Вы находитесь на странице: 1из 26

ChE3070 Spring 2015

Capital Investment - I
Chemical Engineering 3070

Process Economics & Simulation

Lecture 6
Capital Investment - I

Adjunct Professor John Myers

jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Agenda
Capital

Types of Capital
Estimating

Types of Estimates
Cost Indexes
Components of Capital Investment
Scale Factors and Scaling Equation & Capacity Cost Curves

jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Capital
Capital: accumulated wealth; savings that the owner can use as desired

How is Capital Used?

Financial investments (CDs, stocks, bonds)


Investment in producing assets (real estate, chemical plants, )

Lots of capital terms/definitions be careful !


jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Types of Capital
Fixed Capital Investment (FCI); also called Capital Costs

Capital required to install processing equipment with all components required for
operation
Manufacturing Fixed Capital Investment (MFCI): capital required for the process
itself
Non-Manufacturing Fixed Capital Investment (NMFCI): required to support the
process; land, admin buildings, labs, shipping/receiving,
Construction Overhead (CO): construction offices, engineering expenses, etc.;
sometimes proportioned and included in MFCI and NMFCI

FCI = MFCI + NMFCI + CO


Total Capital Investment (TCI) : FCI plus Working Capital (WC)

TCI = FCI + WC
jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Working Capital
Total money for a plant that is invested for:

Raw materials and supplied in stock (inventory)


Finished products in stock (inventory)
Accounts receivable
Accounts payable
Cash on-hand for operating expenses (salaries, utilities,
purchasing, )
Taxes payable

NOTE: negative CF at start-up (usually T=0) and


positive CF at end of project
jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Working Capital
Common Assumptions:

Raw materials and supplied in stock: 1 month


Finished products in stock: 1 month

Accounts receivable: 1.5 month production cost


Accounts payable: 1 month of expenses
Cash on hand: 0
Taxes: 0
Companies/Business Units usually have specified assumptions
Often estimate as % of TCI (typically 10-20% TCI, but can be up to 50%)
jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Working Capital
Cash Flow Implications

-CF at start-up (usually T=0)


+ CF at end of process life (which may be longer than project
evaluation assumption)
Can inflate through a series of extra mini-CFs
Not taxed
Not a Cash Expense
Not depreciated

BUT it affects NPV and IRR


jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

Estimating Capital Investment


Fixed Capital Investment (FCI)

Most based on cost of individual pieces equipment that are summed


or based on cost of similar plants

Direct Costs
Indirect Costs (same as Contractor Overhead CO)

jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

FCI Direct Costs


P&T Table 6-1 and Table 6-9
Direct Costs
Purchased equipment
Installation of above
Instrumentation and control
Piping
Electrical systems
Buildings (maint shops, operations buildings, control rooms, )
Site Improvements (sidewalks, roads, )
Service Facilities (utilities, packaging, facilities, )
Land
jemyers

3070_6_capital_I.ppt

ChE3070 Spring 2015

FCI Indirect Costs


P&T Table 6-1
Indirect Costs
Engineering & Supervision
Legal
Construction Expenses (trailers, tools, guards, safety, training,
permits, taxes, insurance, )
Contractors Fee
Contingencies

FCI = Direct Costs + Indirect Costs


jemyers

3070_6_capital_I.ppt

10

ChE3070 Spring 2015

FCI ISBL & OSBL


ISBL (Inside Battery Limits)

Process itself
OSBL (Outside Battery Limits)

Tanks, buildings, etc


Often a % of ISBL but can be location specific (0 > 20% typical)
FCI = ISBL + OSBL

Battery Limits: a geographic boundary defining a project; tankage,


buildings usually are OSBL
jemyers

3070_6_capital_I.ppt

11

ChE3070 Spring 2015

Types of Capital Estimates


Based on expected accuracy; GENERALLY greater accuracy means
more work
Order of Magnitude (Scoping) Estimate: +/- 30%; usually a
generalized correlation or ratio

P&T

Factored (Study or Scoping) Estimate: +/- 30%; estimate major


equipment purchase cost and then apply a factor
Preliminary (Budget) Estimate: +/- 20%; factored and computer
models; often used for project approval
Definitive (Project Control) Estimate: +/- 5-10%; computer models

Detailed Estimate: +/- 5%; based on bids, quotes; provided by project


engineering contractor; very expensive to generate
jemyers

3070_6_capital_I.ppt

12

ChE3070 Spring 2015

Types of Capital Estimates


Corporations usually have assumptions for accuracy of estimate
required:
Amount of capital required
State of process technology (risk)
R&D, initial proposals, budget approval,
Stage Gate Process
series of approvals with each requiring better process
information and better capital estimates
Appraise, Select, Define, Execute
jemyers

3070_6_capital_I.ppt

13

ChE3070 Spring 2015

Types of Capital Estimates


Required Information for Different Types of Estimates

P&T Figure 6-4


Comments:

All estimates require heat material balance information (usually


from simulations); more detailed as capital estimates increase
All require process flowsheets of some sort Aspen simulator

jemyers

3070_6_capital_I.ppt

14

ChE3070 Spring 2015

FCI Computer Modeling


Two major programs for chemical process capital estimation

ICARUS Suite
Richardson Process Plant Cost Estimating Standards

Can get very accurate installed capital estimates


new units & debottlenecks & retro-fits
Both from Aspen Technology (www.aspentech.com)
we wont be using these
highly specialized training reqd
jemyers

3070_6_capital_I.ppt

15

ChE3070 Spring 2015

Cost Indexes
Allow escalation of capital costs with time

Inflation
Many different but the Marshall & Swift and Chemical Engineering
(CE) indices are most commonly used.
Also, refer to
For class, well use CE index. Refer to Table 6-2.

