Вы находитесь на странице: 1из 10

Chapter 5

Present Worth
Analysis

Background

An engineering project or alternative is formulated to make or purchase a product,


to develop a process, or to provide a service with specified results

An engineering economic analysis evaluates cash flow estimates for parameters


such as initial cost, annual costs and revenues, etc., over an estimated useful life of
the product; process, or service

We have learned some basic tools in pervious chapters

In this chapter (and next few chapters.Stage 2) we are going to use the basic tools
(we learnt already) with some more techniques to evaluate one or more
alternatives using the factors and formulas learned in Stage 1

After completing these chapters, you will be able to evaluate most engineering
project proposals using a well-accepted economic analysis technique, such as
present worth, future worth, capitalized cost, life-cycle costing, annual worth, rate
of return, or benefit /cost analysis

Engineering Economy

Why we need this Chapter ?


(Present Worth Analysis)

Content of the Chapter

A future amount of money converted to its equivalent value now has a


present worth (PW) that is always less than that of the future cash flow,
because all P/F factors have a value less than 1.0 for any interest rate
greater than zero

1.

Formulate Alternatives

2.

Present Worth of equal-life alternatives

For this reason, present worth values are often referred to as


discounted cash flows (DCF) , and the interest rate is referred to as the
discount rate

3.

Present Worth of different-life alternatives

4.

Future Worth analysis

Up to this point, present worth computations have been made for one
project or alternative

5.

Capitalized Cost analysis

In this chapter, techniques for comparing two or more mutually


exclusive alternatives by the present worth method. Full details of
contents of the chapter is on next slide

From Chapter 1:
Steps in an Engineering Economy Study
Step 1 in
Study
Step 2

Available data
Alternatives for solution

Step 3

Cash flows and other


estimates

Step 4

Measure of worth criterion


(PW, B/C, IRR etc)

Step 5

Engineering Economic
Analysis

Step 6

Best alternative Selection

One or more approaches to


meet objectives

Expected life
Revenues
Costs
Taxes
Project Financing

Step 1 in
Study

concept from probability theory

Implementation and
Monitoring
New Problem description

Mutually Exclusive events

If two events cannot occur at the


same time, it is called mutually
exclusive events

Mutually exclusive means two


outcomes cannot happen
simultaneously

An example is tossing a coin


once, which can result in either
heads or tails, but not both.

Tools u will be learning in


this course are used here

Time Passes
Step 7

Two types of the Events: basic

Problem description
Objective statement

New engineering economic


study begins

Independent Events
One event is independent of
the other event
In this case the occurrence of
one event is totally
independent of another
event
E.g., it rained today. And a
chair broke down in office
today. These are two
independent events

Formulating Alternatives

Project or alternatives types


based on Cash flows

Two types of economic proposals:


1.

Mutually Exclusive (ME) Alternatives: Only one proposal can be


selected; Compete against each other and are compared pairwise. These
proposals are normally called alternatives
e.g., A selection of Best diesel powered engine among the available models

2.

Independent Projects: More than one can be selected , these proposals are
called projects; it competes only against DN

Do Nothing (DN) An ME alternative or independent project to


maintain the current approach; no new costs, revenues or savings
In this chapter, we will learn Present Worth Method to
evaluate either type of proposal ..in next chapters we will learn
some more such techniques.

There are two types of alternatives based on Cash flows


1. Revenue each alternative project being evaluated generate
costs and revenues over life period of alternative.
E.g., new systems, products/services that involve capital costs
Criteria of selection is to maximize the economic measure (e.g.,
profit in case of introducing new product).
2. Cost ( or service based) Each alternative has only cost cash
flow estimates (revenues are same for all alternatives)
E.g., which 100-seat plane to buy?
Criteria of selection is to minimize the economic measures (e.g.,
in this case cost of buying 100-seat plane)

Example 1: Selection of Alternatives

Mandates, Ideas, identifications,


experience, Plans, Estimates

Not viable

viable

Formulating
Alternatives

Mutually
Exclusive
Alternatives

Select
only
one

Either of
these

1
2
3
.
.
.
m

by Present Worth Criteria

For the alternatives shown below, which should be selected if they

Not viable

are (a) mutually exclusive; (b) independent?

