Академический Документы
Профессиональный Документы
Культура Документы
Topic 4
Cost Management
Paulo Faroleiro
Project Management
Part IV
Cost Management
Cost Management
1. Price Estimation
2. Cost Control
TYPES OF ESTIMATES
Order of magnitude estimates
Made without any detailed engineering data
May use past experience
Accuracy +- 35% within the scope of the project
Approximate (rule of thumb) estimates
Made without any detailed engineering data
May use previous similar projects - Accuracy +- 15%
Definitive (or detailed) estimates
Prepared from well-defined engineering data, vendor quotes, unit
prices, etc. Accuracy +- 5%
Estimating manual
Developed over time
Use to price out effort. Accuracy +-10%
ADDITIONAL ESTIMATING
METHODS
Direct Estimate
Estimate/experienced person
Requires judgement
Estimate by analogy
Compare with similar activities
Requires judgement
Factored method
Based on historical data
Requires equipment lists, sizes
Starts with equipment quotes
Gross proration method
Based on historical data
Near duplicate information
Detailed estimate
- Uses the WBS
- Takes the WBS down several levels
Quotation method
- Compare three quotations
- Select the best quotation
Handbook manuals
Learning curves
Construction
Cost Estimates
COST FOUNDATIONS
Actual costs to date and estimates to completion
Proposal data
Marketing intelligence
Management goals
Past performance and trends
Establishing The
Project Budget
PRICING METHOD
Work is priced out at the department average, and all work
performed is charged to the project at the department average
salary, regardless of who accomplished the work.
Do Project
Managers Control
Costs, Monitor
Costs Or Both?
COST MANAGEMENT
Cost estimating
Cost accounting
Project cash flow
Company cash flow
Direct labor costing
Overhead rate costing
Others, such as incentives, penalties, and profit-sharing
PLANNING
PHASE I
PLANNING
CYCLE
WORK
DATA
AUTHORIZATION
COLLECTION
AND RELEASE
AND REPORTING
PHASE II
PHASE III
COST
ACCOUNTING
PHASE IV
OPERATING CYCLE
CUSTOMER AND
MANAGEMENT
REPORTING
PHASE V
PROJECT
COSTS
CAPACITY PLANNING
The Work
Authorization Form
03 Feb 01
18 March 01
C
Description
- Test Material
- Processing
- Final inspection
- Packaging
- Delivery
2400
2610
2621
2623
2624
150
160
140
46
R4500
R7500
R3500
R 750
R 350
1 Aug
15 Sept
Work packages
M
G
R
Org
Org
Org
Work Package
WP______ORG_______
Description of task_____
____________________
Sched: Start____Stop__
Budget:______________
DESCRIPTION OF CHANGE:
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
REASON FOR CHANGE:
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
__________________________________________________________________________________
Labor Hours
Materials
ODCS
Requested Budget
_________________
_________________
_________________
Authorized Budget
_________________
_________________
_________________
Period of performance
From _____________
To
_____________
BUDGET SOURCE:
Funded Contract Change
Management Reserve
Undistributed Budget
Other _________________
INITIATED BY: ____________________________
TYPES OF BUDGETS
COST DATA
Distributed budget
Labor
Management budget
Material
Undistributed budget
Contract changes
Overhead
VARIANCE ANALYSES
Monthly Total
Program Effort
BCWP
Weekly Labor
Reports
ACWP
Inventory
Accounts
Computer
MCCS Comparison
VARIANCES
The cost variance compares deviations only from the budget and
does not provide a measure of comparison between work
scheduled and work accomplished.
The scheduling variance provides a comparison between
planned and actual performance but does not include costs.
