Академический Документы
Профессиональный Документы
Культура Документы
Q. 2003 / 6(b) : Activities of a project are described below. Calculate the following
1.
2.
3.
4.
ACTIVITY
ESTIMATED
DURATION
3
1
2
7
8
3
1
2
A
B
C
D
E
F
G
H
IMMEDIATE
PREDECESSORS
A
A, B
A, D
B
E, F
D
Answer
ACT
A
B
C
D
E
F
G
H
ES
EF
LF
LS
TF
FF
DUR
3
1
2
7
8
3
1
2
=
=
=
=
=
=
=
=
=
PRED
A
A, B
A, D
B
E, F
D
SUC.
B,C,E
C,F
E,H
G
G
-
ES
0
3
4
0
7
4
15
7
EF
3
4
6
7
15
7
16
9
LS
4
11
14
0
7
12
15
14
LF
7
12
16
7
15
15
16
16
TF
4
8
10
0
0
8
0
7
FF
0
0
0
0
0
8
0
0
Total time taken for the project is 16 days and the critical path is D-E-G as the total
floats for these activities are zero.
A urobindo
Page 1 of 23
IMMEDIATE
PREDECESSOR
A
B
A
C,D
C,D
E,F
G
DURATION
NORMAL
CRASH
5
3
5
1
10
5
7
2
6
2
11
5
6
4
5
1
4
1
Answer :
ACT
PRED.
SUCC
A
B
C
D
E
F
G
H
I
A
B
A
C,D
C,D
E,F
G
C,E
D
F,G
F,G
H
H
I
-
Cost Slope
(Cost / Duration)
DUR
N C
5 3
5 1
10 5
7 2
6 2
11 5
6 4
5 1
4 1
COST
N
C
400
600
300
500
400
700
400
600
300
500
600
930
300
600
200
400
200
500
3100 5330
ES
EF
LS
LF
TF
FF
0
0
5
5
5
15
15
26
21
5
5
15
12
11
26
21
31
25
0
3
5
8
20
15
21
26
27
5
8
15
15
26
26
27
31
31
0
3
0
3
15
0
6
0
6
0
0
0
3
15
0
0
0
0
E
A
A urobindo
COST
SLOPE
100
50
60
40
50
55
150
50
100
TECH. SEQ.
P1 : AE H
P2 : ACFH
P3 : ACGI
P4 : BDFH
P5 : BDGI
ND
16
31
25
28
22
CD
6
14
13
9
8
Page 2 of 23
CRASH
ACTIVITY
F&H&C
BY
DAYS
3
P1
P2
P3
P4
P5
16
13
31*
22
25
22
28
22
22
22
ACT.
COST
3100
CRASH
COST
495
The extra fund available to crash the project is limited upto Rs.500,000. Considering
the technological sequence the Normal Duration (ND) of Path P2 : ACFH is 31 days.
Hence, we take activities in this path for crashing first. In the path the cost slope of
activity A is 100, C is 60, F is 55 and H is 50. Considering 3 days crashing of each
activity F, H & C the crashing cost comes to 3 x (50+55+60) = Rs.495,000 which is
within the limitation of Rs.500,000.
Hence the project can be crashed by 9 days to finish in 22 days.
A urobindo
Page 3 of 23
Immediate
Predecessor
Estimated
duration in
days
Budgeted
Cost of
activity
A
B
C
D
E
F
G
H
I
j
A
B
B
D
E
C
F
G
3
1
4
4
5
2
3
4
2
3
600
200
800
700
500
200
500
400
600
300
% of
Completion
at end of 7
days
100
100
75
100
95
80
50
0
0
0
Answer
Act.
Pred.
Dur.
Bud.
Cost
A
B
C
D
E
F
G
H
I
j
A
B
B
D
E
C
F
G
3
1
4
4
5
2
3
4
2
3
600
200
800
700
500
200
500
400
600
300
4800
% of
Completion at
end of 7 days
100
100
75
100
95
80
50
0
0
0
BCWP
600
200
600
700
475
160
250
0
0
0
2985
%
Scheduled
Completion
100
100
100
100
100
100
33.33
0
0
0
BCWS
600
200
800
700
500
200
167.7
0
0
0
3167.7
A urobindo
Page 4 of 23
Gantt Chart
Act.