Project ID

Independent
projects

Select
all
justifi
ed

1
2
3
.
.
.
DN

Solution:

Type of Cash flow Estimates


- Revenue Alternatives
- Cost Alternatives
Revenues and costs
Costs only

Present Worth

A
B

$ 30,000
$ 12,500

$ 4,000

2,000

(a) Select numerically largest PW; alternative A


(b) Select all with PW > 0; projects A, B & D

Performance evaluation and make selection

Present Worth Analysis


Evaluation

Present Worth (PW) analysis

Mutually exclusive projects


This is the process of obtaining the equivalent worth of future
cash flows at present time

That is, finding PW of cash flows

We say that future cash flows are discounted to time 0

The higher the PW, the better PW is evaluate based on an


interest rate, which is equal to the organizations MARR

For one project, it is financially viable if PW 0.


For 2 or more alternatives, select the one with the
(numerically) largest PW value.

Independent Projects

Select all projects with PW 0


However, in practice a budget limit exists (details in chapter 12)

REMEMBER: This Evaluation is for the case when


alternatives have equal life

Example 2: PW evaluation of equal-life


Mutually Exclusive alternatives

PW Analysis Procedure
The present worth method is quite popular in industry
because all future costs and revenues are transformed
to equivalent monetary units NOW

Alternative X has a first cost of $20,000, an operating cost of $9,000 per year, and a
$5,000 salvage value after 5 years.
Alternative Y will cost $35,000 with an operating cost of $4,000 per year and a salvage
value of $7,000 after 5 years.
At an MARR of 12% per year, which should be selected?

Solution:

This Criteria work as follows;

Cash flow diagram ? Any one ?

Find PW at MARR and select numerically larger PW value

Convert all cash flows to Present Worth (same as


present value) using MARR
Precede costs by minus sign; receipts by plus sign

PWX = 20,000 9000(P/A,12%,5) + 5000(P/F,12%,5)


= $49,606
PWY = 35,000 4000(P/A,12%,5) + 7000(P/F,12%,5)
= $45,447

Class Practice: 5 minutes

Electric powered

First Cost($)
Annual Operating Costs ($/year)
Salvage value S ($)
Life years
10%

Gas powered

4500
900
200
8

Single Payments

Solar powered

3500
700
350
8

600
50
100
8

Uniform Series Factors

Compound
Amount

Present
Worth

Sinking Fund

(A/F)

Compound
Amount

2.1436

0.4665

0.08744

11.4359 0.18744 5.3349

(F/P)

(P/F)

(F/A)

Capital
Recovery

(A/P)

Present
Worth

(P/A)

PW of Different-Life Alternatives
For alternatives with unequal lives the rule is:
PW must be compared over the same number of years
This is called equal service alternatives requirement (i.e.,
alternatives must end at the same time) Why its
important ?
Because if this condition is not meet, For COST
ALTERNATIVES (which involves only cost) will always favor
the shorter-lived mutually exclusive alternative, even if it is
not the more economical choice, because fewer periods of
costs are involved

Precede costs by
minus sign; receipts by
plus sign

Practice: Example 5.1

Select alternative Y

A university lab is a research contractor to NASA for in-space


fuel cell systems that are hydrogen and methanol-based. During
lab research, three equal-service machines need to be
evaluated economically. Perform the present worth analysis
with the costs shown below. The MARR is 10% per year.