CV = BCWP - ACWP
SCHEDULE VARIANCE
CALCULATION
A NEGATIVE VARIANCE INDICATES
A BEHIND SCHEDULE CONDITION
SV = BCWP - BCWS
MANAGEMENT RESERVE
CONTRACTED COST
MANAGEMENT
RESERVE
ACTUAL COST
RELEASED BUDGET
TIME
PROJECTED COST
$
QUALIFICATION
PHASE II
TIME
DEVELOPMENT
PHASE III
VARIANCE PERCENTS
SCHEDULE VARIANCE %
(SVP)
COST VARIANCE %
(CVP)
SV
BCWS X 100
CV
BCWP X 100
Trend
Analyses
INFORMATION REQUIREMENTS
Budgeted cost for work scheduled (BCWS)
Budgeted cost for work performed (BCWP)
Actual cost for work performed (ACWP)
Estimated cost at completion
Budgeted cost at completion
Cost and schedule variances/explanations
Traceability
VARIANCE REPORTING
Variance reporting is accomplished at each reporting
interval. However, the variance threshold reports are
exception reports and occur only when the variances exceed
the upper and lower boundaries of the project variances
envelope.
REPORTING INTERVALS
Depends on the type of organization and characteristics of
the projects.
Project-driven organization - weekly.
Non-project-driven organization - monthly
Variance
Reporting level
As of
At completion
Budget EAC Var.
Date
ANALYSIS
BUDGETED COST FOR WORK
Budget - 6
Scheduled (BCWS)
Performed (BCWP)
Cost account budget = 100
(thousands)
8
14
12
10
Work packages
12
8
BCWS = 38
BCWP = 49
SCHED. VARIANCE = +11
12
10
8
4,000
TIME LINE
10,000
LEGEND
12,000
COMPLETED
4,000
NOT COMPLETED
6,000
BCWS = 34,000
BCWP = 33,000
BAC = 52,000
6,000
10,000
TIME
CUMMULATIVE COST, $
TIME LINE
BCWS
ACWP
SV
CV
BCWP
TIME
Estimated Cost At
Completion
STATUS
REPORTING IS
MORE THAN
JUST A
COMPUTER
PRINTOUT.
INTRANET
STATUS
REPORTING
REPORTING
FAVORABLE
STATUS
REPORTING
UNFAVORABLE
STATUS
PROGRESS REPORTING
Progress reporting needs to answer four fundamental
questions:
1. Where are we today (time and cost)?
2. Where will we end up (time and cost)?
3. What are the present and future risks?
4. Are there any special problems that need to be
addressed and what can management do to help?
Overrun
3. COST SUMMARY
Costs are running approximately 5.9% over budget due to
higher salaried labor.
4. SCHEDULE SUMMARY
The 24.4% behind schedule condition is due to subtasks 4
and 6 which have not yet begun due to lack of raw materials
and the 50/50 method for booking costs. Overtime will get us
back on schedule but at an additional cost of 2.5% of direct
labor costs.
DATA ACCUMULATION
Organization
WBS
Budget
BCWS
SCHED
VAR
BCWP
ACWP
COST
VAR
FINANCIAL
CLOSE-OUT
COST PROBLEMS
Poor estimating techniques and/or standards, resulting in
unrealistic budgets
Out-of-sequence starting and completion of activities and
events
Inadequate work breakdown structure
No management policy on reporting and control practices
Poor work definition at the lower levels of the
organization!
Omissions
Inaccuracy of the work breakdown structure
Misinterpretation of information
Use of wrong estimating techniques
Failure to identify and concentrate on major cost elements
Failure to assess and provide for risks!!
SUMMARY
1. A cost estimate is
prepared
As a basis for control
To assess the projects
viability
To obtain funding
To allocate resources
To estimate durations
To prepare tenders for
bespoke contracts
SUMMARY
3. The proposal estimate is prepared at the concept stage to commit
resources to the feasibility. The budget estimate is prepared during
feasibility to initiate the project, and commit resources to design. The
sanction estimate is prepared during design to gain funding for the
project, or approval from the project sponsor. The control estimate is
prepared during implementation planning.
SUMMARY
5. The cost control cube, a three-dimensional matrix of the WBS OBS
CBS provides a structure for estimating and controlling costs. The
estimate is prepared by breaking the work down to an appropriate level of
WBS, and then estimating the cost of each element in the cost control
cube. Effectively we estimate each type of cost for each cell in the
responsibility chart at that level. Spreadsheets can be used to support
this process.
SUMMARY
7. Cost is most easily controlled by forecasting cost at completion, by
adding the actual work to date to the estimated cost of work remaining,
and comparing that to the original estimate.
Part IV
Cost Management
1. Topic 5 and 6
Quality and Risk Management