Академический Документы
Профессиональный Документы
Культура Документы
DEVELOPMENT
CONSULTANTS
PRIVATE
LIMITED
CONSULTING ENGINEERS
MUMBAI , INDIA
SEPCO ELECTRIC POWER CONSTRUCTION CORPORATION.
Jinan,China
NORTHEAST ELECTRIC POWER DESIGN INSTITUTE
Changchun,China
Emerson Process Management Power&Water Solution(Shanghai) CO., LTD
EMERSON
PROJECT
CLIENT
DOCUMENT TITLE
DOCUMENT NO.
xxxxxx-xx
REV. NO.
1.1
ENDORSEMENTS
1.0
Rev
No
28-1-11
First Issue
Initials
Date
Description
Sgn. Initials
Prepared by
Sgn.
Reviewed by
Rev. 1.0
Initials
Sgn.
Approved by
Initials Sgn.
Issue
Authorization
Page 2 of 74
Contents
1.
GENERAL ....................................................................................................................3
1.1.
2.
3.
4.
Definitions ........................................................................................................3
2.2.
Abbreviations .......................................................................................................3
3.2.
3.3.
4.1.1.
MFT Conditions
4.1.2.
4.1.3.
4.2.
5.
4.2.1.
4.2.2.
5.2.
5.2.1.
5.2.2.
5.3.
Rev. 1.0
Page 3 of 74
5.3.1.
5.3.2.
5.4.
5.4.1.
5.4.2.
5.5.
5.5.1.
5.5.2.
5.5.3.
5.5.4.
5.6.
6.
5.6.1.
5.6.2.
6.1.1.
6.1.2.
6.1.3.
6.2.
6.2.1.
6.2.2.
6.2.3.
7.
Rev. 1.0
Page 4 of 74
7.2.
7.3.
7.3.1.
7.3.2.
A ..........................................3
7.4.
7.5.
7.6.
Pulverizer A A ..................................................................................................3
7.6.1.
7.6.2.
7.7.
7.8.
7.9.
7.10.
7.11.
7.12.
7.13.
7.14.
7.15.
7.16.
7.16.1.
7.16.2.
Rev. 1.0
Page 5 of 74
1.
GENERAL
1.1.
Purpose of Document
This FSSS write up define the function specification of the FSSS control system for the
KSK 6*600MW power Project. KSK 6*600MW FSSS
This document outlines the FSSS hardware design and describes the control, interlock
logic and operation of the FSSS. FSSS
2.
The following definitions and abbreviations shall apply for use in this specification.
2.1.
Definitions
EMERSON
Third Party
End user
Others
Field
2.2.
Abbreviations
FSSS
CCS
MFT
MCR
OFT
DCS
Rev. 1.0
Page 6 of 74
Rev. 1.0
Page 7 of 74
3.
SYSTEM OVERVIEW
3.1.
Hardware Configuration
The Furnace Safeguarding and Supervisory System (FSSS) is part of the total plant
DCS system. Since MFT plays a crucial role in preventing operator-made accident
and boiler explosion due to device malfunction, it is the indispensable automation
systemTMR for safe boiler operation in large power plant. FSSS DCS
MFT
In KSK power project, ONE TMR Controller for MFT, Three Emerson Ovation
Controller for FSSS Device management.
Controller
Description
TMR
(ICStriplex advance)
MFT
CTRL01
(Emerson OCR400)
CTRL02
(Emerson OCR400)
CTRL03
(Emerson OCR400)
HFO FG,Pulverizer
E/F/G Line
FG E/F/G
The MFT processing functions implemented in TMR controller .The function is all
critical for safe boiler operation, so the Safety Manager is used for TMR controller. Safety
Manager is a safety solution designed to protect safety-critical processes from runaway
situations, and allows the system to comply with SIL3. For the detailed information about
Safety Manager please refer the Hardware ICStriplex Aadvance Safety Manager
Rev. 1.0
Page 8 of 74
Three ovation controller implements other fsss control. For the detailed information
about ovation OCR400 refer the document Hardware
OVATION FSSS OVATION OCR400
MFT trip relay cabinet is used in KSK 6*600MW power project for boiler trip (protection);
only relays and hardwired connection exist in this cabinet. If the MFT trip relay is activated,
all fuels supply will be shut-off to protect the boiler, and the MFT signal will be sent to other
relevant system immediately.
