If project content is allowed to change freely, the rate of change will exceed
the rate of progress.
If any can go wrong, it will.
What is a Project
A project is a planned non repetitive enterprise undertaken to achieve planned result
within a time limit and a cost budget with Limited Resources.
1 - SITE ENVIRONMENT
Physical
Location of Site
Weather
Facilities available
Conveyance
Accommodation
Food
Local Language
Entertainment
Connectivity
Banks / Schools / Hopitals
Safety & Security
Behavioral
Interpersonal Relations
Motivation
Commitment towards Organization / Project Goal
Sense of Belonging
Recognition
Growth Potential
Organizational Culture
Social
Land Acquisition / Compensation
Political
Sons of the Soil
Environmental / Ecological
Socio / Cultural Factors undesirable activities / conditions around Project
2 - HR ACTIVITIES AT SITE
Various Acts Applicable to SITES:
Contract Labour (Regulation & Abolition) Act 1970
Employees Provident Funds And Miscellaneous Provisions Act, 1952
Employees State Insurance Act 1948
Equal Remuneration Act 1976
Minimum Wages Act 1948
Payment of Bonus Act 1965
Payment of Wages Act 1936
Personal Injuries (Emergency Provisions) Act 1962
Weekly Holidays Act 1942
The Child Labour (Prohibition and Regulation) Act 1986
Workmens Compensation Act 1923
Labour Welfare Fund Act 1953
IMPORTANT POINTS DURING SITE MOBILIZATION:
INSURANCES
Transit Insurance
Erection All Risk / Storage cum Erection Insurance
WC insurance
CONTRACT LABOUR LICENCE:
First apply for Certificate of Registration to ALC or DLC as may be the case and
then issue Form V to your Contractor for him to apply and obtain Labour License
for maximum number of workmen to be employed at site.
PF CODE :
Each Contractor has to obtain PF Code for workmen engaged by him.
ESI REGISTRATION :
Each Contractor has to obtain ESI Registration if the area of work is covered
under ESI. Other wise WC Insurance needs to be taken by the contractor.
MAINTENANCE OF VARIOUS REGISTERS / RECORDS
2
Ensure that All the required Records / Registers are properly maintened.
REFER THE CHECK LIST GIVEN AS HARD COPY.
3 PLANNING SITE ACTIVITIES
OPENING THE SITE
Site Mobilization
First Survey Collect all information
Scout Party
Establish Base Camp
Establish Communication
Contractor / Labors
Construction Equipments
You have now MOBILIZED THE SITE.
Inform HO / Client as usually it is linked to release of Payments
All Capital Goods / Plants are usually very long delivery and cost intensive items
which need to be ordered much before Site is born
Just in Time concept has less importance especially in India. It changes to NOT
AT SITE = NOT AVAILABLE WHEN NEEDED.
For major requirements Project team should decide the Supplier, Rates and
Delivery Schedule well in advance, i.e. for items like
o Cement
o Steel Sections / Rounds
o Stone / Sand
o Construction Equipments
o Cables
o Bulk & special Consumables
Major Responsibilities of Site Purchase Team is
Those items which are procured in Bulk, is available near site and quantity
is huge e. g. Sand, Bricks, Stone, Diesel etc. for which Transportation is
also substantial (some times even water)
Emergency Procurement of
Spare Parts
Consumables
Short Supplies by Plant/Equipment supplier
Damaged Parts
Chasing all suppliers
Escorting-when Over Sized Equipment has reached your vicinity
Difficulties experienced during site purchases
Requirement is known only at the last moment
Unknown market
Lack of correct specification
Lack of supporting infra structure
5
Insist for Test Certificates of All Material Handling and Lifting Equipments, Tools &
Tackles, Electrical Equipments to be obtained from Competent Authorities.
Check for Physical Appearance of All Material Handling and Lifting Equipments, Tools
& Tackles, Electrical Equipments.
CHECK FOR DRINKING HABITS OF ALL OPERATORS AND ENSURE THAT NO
BODY REPORTS ON DUTY IN DRUNK CONDITION.
MONEY:
Only thing required from Site Manager is Cash Flow.
Usually Corporate Policy Decides Mode of transfer of Funds and Authorization to use
and withdraw money.
How much and when will be decided to suit Project Execution Planning.
As far as possible try to use minimum possible CASH at site.
Plan for secured withdrawal and carrying cash to site.
If Site and Bank is far apart, and money you handle is large, let proper Agency handle it.
Take proper Insurance coverage for Cash Carrying.
As far as possible withdraw in smaller amounts.
Use Cheques as far as possible for money disbursement.
