Академический Документы
Профессиональный Документы
Культура Документы
IN SOLVENT EXTRACTION
by Baxter1 K.G., Richmond2 G.D., and White3 M.
1 Technical Manager - Copper - Bateman Brown and Root.
2 Group Metallurgist - Western Metals.
3 Manager, Mineral Processing ConSep Pty Ltd.
1.0 INTRODUCTION
In October 1998 a new autoclave leaching and solvent extraction circuit was commissioned on
the Gunpowder Copper mine site (subsequently Mt Gordon Operations, Western Metals) in
Northern Queensland to treat secondary copper sulfides. A key component of the new process
plant was the Pregnant Liquor Solution (PLS) clarification circuit which was developed around
the concept of a Pinned Bed Clarifier (PBC).
The concept of the PBC is not new. Small scale
units operating on similar principles have been
used on river water clarification in Africa and a
device described as buoyant media filtration has
been used in the electroplating industry. The
incentive to progress application of the
technology came from the failure of conventional
clarification options to meet the tight
requirements for suspended solids levels in the
PLS liquor feed to solvent extraction.
Research of published literature on the topic (see
references) established that a PBC should be
capable of meeting the project process
requirements. Bateman Process Equipment
(BPE) were approached to assist in the
development of a test work program and to
provide a pilot rig to evaluate the performance of
a unit on real liquors produced in a pilot plant on
site.
Picture 1: Pinned Bed Clarifier
The pilot unit design was based around the Ultrasep thickener configuration with the required
modifications. Data from the pilot test program met process expectations and a decision was
made to proceed to engineering.
2.0
PROCESS ISSUES
A key issue in the design of an agitated leach followed by solvent extraction is to ensure that
the PLS feed to solvent extraction is properly clarified and protected from process upsets. The
process requirement was to produce a PLS stream containing less than 40 ppm suspended
solids.
The process slurry entering the solids liquid separation stage can be categorized as follows:
Solution Flowrate
Solids Flowrate
Temperature
Size Distribution
Liquor S.G.
pH
Test work had shown that under normal operation the overflow from a thickener treating
leached slurry contained too high a level suspended solids for subsequent sand filtration prior
to solvent extraction. Attempts to further coagulate/flocculate those fines were unsuccessful.
Evaluation of a range of pressure filters with and without precoat failed to provide satisfactory
unit filtration rates and the requirement for precoat was excessively high.
However if the thickener was allowed to run dirty by the reduction/elimination of flocculant
addition then the subsequent dirty overflow could be readily coagulated and flocculated. That
is, a certain minimum solids loading was required before sufficient size flocs could be formed.
A range of coagulants and flocculants were tested. Responses varied with different ore types
but a combination of up to 20 ppm PEG coagulant and 20 ppm of nonionic flocculant give the
best results.
The process issue then became one of clarifying a PLS stream of up to 283 m/h containing
5,000 - 50,000 ppm suspended solids of less than 10 m to <40 ppm suspended solids. The
suspended solids were a mixture of fine pyrite, silica, gangue and sulphur that exhibited a
bimodal size distribution with peaks at 0.8 microns and 8 microns. The ultra-fines present in
this stream proved to be difficult to filter by conventional means.
Sand filters cannot be used at the high suspended solids loading hence the initial test work
focussed on pressure filtration with and without a precoat on the filter cloth. Subsequent
evaluation of a range of pressure filter equipment and precoat types failed to provide
satisfactory unit filtration rates and the requirements of precoat were excessively high.
Filtration of the PLS through a flocculated blanket of solids was proposed and after some
investigation and a literature survey of the concept, it was decided to produce a pilot unit. The
unit was taken to site and installed as part of the pilot plant that was operated on site to provide
test work data for the process.
The results achieved were within the target suspended solids range and there was sufficient
confidence in the robustness of the concept to proceed to engineer a full scale unit to the
required duty.
3.0 CONCEPT
The concept of a PBC differs from the wide range of flocculated bed clarifiers that have been
used in the mining industry to date. Most have relied on the rise velocity of the solution to
suspend the bed and as such the operation of a unit was sensitive to fluctuations in the feed
rate.
In this case, as illustrated by Figure 1, the PBC comprises a cone and outer cylinder outer
body similar to a pachuca with a central feed pipe down to the level of the top of the cone. The
greater proportion of the flocculated solids are withdrawn through the base of the cone and a
smaller proportion rise with the liquor flow and are pinned against a layer of fine beads that are
in turn pinned against a fine screen deck. The screen is located horizontally in the top of the
cylindrical section of the unit.
Feed
Feed pipe
Liquor
Level
Overflow Launder
Screen
Overflow
Beads
Pinned Bed
Backwash Pipe
Underflow
Figure 1: Pinned Bed Clarifier
Configuration
The feed pipe is extended above the platform level on the top of the unit and the differential
head between the overflow of the clarifier and the level in the feed pipe provides a measure of
the differential head through the flocculated bed.