Convert all cash flows to


Present Worth (same
as present value) using
MARR

Class Practice
Electric powered
First Cost($)
Annual Operating Costs ($/year)
Salvage value S ($)
Life years
10%

Gas powered

Solar powered

4500

3500

600

900

700

50

200

350

100

Single Payments

Uniform Series Factors

Compound
Amount (F/P)

Present
Sinking Fund
Worth (P/F) (A/F)

Compound
Amount
(F/A)

2.1436

0.4665

11.4359 0.18744 5.3349

0.08744

Capital
Recovery
(A/P)

Present
Worth
(P/A)

PWE = 4500 900( P/A ,10%,8) + 200( P/F ,10%,8) = $9208


PWG = 3500 700( P/A ,10%,8) + 350( P/F ,10%,8) =$7071
PWS = 6000 50( P/A ,10%,8) + 100( P/F ,10%,8)= $6220
$6220 Solar powered alternative should be
selected

PW of Different-Life Alternatives
The following are two equal ways of meeting the equal
service requirements:
1. Least Common Multiple (LCM) of alternative lives
Compare the PW of alternatives over a period of time
equal to the least common multiple (LCM) of their
estimated lives
2. Study Period Approach
Compare the PW of alternatives using a specified study
period of n years. This approach does not necessarily
consider the useful life of an alternative. The study period
is also called the planning horizon.

LCM of Alternative Lives


Approach
This approach compare the PW of alternatives over a
period of time equal to the least common multiple
(LCM) of their estimated lives

Three assumptions of LCM Approach


1. The service provided is needed for LCM years or
more.
2. The selected alternative is repeated over each life
cycle of the LCM in exactly the same manner.
3. Cash flow estimates are the same in every life cycle
(i.e., change are exactly by the inflation or deflation rate only)

Evaluation of Present Worth


Using a LCM Approach
First, find the LCM for the life of alternatives
Expand the cash flows for each alternatives till the
LCM period thus meeting the equal service
requirement
Calculate the present worth for all the alternatives
Use the criteria used for Equal Life Alternatives to
evaluate the alternatives

Evaluation of Present Worth


Using a Study Period

Study Period Approach


Compare the PW of alternatives using a specified
study period of n years. This approach does not
necessarily consider the useful life of an
alternative. The study period is also called the
planning horizon.
A study period analysis is necessary if the first
assumption of LCM approach (i.e., The service
provided is needed for LCM years or more ) cannot be
made.

For the study period approach, a time horizon is chosen over


which the economic analysis is conducted, and only those
cash flows which occur during that time period are
considered relevant to the analysis
Once a study period is specified, all cash flows after this time
are ignored
Salvage value is the estimated market value at the end of
study period (at this stage we will just use Salvage value as it is)
Short study periods are often defined by management when
business goals are short-term

Example: Different-Life Alternatives

National Homebuilders, Inc., plans to purchase new cut-and-finish


equipment. Two manufacturers offered the estimates below.
First cost, $
Annual cost, $/year
Salvage value, $
Life, years

Vendor A
15,000
3,500
1,000
6

Vendor B
18,000
3,100
2,000
9

(a) Determine which vendor should be selected on the basis of a present


worth comparison, if the MARR is 15% per year.
(b) National Homebuilders has a standard practice of evaluating all options over
a 5-year period. If a study period of 5 years is used and the salvage values
are not expected to change, which vendor should be selected?

(a)

Determine which vendor should be selected on the basis of a present worth


comparison, if the MARR is 15% per year.

Solution:

LCM = 18 years; We draw its cash flows to make things easy


To meet the criteria of equal
service alternatives we extended
the project life from 6 years to 18
years for the first alternative (& 9
to 18 for 2nd alternative)
NOW You have equal life two
alternatives(equal service
condition meet) with cash
flowsyou can use standard
procedure to obtain the present
value of both and compare it.

Example 5.3: Different-Life Alternatives

Example 5.3: Different-Life Alternatives

Solution (b): Now


comparison is required for
5 years. Since cash flows
are of 6 years no cycle
repeat is required

Solution:
PWA = -15,000 15,000(P/F,15%,6) +1000(P/F,15%,6) 15,000(P/F,15%,12)
+1000(P/F,15%,12) + 1000(P/F,15%,18) 3,500(P/A,15%,18)

= $ 45,036

PWA = -15,000 3,500(P/A,15%,5) +1000(P/F,15%,5)

= $ 26, 236

PWB = -18,000 18,000(P/F,15%,9)+ 2000(P/F,15%,9)+ 2000(P/F,15%,18)


3100(P/A,15%,18)

PWB = -18,000 3100(PA,15%,5) + 2000(P/F,15%,5)


= $ 27,397

= $ 41,384

Which one to select ? A or B ?