MFT
MFT
For the boiler emergency shutdown system two set of hardwired emergency pushbutton
and trip relays are provided. In case of rare DCS system failure or no any response on
station LCD, operator can press the emergency pushbutton on console desk to directly
activate the MFT relays. DCS
MFT
MFT trip relay cabinet is redundant design Loop, two set of MFT relays are mounted in this
cabinet, and every set of the MFT relays independent 220VDC power supply is used.
These two set of MFT relay hardwired loops adopt separate input signal, its relays output
are connected together at the terminal in this cabinet, and provide one output to field for
devices MFT protect trip. MFT MFT
MFT 220VDC
Totally XX relay outputs are designed for one set of MFT. Please refer the document DCS
MFT Cabinet for the detailed MFT trip relay cabinet drawing MFT XX
MFT
Rev. 1.0
Page 9 of 74
3.2.
Software Function
The FSSS software can be divided into three part functions: MFT control logics, common
control logics,Fuel oil control logics and Coal-fired control logics.
In KSK power project , based on the function important levels and the good
engineering practice, MFT Control logic is implemented in ICStriplex Aadvance controller.
Common control logics and Fuel oil control logics and Coal-fired control logics are
implemented in OCR400
controller
FSSS MFT
MFT ICStriplex Aadvance OCR400
The Common control logic also include the control of the common used FSSS device as
cooling air fan, fuel oil shut-off valve etc.
FSSS
Fuel oil control logic includes the oil burner start/stop control, coupling and layer start/stop
control.
Coal-fired control logic includes all seven layers pulverizer system sequence control and
the single device interlock control like coal feeder, pulverizer and its relevant damp.
As the part of DCS, the major FSSS operator interface is through station LCDs graphic.
DCS FSSS LDC
3.3.
As per the Customers requirement, Safety manager is used for boiler critical protection.
All Signals between DCS and ICStriplex Aadvance controller will not use peer-to peer
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 10 of 74
Rev. 1.0
Page 11 of 74
Rev. 1.0
Page 12 of 74
4.
Master Fuel Trip (MFT) is the key content of the boiler protection, and also is the most
important safety function of FSSS. On any dangerous situation which will keep boiler from
safe operation occurs, MFT will fast cut off all the fuel oil and coal feeder to make the boiler
in safety status, avoid or limit the accident.
MFT FSSS
MFT
MFT logic has the function of the first out trip condition memorize, it can record the first
occurred condition when MFT activate. The first out alarm will be cleared after MFT Reset.
MFT MFT
Rev. 1.0
Page 13 of 74
Flame detector scan air header pressure is below low value II, two of three hardwired
input from field with 30 second on delay;
30s
Turbine tripped on generator load great than 50%, two of three hardwired input from
ETS;
Rev. 1.0
Page 14 of 74
Turbines either all TV or all GV closed and Both HP bypass CVs are closed.
2 4 2
b)
Turbines either all RSV or all IV closed and Both LP bypass CVs are closed.
2 2 2
Ignite fail protection, includes two conditions as following, any condition will trigger this
protect:
a)
After MFT reset (initial ignition permit) and the LDO supply oil shut-off valve has
b)
MFT 3
Rev. 1.0
Page 15 of 74
a)
All twelve HFO burners oil valve closed or HFO header oil cut off valve closed
b)
All LDO burners oil valve closed or LDO header oil cut off valve closed
c)
Loss of all flame, all the flowing conditions with 3 second on delay and with Coal
Burner Running memorize will trigger this protection. Normal stoppage of the boiler will
not trigger MFT.
3s
MFT
a)
b)
Both of the primary air fans are stopped during any coal layer in service but no fuel oil
layer running will cause the MFT.
2
Both DCS supply power loose ,the function will be implement in MFT hardwire panel.
two of three hardwired input from DCS supply power cabnet.
DCS
All Boiler recycle pumps stopped
Rev. 1.0
Page 16 of 74
a)
Retract all oil gun directly (no oil gun post purge);
Rev. 1.0
Page 17 of 74
c)
d)
Send the hardwired signal to DCS, ETS, Bypass, and Soot blowing system,ESP system
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 18 of 74
signal to
these devices. For example, the fuel oil supply shut-off valve will receive two close
command from separate panel when MFT.