The benefits of this approach are:
Periodically, the clarifier can be back-washed and the flocculated bed back flushed out the side
of the unit. Once the bed is re-established, the unit returns to service.
Conceptually, the PBC satisfied the requirements of the process.
The components were installed in the Ultrasep and test work commenced. Partly due to the
short time scale and partly due to the nature of test work a number of minor problems were
experienced with the feed arrangements. These problems included variation in the feed flow
rate, variations in the feed density due to the manual mixing of the synthetic feed and coarse
particles scooped up with the dry filtrate blocked control valves and the static mixer. The
modifications to the Ultrasep also proved to be less than ideal in some areas.
Despite these problems the first round of test work showed excellent promise. Output clarity,
although variable, was significantly better than that achieved with conventional clarifiers, with
some readings better than 40 ppm. Viewing windows in the Ultrasep allowed observation of the
bed formation, conditions leading to channeling through the bed and the impact of backwash
on bed cleaning. The test work showed that significantly better clarity was achieved by dosing
floc well ahead of the test unit to allow for floc contacting.
Information gained from the first round of testing was used
in the design of a dedicated PBC demonstration unit
(Picture 3). The PBC demonstration unit is a simplified
section through a PBC. The diameter is only 200 mm so
flows are well within the capacity of small scale pilot plants.
It is constructed entirely in plastic both for corrosion
resistance and to allow easy observation of floc build up
and cleaning. The unit was provided with a small header
tank which does the dual duty of providing residence time
for floc contacting and gives variable head to drive the
system. A manual backflush valve was provided.
A test program was commenced using the PBC
demonstration unit. Work was carried out to optimize the
type of beads used in the pinned bed, establish driving
head required, throughputs, backflush rates and estimated
period between backflushing. Regular samples were taken
for overflow clarity. Information collected in the first round of
testing proved invaluable as a springboard to the second
test series which was very successful. The 200 mm PBC
demonstrator produced consistent overflow clarity of better
than 20 ppm with some figures as low as 12 ppm. Build up
rate of the pinned bed, throughput, backflush rates and
driving head were very consistent throughout the testing
giving us good confidence in the data.
Picture 3: Clarifier Pilot Plant
Commissioning of the Gunpowder PBC and subsequent test work at other sites has shown
that scale up from the 200 mm unit to full size is reliable and has allowed us to establish the
operating parameters for the PBC on a range of different feed types.
Nonionic Flocculant
Cationic Flocculant
Flowmeter
In Line Mixer
CCD Wash
Circuit
Backwash
Valve
Coagulant
Leach Circuit
Discharge
PID
Sand
Filters
Control
Valve
VSD
Control
Valve
Residue
Filter
VSD
Transfer
Tank
Pinned Bed
Clarifier
VSD
Flocculant
Conditioning
Tank
Surge Tank
Hydroclassifier
Clarifier overflow is pumped from the transfer tank to a series of three sand filters operating in
parallel which perform a final clarification on the PLS. The sand filters also act as a final safety
check against any process upset of the pinned bed which could discharge high levels of
suspended solids to solvent extraction. In practice, the concept of providing the sand filter
backup has proved to be correct and on irregular occasions has performed the duty required
with very high but short term solids feed loading.
1400
1200
PPM
1000
800
600
400
200
Date
Graph 1: Pinned Bed Clarifier Performance
1/05/99
1/04/99
1/03/99
1/02/99
1/01/99
1/12/98
1/11/98
1/10/98
1/09/98
1/08/98
8.0 CONCLUSIONS
As a first time installation a number of process, mechanical and operational problems were
experienced. As our knowledge and experience with the unit has increased these have been
overcome so that the PBC is now an operationally robust and stable piece of operational plant. It is
able to handle a wide range of flows and solids loading without constant attention from the
operators. Clarity is not affected by solids in feed or by throughput within the design range.
Operation attention is decreasing as experience is gained with the unit.
The test work and scale up procedure has been shown to be reliable and consistent. Mechanical
design has been improved to overcome initial structural problems and the loads applied by
operation of the machine are now well understood, providing a sound basis for future designs.
Further design refinements present themselves as a means of improving operation in aspects
such as bead loading.
The combination of the PBC and sand filters provides good output clarity at far lower capital and
operating costs than pressure filters alone. In many cases the PBC alone may suffice.
Solution clarity is becoming an issue on more and more processing plants with the increasing
prevalence of hydrometallurgical process routes. The PBC represents a unique new process
option for plants where solution clarity is an issue. PBC test work has now been carried out at a
number of other sites. This work has confirmed the operating parameters and clarities achievable
and provided a reliable model for design and performance prediction. The Pinned Bed Clarifier can
now be offered as a standard piece of equipment with confidence in its performance.
REFERENCES
Scalise J. Filtration concepts for water soluble non ferrous wire drawing.
International
Wire Journal