10
11
12
A
B
C
D
E
F
G
H
I
J
Date of reporting
Cost Performance Indices (CPI)
= BCWP/ACWP = 2985 / 3100 = 0.96
Schedule Performance Indices (SPI) = BCWP/BCWS = 2985 / 3167.7 = 0.94
Cost of Completion = Budgeted Cost / CPI = 4800 / 0.96 = 5000
Time of Completion = Scheduled Duration/SPI = 12/0.94 = 12.76 i.e. 13 days
Q. 2003 / 2(b)
Following data is available about actual sales for the past 14 years.
YR
Sales
1
2.3
2
2.2
3
2.0
4
2.25
5
2.60
6
3.0
7
3.5
8
4.1
9
3.8
10
4.0
11
4.3
12
4.2
13
4.8
14
5.2
Find the Forecast for the yr 15 using Two Years as well as three years moving
averages. Which of the two forecasts is more reliable on the basis of Mean Squared
Error (MSE) criterion ?
Q.2003 / 3(b)
Q. 2003 / 4 (b)
A urobindo
Page 5 of 23
Answer :
Introduce
C
2
D2
LA (0.36)
Not-Introduce
Favourable (0.5)
C1
Test
Un-favourable (0.5)
HA (0.16)
Introduce
C
3
D3
D1
LA (0.84)
Not-Introduce
NoTest
HA (0.40)
Introduce
C
4
D4
LA (0.60)
Not-Introduce
A urobindo
Page 6 of 23
Hence the decision is to go for test marketing and then introduce the new car.
Q 2002 / 6 (b)
A new pharmaceutical product is to be released on a deadline for which 44 days are
left. Activities involved in product launch with their interdependencies and
probabilistic times for completion are given in the table. Draw a project network and
find the probability of completing the project in time.
Activity
A
B
C
D
E
F
G
H
I
J
K
L
Predecessor
A
A
B
D
C
D
G
C,G
I
H
J, K
Optimistic
6
1
16
3
2
7
1
1
2
2
1
1
Time Delays
Most Likely
10
2
20
5
3
10
2
3
2
3
1
2
Pessimistic
14
3
30
7
4
13
3
5
2
4
1
3
Extract from Z value table with some cumulative probabilities for normal
distribution curve is given.
Answer : Project estimation
Maximum Time or Pessimistic Time (tp)
Minimum Time or Optimistic Time (to)
Most Likely Time (tm)
Average Time (ta ) = (to + 4 tm + tp ) / 6 ------- Classical Formula
A urobindo
Page 7 of 23
Act.
Pred.
Succ.
Duration
ES EF LS LF
(to)
(tm)
(tp)
(ta )
A
B,C
6
10
14
10
0
10 10 10
B
A
D
1
2
3
2
10 12 26 28
C
A
F,I
16
20
30
21
10 31 10 31
D
B
E,G
3
5
7
5
12 17 28 33
E
D
2
3
4
3
17 20 38 41
F
C
7
10
13
10
31 41 31 41
G
D
H,I
1
2
3
2
17 19 33 35
H
G
K
1
3
5
3
19 22 35 38
I
C,G
J
2
2
2
2
31 33 36 38
J
I
2
3
4
3
33 36 38 41
K
H
L
1
1
1
1
22 23 38 39
L
J, K
1
2
3
2
36 38 39 41
Calculate average time considering the Classical formula and this is
for calculating ES,EF,LS & LF.
TF
Var
Var2
0
16
0
16
21
0
16
16
5
5
16
3
to be
1.33
1.77
2.33
5.43
1.0
1.0
considered
As highest EF is 41, the LF of all activities with no successors i.e last activities E,F,J &
L will be 41. Then the LS can be calculated.
ACF are critical activities as there is no float available. As the distribution would be a
normal distribution we have to calculate the variance of critical activities only.