MFT MFT
DCS MFT
MFT
If DCS is not working, operator also can stop these MFT hardwired device through
hardware interlock loop by pressing the emergency button.
DCS MFT
MFT
4.2.
Oil fuel trip (OFT) logic inspects the fuel oil parameters. On any dangerous situation which
will keep boiler from safe operation occurs, OFT will fast cut off the running oil burners and
close the oil supply shut-off valve.
OFT
OFT
FSSS continuously supervise the OFT conditions and will trigger the OFT if any of the
condition occurs. The first OFT condition will be memorized and alarming on station LCD,
the first out condition will reset by OFT reset signal.
Rev. 1.0
Page 19 of 74
Rev. 1.0
Page 20 of 74
Rev. 1.0
Page 21 of 74
5.
5.1.
The common control logic include oil leak function, boiler purge function and auxiliary
FSSS device control, and the interface of DCS with other systems. The detailed function is
as following:
FSSS DCS
1. Ensures no oil will leak in fuel oil supply pipe by executing the fuel oil leak test
procedure.
2. Ensures furnace purge success and no any fuel stored in furnace before boiler ignites
3. Establish the ignition condition including LDO ignition permission, HFO ignition
permission. Forbid oil layer to start before all relevant oil ignite permissions are satisfied.
Rev. 1.0
Page 22 of 74
4. Control the auxiliary devices of FSSS like fuel oil shut-off valve, cooling air
fan,Pulverizer
FSSS
5.2.
The Fuel Oil Leak test logic is designed to prevent the fuel oil leak from supply oil pipeline
(include leak to furnace). The test will be performed to check whether fuel oil leakage is
there between the fuel oil supply shut-off valve and all burner oil valves.
In KSK power project, fuel oil system includes Light Diesel Oil system (LDO) and Heavy
Fuel Oil system (HFO), these two fuel oil system should be performed the oil leak test
separately. Operator can send the LDO/HFO fuel oil leak test start command on LCD
graphics. If the test is confirmed to be unnecessary, it could be by-passed, but this is not
recommended for safe boiler operation.
LDO is available only in the BCEF layer, and HFO is available in the AB, CD, and FG
layer.Fuel oil leak test succeed is one of the furnace purge permit conditions.
(LDO)(HFO)
CRT (LDO)(HFO)
5.2.1.
Rev. 1.0
Page 23 of 74
1. Opening of LDO supply oil shut-off valve to fill the oil into header pipeline, and it will be
closed after 60 Second when the oil pressure before LDO return valve is greater than 25
bar. If the filling oil pressure could not reach 25bar during 60 second after the supply
shut-off valve opened, the message Fill Oil Load Failure will be occurred, check the leak
point and do the test again.
(LDO)(LDO) 2.5MPa
(LDO) 60S 2.5MPa
2. If the oil pressure after filling is normal, LDO supply oil shut-off valve is closed, and
then the oil pressure shall be checked for 180 second period. If the filling oil pressure falls
below than 20 bar, the message LDO burner oil valve Leak will be displayed, check the
leak point and do the test again.
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 24 of 74
4.
If the LDO return oil shut-off valve closed after successful oil unloads, then start the
oil pressure check within a 120 seconds period. If the oil pressure becomes greater than 2
bar, the logic will send the message LDO supply oil shut-off valve Leak.
120 0.2Mpa
5. If no any oil leak or failure signal occurs during the all LDO oil leak test procedure, the
message LDO Oil Leak Test successes will be displayed on station LCD. The total LDO
oil leak test will be completed in about 450 second, and the test countdown timer will be
displayed also.
450s
During the LDO oil leak test, any of the following conditions will cancel the test procedure:
Rev. 1.0
Page 25 of 74
LDO Oil Leak Test success signal will be reset under any of the following conditions:
5.2.2.
The HFO have the similar Leak test procedure with the LDO test procedure.
