Method Statement
For
Waterproofing System
(WP2)

Project: Venetian Macau in Cotal, Macau


Re: Work Package 5115 (Top Builders), Prefabricated Bathroom
Revision: B
Date: 2006/06/19

Method Statement for


Waterproofing System (WP2)

Table of Content

Content

..

Scope of work

..

Relevant submission

..

Application of waterproofing

..

3-5

Preparation work

..

Concerns

..

Installation

..

Field quality control

..

Protection

...

Cleaning

...

Appendix

i iii

Demarcation Plan

Hazard identification

ii

Risk assessment

iii

Page 2 of 5

Method Statement for


Waterproofing System (WP2)

Scope of work
Trade contractor of this project will be responsible for the execution of the work in
accordance with the specifications and relevant approved documentations. The
scope of work includes supply and installation of waterproofing system (WP2)
including PCI gisogrund protective primer, PCI lastogum waterproof coating,
and PCI pecitape fabric tape system at the L33 to L37 tower suite bathroom
areas.

Relevant submission

Material Submission of the wash and protective primer PCI gisogrund for
walls and floors.
Material Submission of the waterproof, flexible protective coating PCI
lastogum under marble panels in toilets, shower and bathrooms with
official test certificates.
Material Submission of the special fabric tape system PCI pecitape for
waterproof corner and perimeter joints, pipe culverts and floor drains.

Application of waterproofing system

Preparation work
1. Site Cleaning
2. Site surveying and setting out
3. Erect working platform if necessary and according site safety
regulations.

Concerns
1.

Working at Height
Working platform will be provided if higher than 2m and erected by
experience competent worker and inspected by the appointed
professional person signing and certifying Form 4 & 5 before use and
re-inspection on 7-14 days.

2.

Substrate Preparation
Substrate must be solid, dry, clean and free from oil.
The surface must not have any pockets, gaping cracks or ridges.

3.

Factor affecting Evaporation Time for Lastogum


Higher temperatures reduce and lower temperatures increase these
times. The airflow will affect the evaporation time as well.

4.

Quality of drywall
The surface of the board, the workmanship of the joints between
boards and wall to floor joint alignment should be inspected before
application.
Page 3 of 5

Method Statement for


Waterproofing System (WP2)

Installation
1. Remove all debris on wall and floor surface.
2. Absortive mineral substrates are to be primed with PCI gisogrund
with 1:1 water.
3. Wait the primer to completely dry for at least 3 hours.
4. Application of PCI lastogum liquid applied waterproofing membrane.
5. The first coat should be applied with PCI lastogum red. Evaporation
time after first coat is minimum 3 hours at 23 degree and 50% relative
humidity.
6. Sealing the corner and wall to floor and wall to wall joints by pressing
PCI pecitape 120 sealing tape onto the fresh first coat at corner or
joints. Cut the tape to fit corners.
7. Sealing the pipe penetrations by using the fingers, stretch a PCI
pecitape 10X10 sealing gasket to give tight fit over the pipe. Place it
in position, bedding it onto the fresh first coat.
8. Sealing a floor drain by cutting PCI pecitape 35X35 sealing gasket to
suit drain system to be used. Place it in position, bedding it onto the
fresh first coat. Insert loose flange of the floor outlet and screw down.
9. For wall application, apply the second coat of PCI lastogum gery
which is a one-component system. Or floor application, apply second
coat of PCI lastogum grey, which is a two-component system.
10. Ensure the cured waterproofing membrane is dry and has not been
damaged before fixing marble.
11. Water testing as per requested in the specification, please refer to
field quality control section.
12. Waterproofing need to be protected after water test.

Field quality control


1.

Visual inspection
z Visually inspect waterproofing system installation thoroughly in
presence of contractors representative for mock-up trail and bubbles
formed in the waterproofing system or any defects will be made good
as recommended by manufacturer.

Page 4 of 5

Method Statement for


Waterproofing System (WP2)

2.

Testing of horizontal installation


z After allowing waterproofing system installation to completely cure and
set, flood test horizontal installations with a minimum of 50mm of water
for 24 hours examine for identify and repair any leaks.
z Make joint inspection with architects, consultants and main
contractors representative throughout the test. Record the testing
result on inspection forms, taking record photos where necessary.

