Академический Документы
Профессиональный Документы
Культура Документы
Abstract
In the Arabian Gulf, a rotary-steerable system utilizing pointthe-bit technology decreased the well-construction cost in
two Saudi Arabian offshore oil fields. Drilling offshore, in
many (if not all) parts of the world, is an expensive adventure.
Point-the-bit technology has successfully and consistently
controlled capital expenditures for wells in these offshore
fields and, in head to head comparisons, has cost less money
when compared to the conventional drilling systems that had
previously been used.
When it comes to offshore operational costs, time is a
nemesis. The application of point-the-bit technology as a
way to help solve this problem by permitting the economical
completion of a quality borehole will be discussed in this
paper. A major concern has been that the phenomenon known
as hole-spiraling which has created hole-quality issues.
These issues range from tortuous paths, torque-and-drag
frictional forces, key-seating or sump effects, and poor log
responses to name just a few of the problems. Thus, when the
quality of a borehole and the time it takes to drill it are
considered less than desirable, the drilling process and its
resultant effects increase well costs and reduce
operational efficiencies.
Several case histories within two offshore fields will be
presented in this paper. These case histories will show that
having the capability to make adjustments to downhole
drilling tools on-the-fly makes for better steering control
and creates better hole geometries. Correctly applying pointthe-bit rotary-steerable systems on these wells demonstrates
the value-added potential of this technology.
Introduction
The price and/or cost to do business in the oil-industry for
operations such as exploration, drilling, field-development,
and production has continually increased over time. Even in
SPE/IADC 85339
First (1223). This was the first run for the subject RST
system with point-the-bit technology in the Kingdom of
Saudi Arabia. The plan was to complete the 8 -in. build to
89.84 degrees at a build rate of 3 degrees/100 feet and
continue drilling to 10,239 feet MD. Since it was not known
how this RST system would respond, it was initially set for
maximum build (high-side tool-face at 100 percent
deflection). This setting was found to give build rates of
approximately 6.5 degrees/100 feet. The deflection was soon
reduced, and the build section was completed with a
combination of zero and 60 percent deflections in order to
achieve the required 3 degree/100 foot build rate.
In the lateral, it was found that zero deflection gave a build
of about 1.3 degrees/100 feet, and that an approximately 25
percent deflection on the low side would hold the angle. To
be sure no hole cleaning issues developed, the ROP was
limited to 120 feet/hour on instructions from the company
representative. It was evident, however, that a much higher
ROP could have been achieved at times.
The build was completed, and the 3,300 foot lateral section
was drilled in one 57-hour run with a PDC bit at an ROP of
69.7-ft/hr while still keeping within two-feet of the
proposed TVD.
Second (2227). This hole section was drilled with oilbased mud and the RST system using the maximum possible
drilling parameters. The angle and direction were controlled
with small deflection changes. After drilling approximately
3,000 feet, a short trip was made to add more drillpipe below
the HWDP and to check hole conditions.
The hole was in good shape, and the remaining 2,000 feet
was drilled to TD without problems. The 5,000 foot build and
lateral section was drilled in 58.5 hours for an average ROP of
85.5-ft/hr. At times, maximum rates as high as 150-ft/hr were
seen while drilling this hole section.
Third (3277). An across-the-board evaluation of this case
history indicates that it could have been a more costly
operation. Given the small target window operations had to
work in, a conventional system would probably have taken
longer to drill due to control problems. The on-the-fly
downlink command capability of the RST system enabled
corrections to be made without too much delay, something a
conventional system would not have been able to provide.
This 8 -in. hole section was drilled with an oil-based
mud. The 6 -in. Geo-Pilot system exhibited excellent
trajectory control and held within the two foot TVD window
requested by Reservoir Management.
This BHA drilled a total of 3,188 feet in 60.5 hours for an
average ROP of 52.6-ft/hr., a little slower than previously
seen. With constant doglegging to keep within a specific
window and being oriented 65 percent of the time, ROP
inevitably suffered. Averages of 80-ft/hr were achieved when
on bottom drilling. Torque was never an issue in this hole
section. Upon reaching TD, no tight spots were noticed when
the BHA was pulled out of the hole.
The 12 -in. hole section leading up to the 8 -in. hole
was also drilled with the subject RST system. The 1,445 feet
was drilled to a >71 degree inclination in 23 hours for an
average ROP of 62.8-ft/hr. Based on previous technical
literature,3 it is plausible to believe the ease with which the 8
-in. hole section was drilled, along with the low frictional
SPE/IADC 85339
SPE/IADC 85339
Conclusions
This paper discussed how time and hole cleaning can be
independent measures, but either one can be dependent on the
other. A mechanical issue that was not really addressed was
the reduction of downhole vibration. This concern mostly
affects the bottom line of service companies by reducing the
amount of time, thus affecting wear and tear on drilling and
MWD/LWD tools. This consideration can also have an effect
on time, thus affecting the amount of money spent due to
hole quality.
There were three wells in which the 12 -in hole sections
were drilled with the Geo-Pilot system. They were briefly
mentioned but were not fully described as further analysis is
required to determine the feasibility of future use for this
system in this hole section. Other conclusions concerning
these case histories that involved Geo-Pilot include:
1.
2.
3.
4.
