TOP DOWN CONSTRUCTION

Search

Go

Concurrent above and below grade construction


Conventionally, buildings with underground basements are built by bottom-up method
where sub-structure and super-structure floors are constructed sequentially from the
bottom of the sub-structure or lowest level of basement to the top of the super-structure.
Though this conventional method, also called as bottom-up method, is simple in both
design and construction, it is not feasible for the gigantic projects with limited
construction time and/or with site constraints. Top-down construction method as the
name implies, is a construction method, which builds the permanent structure members
of the basement along with the excavation from the top to the bottom. Top-down method
is mainly used for two types of urban structures, tall buildings with deep basements and
underground structures such as car parks, underpasses and subway stations. In this case
the basement floors are constructed as the excavation progresses. The top/down method
has been used for deep excavation projects where tieback installation was not feasible
and soil movements had to be minimized. Top-down construction method which
provides the significant saving of the overall construction time has been adopted for
some major projects where time factor is of primary importance. The sequence
construction begins with retaining wall installation and then load-bearing elements that
will carry the future super-structure. The basement columns (typically steel beams) are
constructed before any excavation takes place and rest on the load bearing elements.
These load bearing elements are typically concrete barrettes constructed under slurry (or
caissons).

PROCEDURE
The typical construction procedure of top down construction is as follows
Construct the retaining wall.

AMAZON

Construct piles. Place the steel columns or stanchions where the piles are

constructed.
Proceed to the first stage of excavation.

Cast the floor slab of first basement level

Begin to construct the superstructure

Proceed to the second stage of excavation; cast the floor slab of the second

POPULAR POSTS

DAMP-

PROOFING IN
RESIDENTIAL
BUILDING

basement level.
Search

Go

Repeat the same procedure till the desired depth is reached

Construct the foundation slab and ground beams, etc. Complete the basement

Keep constructing the superstructure till it gets finished.

Materials
used for damp
proofing Definition
of...
WATER

Search

Go

PROOFING FOR
ROOFS
Terrace is the most
crucial segment of a
building, and it is
exposed to direct
climatic variations,
extremes of rainfall
and structural ...

GOOGLE+
FOLLOWERS

Construction Updates
Follow

TOP
DOWN

INSTALLATION OF RETAINING WALL

77 have us in
circles

CONSTRUCTION
Concurrent above
and below grade
construction
Conventionally,
buildings with
underground
basements are built
by bottom-up ...

View
all

SUBSCRIBE NOW:
STANDARD

Singly

RELATED TOPICS

2015 (1)
2014 (5)
2013 (4)

The underground retaining wall which is usually a diaphragm wall, is installed before
excavation commences.
Excavation and installation of steel strut

2012 (85)
June (2)
May (4)
March (6)
February (47)

reinforced
beam(Limit state
method of design)
Different methods of
design of RCC
1.Working Stress
Method 2.Limit State
Method 3.Ultimate
Load Method
4.Probabilistic
Method of Desi...

BITUMEN
PROPERTIES
OF BITUMEN
WATERPROOFI
NG OF
BUILDINGS
TOP DOWN
CONSTRUCTI
ON
PRESTRESSING
METHOD IN
MULTISTORIED
BUILDING
FRAM...

The soil is excavated just below roof slab level of the underground structure. Struts are
installed to support the retaining walls, which in turn support the soil at the sides
Construction of underground structure

MATERIALS USED
FOR DAMP
PROOFING
Damp proofing in
Residential Building
Material used for
damp proofing 1.
Property of the
material An effective
damp proofing
materi...

PILE
FOUNDATION
S
NEW
MATERIALS IN
CONSTRUCTI
ON
(CONCRETE)
Insulated
Concrete
Forms
PROJECT
SCHEDULE
CONTROL
VARIOUS
TYPES OF
FLOOR
FINISHES IN
CONSTRUCTIO
N
EQUIPMENT

The roof slab is constructed, with access openings provided on the slab for works to
proceed downwards. The roof slabs not only provides a massive support across the .
Construction of underground structure

MARINE PILING PROCEDURE &


COMPONENTS
Pile Foundations Pile
foundations are the
part of a structure
used to carry and
transfer the load of
the structure to the
bearing grou...
NEW

MATERIALS IN
CONSTRUCTION
(CONCRETE)

The development
and application of
new materials in
construction
continually adds to
the choices and
decisions facing
clients, designers
and...

