Академический Документы
Профессиональный Документы
Культура Документы
155
Hazards XXI
# 2009 IChemE
INTRODUCTION
A term now in common usage within the oil & gas industry
is inherently safer design. The objective of this phrase is
to promote designs for hydrocarbon extraction and processing facilities that, where practicable, eliminate hazards
completely or reduce the magnitude of the consequences
of hazard scenarios sufficiently to eliminate the need for
elaborate safety systems and procedures.
This paper presents a case study where the principles
of inherently safer design were used to challenge the normally accepted interpretation of the requirements for
depressuring (blow down) systems as set out in the standard
API STD 521, Pressure-relieving and depressuring
systems, (API 2007).
Offshore oil and gas extraction platforms have hydrocarbon containing equipment onboard. The hydrocarbon
containing equipment has maximum design operating parameters, such as a maximum design pressure. Hydrocarbon
extraction is a dynamic process. The hydrocarbon containing equipment is generally equipped with sensors which
monitor the value of parameters, such as pressure. The
sensors often have associated alarms which notify the
plant operator that pressure is increasing. The operator can
then take actions to return the parameter to its normal
value. If the operator intervention fails there is often an
executive action also attached to the sensor which initiates
a shutdown of the plant before the design limits are
reached. In case the shutdown system fails there is often a
secondary protection system. In the case of overpressure
this is generally a relief valve that dumps excess pressure
to a vent or flare.
As well as the protection systems described above, a
blow down system is also generally installed. It has two
main purposes:
1.
2.
BACKGROUND
When designing pressure-relieving and depressuring (blow
down) systems reference is generally made to API STD 521.
349
Hazards XXI
ASSESSMENT METHOD
The assessment was based on evaluating the impact on the
consequences of leaks from the process equipment rather
than protecting the equipment from overpressure in a fire
scenario. In particular, the impact on the escalation potential
of fire and explosion hazard scenarios was evaluated as this
is the primary criterion for distinguishing controllable from
evacuation hazard scenarios.
If a process release on the platforms under study
ignites early, it is characterized by a jet fire and if the
ignition is delayed, a vapour cloud explosion will occur,
possibly followed by a jet fire.
Escalation can be through failure of other process
equipment or structures with the explosion.
There are many references which give details of
impacts of fires on components, characteristics of jet fires
and rules of thumb regarding the time taken for items to
fail under fire loading and explosion overpressure. The following is typical and reproduced from Spouge 1999.
Figure 1 demonstrates that steel loses it strength at
elevated temperatures.
A point in time is reached when the heat absorbed by
the steel component reduces its strength to the point at
which the stress in the component5 is greater than the
remaining strength of the steel and the component fails.
The greater the heat flux from the fire the quicker it will fail.
The heat flux at the boundary of a gas jet flame
depends on the composition of the gas and other factors
but is of the order of 200300 kW/m2. This value drops
of dramatically with distance from the flame as shown in
Figure 2.6
Controllable hazards2
Evacuation hazards3
Catastrophic Hazards,4
2.
3.
4.
# 2009 IChemE
To assess whether the challenge was justified the following questions were addressed:
Does a more rapid blow down system produce
an inherently safer design?
Does a more rapid blow down system significantly impact the number of controllable
hazard scenarios?
Is a more rapid blow down system
practicable?
1
350
Hazards XXI
# 2009 IChemE
351
# 2009 IChemE
Hazards XXI
Table 1. Typical component failure time from fire loading (Spouge 1999)
Times to failure (minutes)
Component
Type of failure
Jet flame
Pool flame
37.5 kW/m2
Steel plate
Steel plate
Steel beam
Steel beam
Jacket leg
Pipe/riser/process vessel
A rated fire wall
H rated fire wall
Yield
Fire penetration
Yield
Collapse
Buckling
Rupture
Fire penetration
Fire penetration
1
5
1
5
15
5
15
100
3
10
2
10
30
10
45
260
20
60
60
120
150
60
70
400
Slow blow
down
Rapid blow
down
28
95
113
42
71
113
DISCUSSION
The initial blow down rate is not the only variable that influences the number of controllable hazard scenarios. The
volume of the inventory isolated when shut-in also has a significant impact. If, for example, the isolated inventory was
reduced by one third, the flame length after 5 minutes
would be reduced to 1m rather than the 5 m with the
revised blow down rate.16 The reason for discussing this
volume is because the present design of the NUI platforms
has emergency shut-down valves at the wells and export
riser. The topside is effectively a single inventory. There
13
Escalation is the failure of critical equipment e.g. other pipes, vessels,
key structural members or evacuation equipment.
14
Various leak hole sizes and leak locations within the process area.
15
Evacuation hazard scenarios include fire & explosion hazard scenarios with the potential to escalate.
16
Based on a 10 mm dia. leak.
352
Hazards XXI
are two manifolds which have manual isolation valves separating them from the remainder of the topside pipe-work.17
Both manifolds and the topside pipe-work have blow down
valves installed. If these isolation valves were actuated and
tied into the shut-down system there would have been three
isolatable sections each with approximately one third of the
inventory.
As can be seen form the above when developing the
hazard management strategy for process fires there is
value in considering variations in both blow down characteristics and isolation philosophy.
One item not discussed so far which should not be
overlooked when developing the design of a blow down
system is the effect that rapid blow down has on the temperature of the hydrocarbon, both upstream and downstream
of the blow down valves. Very low temperatures can be generated at high blow down rates and appropriate pipe and
17
# 2009 IChemE
REFERENCES
API 2007, Pressure-relieving and Depressuring Systems, Standard 521
BP 2008, Inherently Safer Design bp Group GP 48-04
BP 2009, Fire and Explosion Hazard Management (FEHM) of
Offshore Facilities GP24-20
Spouge, John 1999, A guide to Quantified Risk Assessment for
Offshore Installations CMPT publication 99/100a
353
Hazards XXI
354
# 2009 IChemE
Hazards XXI
Figure A2. Blow down to 50% of Operating Pressure in 15 mins. 10 mm dia. leak
355
# 2009 IChemE
Hazards XXI
356
# 2009 IChemE
Hazards XXI
357
# 2009 IChemE