Cost Index
PDF file

CE published regularly at end of the Chemical Engineering magazine


WyoWeb e-Journal

FCInow = FCIpast * Indexnow / Indexpast


jemyers

3070_6_capital_I.ppt

16

ChE3070 Spring 2015

Cost Indexes
Example:

A plant cost $200,000,000 in 1990


CE Cost Index 1990 = 357.6

What is the cost in 2000?


CE Cost Index 2000 = 394.1

Cost2000 = 200E6 * 394.1 / 357.6 = 220.4E6

jemyers

3070_6_capital_I.ppt

17

ChE3070 Spring 2015

Components of Capital Investment


General Guidelines in following P&T Tables:

Table 6-3

% of different components as f(FCI)

USEFUL

Table 6-5

Installation cost as % of purchased equipment cost

for different types of equipment


Table 6-6

Piping as a f(FCI) for different types of processes

Table 6-9

Summary of Typical Values


as f(delivered equip cost)

jemyers

3070_6_capital_I.ppt

Refer to
Inst Factor
XLS file

18

ChE3070 Spring 2015

Table 6-9
Table 6-9 is used to essentially create your own, customized
Installation Factor.
Other Tables in Chapter 6 can be used to provide adjustments to the
usual values provided in Table 6-9
Table 6-5 Installation of equipment as f(FOB)
Table 6-6 Piping labor and materials as f(FOB) and f(FCI)
Table 6-7 Buildings as f(FOB) and f(FCI) and f(site-type)
Table 6-8 Different Services as f(FCI)
Table 6-12 Relative Labor rates and productivity
Installation
Note that Installation of Purchased Equipment is a separate line item
Note that installation of Instruments, Piping, etc is included in these
individual line items
jemyers

3070_6_capital_I.ppt

19

ChE3070 Spring 2015

Components of Capital Investment


P&T Table 6-3 Comments:

Purchased Equipment is 15>40% of FCI


FCI = (2.5 > 7) * Delivered Equipment

FCI = Install_Factor * Delivered Equipment


Sometimes FCI = Install_Factor * FOB
Large % Items:
Engineering
Buildings
Construction Expenses
Piping
Service facilities
jemyers

NOTE:
Purchased Cost often called
FOB (freight on board) cost;
does NOT include delivery!

3070_6_capital_I.ppt

20

ChE3070 Spring 2015

Capital Costs by Scaling


Based on graphs like below. NOTE: usually do NOT include delivery!

jemyers

3070_6_capital_I.ppt

21

ChE3070 Spring 2015

Capital Costs by Scaling


Cost on y-axis

Size Basis on x-axis


Usually reference a date.

Specific diagrams for different equipment


Multi-curves for equipment options and materials of construction

Usually straight line on ln-ln plot


Costa = Costb (Sizea/Sizeb)SE
jemyers

3070_6_capital_I.ppt

22

ChE3070 Spring 2015

Capital Costs by Scaling


Costa = Costb (Sizea/Sizeb)SE
SE is the Scale Exponent
usually between 0.5 and 0.8; 0.6 or 0.65 are most common
six-tenths rule (use 0.6 for SE)
economy of scale

P&T Table 6-4 has list of SEs

jemyers

3070_6_capital_I.ppt

23

ChE3070 Spring 2015

Capital Costs by Scaling


Costa = Costb (Sizea/Sizeb)SE

NOTE: can include escalation indexes as:


Costa = Costb ( Sizea/Sizeb )SE ( Indextime/Indexb )

Example:
Use SE=0.6
Cost of HtEx with 2000 ft2 = 1E6
Cost of HtEx with 4000 ft2?
Cost4000 = 1E6 * (4000/2000)0.6 = 1E6 * 1.516 = 1.516E6
jemyers

3070_6_capital_I.ppt

24

ChE3070 Spring 2015

Process Specific Capacity Curves


Usually Same form as above (straight line on ln-ln plot)

Cost usually $/lb or $ basis


Usually based on building many similar technology plants of differing
sizes
Can be for sections of a process or an entire process
Often very accurate (+/- 20%)
Example:
Cost/tonne = 2 * Tonne_per_year 0.5
What is cost of a 300000 tonne per year plant?
Cost/tonne = 2 * 300000 0.5 = 2 * 548 = 1096
Cost = 300000 * 1096= $328,800,000
jemyers

3070_6_capital_I.ppt

25

ChE3070 Spring 2015

FCI many definitions


FCI = MFCI + NMFCI + CO

FCI = Direct Costs

+ Indirect Costs

FCI = ISBL + OSBL

FCI = Install_Factor * Delivered Equipment

FCI

is NOT

TCI

TCI = FCI + WC

jemyers

3070_6_capital_I.ppt

26

Вам также может понравиться