it will give better result and
improve the production of the company.
2. Infrastructure of Civil Contractor Cell should be
more developed for giving the contract to the
best contractor.
3. Welfare facilities should be increase in for civil
engineers of Construction Company.
4. For the safety of civil engineers at the
construction, company should give the best
equipments of safety to the civil engineers.
5. The hostel facility and amenities should be
improved so that the civil engineers could work
with more efficiency.
6. The civil engineers are advised to do their work
in slot as they do it bulk which create adverse
problems for example the road was dug during
the rainy season in one flow which resulted in
heavy loss of material, money and machinery of
the company. The work should have been done
76
77
BIBLIOGRAPHY
79