Академический Документы
Профессиональный Документы
Культура Документы
ABSTRACT
This paper presents a comprehensive overview of various floatover
technologies based on the latest advancements in offshore installation
and decommissioning technology. Each floatover methodology is
briefed and categorized into specifically defined divisions in a system
of classification, including mechanical and non-mechanical schemes,
single-barge, catamaran-barge and twin-barge schemes, etc. The
presentation of these various floatover technologies will reveal the
floatover history and evolution, the advantages and disadvantages of
different methods, as well as the promising prospect of their wide
applications in installation and decommissioning of integrated topsides
onto and from various fixed and floating substructures.
INTRODUCTION
Various floatover technologies have been developed and successfully
applied to offshore installations of integrated topsides onto different
fixed and floating platform substructures since the first floatover
installation was successfully adapted for the production platform
topsides of 18,600 tonnes on the Phillips Maureen Project in 1983. A
string of offshore facilities using the floatover concept followed,
In the early of 1980s two North Sea projects, i.e. Phillip's Maureen and
Conoco's Hutton, placed integrated topsides on steel GBS and TLP
substructures in relatively sheltered areas and inshore shallow locations.
Recently floatover technology can be employed from shallow water to
deep water in swell conditions or harsher random waves. Moreover, the
floatover substructures can cover almost all types of existing fixed and
floating systems, including jackets, GBSs, TLPs, SEMIs, compliant
towers, and spars, except FPSOs.
FLOATOVER PROCEDURES
Typical floatover operations may be divided into the following major
stages:
Loadout: Upon weighing, the integrated topsides will be jacked up by
a mega jacking system of hydraulic cylinders or lifted by strand jacks
before a tall DSF/LSF can be inserted under the topsides prior to
loadout operation. Topsides may be skidded onto pre-selected floatover
barge longitudinally, or laterally if longitudinal strength is limited, via a
pulling system of strand jacks or Self Propelled Modular Transporter
(SPMT) trailers with a sophisticated ballast spread.
10
Floatover Barge(s): Upon loadout, the barge will transport the topsides
to site and floatover install the topsides onto a pre-installed fixed
substructure offshore or a floating substructure in place or inshore.
Beam Seas
Quartering Seas
1.5m
0.8m
1.2m
5 - 10 sec
4 - 7 sec
5 - 8 sec
10m/sec
10m/sec
10m/sec
1.5m/sec
1.5m/sec
1.5m/sec
11
The floatover barge will be brought between the substructure slot with
a combination of positioning tugs, mooring lines, and soft-line winches
at an approaching speed of 3-5m/min. As Fig. 2 shows, the concrete
GBS has been designed to allow 4 meters clearance between the barge
sides and the GBS shafts. Eight mooring lines are attached to the barge
as the barge progresses through the GBS. With the aid of fendering
system and soft-line winching system, these mooring lines will be used
to hold the barge steady in its final lowering position.
12
When the transportation barge, together with the DSF, are clear from
the substructure slot the final mating operation will commence. Sand
jacks located in the LMUs will be activated to lower the deck and allow
the deck legs to come into steel-to-steel contact with the substructure
legs if non steel-to-steel LMUs are employed. The contact points will
then be welded together to form the one permanent structure of the
platform. Before departing from the platform, the construction support
vessel will perform post installation surveys including the deployment
of a ROV for underwater surveys.
Smart-Leg Technique
The first successful shockless Smart-Leg System was completed
offshore Nigeria in June 1997 by McDermott-ETPM for the 4,100Te
topsides of Ekpe Gas Compression Platform located in a water depth of
50 meters. The barge preparations were done in 3 days while the
floatover operation only lasted about 6 hours. The Smart-Leg
Technique is a mechanical method with a single barge configuration.
This technology was successfully used in November 1996 to position a
192m long and 8000Te heavy bridge spans crossing the strait between
Prince Edward Island and New Brunswick in Canada.