Rev. 1.0
Page 26 of 74
After all the conditions has been satisfied, the message HFO Leak Test Permit will be
displayed on station LCD, operator can push the button labeled with start HFO Leak Test
on LCD to start the test. When the test demand output, the logic will close HFO return
header shut-off valve, send the bypass command to MFT hardwired trip relay for HFO
supply shut-off valve, open the HFO supply shut-off valve and HFO supply oil pressure
adjust CV and the message HFO Oil Leak Test in Progress will be displayed on station
LCD. The following procedure will be started:
CRT (HFO)
CRT
(HFO)(HFO)(HFO)
CRT
1. Opening of HFO supply oil shut-off valve to fill the oil into header pipeline, it will be
closed after 60 second when the oil pressure before the HFO return valve is greater
than 25 bar. If the filling oil pressure could not reach25bar during 60 second after the
supply shut-off valve opened, the message Fill Oil Failure will be occurred, check the
leak point and do the test again.
(HFO)(HFO) 2.5MPa
(HFO) 60S 2.5MPa
2. If the oil pressure after filling is normal, HFO supply oil shut-off valve will be closed,
and then the oil pressure shall be checked for 180 seconds. If the filling oil pressure falls
below than 20 bar, the message HFO burner oil valve Leak will be displayed, check
the leak point and do the test again.
(HFO)180
2.0MPa,
Rev. 1.0
Page 27 of 74
4. If the HFO return oil shut-off valve is closed after successful oil unloads, then start
the oil pressure check within a 120 seconds period. If the oil pressure becomes greater
than 2 bar, the logic will send the message HFO supply oil shut-off valve Leak.
90 120 0.2Mpa
5. If no any oil leak or failure signal occurs during the all HFO oil leak test procedure,
the message HFO Oil Leak Test successes will be displayed on station LCD. The total
HFO oil leak test will be completed in about 450 seconds, and the test countdown timer
will be displayed also.
450s
During the HFO oil leak test, any of the following conditions will cancel the test procedure:
(HFO)
MFT trip pulse
MFT
MFT reset pulse
MFT
Fill Oil Failure pulse
Rev. 1.0
Page 28 of 74
HFO Oil Leak Test success signal will be reset under any of the following conditions:
(HFO)
MFT trip pulse
MFT
HFO Oil Leak Test in Progress pulse
5.3.
Furnace Purge
As per the basic rules of NFPA85, furnace must be purged with proper air flow rate for a
predefined time before any fuel enters the furnace. Excess combustible matters may be
accumulated at the boiler convection pass, flue pass, and the induced draft fans which is
used for transfer flue gas to chimney. If these combustible matters mixed with proper air
rate and meet the ignition energy source that may lead to the boiler explosion. Hence
boiler purging is required after every MFT before the boiler start up.
The purpose of furnace purge is to clean the residues combustible matters to prevent the
deflagration during boiler ignition.
NFPA85
Rev. 1.0
Page 29 of 74
5.3.1.
The following conditions must be satisfied for the furnace purge cycle:
Primary furnace purge condition lists are as below:
()
MFT activate
MFT
All burner oil valves and its purge valves, atomizing steam/air valves are closed
Rev. 1.0
Page 30 of 74
Rev. 1.0
Page 31 of 74
The logic will auto start the LDO/HFO fuel oil leak test and set the auxiliary air dampers to
the purge position first after receiving the start command, then it will wait for the secondary
purge conditions becomes true, and when all purge permissions satisfied the furnace
purge start actually. The message Furnace Purge in Progress will be displayed on LCD,
purge countdown timer will also be started. The purge time is 300 second as predefined.
CRT
300
In order to purge the furnace completely and cleanly, the purge procedure must be lasted
300 seconds with between 30% and 40% rated total air flow rate.
30-40% 5
During purge process, FSSS logic will continuously supervise all the primary and
secondary purge conditions. The primary purge conditions are the necessary condition for
FSSS goes into purge mode; and the secondary purge conditions will start the purge
timer.
FSSS
FSSS
If the secondary purge conditions (e.g. total air flow less than 30%) are not satisfied during
purge process, the purge timer will be reset. But the purge procedure not exit, and the
message Purge Interrupt will be blinking displayed on LCD. After the secondary purge
conditions are satisfied again, the purge timer will be started once more.