Select vender B

LCM or Study Period


Approach
In Previous Example LCM suggest to select Vendor B
Study Period approach suggest to select Vendor A

Which one to select ? A or B ?

Salvage value is
the estimated
market value at the
end of study period

Select vender A

PW of Different-Life Alternatives for


independent alternatives

For independent projects , use of the LCM


approach is unnecessary since each project is
compared to the do-nothing alternative, not to
each other

In such situations, the standard practice of using a fixed


study period should be carefully examined

Equal-service requirement is not a problem

It should be ensured that the appropriate approach,


that is, LCM or fixed study period, is used to satisfy the
equal-service requirement

Use the MARR to determine the PW over the


respective life of each project, and select all
projects with a PW 0

Future Worth Analysis


Future Worth is exactly like PW analysis, except
Future Worth Must compare alternatives for equal
service (i.e. alternatives must end at the same time)
The selection guidelines for FW analysis are the same
as for PW analysis; FW 0 means the MARR is met or
exceeded
For two or more mutually exclusive alternatives, select
the one with the numerically largest FW value.

Future Worth Analysis


If life of two alternatives are not equal, one need to fulfill the
equal service requirement for using FW criteria.
Two ways to compare equal service:
1. Least common multiple (LCM) of lives
2. Specified study period
Same way as used for Present Worth Analysis expect once
life of alternatives are equal for cash flows, one need to
compare the Future Worth instead of Present Worth

Try: Future Worth Analysis


(Problem 5.26)
An industrial engineer is considering two robots
for purchase by a fiber-optic manufacturing
company. Robot X will have a first cost of
$80,000, an annual maintenance and operation
(M&O) cost of $30,000, and a $40,000 salvage
value. Robot Y will have a first cost of $97,000, an
annual M&O cost of $27,000, and a $50,000
salvage value. Which should be selected on the
basis of a future worth comparison at an interest
rate of 15% per year? Use a 3-year study period.

Future Worth Analysis


(Problem 5.26)
i = 15%

F=?

F=?
0

$80,000

A = $27,000

A = $30,000
$97,000

Robot X CF

Robot Y CF

FWX = -80,000(F/P,15%,3) 30,000(F/A,15%,3) + 40,000


= -80,000(1.5209) 30,000(3.4725) + 40,000
= $-185,847
FWY = -97,000(F/P,15%,3) 27,000(F/A,15%,3) + 50,000
= -97,000(1.5209) 27,000(3.4725) + 50,000
= $-191,285

Capitalized Worth Analysis


Capitalized worth is the present worth of all revenues
or expenses over an infinite length of time

$50,000

$40,000
i = 15%

Select robot X

The Capitalized Worth Analysis


The Capitalized Worth of a series of end-of-period uniform
payments A, with interest at i% per period, is
CW (or CC) = A(P/A, i%, n) where n

If only expenses are considered this is referred as


capitalized cost
The capitalized worth method is especially useful in
problems involving public projects with indefinite lives,
or permanent endowments(or donations) for charitable
organizations and universities

As N becomes very large (if the A are perpetual payments)


We already know that P/A is given as P/A=

So, the above equations become as:


Capitaized Worth (or Capitalized Costs) =

Example: Capitalized Worth


(Costs) Problems

Consider a simple Capitalized Cost type problem


A person want to donate $100, 000 for scholarships
in a university. Consider, 20% per year interest rate;
How much money can be withdrawn forever from
this account?

The term in the bracket becomes as n tends to infinity

CW or CC =

Capitalized worth (or costs) type problems vary from


very simple to somewhat complex

or

Example: Capitalized Worth


(Costs) Problem
Draw a Cash Flow Diagram
$ A per year = ?

$100,000

Solution:

CC= A (or AW)


i
Or AW= CC (i)
A = $100,000(0.20) = $20,000 per period

Capitalized Worth (Costs) Recurring


and Non-recurring

The Capitalized Worth Analysis

The equation can be understand by thinking of ..