Smart Fins and Smart Fenders are also developed to restrict the motion
of the barge in sway, surge, and yaw. The Smart Fins and Smart
Fenders are deployed and recovered by hydraulic rams installed on
barge deck. Smart Fins are equipped with hydraulic shock absorbers to
establish contact at the four corner legs, thus reducing the surge to
under 25mm excursion. Then the Smart Fenders will be activated to
progressively eliminate the sway. Upon aligning, the Smart Leg System
can be activated to start the deck mating. After partial load transfer
occurs as a result of locking of Smart-Leg Jacks, say 50% load transfer,
the remaining load transfer can be achieved by ballasting the barge and
further jacking up the deck to the point where the Smart Shoes can be
actuated to collapse with explosive split nuts, thus yielding a 2.7m
undocking clearance. The Smart Shoes are special deck support two AFrames with sliding bearing pads adapted to fit onto skid rails. Refer to
Figs. 3a and 3b for details.
The major disadvantage of this scheme is lack of controlling the final
elevation of the topsides and its levelness since the Smart Leg is
activated by the vertical motion of the barge when the deck leg rises to
its highest position before falling in the swell. In addition the Smart
technology is based on complex active mechanism and do not allow
single failure, less reliable compared with passive LMUs and DSUs.
13
y
y
wires.
Lower the 4 inner legs onto the pre-installed piles and transfer the
leg reaction load pre-defined by a finite element analysis to the 4
inner legs by using hydraulic collar jacks.
Weld the shim blocks between the 4 inner leg sleeves and the 4
inner legs before decommissioning and removing the hydraulic
screwed locking collar jacks and strand jacks from the 4 inner legs.
UNIDECK Technique
The Unideck technology was engineered by Technip for the installation
of topsides by floatover and hydraulic jacking technique, a mechanical
and single-barge scheme. The Unideck technigue is entirely reversible
during installation and is particularly well suitable for benign
environments and in long period swell conditions such as West Africa.
So far there have been 12 successful floatovers completed, including 3
in West Africa. The EAP GN Topsides is the largest topsides installed
by the Unideck technique in the swell condition offshore Nigeria. The
floatover installation of the 18,000Te topsides was executed in early
November 2005, during the West African installation season running
from early November to end of March.
Fig. 5a: Hydraulic Jacks Can Elevate and Quickly Lower the Deck
14
extending jacks 2nd time. When the 75% load transfer is completed, a
rapid ram retraction is performed within one second to complete the
100% load transfer, thus achieving an instant 1.5m gap for safe
undocking. Refer to Figs. 5a and 5b and Tribout (2007) for details.
Technip also developed the Floatover High Air Gap (FOHAG) concept
derived from the Unideck and TPG 500 technologies. It allows deck
floatover installation applicable to the high air-gap areas, such as
Canada and Sakhalin Island, where platforms are exposed to large
amplitude waves or cyclonic conditions like in South East Asia. During
installation, the deck is elevated well above the air gap and positioned
above the substructure and lowered down in place.
The geometry of the Amplemann system will have a large effect on the
system performance. This technology is still subject to the financial
feasibility and technical reliability of complex mechanism and
complicated control/monitor system. Refer to Gerner et al. (2007).
Twin-Barge Technique
In November 2006, the twin-barge floatover technology was applied to
install the 3,400Te Kikeh topsides onto the first-ever spar outside of the
Gulf of Mexico for the first time in open waters. The installation site is
located in 1320m water depths offshore East Malaysia, South China
Sea. The twin-barge concept was developed by Technip with the
topsides resting astride on two identical barges. The twin-barge
configuration is centered above the submerged spar hull which is
anchored at its final in-place site. Refer to Fig. 7 and Edelson et al.
(2008) for details.
15
y
y
y
y
y
y
The floatover barges are positioned under topsides either side of the
transportation barge one at a time, where additional four tubular
members provide diagonal supports to the vertical stanchions at the
barge sideshells.
The topsides will be transferred from the transportation barge to the
twin barges by ballasting the transportation barge beneath the
topsides and deballasting the twin barges, thereby transferring the
topsides load completely onto the floatover barges before removing
the middle barge.
Seafastening is installed to make the topsides and floatover barges
into a rigidly connected catamaran.
The twin barges are towed from Labuan approximately 110 km to
the Kikeh site via a single main tug connected to primary tow
bridles to minimize splitting loads on the deck support frames while
additional tug connected to temporary stern bridles to improve
directional stability and to tail the catamaran for a sharp turn.
