Contract C311333 - Amal Heat Recovery Steam Generator (HRSG) -1

Petroleum Development Oman LLC


Contract Number C311333
Amal Heat Recovery Steam Generator (HRSG) -1
Section C5,
Scheduel E - Milestones

Section C5, Schedule of Rates


Schedule E Milestones Rev 1 Oct.2011

Page 1 of 5

Contract C311333 - Amal Heat Recovery Steam Generator (HRSG) -1

SECTION C5
SCHEDULE E MILESTONES
The following definitions of Milestones (MS) and related Contract Price percentage
valuations shall apply in accordance with the terms of the Contract.

M
S
Re
f

Acceptance Criteria For Achieving


Milestone

Mobilisation:Completion/Approval of: The Contract Execution Plan with a


preliminary Construction Plan as per
C4-General Clause 4.4
Approval of Key personnel.
Documents To Be Submitted Within
42 Days from Effective Dateas

per
C4-General
Contractor has completed issue of
purchase order for the primary design
consultant who is appropriately
registered and approved by the
Company for this project.
Approval of Contract Work Plan and
Program.
Approval of Contract Quality Plan.
Approvals
of
Contract
HSE
Programme, Completed HSE kick of
meeting and detailed HSE Plan.
Issue of bank garantee
Site Establishment:Completion/Approval of: Completed and signed off HSE kick-off
meeting & HSE Workshop at Site
Completion/Approval of all activities
on 'HSE Certificate for mobilisation
Compliance' checklist.
Completion of all safety training and
equipment certification.
Completion
of
Contractors
Mobilisation including establishment
of site camp/fabrication facilities and
completion of route survey on Site.
Site leveling, grading and drainage
Detailed
Contract
Construction
Schedule.
Mobilisation
of
identified
Key
Personnel as per mobilisation periods
specified in document C4-General

Section C5, Schedule of Rates


Schedule E Milestones Rev 1 Oct.2011

% of
Contract
Price on
Mileston
e

Contract duration for


completion of
Milestone

Date for
completio
n of
Milestone
#

. Days
5%

(Bidder to
specify)

dd/mm/yyyy

dd/mm/yyyy
9%

90 Days
Penalty MS

Page 2 of 5

Contract C311333 - Amal Heat Recovery Steam Generator (HRSG) -1

Upon completion of issue of


purchase orders for following
equipment:

5a

5b

6.6kV and 415V Switchboards and


associated transformers.
Instrument Air Compressor
UPS (A/C & DC )
Steam & Drain Pipes (Bulk)

(Contractor to provide an unpriced copy of the full formal


written purchase orders and a
copy of acceptance and order
conformation by the Vendor)

10 %

90 Days

dd/mm/yyyy
Penalty MS

Upon Completion of Engineering


activities for:

Detail design including incorporating


PDO Design Reviews; IPF/HAZOP and
SAFOP comments to the satisfaction
of the Company

Issue of all design calculations


released for Construction of the Work
as per Clause 5.1.1 of C4 General
Scope

Issue of details to enable Company


to finalize protection settings

Approval of CCMS worksheets.

Upon completion of following Civil


Work:
All foundations for the HRSG Unit
and ancillaries
Upon completion of following Civil
Work:
HRSG Control Building
Blowdown pit.
Piperacks supports and piping.
Upon receipt at Site of following
equipment (including
documentation):

. Days
10 %

(Bidder to
specify)

5%

320 Days

5%

420 Days

10 %

390 Days

dd/mm/yyyy

Penalty MS

dd/mm/yyyy
Penalty MS
dd/mm/yyyy
Penalty MS

6.6kV and 415V Switchboards and


associated transformers.
Instrument Air Compressor
UPS (A/C & DC )
Steam & Drain Pipes (Bulk)

Section C5, Schedule of Rates


Schedule E Milestones Rev 1 Oct.2011

Page 3 of 5

Contract C311333 - Amal Heat Recovery Steam Generator (HRSG) -1

-Approval of SAP Data for EpC


scope as outline in SAP
format/Check sheets.
-completion of MS-4 activities
7

Upon
completion
of
following
work: Erection of HRSG column
Installation of Floor casing panel
Installation Wall casing panel
Installation Roof beam

. Days
10 %

dd/mm/yyyy

(Bidder to
specify)

Module erection
Pumps package installation
8

Upon completion of following work:

All electrical works

All instrument works

Energizing 6.6kV; 415v switchboard


and instrument air compressor.

All tie-in and interfaces with Power


Plant and AMAL Steam.

(Bidder to
specify)

12 %

550 Days

dd/mm/yyyy

Upon Mechanical completion and


pre-commissioning
of
HRSG
package including all auxiliaries

10

. Days
12 %

Mechanical completion EpC


scope of work and signed off all
construction check sheets.
- Completion of all loops checks,
function checks & Demonstration
of all Cause & Effects.
- Acceptance by the Company of
above Work as being ready for
commencement of Commissioning.
This includes satisfactory close-out of
pre-start-up audit, completion of all
training and closeout of all precommissiong punch list items.
Receipt of all spare parts in
Companys stores
Receipt of Approved Maintenance &
Operating Manuals

Completion: Completion of all access roads


and fencing
Completion of Commissioning,
demobilisation,
approval
the
Company of; 'As Built' drawings,
Operation
&
Maintenance
Manuals,Completion of all punchlist items together with Site
clearance and reinstatement.

Section C5, Schedule of Rates


Schedule E Milestones Rev 1 Oct.2011

dd/mm/yyyy
Penalty MS

. Days
10 %

(Bidder to
specify)

dd/mm/yyyy

Page 4 of 5

Contract C311333 - Amal Heat Recovery Steam Generator (HRSG) -1

# Note: Calendar dates for achievement of respective Milestones should be inserted at


the time of finalizing the contract documents.

Section C5, Schedule of Rates


Schedule E Milestones Rev 1 Oct.2011

Page 5 of 5