Академический Документы
Профессиональный Документы
Культура Документы
2.0
and
Costing -
QUS
202
All projects are not the same. Even if you are in the business of building the same facility over
and over, the price of each project will differ. Many specific factors will always influence the
pricing of the project, and the estimator must be able to discern the level of impact for each.
Many of these factors call for the art of estimating, and the more experienced the estimator, the
more accurate the gut feel for some of these impacts will be. Lets consider several of these
factors and see just how they might influence the pricing of the project.
2.1
Shape On Plan
The shape of a building has an important effect on cost. As a general rule the simpler the shape
of a building, the lower will be its unit cost.
The rule of thumb is that every time you turn a corner, it is going to cost you more money. The
facility can be exactly the same square metres, but if the shape moves from a square or rectangle
and the number of corners increases, the price is going to go up. Shape impacts the price of all
elements of the building: the ceiling, the roof, the doors, the windows, the staircases, and so on.
A flat ceiling is easier to construct than a vaulted ceiling. A gable roof is easier to build than a hip
roof. A rectangular window costs less than a circlehead window. A rectangular door costs less
than an arch top door. And a straight stair costs a lot less than a winding stair. Shape clearly
impacts cost.
Let us illustrate this as follows:
A. Irregular Shapes
Building A
Building B
Estimating
and
Costing -
QUS
202
We note that both plans have exactly the same floor areas, yet building B is far more expensive
due to the shape of its design. Reasons for the increase in costs are:
Building B has a higher perimeter/floor area ratio (as discussed before) and requires 6%
more external walling to enclose the same floor area than Building A.
Setting out costs will be increased by as much as 50%.
Excavations will cost between 6% and 20% more.
Drainage costs will increase by approximately 25% due to the extra manholes and extra
length of piping needed.
Additional costs will also result from other elements of the building such as the walling
and roofing due to the work being complicated by the shape.
It can therefore be concluded that the irregular shapes of buildings add to their overall cost.
B. Regular Shapes
Regular shapes in contrast, become more expensive the longer and narrower they are planned.
This can be illustrated by the following examples of a square and rectangular building with the
same floor area.
BUILDING A
BUILDING B
CASE A
Area on plan = 400m
Length of walling = 80m
Assume 3m high walling @ RWF 50,000/m2
Then cost/m = 80 x 3 x 50,000 400 = RWF 30,000 m2
CASE B
Area on plan = 400m
Length of walling = 208m
Estimating
and
Costing -
QUS
202
SIZE OF BUILDING:
Increases in the size of a building usually produces reductions in unit cost such as the square metre
rate. The prime reason for this is that on costs do not rise proportionally with increases in the
plan size of a building. Expressed in another way we can say that the Preliminary and General
items expressed as a percentage of total cost tends to decline with an increase in size and cost. A
practical illustration would be the construction of two shops for RWF 125,000,000 and RWF
375,000,000 respectively:
Estimating
and
Costing -
QUS
202
SHOP A
Cost : RWF 125,000,000
Foremans salary : RWF 2,500,000/month
Construction time : 3 months
Percentage of on-costs = RWF 2,500,000 x 3 (RWF 125,000,000 - (RWF
2,500,000 x 3))
= RWF 7,500,000 RWF 117,500,000
=6.4%
SHOP B
Cost : RWF 375,000,000
Foremans salary : RWF 2,500,000/month
Construction time : 5 months
Percentage of on costs = RWF 2,500,000 x 5 (RWF 375,000,000 - (RWF
2,500,000 x 5))
=3.4%
In larger buildings other reductions in unit costs may arise due to savings in:
(i)
(ii)
(iii)
2.3
We have already seen that the plan shape directly conditions the enclosing walls. The
Perimeter/Floor area Ratio allows us to compare different plans to establish the more economical
proposal.
The lower the ratio, the more economical will be the proposal. Circular buildings have the best
ratio but savings are more than offset by the higher cost of circular work.
Let us once again look at a practical example:
Assuming that both buildings have an identical floor to ceiling height of 3.00m then the:
Estimating
and
Costing -
QUS
202
Estimating
2.4
and
Costing -
QUS
202
Circulation Space
The minimization of circulation space by the economic layout of the building provides a definite
cost benefit. Entrance halls passages corridors, stairways and lift wells can be regarded as dead
space which cannot be used profitably, but involve considerable cost in air-conditioning, lighting
cleaning and decorating.
In doing a trade-off analysis between cost and circulation space, one has to consider the
functional and aesthetic inputs as previously discussed, but substantial savings can be made by
sound subjective judgment.
A fair ratio for circulation to total space can be obtained from previous projects and included in
the criteria given during the design brief.