Upon arrival, the catamaran is hooked up to two pre-installed
moorings of the Tender Assist Drilling unit, one to each floatover
barge, to act as brakes and pull-backs.
Eight maneuvering/positioning soft lines are rigged with the twin
barges to the spar hull.
The docking system pulls the catamaran over the spar hull until the
stabbing cones on the topside align with the LMUs on spar hull legs.
The topsides load transfer is completed by deballasting the spar hull
as fast as possible until the full weight of the topsides has been
removed from the floatover barges and then continues deballasting
until the freeboard reaches storm safe level.
The floatover barges disengage from the soft lines and are towed
clear of the topsides underside, and then disconnected from the
preset moorings before demobilization.
truss technique is that it eliminates the need for the open slot during
docking while reducing the float-over support truss height and therefore
improving transport barge stability. One center transport barge
(40099.520) and two twin barges (2507216), or called
outrigger barges, were used to install all the three decks in less than
three weeks utilizing the same set of Versa-Truss system.
The installation system consists of three pairs of Versa-Truss booms
where the base of each boom is secured to the longitudinal centerline of
the outrigger barge deck utilizing pre-fabricated load spreader bars and
heel pins. The tip of each boom will be inserted into a specially
designed pin installed at the upper deck edge of the topsides. The
topsides are lifted using an operation procedure combining the barge
ballasting and the winch wire tensioning, where the winch wires are
attached to each of the two outrigger barges through the use of the
winches located on each of the outrigger barge deck at the base of the
booms. Tensioning of the winches effectively increases the inclination
angle of the booms, thus transferring the deck load from the center
barge to the outrigger barges and finally lifting the deck off the center
barge. This active lifting system eliminates passive LMUs and DSUs.
The tri-maran and catamaran short tow configurations have no need of
the substructure slot and less requirement of water depth, but they are
vulnerable to rough seas.
16
y
y
y
y
Stage 2a: If required, 40% deck load remained on the center and
60% deck load transferred on the outrigger barges in survival
condition set for tow to safe havens or standby offshore.
Stage 3: When approaching to the site 40% deck load shall be
transferred onto outrigger barges via further paying in the tension
winching rigging lines for preparing removal of the center barge.
Stage 4: Further tensioning up for a total lift and then ballast down
the center barge to achieve a sufficient clearance for undocking the
center barge and avoid any potential impact.
Stage 5: Position the catamaran and hook up the pre-installed
mooring lines and positioning soft lines. Upon docking in a
catamaran configuration, align the mating cones with the
substructure legs with soft-line positioning winches and spread
mooring lines. See Fig. 8a for details.
Stage 6: Lower the topsides by paying out the tension winching
riggings until the final setdown, that is, 100% deck load are
transferred onto the substructure. Upon confirming the full load
transfer, then disconnect all the riggings prior to undocking. Note:
the minimum boom angle shall be determined for the initial contact
while maintaining 100% deck load on the outrigger barges. Fig. 8b
shows the load transfer stage.
y
y
y
y
on the topsides, open the hatches and dump the drop tanks within
10 seconds so that the lifting arms will be lifted to touch the
topsides lifting points, meanwhile approximately 10% of the load is
transferred.
This is to ensure that the arms dont slam against the topsides, thus
tightly connecting together vertically and horizontally.
When both TMLs are connected to the topsides and the drop tanks
are emptied, set DP system on stand-by.
Pump water from the buoyancy tanks to the ballast tanks until 90%
of the topsides load is transferred to the TML lifting arms.
Meanwhile the drop tanks are refilled.
Prior to a total lift, remaining weight on each leg is checked and
adjusted if necessary. The hatches on the drop tanks are fully
opened so that the tanks can be emptied in about 10 seconds to
ensure that all the arms lift the topsides simultaneously by
approximately 2.5meters above the support grillage. See Fig. 9b.
Fig. 9a: TML Lifting Arm with Ballast & Buoyancy Tanks
Fig. 9b: Deck Transfer from Cargo Barge to HTVs prior to docking
y
y
y
y
17
Catamaran Technique
Several catamaran concepts are developed to perform floatover
installations and decommissions on conventional jackets, compliant
towers, and spar type floating substructures, etc. Allseas developed and
planned to build a multi-purpose dynamically positioned large platform
installation/decommissioning and pipelay vessel, Pieter Schelte, which
is 382 m long, excluding tilting lift beam protrusion and stinger, and
117 m wide and the largest offshore construction vessel to be ever-built.