Ensure that your Budget and Requisition is sent in Time.
As Site Manager ensure that Site Account is sent in proper format and in time. At times
there may be some requirement to spend beyond your authorization. Such situations need
to be tackled individually and in accordance with your Corporate Policy.
5 - SITE ORGANIZATION
Requirement of Site Organization
1- Size of Organization should match with Project Requirements like total value,
duration, Technical complicacy, Various Functional Requirements, Site conditions
etc.
2- Requirements and Policies of Parent Organization and Client i.e. Some
Organizations Insist on very Elaborate Reporting Systems, for some Account is
more important, Some insist on close monitoring of Expenses and Purchases,
Some client insist for separate Safety Officer, Engineer QC, Labor Officer etc.
3- No. of workers / contractors
4- Build a Team, not rival Groups
5- Authorities and Responsibilities should be clearly defined
6- Communication Channel should be clearly Defined
7- As far as possible work should be divided in such a way that one gets the type of
work he is expert in and has only one Head to report.
8- Though work is divided, there should not be a Water Tight Compartment for areas
of work so that there is awareness of work status and requirement to other persons
too and each one can contribute in over all Site Working.
To control and co-ordinate all steps of the Project effectively and efficiently during
the necessary period of the project, we will be fully responsible for the following
phases of the project :
1.
2.
3.
1.
Project Management.
Field Construction.
Quality Control and Assurance.
PROJECT MANAGEMENT
Planning.
Budgeting.
Scheduling.
Forecasting.
Reporting.
a)
b)
c)
Management Schedule.
Project Schedule.
Control Schedule.
d)
e)
Reporting :
categories
Progress Report
Cost Report
Financial Report
PROGRESS REPORT
includes narrative discussion and
utilizes tabulations and progress curves to depict and highlight
project accomplishments during the month.
The relative information shall be compiled from both main office
and the job site.
This report shall be expressed in percentage by comparing the
completed works with those of forecast.
COST REPORT
IS DESIGNED TO SUMMARIZE THE
PREVIOUS MONTHS COST ACCUMULATES total cost to
date and present a forecast of future expenditure with monetary
status statement in relation to contract budget.
This information shall be also compiled from both main office
and job sites and includes narrative discussion utilizing
tabulation and graphics to depict the overall project status.
10
2.
FIELD CONSTRUCTION
Before field construction begins the following construction planning activity
shall be performed by the construction manager in conjunction with the
overall project planning and engineering.
a)
be
included
in
the
construction
11
b)
Field Engineering :
Field Engineering shall include the establishment of horizontal and
vertical survey control points, engineering document control,
drawing and specification interpretation, quality and general office
engineering functions.
Following functions shall be included in the Field Engineering
Services.
c)
Administrative Service :
Administrative Services include receiving, administering and
accounting for the project expenses, developing procedures in
method and report and assisting in Government and Public
Relations, as required.
Following functions shall be included in the Administrative Service.
d)
Material Services :
Material Services include receiving, inspecting, sorting and issuing
materials and equipments, establishing procedures to meet site
13
e)
14
f)
Labour Relations :
Labour Relations consist of all personnel functions for Construction
Management Staff. Supervision of labour relations pertain to the
execution of contract, establishing and monitoring safety
programme and executing a security programme in accordance
with the project policy.
Following functions shall be included in Labour Relations Services
15
3.
a)
Quality Assurance.
Quality Control.
Inspection.
Quality Assurance :
Quality Assurance Engineer checks the quality control and
inspection records to make certain correctness of quality
requirements, correct interpretation and inspection as well as
proper documentation. He also ensures that the quality control
problems are brought to the attention of Construction Manager.
b)
Quality Control :
Quality Control Engineer is responsible for publishing quality control
procedure to comply with the requirements of quality control and to
assure that the system is constructed in accordance with good
construction practices. Procedures state the measurements and
tolerances of the tools / equipments and techniques to be used to
complete the inspection for acceptance of the item. All these
procedures are reported and properly documented.
c)
Inspection :
16
18
19
8 - BILLING
Site Invoicing depends on Type of Project, Price Structure (whether Taxes &
Duties are included in price), Supply & working methodology and Payment
Terms. It can be classified into following categories:
A- Invoicing for Supplies B- Invoicing for Services / Labor Jobs
Invoicing for Supplies attracts various taxes and duties where as for
Labor Jobs it is Service Tax
Civil works on only - unit labor rate basis for this site measurement has to be
certified at site in MB
Civil work including material supply on Total LS Basis for this work done is to
be certified at site
Total Plant Supply for this Billing Breakup (based on Mile Stones) is prepared,
got approved by client, then Mile Stone Wise Invoicing is done
For Direct Bought-out some times Sale in Transit is preferred.