INTEGRATION
FLY ASH
BRICKS
PREFABRICATIO
N METHODS
FOR MASS
HOUSING
WATERPROOFI
NG IN
BASEMENTS
CEMENT
Good Practices in
Construction
HVAC
DESIGN AND
CONSTRUCTI
ON OF PILE
FOUNDATION

The next level of slab is constructed, and this process progresses downwards till the
base slab is completed
Construction of underground structure

MIVAN
(Aluminium
Formwork)

VARIOUS TYPES
OF FLOOR
FINISHES IN
DEFINITION OF
FLOORS: Floors are
horizontal elements
of building structures
which divide building
into different levels
for the purpose of...

MECHANICAL &
CEMENT
STABILISATIO
N OF SOIL
FIREFIGHTING
IN
COMMERCIAL
BUILDINGS
MECHANICAL
AND CEMENT
STABILIZATIO
N OF SOIL
(DAMS)...

The side walls are constructed upwards, followed by removal of the intermediate
struts. The access openings on the roof slab are then sealed.
Backfilling and reinstatement

DAMPPROOFING IN
RESIDENTIAL
BUILDING
WATER
PROOFING
FOR ROOFS
NEW
TECHNOLOGI
ES OF
WATERPROO
FING IN
RESIDENTIAL
B...
Geosynthetics
Specification of
Tunnel lining
BRIEF AND
DETAIL
SPECIFICATIO
NS OF
ROADS
BRIEF AND
DETAILED
SPECIFICATIO
NS OF
PAVEMENT
QUAL...
SPECIFICATION
S ON
INTERNAL
PAINTING
SPECIFICATION
ON HVAC
SYSTEM
SPECIFICATION
S FOR
EXCAVATION
FOR ROAD
Plain cement
concrete for
combine
footing.
BRIEF AND
DETAILED
SPECIFICATIO
NS FOR
ROAD
PACKAGI...

After the underground structure is completed, the soil is backfilled to the top strut level
before the strut is removed. This is followed by completely backfilling the top of the
underground structure and finally reinstating the surface areas.

STRUCTURAL MEMBERS REQUIRED FOR TOP-DOWN


CONSTRUCTION (Top Down Construction- Part 2)

Posted by The Civil Engineer at 09:47


+3 Recommend this on Google

CHEMICAL
ADMIXTURES IN
CONCRETE-Part 2
CHEMICAL
ADMIXTURES IN
CONCRETE- Part 1
Accelerators:
Accelerating
admixtures are
added to concrete to
increase the rate o...

FIREFIGHTING IN
COMMERCIAL
BUILDINGS
DEFINITION OF
FIRE: Fire is a
chemical reaction, in
which substance
(fuel) combines with
oxygen. The reaction
is exothermic and
usuall...

DETAIL AND
GENERAL
SPECIFICATIO
N FOR THE
PLAIN CEM...

2 comments

MEASUREMENT
S in
Construction

Add a comment as ninditya mustikasari

ESTIMATION
Public Private
Partnership
CONSTRUCTIO
N CLAIMS
CONTRACT
MANAGEMEN
T
Arbitration
slowdown
CAPACITIES OF
VARIOUS
PLANT AND
MACHINERY
Breach of
Contract &
remedies,
Application of
prov...

Top comments

didi rd 1 year ago - Shared publicly


great.. but i hope can be show on detail the top down process from the high rise to
the low rise and build up to new design build project construction ..
1 Reply

sitaram 2 years ago


i cannot understand so ple sent to my mail id mareddy004@mail,com

Steps/Command
s to work on
Ms Project
THE INDIAN
CONTRACT
ACT, 1872
Equipment
calculation for
Solid gravity
concrete d...

Newer Post

Home

Older Post

Subscribe to: Post Comments (Atom)

Valuation of
Immovable
property
January (26)
2011 (6)

FEEDBURNER FEEDCOUNT

CONSTRUCTION UPDATES HEADLINE ANIMATOR

The Civil Engineer. Picture Window template. Powered by Blogger.

Вам также может понравиться