Pieter Schelte will be classed as DP III and has a transit speed of 14
knots and an accommodation of 571 persons. For offshore
decommission and installation operations, the vessel will have a
capacity to handle topsides of 48,000 metric tons and jackets up to
25,000 metric tons. In addition, Pieter Schelte will be equipped with a
170m stinger, total tensioner capacity of 4500Te at 30m/min, and
pipelay capacity up to 6 to 68 O.D. pipelines.
18
and not as important as the fixed substructures. The water plane of the
floating substructure acts as a soft spring to absorb impact energy and
ease separation. However, the general requirement of a catamaran
barge configuration for spars may complicate the transportation process.
The increased water depth decreases the effectiveness of conventional
mooring and docking systems. Since the free-floating substructure is
also subject to motion, the relative motions between the barge and the
substructure may further complicate barge docking as well as
suppression of relative surge and sway motions. The deep water
presents challenges for docking operation, especially in heavy seas or
swell conditions.
special barge was devised and constructed to be suitable for the loadout,
transportation and installation of the two largest integrated topsides
ever floatover installed in open sea. The barge is capable of supporting
heavy loadout loads transferred from shore by skid ways and having
sufficient stability and ballasting capacity to operate in the various
conditions of loadout, transportation, and mating operations. The barge
consists of 33 ballast tanks with gravity filling system in order to
supply the required ballasting capacity and to minimize the impact
loads transferred to the GBS during floatover mating. The T-shaped
configuration can be divided into two major portions, one main barge
hull and two wing pontoons. The two pontoons are connected to the
port side and the starboard side of the aftbody of the main barge hull.
Both pontoons have same shape and dimensions. See Fig. 13b for the
configuration. The main particulars are given as follows:
Particulars
T-Shape Barge Length Overall
T-Shape Barge Width Overall
Values
190.0m
92.0m
45.0m
47.5m
23.5m
Depth Moulded
12.5m
Fig. 12: Pre-Docking Operation of P-52 SEMI Deck & Hull Mating
in a water depth of 50m inshore
19
concrete GBS. The massive topsides were then slowly and smoothly
lowered over the four legs by ballasting down the transport barge.
Special large capacity of four LMUs built into the four legs allowed the
topsides to achieve a perfect fit and acted as shock absorbers during the
initial contact and mating. The noticeable difference of the barge
comparing with other conventional cargo barges is the protruded
pontoons from its port and starboard at the aftbody outwards. The
pontoons are aimed to provide the additional stability while the frontal
area of the T-Shape barge also induces additional environmental loads
acting on the GBS structure.
CONCLUSIONS
DP Vessel Technique
The floatover technology has been growing to full stature as the
preferred installation and decommissioning methods for offshore
facilities. The wide range of its application has covered the strand-jack
lifting topsides onto the pre-installed piles in the extremely shallow
water of Bohai Bay, just 1.78m as per chart datum, and the twin-barge
floatover configuration of the topsides onto the floating spar hull
moored in the 1,320m deep water offshore East Malaysia in South
China Sea. Through building track records and benefits over modular
lifting installations, the floatover technology will be further developed
as a reliable means of installing and decommissioning different kinds of
offshore platforms. This paper intends to present the state of the art in
the floatover technology and systematically to classify various floatover
technologies, and therefore clarifying basic concepts of different
floatover techniques. This will not only benefit their further
development but also reveal the promising prospect of their wide
applications in installation and decommissioning of integrated topsides
onto and from various fixed and floating substructures.
ACKNOWLEDGEMENTS
Very special thanks to AkerSolutions, ALE/JGP, Allseas, Dockwise,
ETPM, Heerema, KBR, McDermott, Saipem, Technip, Versabar, and
WorleyParsons for their invaluable floatover experience and expertise,
as well as their valuable photograph courtesy.
Fig. 14: Mating Operation of Bunga Raya A Topsides with DP Vessel
REFERENCES
20