What present amount invested today at i will enable an
investor to periodically withdraw an amount A forever
If investor withdraw more than amount A each period, he/she
will be withdrawing a portion of the initial principle and
eventually it will exhausted
If amount being withdrawn each period is equals the interest
earned on the principal for that period, the principal remains
intact, thus series of withdraw will continue forever

More complex problems will have two types of costs associated;


1. Recurring Periodic and repeat
2. Non-recurring One time present or future cash flows

For more complex CC problems one must separate the


recurring from the non-recurring

You will not just face problems to calculate Capital Costs


of a single amount (like the previous example) but you
confronts situations in which you have to make selection
among alternatives using CC criteria

Summary: How to calculate CC and A and how to use

Capitalized Cost Analysis


For the comparison of two alternatives on the basis of
capitalized cost, you will use formula (CC = A/i)
So find the A value (& CCT (the sum of recurring and nonrecurring costs) for each alternative and select the one which
has lowest present worth of costs (or equal to say Lowest
capitalized costs).
Alternatives are automatically compared for same life period
because CCT represents the total present worth of financing and
maintaining a given alternative forever (i.e., infinity).

Example:

CC criteria to select an alternative


Cost (cash flows)
(Step 1)

Recurring

Periodic and repeated

Non-recurring
One time present or future cash
flows (e.g., first cost, cost once
in 25th year etc)

A in a only one cost


Cycle: e.g., cash flow
every 5th year or every
20th year

Non-recurring
Convert it to PW (will be PW of
all non-recurring costs for
whole life)

Convert this to a Uniform


Series (say A1)

(Step 2)

Add values of step 4 and Step 2


to obtain CC of overall cash
flows

(Step 5)

Select the alternative with


lowest capitalized costs

Divide the value of Uniform


Annuity Series by i" (using
CC= A/i) to get the value of
Capitalized worth for
uniform series
(Step 4)

Uniform Equal
Recurring Amounts:
e.g., Annuity Series
(say A2)

Add A1 and A2 to
get one Uniform
Series (Annuity
Series) starting
from time 0 and
continue till infinity

(Step 3)

Step 3 can be skipped if you convert both recurring costs


directly to present worth

Step 1: Draw cash flow Diagram


(for at least 2 recurring cost cycles)

The Haverty County Transportation Authority (HCTA) has just installed


new software to charge and track toll fees. The director wants to know
the total equivalent cost of all future costs incurred to purchase the
software system. If the new system will be used for the indefinite future,
(a) find the equivalent cost now: i.e., a CC value. (b) for each year
hereafter, an AW value.
The system has an installed cost of $150,000 and an additional cost of
$50,000 after 10 years. The annual software maintenance contract cost
is $5000 for the first 4 years and $8000 thereafter. In addition, there is
expected to be a recurring major upgrade cost of $15,000 every 13 years.
Assume that i is 5% per year for county funds.
Can you try to draw its cash flow with you for 2 cycle of recurring costs?

The system has an installed cost of $150,000 and an additional cost of $50,000 after 10
years. The annual software maintenance contract cost is $5000 for the first 4 years and
$8000 thereafter. In addition, there is expected to be a recurring major upgrade cost of
$15,000 every 13 years. Assume that i is 5% per year for county funds.

Step 1: Draw cash flow Diagram


(for at least 2 recurring cost cycles)

Step 2: Convert Non-

Recurring costs into PW

Non- Recurring Costs:


$150,000 (Initial Costs) and
$50,000 (in year 10th)
Non- Recurring Costs: $150,000 and $50,000
Recurring Costs (A in a life cycle): $15000
Recurring Costs (uniform A series): $5000, $8000

Step 3 & 4: Convert Recurring Costs (A in one life


cycle) into Uniform Costs and add it with Uniform
Recurring Costs
Recurring Costs (A in one life cycle): $15000
A1 = 15000(A/F, 5%, 13)
= $ 847 cost of one cycle
CC2 = 847 / 0.05
= $ 16,940 (for all cycles)

CC1 = 150,000 50,000(P/F, 5%, 10)