Variance of critical activities = (tp - to ) / 6
________
(var)
_____
=
8.196 = 2.86
= 41
+1 = 43.86
+2 = 46.72
+3 = 49.58
-3 -2 -1
+1
-1 =38.14
-2 = 35.28
-3 = 32.42
+2 +3
There is very remote chance that the project will go beyond +3 = 49.58 i.e. 50
days i.e. 99.9 % chance . The earliest time period during which the project can be
completed is 32 days i.e. -3 = 32.42 i.e. 0.001 % chance. To find out the
possibility that the project can be completed in 44 days :
Z = (Desired Duration- Minimum Duration)/ = (44-41)/2.86 = 1.049
Z value of 1.049 from the normal distribution table is 0.8531 and hence the
possibility of completing the project within 44 days is 85.31%.
A urobindo
Page 8 of 23
Cost (Rs.000)
Normal
Crash
24
34
12
22
20
28
29
47
26
34
34
52
27
47
34
48
The project attracts a penalty of Rs.10,00 per day for the project completion beyond
18 days. Draw the project network by PDM(AON) method and find out the number of
days delay intended beyond the stipulated date to minimize the total project cost.
Answer :
ACT
PRED.
SUCC
A
B
C
D
E
F
G
H
A
A
B
B
C, E
D, F
C,D
E,F
G
H
G
H
-
Precedence Diagram
( Activity on Node)
DUR
N C
5 4
4 3
5 3
7 4
6 5
8 5
10 6
9 7
COST
N
C
24
34
12
22
20
28
29
47
26
34
34
52
27
47
34
48
206
COST
SLOPE
5
10
4
6
8
6
5
7
ES
EF
LS
LF
TF
FF
0
0
6
6
4
4
11
13
6
4
11
13
10
12
21
22
0
1
7
6
6
5
12
13
6
5
12
13
12
13
22
22
0
1
1
0
2
1
1
0
0
0
0
0
1
1
0
0
C
A
D
E
B
TECH. SEQ.
P1 : A-C-G
P2 : A-D-H
P3 : B-E-G
P4 : B-F-H
ND
21
22
20
21
CD
13
15
14
15
A urobindo
Page 9 of 23
CRASH
ACTIVITY
A
H
G&H
0
1
2
3
BY
DAYS
1
1
1
P1
P2
21
20
20*
19
22*
21*
20*
19
P3
20
20
20*
19
P4
ACT.
COST
206
206+5
211+7
218+12
21
21*
20*
19
PENALTY
COST
40
30
20
10
TOTAL
COST
246
241
238
240
1st crashing : P2 (A-D-H) as this sequence takes maximum no. of days. Activity A is to be
crashed as this activity has the minimum slope amongst the three activities involved in this
sequence.
2nd Crashing : P2 & P4 as this sequence has the maximum no. of days after the first crashing.
Activity H is to be crashed as this activity has the minimum cost slope.
3rd crashing : All paths as all have equal no. of days. This is to test whether the total cost
increases or decreases after the previous crashing. Activity G & H are to be crashed as the
cost slopes are minimum in these cases.
As the total cost goes up in 3 rd crashing, it is advisable to adopt Sr.No.2. ie. Pay penalty for 2
days and complete the project in 20 days instead of 18 days.
Q.2002 / 8 (b)
The following information is available at the end of day 40 of a new plant erection project.
Determine if the project is under control based on Earned Value evaluation system, and if not,
what is the likely extent of cost and time over-runs at completion.
Activity
Predecessor
A
B
C
D
E
F
A
A
C
B,D
E
Duration
10
8
12
0
18
16
Total Budget
In Rs.000
300
400
350
0
405
450
Act.
%
of
completion
100
100
100
0
70
0
Answer :
Act.
Pred.
Dur.
A
B
C
D
E
F
A
A
C
B,D
E
10
8
12
0
18
16
Total
Budget
In Rs.000
300
400
350
0
405
450
1905
Act. Cost
till date
Act. % of
completion
EV=BCWP
% Sched.
