Академический Документы
Профессиональный Документы
Культура Документы
ABSTRACT: An underpass was constructed recently in Bangalore using soil nailing, box jacking and the geotechnical
aspects and these techniques are reported in this paper. The construction procedure and various aspects of the
construction are also discussed. Soil nailing technique has been used extensively throughout the project to improve the
stability of excavated vertical cuts. Soil nailing and the underpass are examined by detailed numerical analysis using
FLAC3D. A few results of the analysis of excavations stabilized using nailing and the construction of underpass are given
in the paper.
1. INTRODUCTION
For the construction of underpasses, soil nailing and box
jacking techniques have been used. With the soil nailing,
stabilization of excavations was made for approach roads
of the underpass and, box jacking was used to push and
place the concrete box elements without disturbing the
traffic above. The concept of soil nailing consists of
placing the closely spaced soil nails to increase the overall
shear strength of the in-situ soil and restrain its
displacements during and after excavation. The main
advantage of the soil nailing lies in its relatively low cost
and requires small equipment to drive the nails, as
compared to conventional construction of retaining wall
system and also in terms of saving of space and time
without interrupting the moving traffic on the road above.
The adaptability of soil nailing to different site conditions
and its capacity to withstand large total and differential
settlements than conventional structures, particularly in
earthquake prone areas prompts engineers for its use.
1.1
It is a non-intrusive method for constructing a new underbridge, culvert or subway beneath existing surface
infrastructure, for example railways and highways. The
method enables traffic flows to be maintained throughout the construction period, and maintained with only
minor restrictions during the brief period of tunneling.
The inconvenience and costs of disruption to
infrastructure and traffic flows experienced with
traditional construction methods can be avoided.
Typically, an open-ended reinforced concrete box is cast
on a jacking base adjacent to the road where the underpass
Soil nailing
759
Red soil
18 kN/m3
19 kN/m3
Nail
Property
20,000 kN/m2
15 kN/m2
Friction angle ()
26
0.28
210E06 kN/m2
0.02 m
0.30
2.
760
tan input
tan reduced
c input
c reduced
FS =
amit
FS
Displacement
(mm)
0.52
1600
17.12
II
1.48
13.38
0.20
Rotation:
X: 10.000
Y: 0.000
Z: 0.000
Mag.:
1
Ang.: 22.500
Center:
X: 5.000e+000
Y: 5.000e+000
Z: 4.998e+000
Dist: 3.434e+001
Rotation:
X: 20.000
Y: 0.000
Z: 10.000
Mag.:
1
Ang.: 22.500
761
Pathway
Carriageway
Carriageway
ACKNOWLEDGEMENTS
762