Records Needed for Site Billing
Depending on Size of Project and Policies of Organization first decide whether all
Invoicing will be from HO or Site.
20
Deciding Factors:
1. Size of Project
2. Value of Project
3. Organizational Policies
4. Duration of Site Activities
5. Payment Terms
6. Facilities available at site
7. Taxes and Duties
8. Payment mode of Client
9. Location of Bankers
Some Organizations prefer all Invoicing from HO only where as for some all Supplies are
billed from HO and Labor works are invoiced from Site.
Requirements for Invoicing: Appropriate Staff for Measurements
Proper Infrastructure for Record Keeping
Proper Knowledge about Taxes and Duties
Correct understanding about Contract Terms & Conditions
Advantages of HO Billing
Centralized Recording
HO gets Automatic confirmation of Progress
Better control on over all Cash Flow
Better management of Tax Burden
Better management of Bank Facilities
Coordination with HO
1 Communication
2 Reporting
Progress
Commercial
Requirements of Material/Resources
Technical Clarifications/Modifications
Discussions/MOM
3 Movement of Materials
4 Movement of Personnel
5 Movement of Documents
6 Queries regarding suppliers/contractors & their services
IT SHOULD BE ONE TO ONE COMMUNICATION ONLY
The Project Manager at Site should communicate with one Designated Coordinator in
HO and vice versa.
Procedure:
21
1.
2.
3.
4.
5.
6.
7.
Sr.
Report
No
.
1. Site Report
To
Responsibility
/ sender
HOD
Site In Charge
2.
Site Account
HOD
3.
Copy of Site
HOD
Site In Charge /
Commercial
Officer
Site In Charge /
Mode of Frequency
Despatc
h
Fax/e
Daily
mail
Courier
Courier
22
Vehicle LogBook
4. Copy Constn.
Eqpt. LogBook
5. Site Staff
Attendance
Record
6. Site Labour
Attendance / OT
Record
7. Summary of
Labour
Attendance & OT
8. Copy of Inward
Register
9. Er. Equipment
List
10. Site Fund
Requisition
11. Accident Report
HOD
P&A
HOD
CO.
Site In Charge /
CO.
Site In Charge /
Commercial
Officer
Site In Charge /
CO
Courier
Courier
Monthly on
3rd
HOD
Site In Charge /
CO
Fax / e
mail
Monthly on
1st
HOD
Courier
HOD
Site In Charge /
CO
Site In Charge /
CO
Site In Charge
HOD
Site In Charge
Fax e
mail
Phone /
Fax / e
mail
Monthly on
1st
Monthly on
10th
Monthly on
25th
Immediate
Site In Charge /
CO
Fax e
mail
HOD
(if necessary
even at
Residence)
12. Receipt of
Damaged / Short
Consignment
Courier
2nd
Monthly on
2nd
Monthly on
2nd
HOD /
Stores
Courier
Immediate
DE-MOBILIZATION OF SITE
IT ALL DEPENDS ON TYPE AND SIZE OF PROJECT
Major Activities:
1. Obtain work completion Certificate
2. If it is a Process Plant then Hand over site to Commissioning Team
3. Complete following:
a. Invoicing
b. Material Reconciliation
c. Certification of Measurements
d. Certification of Subcontractors bills & make their Final Bill
e. Get Subcontractors consent of Final Summery including Debit/Credit
Notes if any.
f. Close Site Account / Bank Account
g. Make Final Summery of all pending Points
h. Ensure that all subcontractors have paid Full & Final Payments to their
labors and take their undertaking to this effect
23
i. Take All Dues Cleared Certificate from your direct suppliers as well as
from those which supplied to Subcontractors.
j. Serve Proper Notice of Closure of all Activities to all Concerned Govt.
Departments.
k. Ensure that all Telephones / Mobiles are suitably returned / disconnected
( if not done this can be very serious HAZARD in future )
l. Dispose off Scrap as per Company Policy.
m. Make a detailed report of Pending Insurance claims.
n. Segregate All Documents as below and take appropriate action:
i. Commercial Documents to be Preserved and sent to HO with List
and Receipt
ii. Contractual Documents to be Preserved and sent to HO with List
and Receipt
iii. Documents to be handed over to Client with Receipt make a
copy to be sent to HO
iv. Documents which can be destroyed
o. Discontinue hired vehicles etc. and vacate Hired Residences
p. Demolish or Hand over all temporary construction to client as may be
required.
q. Retrench all Temporary staff / workers hired directly.