Acknowledgements
The authors wish to thank the management of both Saudi
Arabian Oil Company (Saudi Aramco) and Halliburton
Sperry-Sun for permission to publish this paper. We also wish
to thank the personnel on location from both companies who
worked hard to ensure the operations were safely and
successfully completed.
Nomenclature
BHA =
ft/hr
=
MD
=
ROP
=
RST
=
TD
=
TVD
=
References
1.
2.
3.
4.
SPE/IADC 85339
FIELD CASE 1
Wells
Hole Size
(in)
Footage
(ft)
Est ROP
(ft/hr)
Drlg
Days
Est. #Bits
* Cost #1
(000s USD)
Act. ROP
(ft/hr)
Drlg
Days
* Cost #2
(000s USD)
1223
8.500
3992
54.4
3.1
345.5
70.0
2.4
313.9
2227
8.500
5000
54.4
3.8
405.2
85.5
2.4
321.5
3277
8.500
3188
54.4
2.4
298.0
52.7
2.5
327.2
4276
8.500
595
54.4
0.5
145.5
91.5
0.3
132.9
5324
8.500
3860
54.4
3.0
337.7
89.8
1.8
264.0
12.7
1531.9
9.3
1359.5
TOTALS
FIELD CASE 2
Wells
Hole Size
(in)
Footage
(ft)
Est ROP
(ft/hr)
Drlg
Days
Est. #Bits
* Cost #1
(000s USD)
Act. ROP
(ft/hr)
Drlg
Days
* Cost #2
(000s USD)
1157
8.500
4740
38.6
5.1
462.1
56.8
3.5
423.4
2159
8.500
3363
38.6
3.6
357.2
55.6
2.5
336.3
6.0
759.7
*Cost
#1:
*Cost
#2:
TOTALS
8.7
2
Includes rig cost, PDC bits, drilling services, and trips in and out of hole
819.3
Includes rig cost, Geo-Pilot system, and trips in and out of hole
Table 1. Cost summary of Geo-Pilot RST system versus the planned conventional summary of drilling data for field case history wells
Well 3277
Well 4276
Well 6325
Item(s)
O.D.
(in)
Item(s)
O.D.
(in)
Item(s)
O.D.
(in)
Item(s)
O.D.
(in)
Item(s)
O.D.
(in)
Bit
8.500
Bit
8.500
Bit
8.500
Bit
8.500
Bit
8.500
Bit
8.500
Geo-Pilot
6.750
Geo-Pilot
6.750
Geo-Pilot
6.750
Geo-Pilot
6.250
Geo-Pilot
6.750
Geo-Pilot
6.750
FE Stab.
6.800
M/LWD
6.750
M/LWD
6.750
M/LWD
6.750
M/LWD
6.750
M/LWD
6.750
M/LWD
6.750
M/LWD
6.750
M/LWD
6.750
Float Sub
6.750
M/LWD
6.750
M/LWD
6.750
Float Sub
6.500
Float Sub
6.500
FEWD
6.750
Flex DC
6.750
Float Sub
6.500
FEWD
6.750
Stabilizer
8.500
HWDP
5.000
Float Sub
6.500
Spiral DC
6.500
HWDP
5.000
Float Sub
6.500
HWDP
5.000
Drlg Jar
6.300
Stabilizer
8.000
Drlg Jar
5.000
Drlg Jar
6.500
HWDP
5.000
Drlg Jar
6.500
HWDP
5.000
HWDP
5.000
Sub
6.300
HWDP
5.000
Drlg Jar
6.500
HWDP
5.000
DP
5.000
Drlg Jar
6.500
HWDP
5.000
DP
5.000
HWDP
5.000
DP (G)
5.000
HWDP
5.000
HWDP
5.000
HWDP
5.000
DP
5.000
HWDP
5.000
DP
5.000
HWDP
5.000
HWDP
5.000
Table 2. Geo-Pilot system BHA assemblies used in the field case history wells
SPE/IADC 85339
Field
Well
Motor
Run
Hole Size
(in)
Footage
Drilled
(ft)
Inc In
(deg)
Inc Out
(deg)
Azi In
(deg)
Azi Out
(deg)
Drlg
Time
(hrs)
Avg ROP
(ft/hr)
1223
GP-1
8.500
3992
68.7
89.9
348
348
57.0
70.0
2227
GP-1
8.500
5000
89.2
90.0
93
90
58.5
85.5
3277
GP-1
8.500
3188
73.2
91.1
24
20
60.5
52.6
4276
GP-1
8.500
595
80.1
90.9
291
292
6.5
91.5
5324
GP-1
8.500
3860
81.1
89.9
337
329
43.0
89.8
1157
GP 1
8.500
4740
62.5
64.7
104
100
83.5
56.8
2159
GP 1
8.500
3363
84.8
89.9
144
144
60.5
55.6
$4.00
$5.00
$1.00
$2.00
$3.00
$ / BBL Produced
Direct Lifting Cost
Fig. 1 Lifting cost comparison worldwide
SPE/IADC 85339
100.0
6000
5000
4000
80.0
60.0
3000
2000
1000
0
40.0
20.0
0.0
1223
2227
3277
4276
5324
1157
Wells
Footage Drilled (ft)
Fig. 4 ROP comparison between wells versus drilled footage
2159
ROP (ft/hr)
Drilled Footage
(ft)