Completion
250
450
380
0
400
1905
100
100
100
0
70
0
300
400
350
0
283.5
0
1333.5
100
100
100
0
100
0
BCWS
300
400
350
0
405
0
1455
A urobindo
Page 10 of 23
10
10
10
18
22
10
12
18
22
22
40
40
56
16
22
0
From the above diagram it can be seen that at the end of 40 th day all activities upto
should be completed as per schedule. Hence, percentage of scheduled completion
will be 100 % for all activities upto E, although the actual % of completion of E is
only 70%.
Cost Performance Indices (CPI)
= BCWP/ACWP = 1335.5/1480 = 0.90
Schedule Performance Indices (SPI) = BCWP/BCWS = 1335.5/1455 = 0.92
Cost of Completion = Budgeted Cost / CPI = 1905 / 0.90 = 2116.7
Time of Completion = Scheduled Duration/SPI = 56/0.92 = 60.9 i.e. 61 days
Hence the cost over-run would be Rs.211,700.00 and the duration for completion
would be 61 days instead of 56 days.
A urobindo
Page 11 of 23
Q. 2001 / 6 (b)
Following table lists the various details of project activities
Activity
Predecessor
DURATION in WEEKS
(to)
(tm)
(tp)
A
1
1
7
B
1
4
7
C
2
2
8
D
A
1
1
1
E
B
2
5
14
F
C
2
5
8
G
D, E
3
6
15
1. Draw the project network using the AOA convention and identify all paths through
it.
2. Find expected average duration and variance for each activity.
3. What is the expected duration of the project with 50% chance of completion
4. What would be your level of confidence to accept the project deadline of 20
weeks
Note : A normal distribution curve covers 50.0%, 84.1% and 97.7% area to its left
for 0, +1 and +2 SD from the mean respectively.
Answer :
(i) Project Network Diagram using AOA convention
A(2)
1
D(1)
B(4)
3
E(6)
G(7)
6
F(5)
C(3)
4
(ii) Average Time (ta ) = (to + 4 tm + tp ) / 6
Act.
ES
EF
LS
LF
TF
Var
0
0
0
2
4
3
10
2
4
3
3
10
8
17
7
0
9
9
4
12
10
9
4
12
10
10
17
17
7
0
9
7
0
9
0
1
1
1
0
2
1
2
A
B
C
D
E
F
G
Pred
.
A
B
C
D, E
A urobindo
DURATION
(to)
(tm)
1
1
1
4
2
2
1
1
2
5
2
5
3
6
in WEEKS
(tp)
(ta )
7
2
7
4
8
3
1
1
14
6
8
5
15
7
Var2
4
4
Page 12 of 23
Standard Deviation
: = (var)
__
9 = 3.0
50 %
84.5 %
97.3 %
= 17
+1 = 20
+2 = 23
99.9 %
-3 -2 -1
+1
+2 +3
A(9)
1
B(8)
C(15)
SR.NO.
0
1
2
3
4
CRASH
ACTIVITY
E
C
F
A urobindo
Critical Path :
P1 : B-E-F = 20 Days
D(5)
E(10)
F(2)
5
dummy(0)
BY
DAYS
4
1
1
P1
20*
16
16
15
P2
16
16
16
15
P3
17
17*
16
15
Crash
Cost/day
15000
30000
40000
60000
90000
130000
Page 13 of 23
700
600
500
400
300
200
100
M
ay
-0
Ju 1
n01
Ju
l-0
A 1
ug
-0
Se 1
p0
O 1
ct
-0
No 1
v0
De 1
c0
Ja 1
n0
Fe 2
b0
M 2
ar
-0
A 2
pr
-0
M 2
ay
-0
Ju 2
n02
Ju
l-0
A 2
ug
-0
Se 2
p0
O 2
ct
-0
No 2
v0
De 2
c02
Tim e
The cost of a project rises gradually, then rises steeply and towards the completion
of the project slows down again, thus resembling the alphabet S.
A urobindo
Page 14 of 23
Investing this amount in existing business will given assured return of 8%.
Alternatively , the amount can be invested in diversification, which if:
1. successful will give estimated return of 17% and
2. unsuccessful will give estimated return of 2%.
