Академический Документы
Профессиональный Документы
Культура Документы
Article I
Size
Generation capacity of 122 GW; 590 billion units produced (1 unit
= 1kwh)
- CAGR of 4.6% over the last four years
India has the fifth largest electricity generation capacity in the
world
- Low per capita consumption at 606 units; less than half of China
Policy
100% FDI permitted in Generation, Transmission & Distribution the Government is keen to draw private investment into the sector
Capacity G T D
Public Sector
NTPC
National Hydro Electric Power Corporation
23,749
3,615
2,770
2,203
1,005
Reliance Energy
885
655
Marubeni Corporation
330
G - Generation T - Transmission D - Distribution
Source: Ministry of Power, Capitaline
Opportunity
Outlook
Power costs need to be reduced from the current high of 810 cents/unit by a combination of lower AT & C losses,
increased generation efficiencies and added low cost
generating capacity
Potential
Article II
Introduction
Power is a critical infrastructure for the economic
development of the country. To meet the projected
power requirement by 2012, an additional capacity
addition of 100000 MW is required in the next two five
year plans. A capacity of nearly 41000 MW would be set
up in the 10th plan and the remaining in the 11th plan with
a stronger focus on hydro power. The central sector
would contribute 22,5000 MW, the state sector 11400
MW and Private Sector 7,100 MW in the 10 th Plan.
Projects of above 19000 MW are already under
construction and projects of 8900 MW aggregate capacity
have the requisite approvals.
Generation & Capacity Addition
Generation
The overall generation in the country has increased from
301 Billion Units (BUS) during the 1992-93 to 515.3 Bus
during 2001-2002. The overall generation (Thermal +
Nuclear + Hydro) in public utilities in the country for the
last five years are as under:
Year
2000-01
2001-02
2002-03 (Upto
Jan. 2003)
2002-03
Plant Load Factor (PLF)
Generation
(Bus)
499.5
515.3
443.9
545.5
licensees
would
be
free
to
undertake
7
ARTICLE III
10
Total
69,065
72,330
76,753
81,171
83,294
85,744
For detailed & updated information on the Indian Power Sector, refer
to the report - 'Overview of Power Sector in India 2005- revised
edition'
Electricity Consumption
The elasticity ratio (elasticity of electricity consumption with respect to
GDP) was 3.06 in the first Plan and peaked at 5.11 during third plan
and declined to 1.65 in the Eighties. While consumption went up by
3.14% for every 1% growth in GDP in the first five-year plan period
(1951- 56), it went up by only 0.97% in the eighth plan period (199297).
The growth in electricity consumption over the past decade has been
slower than the GDPs growth. This could be due to high growth of
the services sector or it could reflect improving efficiency of electricity
11
Year
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
2000-01
2003-04
Year
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
2000-01
2003-04
ENERGY SHORTAGE
Demand
Available
Shortfall
(billion kWh) (billion kWh)
267.632
246.560
21.072
288.974
266.432
22.542
305.266
279.824
25.442
323.252
299.494
23.758
352.260
327.281
24.979
389.721
354.045
35.676
413.490
365.900
47.590
507.216
467.400
39.816
559.264
519.398
39.866
(%)(billion kWh)
7.87
7.80
8.33
7.35
7.09
9.15
11.51
7.8
7.1
(%)
15.53
18.79
20.49
18.31
16.45
18.28
17.97
12.3
11.2
13
14
Hydro Generation
Hydroelectricity generation enhances Indias energy security, is ideal
for meeting the peak demand and is not linked to issues concerning
fuel supply, especially the price volatility of imported fuels. Only about
17
18
20
1996-97
23.41
For detailed & updated information on the Indian Power Sector, refer to the
report - 'Overview of Power Sector in India 2005- revised edition'
Renovation & Modernization
In order to bridge the gap between demand and supply, especially in
the context of limited financial resources available, it has become
imperative to look for other options which are not as capital intensive
as new capacity addition and which could be implemented in a
comparatively shorter time frame.
In this regard, optimum utilisation of existing installed capacity in India
to maximise the generation through renovation, modernisation,
uprating and life extension of existing power plants is considered to
be the most cost effective option with lesser gestation period.
SEBs/Utilities may review the priorities and go for renovation,
modernisation and uprating of their existing plants and avail the
opportunity of getting grants/loans through AG&SP and other
incentives being provided by the Government thereby ensuring power
generation at minimal cost.
One of the major achievements of the power sector has been a
significant increase in availability and plant load factor (PLF) of
thermal power stations especially over the last few years The overall
national average PLF has improved from 55% to 73% in last 20 years
Renovation and modernization, with financial support of Government
of India, for achieving higher efficiency levels is being pursued
vigorously and all existing generation capacity is targeted to be
brought to acceptable level of performance.
Revised 10th and 11th Plan Programmes
The schemes identified by CEA under National Perspective Plan and
not completed till the beginning of 10th plan have been reviewed in
consultation with SEBs/ PSUs/ PFC and the revised 10th Plan
programme has been finalised. As per 10th Plan Programme
reviewed in consultation with the utilities a total of 72 schemes (11
nos. under Central Sector and 63 nos. under State Sector) have been
22
The Ministry of Power has also created, under this Act, a central
coordinating body called Bureau of Energy Efficiency, which will be
responsible for promoting energy saving measures. Energy saving of
400 MW and other energy inputs totaling Rs 2300 cr has been
achieved during last five years.
24