If the primary purge conditions are not satisfied during the purge process, the purge
procedure will be stopped and FSSS exit the purge mode, the purge timer will be reset
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 32 of 74
If the purge procedure lasts for 300 seconds and all purge conditions are satisfied, the
message Purge Complete will displayed on LCD.
5 CRT
Furnace purge complete signal is the necessary condition for MFT reset.
MFT
The MFT pulse will clear the Purge Complete signal.
MFT MFT
5.4.
Rev. 1.0
Page 33 of 74
Rev. 1.0
Page 34 of 74
5.5.
After the successful fuel oil leak test, FSSS will auto reset the OFT and then operator can
open the supply oil shut-off valve.
FSSSOFT
.
If OFT is there, FSSS will auto close the supply oil shut-off valve.
OFT
During fuel oil leak test process, FSSS will override open the supply oil shut-off valve, and
close it when the filling oil pressure reaches the predefined value.
Rev. 1.0
Page 35 of 74
(LDO)
(LDO)
(LDO)
(LDO)(LDO)
(LDO)(LDO)OFT
Rev. 1.0
Page 36 of 74
(HFO)
(HFO)
(HFO)
(HFO)(HFO)
(HFO)(HFO)OFT
(LDO)
Rev. 1.0
Page 37 of 74
z (HFO)
z (HFO)
z (HFO)
z MFT
5.6.
The flame detector probes are mounted around the furnace burners. Its very important to
keep the flame detector probes cooled and cleaning, the high temperature will reduce the
flame detector working stability and life.
Rev. 1.0
Page 38 of 74
A
Cooling air fan A not running and Cooling air fan B running
A
Any of the following conditions will reset the cooling air fan A in standby
Rev. 1.0
Page 39 of 74
A B
B 20
MFT 2
6.
6.1.
Boiler can be ignited only after the furnace purge completed and all LDO ignition
permissive conditions are satisfied. LDO burner can be ignited by the high-energy arc
ignitor, any other ignition energy source like coal burners flame is not permitted.
The LDO control logic includes LDO layer control, coupling control, and single control.
(LDO)(LDO)
Rev. 1.0
Page 40 of 74
The BC oil layer start command will be reset under any of the following conditions:
BC
MFT
MFT
OFT
OFT
BC layer start complete pulse
BC
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 41 of 74
BC oil layer in service signal will be established when three of four BC layer burners are
running.
BC3BC
This document only describes the LDO BC1 burner; other LDO burners have the similar
logic.
Rev. 1.0
Page 42 of 74
If the first LDO oil gun ignition failed, FSSS logic will start the 1 minute post purge to
ensure that no combustible matters will be accumulated in furnace. So the Initial ignition
permit condition will lose when any of the oil guns ignites failed to disable the oil gun start
during the FSSS in purge process. After 1 minute Initial ignition permit condition will
occurs again. If any oil gun is running in furnace normally, the Initial ignites permit
condition will always exist.
FSSS logic permit two times of oil gun ignition failure and the third oil gun ignition failure
will activate the MFT.
(LDO)
FSSS11
11
MFT
Rev. 1.0
Page 43 of 74
2. Opening the oil gun purge valve and closure of it after 10 seconds later. (No this
pre-purge process if RB start this oil gun)
10sRB
3. Extend the high-energy arc ignitor and spark
5. After the burner oil valve opening, if the BC1 flame can be detected during 10
seconds then the ignitor sparking is stopped and retracted. Oil gun running successfully.
10 s
Rev. 1.0
Page 44 of 74
BC1 burner flame on signal will be established if all of the following conditions exist:
BC1
BC1 flame detected
BC1
BC1 oil valve opened
BC1
BC1 burner in service signal will be established if all of the following conditions exist:
BC1
BC1 flame detected
BC1
BC1 oil valve opened
BC1
BC1 purge valve closed
BC1
BC1 oil gun extended
BC1
Note: If no flame detected during 10 seconds after oil valve is opened, logic will consider
ignition failure, this is the burner failure and will close the oil valve immediately. At this time,
if no MFT occurs the logic will open the purge valve to start the post-purge process, and
retract the oil gun when purge complete; but if MFT/OFT occurs on burner failure the logic
will directly retract the oil gun, stop the high-energy arc ignitor sparking and retract it.