CC1 = $-180,695

Step 3 & 4: Convert Recurring Costs (A in one


life cycle) into Uniform Costs(for whole life)
and add it with Uniform Recurring Costs

Recurring Costs (uniform):

$5000, $8000
CC3 = 5000 (P/A, 5%, )
= 5000/i or 5000/0.05
CC3 = = $ 100,000
Alternative:
A1 = $ 847
A2= $ 5000
A = A1+A2 = $ 5847
CCA = $5847(P/A, 5%, )
= 5487/0.05 = $116940
(same as CC2 + CC3 above)

Step 5: Add values of Step 2 and Step 4 to


Obtain CC

CCT = CC1 + CC2 + CC3 + CC4


= 180,695 16,940 100,000 49,362
= 346,997
Interpretation: The $-346,997
represents the one-time t = 0
amount that if
b) CC = A/i
invested at 5%/year would fund the
AW= CCT (i)
future cash flows as
= 346.997 (0.05)
shown on the cash flow diagram
= $17,350
from now to infinity!
Interpretation: This means Haverty County officials have committed the
equivalent of $17,350 forever to operate and maintain the toll
management software

Recurring Costs (uniform):

If we calculate the present worth of A = $3000 (which is starting


from year 5)it will be on 4th year. Need to multiply it with single
factor for four year to bring it to time 0.
CC4 = (A/i)(P/F, 5%, 4)
3000 (1/0.05) (P/F, 5%, 4)
CC4 = = 49,362

Capitalized Cost Analysis


If you have more than one alternative and you
have to chose one out of it on Capitalized Cost
Analysis.
You need to calculate the CC for every
alternative as explained in 5 step procedure
and then you select the alternative which
value is lowest

Example

Capitalized cost analysis for a


finite-life alternative
If a finite-life alternative is compared to one with an infinite
life on the basis of their capitalized costs, proceed as
follows:

Given the following two mutually exclusive


alternatives, use the Capitalized Worth method to
determine which project you should invest in (MARR
= 15%):

To determine capitalized cost for the alternative with a


finite life, calculate the equivalent A value for one life cycle
and divide by the interest rate.

First Cost, $

It maybe noted that CC/CW method can be applied for


alternatives whose lives are not necessary infinite.

Life, years

First, find AW of each alternative: (bz CC = AW/i)


AWA = $12,000(A/P, 15%, 10) $2,200
= $4,592
AWB = $40,000(A/P, 15%, 25) $1,000 +
$10,000(A/F, 15%, 25)
= $7,141

Practice: Finite versus Infinite life


alternatives

Annual Operating Cost, $ per year


Salvage value, $
Life, years
10%

Single Payments

150000
50,000
8000
5

Alternative N

800000
12000
1000000

Uniform Series Factors

Compoun
d Amount
(F/P)

Present
Worth
(P/F)

Sinking
Fund
(A/F)

Compound Capital
Amount
Recovery
(F/A)
(A/P)

Present
Worth
(P/A)

1.6105

0.6209

0.16380

6.1051

3.7908

0.26380

Second, find CW of each alternative:


CWA = AWA/i = -$4,592/0.15 = -$30,613
CWB = AWB/i = -$7,141/0.15 = -$47,607
Since CW of alternative A yields less cost, it
should be selected.

Solution!!!!

Compare the alternatives shown on the basis of their capitalized costs


using an interest rate of 10% per year
Alternative M

Salvage value, $

B
$40000
1000
10000
25

Solution

Solution

First Cost, $

Annual Operating Cost, $ per year

A
$12000
2200
0
10

For M, first find AW and then divide by i to find CC.


CCM = AWM/i but we don't know AWM
To calculate Annual worth one need to convert all cash
flows into Uniform series!!!!!!
AWM = 150,000(A/P,10%,5) 50,000 + 8000(A/F,10%,5)
= 150,000(0.26380) 50,000 + 8000(0.16380)
= $ 88,260
Salvage value for
CCM = 88,260/0.10
alternative with
= $ 882,600
infinite life is
never realized
CCN = 800,000 12,000/0.10
because n is
= $ 920,000
never reached.
Select alternative M

Thank You

10

Вам также может понравиться