Company profile Owner name, Location of factory, Total Factory Area, Total built-up area,
Department buildings/Functional areas, Last five years business turn-over (Qty & Value)
Organization profile Organization Chart, Details of Total Manpower, Break-up of man power
into Top management & Administration, Technical Managers, Design Engineers, Production
Engineers, Skilled workers, semi-skilled workers, QA/QC staff, Sales & marketing, IT staff.
Product Profile: Main Product intended to supply, product accreditations (if any), sources of
technology, technical collaborations, and Rated Production capacities, Last five years production
& sales data, main customers
Machinery used List of main machinery used in the current production line of proposed
product, with details of manufacturer name, country of origin, when installed.
Lab & Testing Facilities- List of testing equipment, List of type tests/special tests/routine tests
the laboratory can carry-out on the finished product, list of testing equipment used for quality
verification of raw-materials /out-sourced components, accreditations of laboratory (if any) by
Authorized International Accreditation bodies.
Manufacturing Process Quality procedure for selection of raw materials or components, Main
Production process flow chart, details of main manufacturing process , welding and sheet cutting
process, painting process, assembly work, testing of sub-assemblies, testing of finished product,
etc
Quality control - QA/QC Methods & procedures being followed, check-lists used at each stage
of production, details of in-process quality checks/testing methods, rates of rejections etc
FAT Tests- Details of in-process testing plan documents, product test & inspection procedures,
routine tests, visual inspection, and their acceptance criteria, the documents used to record the
FAT tests results of the proposed product.
PART-II / Product Related - General
Duly filled-in Pre-qualification Questionnaire for the specific product only (Note: Do not
propose range of products or multiple products in one application. If you need to obtain prequalification for more than one product, submit separate applications for each individual
product)
Details of Sales history to Utility companies in GCC and other Countries (details should include
names of clients, quantities supplied, date of supply, Capacity/Type/ratings of Panels.
Copy of Valid ISO 9001: 2000 Certificate (not older than 3-Years from the date of issue).
EP-MS-P7/F5
Issue: 0
06-02-2011
Page 1 of 2
SL
No
Statement of Compliance/Deviations from manufacturer against each clause (up to the subsub clause level) of Kahramaa Specification # ED-02-082 ver-3/2008 (Latest Issue). (Note:
Remarks like 'Refer our catalogue, noted or other indirect references are not acceptable.)
Copies of Type Test & Special test Reports covering Di-electric Tests, Short Circuit test,
Internal arc tests (IAC-AFLR, 25kA@1 sec), temperature rise test, Type tests of Earth
Switches, issued from Independent reputed International testing laboratories (like
KEMA/ASTA). (Notes: Each test report should contain full text of the document, partial reports
are not acceptable. The test reports shall not be older than 10-years from the date of Issue.
Technical Data Sheets, Product Catalogues, and sourcing Details of all components,
covering CB truck, Vacuum bottle, CTs, VT, Earth Switches, CVDs, Protection Relays & Test
blocks, Indicating Instruments, LV control Switches, Live Phase Indicators & Phase comparator
sockets, Phase comparator Instrument, Bus-bar coupling kits, etc
Separate Schematic Diagrams of Power (SLD), Protection, Control & Indication circuits, of
each type of panel, mentioning all components & accessories, and its symbols, ratings and parts
list.
MS Engineer:
Head of MS
Section:
Date:
Date:
EP-MS-P7/F5
Issue: 0
06-02-2011
Page 2 of 2