10s
MFTMFT
Rev. 1.0
Page 45 of 74
2. Extend the high-energy arc ignitor and sparking for 10 seconds, after 10 seconds will
be retracted. But if any coal layer is running at the same time, the high-energy arc ignitor
will not be extended.
[10S][]
3. Opening of the purge valve
BC1 oil burner stop signal will be generated if any of the following conditions exists
BC1:
LDO layer stop, or LDO BC1/BC3 coupling stop, or operator manual stop
BCBC1
MFT
MFT
LDO OFT
OFT
BC1 oil gun still not extended after BC1 burner in fire mode after 8 seconds
BC1/8sBC1
Rev. 1.0
Page 46 of 74
Rev. 1.0
Page 47 of 74
6.2.
HFO burner system includes three layers, this document only describes the HFO AB1
burner, and others HFO burners have the similar logic.
The HFO control logic includes HFO layer control, coupling control, and single control.
AB1
Rev. 1.0
Page 48 of 74
AB oil layer in service signal will be established when three of four AB layer burner are
running.
AB3AB
Rev. 1.0
Page 49 of 74
This document only describes the HFO AB1 burner, other HFO burners have the similar
logic.
AB1(HFO)
The following conditions are HFO AB1 burner start permissive conditions:
AB1(HFO)
HFO ignition permissive condition exist
(HFO)
AB1 burner oil valve closed
AB1
No AB1 flame detection
AB1
No AB1 burner trip condition exist
AB1(HFO)
AB1 burner not lost the valve power
AB1
With the HFO AB1 burner start permissive conditions, any of the following command will
start the AB1 burner:
AB1(HFO)AB1
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 50 of 74
2. Opening of the oil gun purge valve and it is closed after 30 seconds. (No this
pre-purge step if RB start this oil gun)
30sRB
3. Extension the high-energy arc ignitor (10HHY61IV001) and spark
5. After the burner oil valve opened, if the AB1 flame can be detected during 10 seconds
then the ignitor sparking is stopped and retracted. Oil gun running successfully.
10s
AB1 burner flame on signal will be established if all the following conditions exist:
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 51 of 74
Rev. 1.0
Page 52 of 74
2. Extension of the high-energy arc ignitor and sparking with 10 seconds, after 10
seconds it will be retracted . But if any coal layer is running at the same time, the
high-energy arc ignitor will no need to extend.
[10S][]
3. Opening the purge valve
AB1 oil burner will be stopped under any of the following conditions effect:
AB1
HFO layer stop, or HFO AB1/AB3 coupling stop, or operator manual stop
ABAB1
MFT
MFT
HFO OFT
OFT
AB1 oil gun still not extended after AB1 burner in fire mode with 8 seconds delay.
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 53 of 74
Rev. 1.0
Page 54 of 74
7.
Coal-fired control logic accomplishes the pulverizer system start/stop control, supervision
of every running coal layer parameters, and fast cut off the coal if necessary to ensure
the furnace in safety condition.
7.1.
All the following conditions must be satisfied for the coal burner ignition:
MFT reset
MFT
The differential pressure of furnace and secondary air wind box is normal
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 55 of 74
The differential pressure of furnace and hot primary air header not low
7.2.
Any of the following conditions satisfied means coal layer A ignition energy is sufficient
A A
AB oil layer in service
AB
Coal layer B RUN under boiler load > 30%
30%B
Any two Coal layers in service under boiler load > 60%
60%
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 56 of 74
30%A
Coal layer C RUN under boiler load > 30%
30%C
Any two Coal layers in service under boiler load > 60%
60%
Any of the following conditions satisfied means coal Layer C ignition energy is sufficient:
C
BC oil layer in service
BC
CD oil layer in service
CD
Coal layer B federate > 50% RUN under boiler load > 30%
30%B 50%
Coal layer D federate > 50% RUN under boiler load > 30%
30%D 50%
Any two Coal layers in service under boiler load > 60%
6%
Rev. 1.0
Page 57 of 74
Rev. 1.0
Page 58 of 74
Coal Layer A in service will be established if all the following conditions are satisfied.
A
Pulverizer A running
A
Coal feeder A have been running for 1 minute
A
At least three flame detected of the corner A1, A2, A3, A4
A 3/4
Rev. 1.0
Page 59 of 74
7.3.
