CONTRACTOR PREQUALIFICATION SUMMARY

CD 009B

APPENDIX I

RFX NO.: 4000053016


CONTRACTOR'S EXPERIENCES ON SIMILAR WORK

Contract No. & Date


[If applicable]

Name of Client

Brief Description of Work

Value [SR]

Completion Date
[yyyy/mm/dd]

Note: Please fill out this form properly. Do not revise this form.
CR Issue Date: 1408/02

Supersedes:

* Denotes Change

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX II

RFX NO.: 4000053016

LIST OF CONTRACTOR'S ON-GOING PROJECTS/CONTRACTS


Contract No. and
Date
[If Applicable]

Description of Work

Name of Client

Start Date
[yyyy/mm/dd]

Completion
Date
[yyyy/mm/dd]

Estimated Value Accomplishment to Date


[SR]
Percent

Value [SR]

Note: Please fill out this form properly. Do not revise this form.
CR Issue Date: 1408/02

Supersedes:

* Denotes Change

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX III

RFX NO.: 4000053016


LIST OF CONTRACTOR'S PROPOSED KEY PERSONNEL TO BE UTILIZED SPECIFICALLY FOR THE WORK

Position

Qualification

Experience [years] with:


Your Co. Others
SEC

Name

A. Management [By Category]

Are all of the above listed proposed manpower employed by your Compan

YES

Nationality

Out-ofInKingdom Kingdom

NO

Page 1 of 2
CR Issue Date: July 2003

Supersedes: 1408/02

* Denotes Change

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX III

RFX NO.: 4000053016


LIST OF CONTRACTOR'S PROPOSED KEY PERSONNEL TO BE UTILIZED SPECIFICALLY FOR THE WORK

Position

Saudi

Other Arabs
In-Kingdom

Out-of-K

U.S. National
In-Kingdom

Out-of-K

Quantity
U.K. National
In-Kingdom

Out-of-K

Asian
In-Kingdom

Out-of-K

Others [Specity]
In-Kingdom

Out-of-K

B. Craftsment [By Category]

[Use additional sheets as necessary]


Are all of the above listed proposed manpower employed by your Company YES

NO. If NO, explain below.

Note : Use additional sheets as necessary.


Page 2 of 2
CR Issue Date: July 2003

Supersedes: 1408/02

* IDenotes Change

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX III-A

RFX NO.: 4000053016

RESUME OF PROPOSED KEY PERSONNEL


[Foreman Level and Higher Positions]]

Name

Nationality

Date of Birth

Educational Background

High School

College/University

Name of Company

CR Issue Date: July 2003

Name of School, College or University

Position

Supersedes: 1408/02

Year Graduated

Job Description

* Denotes Change

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX V

RFX NO.: 4000053016

LIST OF CONTRACTOR'S PROPOSED EQUIPMENT AND TOOLS


TO BE UTILIZED FOR THE WORK/PROJECT
Item
No.

Quantity
Desciption of Equipment/Tool

Capacity

Owned

To be
Leased

Notes:
1. Use additional sheets as necessary
2.

Do not list all equipment your company have. List only those equipment and tools that you
intend to use and are readily available for the work/project.

CR Issue Date: 1408/02

Supersedes:

* Denotes Change

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX VI

RFX NO.: 4000053016


CONTRACTOR'S PROPOSED WORK PLAN

1. Mobilization
*

1.1 Proposed period of complete mobilization from the effective date of


the contract and ready to start the work.

days

1.2 Proposed number of manpower to be mobilized.


1.3 Can you mobilize all your proposed equipment and tools on time to start the work?
YES
NO. If, NO, describe your equipment mobilization plan below.

1.4 Do you plan to request assistance from the Saudi Electricity Company for Visas of any of your
proposed manpower?
YES
NO. If YES, indicate below your reason[s] and list down
the category and number of personnel you intend to recruit.
Reason[s]:

Category of Personnel to be Recruited

Quantity

1.
2.
3.
4.
5.
6.
7.
8.

CR Issue Date: July 2003


Supersedes: 1408/02
2. Transportation and Accommodation

* Denotes Change

2.1 Do you have camp[s] facilities near the Work Site to accommodate your proposed manpower?
YES
NO. If, YES, provide the information below.

CONTRACTOR PREQUALIFICATION SUMMARY


CD 009B
APPENDIX VI

RFX NO.: 4000053016


Capacity
[No. of Persons]

Camp[s] Location:

If NO, where is/are your camp[s] located? Describe your plan below.

2.2 Do you transport your personnel to the Work Site daily from your camp?
2.3 Do you have a material yard near the Work Site?
information below.

YES

YES

NO

NO. If YES, provide the

Material Yard Location: _________________________________________________________


Total Area: _____________ square meter. Fenced?

YES

NO.

If you have no Material Yard near the Work Site, describe your plan below.

3. Subcontracting
*

3.1 Do you plan to subcontract any portion of the Work if you become the successful bidder?
YES
NO. If, YES, provide the information below [for each proposed subcontractor].
Name of Proposed Subcontractor: ________________________________________________
Address: ____________________________________________________________________
Commercial Registration Number: ________________________________________________
Portion of the Work to be Subcontracted:

4. Work Schedule. Etc.

Note: Use additional sheets as necessary.


CR Issue Date: July 2003
Supersedes: 1408/02

* Denotes Change

________________________________________________

Вам также может понравиться