In a decision tree analysis, Decision points are mutually exclusive and are
represented by a small box
, whereas chance points are represented as
8%
Existing business
D1
successful
17%
Diversification
C
1
unsuccessful
2%
A urobindo
Page 15 of 23
8
B(5)
A(3)
K(2)
D(4)
G(5)
C(7)
H(8)
E(6)
L(4)
F(4)
Critical Path : A- C- E G H - L
PRED.
A
A
B
C
C
D,E
G, F
G
H, K
SUCC.
B,C
D
E,F
G
G
H
H,K
L
L
-
DUR
3
5
7
4
6
4
5
8
2
4
ES
0
3
3
8
10
10
16
21
21
29
EF
3
8
10
12
16
14
21
29
23
33
LS
0
7
3
12
10
17
16
21
27
29
LF
3
12
10
16
16
21
21
29
29
33
21
21
TF
0
4
0
4
0
7
0
0
6
0
FF
0
0
0
4
0
7
0
0
6
0
12
D
5
10
16
10
16
ES
EF
23
12
16
21
27
29
29
E
7
12
16
L
6
10
33
4
10
16
10
14
29
21
33
29
TF
H
4
FF
DUR
LS
LF
A urobindo
17
21
21
29
Page 16 of 23
1
2
3
4
5
6
7
8
9
10
TOTAL
1.
2.
3.
4.
5.
6.
7.
% Completion
Scheduled Actual
(A)
(B)
100
100
100
100
70
60
55
50
30
25
10
0
0
0
0
0
0
0
0
0
BCWS
BCWP
Cost Variance
CPI
SPI
Cost of Completion
Time of Completion
=
=
=
=
=
=
=
BCWS
BCWP
(AXC)
10
12
12.6
13.75
6
1.5
0
0
0
0
55.85
(BXD)
10
12
10.8
12.5
5
0
0
0
0
0
50.3
Cost
Variance
0
0
-1.8
-1.25
-1
-1.5
0
0
0
0
-5.55
Rs.55.85 lakhs
Rs.50.3 lakhs
BCWP-ACWP = 50.3 55.5 = -5.20
BCWP/ACWP = 50.3/ 55.5 = 0.91
BCWP/BCWS = 50.3/ 55.85 = 0.90
Budgeted Cost / CPI = 130/0.91 = Rs.142.86 lakhs
Sch. Duration/SPI = 35/0.90 = 38.89 i.e. 39 weeks.
A urobindo
Page 17 of 23
(7)
(14)
(11)
(4)
(5)
(7)
(6)
(18)
6
(11)
Act
Var
Var2
2
2
4
1
2
2
4
1
4
4
4
16
1
4
4
16
1
16
1-2
1-6
2-3
2-4
3-5
4-5
6-7
5-8
7-8
DURATION
(to)
(tm)
3
6
2
5
6
12
2
5
5
11
3
6
3
9
1
4
4
19
in WEEKS
(tp)
(ta )
15
7
14
6
30
14
8
5
17
11
15
7
27
11
7
4
28
18
As the distribution curve is normal curve, variance of only critical activities are
considered for calculating the standard deviation.
________
__
Standard Deviation
: = (var)2
25 = 5.0
50 %
84.1 %
97.3 %
99.9 %
-3 -2 -1
+1
+2 +3
Hence the expected time for completion of project with 84.1 % probability is 41
days.
A urobindo
Page 18 of 23
TF
2
0
2
1
4
0
1
4
0
0
RES.
4
8
5
4
8
6
5
4
5
6
Gantt Chart
Resource Graph
If the resources are limited to
20 workers then the days of
over allocation of resources
are on the 8th day , 9th day ,
10th day and 11th day.
25
R 20
E
S
15
O
U
R 10
C
E 5
S
31
28
25
22
19
16
13
10
0
TIME
Q.1999/ 8 (b)
A urobindo
Page 19 of 23
=
=
=
=
=
Rs.250.00 Crores
80 weeks
End of 50 weeks
Rs.170.00 Crores
Rs.180.00 Crores
Rs. 187.00 Crores
BCWP-ACWP = 170 180 = - 10 Crores
BCWP/ACWP = 170/180 = 0.94
BCWP/BCWS = 170/187 = 0.91
Budgeted Cost / CPI = 250/0.94 = Rs.265.96 Crores
Sch. Duration/SPI = 80/0.91 = 87.91 i.e. 88 weeks.