3.

Water spray test to waterproofing system applied to wall


z For wall exceeding 300mm high only, joint inspection with architects,
consultants and main contractors representative for water spray test
will be arranged at least 72 hours (in any case, as per the
manufacturers advise) after waterproofing membrane is applied.
z Apply water using a common domestic telephone type shower head
fitted to a 13mm diameter supply pipe delivering water pressure of not
less than 0.2N/mm2. Locate the pressure gauge at a distance not
exceeding 1500mm from the shower head.
z Carefully make inspection of the other side of the waterproofed wall
surface to check any water seepage.
z Record the testing result, taking photo record where necessary.

Protection
1.

Ensure that all waterproofing are protected from traffic, weather and
damage during construction. Repair or replace all damaged
waterproofing before covering with other finish materials.

2.

Protect all insulation from damage from wetting, loading or abuse until
they are under protective covering material or finish.

3.

Protect adjacent surfaces and materials from damage and soiling by


the work of this section.

Cleaning
1.

Remove all debris after completion of the work of this section.

2.

Clean adjacent surfaces and materials soiled by any work of this


section.

Page 5 of 5

35
Stone Types:
G-ST1
G-ST2
G-ST3
G-ST4

TURKISH BOTTICINO
DARK EMPERADOR
RED DAMASCUS
GIALLO SIENA
REV.

500

Basin Kohler K-2211

600

350

300

1279

UP
UP
UP
UP

84

524

195

195

DESCRIPTION

DRAFT

TO SKIRTING
TO 950mm A.F.F.L.
TO 2050mm A.F.F.L.
TO FALSE CEILING HEIGHT

150

17

150

90

900

23

1754

1019

WC Kohler
K-3323

195

DATE

WATERPROOFING LEGEND:

Bathtub Baoquan BT-9509A

100 100

100

150

300

195

195

150

100

150

1481

850

150

850

1245

727

F
121

120

180

180

80

150
490

150

150

225

195

300

250

150

195

225

600

1290

882

150

152
1740

20
38
465

1400

900

WC Kohler
K-3323
2240

150

850

150

95

800

100

20

100

38

275

400

645

EQ
100

150

150

1400

EQ

2156

2120 - 5115 - C-2(B) - DEMARCATION PLAN FOR


THE HEIGHT OF WALL WATERPROOFING

PDF created with pdfFactory Pro trial version www.pdffactory.com

120

789

Basin Kohler K-2211

1500

1500

Basin Kohler K-2211

808

DATE

DESCRIPTION

DRAFT

400

WC Kohler K-3323
Supplied by others
Installed by TBI

550

310
300

600

Basin Kohler K-2211


Supplied by others
Installed by TBI

550

38

EQ1

38

45

REV.

EQ
300

EQ

300

300

250

300

290

300

75

UP TO
UP TO
UP TO
UP TO

300
250

SKIRTING
950mm A.F.F.L.
2050mm A.F.F.L.
FALSE CEILING HEIGHT

990

290

990

300

EQ5

90

EQ5

EQ

38

Stone Types:
936

2134

G-ST1
G-ST2
G-ST3
G-ST4

TURKTSH BOTTICINO
DARK EMPERADOR
RED DAMASCUS
GTALLO STENA

2120 - 5115 - DQ_K_K1SUITE - DEMARCATION


PLAN FOR THE HEIGHT OF WALL WATERPROOFING
DQ SUITE (LEFT) L33-L37
K SUITE (LEFT) L33-L37
K-1 SUITE (LEFT) L33-L37

2120 - 5115 - DQ_K_K1 - DEMARCATION PLAN FOR


THE HEIGHT OF WALL WATERPROOFING

PDF created with pdfFactory Pro trial version www.pdffactory.com

WATERPROOFING LEGEND:

EQ

300

1700

300

EQ1

300

2968

300

3046

300

75

300

300

10

35
0

Stone Types:

60
0

5
19

0
34

G-ST1
G-ST2
G-ST3
G-ST4

TURKISH BOTTICINO
DARK EMPERADOR
RED DAMASCUS
GIALLO SIENA

DRAFT

75

300

300

EQ

300

300

0
30

G-ST1

300

30
0
0
30

300

1806

G-ST1

195

30
0
0
30
0
30

75

2
47

75

1740

150

1837

0
30

EQ

0
90

EQ

300

318
0
15

0
30

0
20

30
0

DESCRIPTION

UP TO SKIRTING
UP TO 950mm A.F.F.L.
UP TO 2050mm A.F.F.L.
UP TO FALSE CEILING HEIGHT

EQ

61
4

806

0
30

30
0

60
0

30
0

0
20

75

150

30
0

DATE

WATERPROOFING LEGEND:

12
0

G-ST3

G-ST4
24
50

REV.

le

300

82
15

B
K as i
-2 n
21 K o
1 h

1902
45

850

100

208

809

278

1902

EQ

809

195

260
100 200

300

300

300

120

80

38

590

20

20
378

1400

400

38

300

869

EQ
G-ST1

100 200

EQ

300
300
EQ

1506

300
EQ

1266

300

300

348
100

555

200

300

EQ
300
300

2097

EQ

300

300

250
300

150

300

1906

300

300

75
EQ

614
712

75

614

300

75

195

712

1999

EQ

300

120

150

75

200 100

200 100

Basin Kohler
K-2211

1500

300

600

Basin Kohler
K-2211

EQ

300

260
600

2120 - 5115 - C-2(C) - DEMARCATION PLAN FOR


THE HEIGHT OF WALL WATERPROOFING

PDF created with pdfFactory Pro trial version www.pdffactory.com

278

150

100

195

100

BAOQUAN BT-9509A

Review No.

Date:

HAZARD IDENTICATION SHEET

07-06-2006

Page 1 of 2

Project:

Venetia Cotai, Macau Prefabricated Bathroom

Work Package Code:

Subject:

Waterproofing system (WP2)

Analysis by:

Location:

Hotel Tower

Item

Job Task

General works

Manual
handling and
transporting of
material

Materials
storage

Hazard
Personal injury

Twisted , slipping,
tripping, hit by
objects

People
Affected
worker and
affected
people
nearby

workers

Muscle strain
During manual
handling

Fire

worker and
affected
people
nearby

Cause of Hazard

Lack of site safety


knowledge

Inappropriate use of
PPE

Using improper lifting


method to handle
goods

poor housekeeping

Worker did not wear


and use PPE

Poor Housekeeping

Smoking at the
workplace and storage
yards.

Insufficient Ventilation

Worst Harm
Due to
Hazard
Severely
injured

WP 5115 (Top Builders)


Edward Leung

Existing Control Measures

- Worker should attend Safety Induction


Training provided by GAMMON.
- Provide appropriate PPE to workers.
- Keep stock of PPE to be maintained for
issuing.

Severely
injured

Fatality

- Provide pre-work body exercise to


minimize the risk of injury.
- Wear long sleeve safety shoes to protect
the ankle and foot..
- Use the mechanical equipment if
possible.
- Always keep the workplace dry and tidy.

- Flammable materials and goods must be


kept away from the workplace.
- Provide fire extinguishers at the
workplace and storage yards.
- Clean all the rubbish, paper, scraps all
the time.
- Display no smoking signage and no
smoking is allowed at the workplace.
- Adequate ventilation

Remark

Review No.

Item
4

Date:

Job Task
Waterproofing
application

Hazard
Eye contact and
skin contact

Water proofing
application on
wall

Collapse of
working platform

Water proofing
application on
wall

Fall of person at
height

Water proofing
application on
wall

HAZARD IDENTICATION SHEET

07-06-2006

Falling objects
from the working
platform

People
Affected

Cause of Hazard

Worst Harm
Due to
Hazard

worker
nearby

Improper use of PPE


during the work.

Eye or skin
irritation

worker and
affected
people
nearby

Platform erected by
non-experience
competent workers.

Serious injury

worker

Inadequate platform
being used by workers.

Fatality

Workers did not wear


and use PPE.

Worker working under


the working platform.

