The most effective means available for the construction of high, medium and low rise mass
housing R/C structures.
It is a precision-engineered formwork fabricated in Aluminium.
Monolithic Pouring. Walls, columns, slabs & beam are poured together.
Speed - Induces a disciplined & systemized approach to construction, which creates a daily
work cycle, the essence of the productivity. The productivity generates a overall work cycle, that
can achieve 4/5 day per floor outputs or other cycle times to suit your project requirements.
It is flexible in design and can form any architectural or structural configuration, such as stairs,
bay windows, curved features, etc.
Quality - When struck the aluminium formwork reveals a good quality fair face onto which a 4
5mm skim coat can be applied for a perfect finish eliminating need of plaster.
Provides an Integrated Scaffolding reducing the cost of your scaffolding requirements.
Ease of handling - The formwork panels are manually handled, generating further savings on
heavy equipment and cranage.
Mechanical and electrical installation is simplified where conducts are embedded in the structure
Range is 155 US$ per m2 to 225 US$ per m2, most common being 160 US$ per m2 &
assumed for cost comparison purpose.
For 100 uses it will be 3625/ 100 = 36.25 Rs/sft of builtup area.
Add about 4 months as time to reach typical floor of 1st tower & 6 months for finishing after last
floor of 4th tower.
Conventionally, for 25 storey building, RCC will take about 2 years for including foundation & 12
months for finishing. That is 36 months. This means even after constructing one block at a time,
total construction period is almost same as constructing all 4 towers simultaneously with
traditional formwork.