It is interesting to note that in a recent comparison of two alternative plans, the circulation space
in blocks of flats varied between 22% and 32%
Unfortunately very few cost analysis done in the past give details of circulation space and
information for different uses are sadly lacking.
2.5
Other Variables
Several other variables play a role in determining the cost of the design and should be borne in
mind.
(i) Floor To Ceiling Height
It is obvious that by increasing the height of walls, we must increase our rate per M. Anything a
worker cannot reach by standing on the ground will increase the cost of construction. Whenever
you have to employ ladders, scaffolding, man lifts, and cranes, the price goes up. It takes
additional time to set up, take down, and move this equipment around, and it also takes time to
move manpower and materials up and down the equipment. The expected productivity by a
craftsperson standing on the ground versus the expected productivity of the same craftsperson
working on scaffolding is always less.
(ii)
Height of Building
A comparison of the unit rates for a single storey and multi-storey buildings will show substantial
differences. Savings can be achieved by decreasing the plan size and increasing the height of
buildings but a point is eventually reached where the cost of vertical transportation, services,
substructure etc., outweigh the cost of an additional storey. Land values, plot size and the
buildings function tend to have direct influence on its height.
(iii) Constructional Differences
Reinforced concrete walling in lieu of brick walling of industrialized building methods in lieu of
conventional methods will have a huge influence on the cost. The Quantity Surveyor should be
brought in as early as possible in the design stage to advice on the influence of the proposed
construction method on cost.
Estimating
and
Costing -
QUS
202
Time Of Construction
Time is one of the factors that every estimator must be very aware of when putting together the
numbers for the project. There is always a time period between when a project bids and when
the construction actually starts. There is also the time between when a project starts and when it
is anticipated to endsometimes several years. The estimator must be careful to anticipate
fluctuations in prices and availability of labour during these stretches of time.
An earlier completion date saves money but can only be achieved by careful planning during the
design and construction phases of the project.
The use of C.P.A or network analysis programming tools should be encouraged.
A case can be made for the view that construction time should not be specified in the tender
documents, but that the builder should be given the opportunity to tender on time as well as
price.
The exception should be when a building has to be completed in a shorter period than would be
reasonably contemplated.
It could well be that the higher price from a tender is the most economical, once construction
time, earlier trading and savings on escalations are considered.
Although most tenders make provision for a penalty for late completion, almost none provide
the builder with an incentive bonus for early completion.
A detailed and more specific brief to the Architect may require more effort on the part of the
client, but is the cornerstone to efficient time management.
(vi) Locality Of Area
Building costs within Rwanda vary considerably and allowance should be made for locality in the
cost plan or feasibility for this. The location of the project impacts the ease of procurement and
Estimating
and
Costing -
QUS
202
delivery of materials, labor, and equipment, and therefore it affects the overall pricing of the
project.
Tendered rates within the same town or city may also vary due to conditions imposed on the
Contractor by the Client. An example of this is where work has to be done within a high security
area and the Contractor is subjected to security requirements that result in lost time or a restricted
labour force.
Location also impacts the availability and cost of labour. For example, when trying to construct a
new facility in a small community, the contractor may run up against a shortage of skilled labour
to perform the work. In a case like this, the contractor would have to import the needed labour
from outside locations. When this occurs, the contractor usually has to provide housing and
meals for the workers, adding to the costs of the overall project. If the estimator does not
anticipate this added expense up front, there will be labour cost overruns. On the other hand,
another location may have an abundance of skilled labour, and the estimator can anticipate fairly
competitive pricing in the area and estimate the job accordingly.
(vii) Market Conditions
Market conditions always have an impact on the estimate. The basic laws of supply and demand
go to work here. In very tight markets where construction contracts are scarce, the cost of
construction becomes very competitive, and the estimates will reflect this condition. In an effort
to keep good employees working, some contractors are even willing to take a job at cost with
little or no profit on the project.
However, when there is a lot of construction work going on, the market becomes very selective.
General contractors and subcontractors alike become much pickier about which jobs they are
willing to go after, and their pricing will reflect a more conservative approach to risk. The
estimating team takes all of this into consideration when pricing the project.
(viii) Management Factors
Management factors are those considerations that once again have more to do with the art of
estimating than the science of estimating. Management factors include such things as knowing
that a particular owner or architect is more difficult to deal with than another, sensing that you
are going to have to watch things more carefully with an inexperienced subcontractor, or
knowing that the owner is very slow at making decisions.
Some management factors are much more predictable, such as dealing with a public project
versus a private project. With a military project, for example, the paperwork and reporting
required for standard contract administration tasks such as a submittal or an application for
payment are at least twofold. All of that extra work takes extra time, and extra time means extra
cost. Once again, an experienced estimator takes all of these factors into account before
submitting a bid.