2.
Open the pulverizer A sealing air damp, close pulverizer A inlet hot air damp
A ,
3.
4.
5.
Rev. 1.0
Page 60 of 74
Start the pulverizer A and separator under the pulverizer A start condition occurs.
A A
7.
Open the pulverizer A inlet hot air damp nd set the modulated air damps to default
Open the coal feeder A sealing air damp aOpen the coal feeder A outlet valve and
9.
2.
3.
seconds
<70 20s , A
4.
Stop the coal feeder A in coal feeder A inlet valve has been closed 60 seconds
60 A
5.
Rev. 1.0
Page 61 of 74
Stop the pulverizer A and separator after the coal feeder A outlet valve has been
closed 5 minutes
A 5
7.
Close the pulverizer A inlet hot air damp and set the modulated inlet cooling air
8.
9.
10.
Close the pulverizer A inlet cooling air damp&release oil pump stby
11.
pump
7.4.
In this project, all pulverizers have two lube oil pumps and only one is running during
normal condition, so the standby logic is designed.
This document only describes the pulverizer A lube oil pump A logic.
The following is the start permissive conditions (and):
Pulverizer A lube oil station oil temperature >25
Pulverizer A lube oil station oil level not low
The following is the stop permissive conditions (or):
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 62 of 74
A 25
A
A 120s
A B
A B
A
A
A 120s
A 65 120s
Rev. 1.0
Page 63 of 74
7.5.
This document only describes the pulverizer A lube oil box heater logic.
The following is the start permission:
Pulverizer A lube oil station oil level not low
The following is the auto start condition:
Pulverizer A lube oil station oil temperature <35
The following are the auto stop conditions:
Pulverizer A lube oil station oil temperature >40
A
A 35
A 40
7.6.
Pulverizer A A
Rev. 1.0
Page 64 of 74
The diff pressure of pulverizer A inlet PA and sealing air low(1.25kPa) with 60 second
delay
A 60s
The primary air pressure low6.2kpa and feeder a running with 2 seconds delay
6.2kpa 2s
Lost the Coal layer A flame trip. The Coal layer A flame is established by three of
four burner flam detected.
3/4A
Lost pulverizer A ignition energy
A
Lube oil trip will generated under the following conditions effect:
a)
b)
c)
Rev. 1.0
Page 65 of 74
Rev. 1.0
Page 66 of 74
b)
c)
d)
Rev. 1.0
Page 67 of 74
7.7.
Coal Feeder A A
The following conditions are the permissive conditions for feeder start up:
Pulverizer A is running
Coal feeder A sealing air damp opened
Coal feeder A outlet valve opened
Coal feeder A outlet temperature not high
Coal feeder A outlet not block
Coal feeder A outlet valve opened
Pulverizer A Primary air flow normal
No any coal layer A trip conditions exist
Coal feeder A will auto stop under the following conditions effect:
Pulverizer A stopped under coal feeder A running
Any pulverizer A trip condition
Coal feeder A outlet valve closed with 5 seconds delay
Coal feeder A outlet blockage with 20 seconds delay
Coal feeder A belt zero coal with 5 seconds delay
Coal feeder A inner over temperature with 3 seconds delay
A
A
A
DOCUMENT NO.: xxxxxx-xx
Rev. 1.0
Page 68 of 74
A
A
A 5s
A 20s
A 60s
5s
7.8.
Rev. 1.0
Page 69 of 74
MFT
7.9.
MFT
A
Rev. 1.0
Page 70 of 74
MFT
A
A
The following is the auto close condition:
Pulverizer A stopped with 60s delay
A 60
Rev. 1.0
Page 71 of 74
A
A
Rev. 1.0
Page 72 of 74
A
The following is the auto close condition:
Coal feeder A stopped with 60s delay
A 60
For the detailed RB conditions please refer the KSK DCS CLCS Write Up
RB DCS CLCS
FSSS system will perform the RB action only when more than three coal layers are in
service; the logic will remove the upper coal layers in service from top to bottom
preferentially in proper time interval to match the boiler load and the boiler auxiliary
devices contribution.
FSSS RB
Rev. 1.0
Page 73 of 74
Rev. 1.0
Page 74 of 74