Till the date of reporting the actual cost of work performed has exceeded the
Budgeted by Rs.10 Crores. The cost of completion would exceed the budgeted cost of
completion by Rs.15.96 crores and the time of completion would exceed the
scheduled completion period of 80 weeks by 8 weeks.
Notes :
Network Relationships : Start to Start (SS)
Finish to Start (FS)
Finish to Finish (FF)
Start to Finish (SF)
SS : Start of the successor depends upon the start of the predecessor
FS : Start of the successor depends upon the Finish of the predecessor
FF : Finish of the successor depends upon the Finish of the predecessor
SF : Finish of the successor depends upon the start of the predecessor
In SS relationship, there can be a lag i.e. SS+Lag meaning the successor starts 3
days after the start of the predecessor activity. It can also be represented as % i.e
SS+20% meaning the successor starts after 20% of the predecessor activity is
completed.
0
10
SS + 3
5
10
10
LAG
13
18
10
FS + 3
10
LEAD
12
FS - 3
5
10
Q. 1998 / 6(b)
A urobindo
Page 20 of 23
ACTIVITY
A
B
C
D
E
F
DURATION
5
3
4
7
5
3
G
H
2
6
I
J
K
3
4
2
5
A
FS-2
PREDECESSOR
A
A
C
C
B
D
E
F
G
G
H
I
RELATIONSHIP
FS
FS
SS
FF
FS
FS
FS
FS
FS
FS
SS
FS
FF
14
FS
11
FS
12
17
H
14
14
23
SS+4
+1
21
17
25
17
LEAD/LAG
-2
+3
+4
-1
-2
+4
-
23
21
25
FS-1
12
C
15
FS+3
FF+1
FS-2
SS
12
15
11
16
16
E
FF+4
18
G
5
12
18
17
17
24
I
2
FS
21
19
K
3
FS
21
26
24
FS
24
26
Critical Path : A C D F H J K
Q.1998/7(b)
A urobindo
Page 21 of 23
NORMAL DUR.
5
6
4
7
9
12
10
7
6
12
CRASH DUR.
2
3
2
4
5
3
6
4
4
7
NORMAL COST
600
700
100
400
600
1600
1500
400
300
400
CRASH COST
900
1000
200
800
920
1960
1800
490
420
850
Draw network diagram and find Critical Path. In case the project duration is required
to be crashed by two days, which activities will get crashed.
(5)
1
(6)
2
(9)
4
(10)
(7)
(4)
7
(6)
(7)
6
5
(12)
9
(12)
ACT.
PRED
SUCC
ND
CD
ES
EF
1-2
2-4
5
2
0
5
2-4
1-2
4-7,4-6
6
3
5
11
1-3
3-4,3-5
4
2
0
4
3-4
1-3
4-7,4-6
7
4
4
11
4-7
2-4,3-4
7-9
9
5
11
20
3-5
1-3
5-9
12
3
4
16
4-6
2-4,3-4
6-7
10
6
11
21
6-7
4-6
7-9
7
4
21
28
7-9
4-7,6-7
6
4
28
34
5-9
3-5
12
7
16
28
There are two critical paths in the problem
CP 1 : (1-2-4-6-7-9) and CP 2 : (1-3-4-6-7-9) and
Other Paths are P3 (1-2-4-7-9) = 26 days and P4
LS
0
5
0
4
19
10
11
21
28
22
LF
5
11
4
11
28
22
21
28
34
34
TF
0
0
0
0
8
6
0
0
0
6
NC
600
700
100
400
600
1600
1500
400
300
400
CC
900
1000
200
800
920
1960
1800
490
420
850
A urobindo
Page 22 of 23
slope
100
100
50
133
80
40
75
30
60
90
The peak requirement of resources are on the Day 7 where the resource required is
12.
A urobindo
Page 23 of 23