No Warning sign

Worker and
affected
people
nearby

Page 2 of 2

Severely
injured

Existing Control Measures

- Wear safety goggles and gloves when


working. .
- After application, worker must wipe off
left-out substance and clean with soap
and water.
- Appointed Registered professional
inspect and sign for the workability of
working platform of height above 1.8m.
- 200mm high toe-board and fence at
450mm and 900mm to be installed.
- Prohibit to move the working platform if
any worker on it.
-

Working platform should be closely


planked with 200mm toe-board
equipped.
No other works shall be carried out
under the activities that are working
above.
Chain block shall be used to the
materials that are heavy in weight and
large in size.
Fence off the working area with barrier
and notice / warning sign should be
provided.

Remark

Review No.

Works Related Projects/Department:


Type of Activity Operation:
Location:

Hotel Tower

Item

Risk

Personal injury

Twisted ,
slipping,
tripping, hit by
objects

Venetia Cotai, Macau

Worker should attend Safety Induction


Training provided by GAMMON.

Provided appropriate PPE as job


required.

Keep minimum stock of PPE to be


maintained for issuing.
Provide pre-work body exercise to
minimize the risk of injury.
Wear long sleeve safety shoes to protect
the ankle and foot.
Use the mechanical equipment if
possible.
Always keep the workplace dry and tidy.

Muscle strain
During manual handling
Fire
-

Flammable materials and goods must be


kept away from the workplace.
Provide fire extinguishers at the
workplace and storage yards.
Clean all the rubbish, paper, scraps all
the time.
Display no smoking signage and no
smoking is allowed at the workplace.
Adequate ventilation

Probability or Likelihood Rating:


Consequence Rating:
Risk Level:

Almost Certain ( 5 )

Page 1 of 2

Works Related Projects/Department Code:

Prefabricated Bathroom

Existing Control Measures

Note:

RISK ASSESSMENT SHEET

07-06-2006

Date:

Analysis by:

Edward Leung

Rating of Harm
1

5115 (Top Builders)

Risk
Level3

Recommended Action

Probability

Consequences

3
(Green)

Safety Induction Training,


Specific PPE required

4
(Green)

Morning Pre-work exercise

5
(Green)

Fire equipments Training,


Specific Training

Probable ( 4 )

Possible ( 3 )

Remote (2 )

Impossible (1)

Very High ( 5 )

High ( 4 )

( RED )

( ORANGE )

Medium ( 3 )

Low ( 2 )

Very Low ( 1)

( YELLOW )

(GREEN)

Remark

Review No.

Item
4

Date:

Risk
Eye contact
and skin
contact

Existing Control Measures


-

Worker should attend Safety Induction


Training provided by GAMMON.

Provided appropriate PPE as job


required.
Keep minimum stock of PPE to be
maintained for issuing.
Sanitary facility should be provided for
workers.

Collapse of
working
platform

Appointed Registered professional


inspect and sign for the workability of
working platform of height above 1.8m.

Fall of person
at height

200mm high toe-board and fence at


450mm and 900mm to be installed.
Prohibit to move the working platform if
any worker on it.

Falling objects
from the
working
platform

Note:

RISK ASSESSMENT SHEET

07-06-2006

Working platform should be closely


planked with 200mm toe-board
equipped.
No other works shall be carried out under
the activities that are working above.
Chain block shall be used to the
materials that are heavy in weight and
large in size.
Fence off the working area with barrier
and notice / warning sign should be
provided.

Probability or Likelihood Rating:


Consequence Rating:
Risk Level:

Almost Certain ( 5 )

Page 2 of 2

Rating of Harm
1

Risk
Level3

Recommended Action

Probability

Consequences

3
(Green)

Use of PPE s training

9
(Yellow)

Specific Training

8
(Yellow)

Specific Training & Safety


Harness required

8
(Yellow)

Specific Training & Safety


Harness required

Probable ( 4 )

Possible ( 3 )

Remote (2 )

Impossible (1)

Very High ( 5 )

High ( 4 )

( RED )

( ORANGE )

Medium ( 3 )

Low ( 2 )

Very Low ( 1)

( YELLOW )

(GREEN)

Remark