1.
2.
NOTE:
a. ALL flushing using temporary pumps flow rate 100m3/hr.
b. Block diagram of chemical cleaning is attached.
c. Flushing water will be drained to neutralization pit. The water will be checked if
can be disposed to open drain by temporary pump or else will be carried away
by truck to dispose to licensed water treatment company.
2)
Determine the injection points and circulation lines including proper vents
and drains.
3)
4)
5)
Locate the area for circulation tank and pump (refer to equipments setting area
lay-out).
6)
Locate the draining points, water supply, power supply, nitrogen supply and
stream supply.
7)
8)
NOTE: The insulation of the permanent system must be finished at least 90%
After all temporary piping has been installed, leak check and water flushing.
2)
Fill the LP&HP super heater with demineralized water using temporary
back fill super heater pump until overflow through stream drums. Then stop
back fill super heater pump.
Note: All demisters are removing from the super heater outlet nozzles will be
leave in side the stream drums and during cleaning process.
3)
Closed all stream drum manholes. Fill the HRSG system with demineralized
water by temporary chemical cleaning circulation pump until full. Circulate water
in the system by temporary chemical cleaning pump.
4)
Heating up the cleaning system by direct steam from package boiler and
indirect heating by temporary heat exchanger to approx. 905 and maintain
this temperature using temporary heat exchanger.
I-1
5)
6)
Adjust the drum level by at half level in HP drum and full of deaerator drum and
LP drum.
7)
Continuous circulate the system and start sampling the solution. Consider
analysis of pH and alkaline every hour and % PO4, TDS and oil every 2 hours.
8)
9)
10)
When analysis show equilibrium result of alkaline (not less then 24 hrs) stop
heating.
11)
Stop circulation pumps and drain the system to circulation tank for neutralizing
and truck out for disposal at licensed waste treatment plant.
12)
After complete draining; the system shall be filled with approx. 70.
demineralized water, heated by steam from package boiler in the temporary
heat exchanger and direct steam. (The system shall be filled the level at higher
level of the alkaline solution level in the HP drum).
13)
14)
Drain the first rinse to tanker and truck out for disposal at licensed waste
treatment plant.
15)
Second rinse; repeat step 11 or 13 again until the fluid is clear and drain to
neutralizing pit. Check the water if suitable to be disposed to open drain. If cant,
it will be carried away by truck to the approved licensed water treatment plant.
16)
17)
I-2
Preservation
1)
Mix. Preservation solution 400 ppm of ELIMINOX and ammonia water to adjust
the pH
9, with demin water in the circulation tank circulate
thoroughly(treated demin water).
2)
Fill the treated demin water in to the system by circulation pump until full
(venting of LP drum, HP drum, deaerator drum, LP super heater lines and HP
super heater lines).
3)
Pressurize the system under nitrogen pressure to 0.5-1.0 bar. Closed all vent
and drain valves and tagging of closed condition.
Safety Plan
1)
Working area shall be barricaded with proper device and warning signs.
2)
Safety Plan
Chemical Cleaning waste solution and first rinse are carrying out for dispose at
licensed waste treatment company. Second rinse and after shall be neutralize to pH
5.5-9.0 at circulation tank before draining through plant drainage system.
I-3