Академический Документы
Профессиональный Документы
Культура Документы
TECHNICAL
REQUIREMENTS
Part n 03
Pipeworks
TECHNICAL SPECIFICATION
PART N 03
PIPEWORK
CONTENTS
Page
REQUIREMENTS OF APPLICABLE REGULATIONS
GENERAL
1.
BURIED PIPES
1.1
1.2
2.
DRAINPIPES
3.
MAIN DRAINS
4.
5.
6.
7.
CULVERTS
8.
SEPTIC TANKS
CTI - 28/10/98
AR/SR
1/4
BURIED PIPES
1.1.
CTI - 28/10/98
AR/SR
2/4
INSPECTION
The tightness check on pipes will be done with the pipes fully exposed, to allow the
joints to be inspected.
Pipes will be clean and free of waste matter or earth.
Pipes to be used under pressure will be subjected to a pressure of 150% of the
service pressure for a period of 4 hours with no change.
Other pipes will be subjected to a pressure of 0.3 bar for a period of 2 hours and
must not show a loss of more than 0.3 l/m_ of inside surface area per hour.
These results will be subject to the approval of the Employer.
2.
DRAINPIPES
Drainpipes will be in clayware, concrete or PVC. They will be laid level and covered with
filtration materials to a depth of 500 mm. Backfilling will be done carefully without crushing the
drain. Above the filtration material, the backfill must be free of clay, mud, vegetable matter,
etc.
3.
MAIN DRAINS
CTI - 28/10/98
AR/SR
3/4
4.
The drinking water system will be designed for a minimum dynamic pressure of 4 bar. Pipes
must withstand a pressure of 1.5 times the maximum pressure.
The materials and constructional details of pipes, valves, joints and hydrants will be subject to
the approval of the Employer, who may request laboratory tests to be carried out at the
Contractor's expense to verify the quality of the materials.
5.
These pipes will be made of concrete or PVC. An inspection pit will be provided at each
change of direction or gradient (at least every 40 m).
Joints must be leakproof. All sewage pipes must undergo pressure tests.
No pipes will have a diameter of less than 150 mm and their gradient will always be more
than 0.5% (1 in 200). Gradients must be adequate to ensure satisfactory operation of the
system.
When full, the pipes must be capable of carrying 150% of their design flow for a speed not
exceeding 3 m/s. The minimum speed will not be less than 0.6 m/s. A design note will be
provided to the Employer in respect of all pipes in the works.
6.
Their foundations will consist of a reinforced or non-reinforced concrete raft. Their walls will
be in reinforced concrete with a recess for fitting the cover slab. A metal angle iron will be
grouted into the concrete as a base for the slab.
They will be made watertight by a smooth waterproof cement grout 20 mm in thickness.
Connections to the incoming and outgoing pipes will be perfectly leakproof.
When the depth of the inspection pit so requires, galvanised iron steps 25 mm in diameter will
be grouted into the wall at vertical intervals of 150 mm. A 25 mm galvanised iron pit ladder
may also be executed with split grouting, with 25 mm diameter steps with shoulder.
7.
CULVERTS
For services supplied through culverts, please see the requirements given in chapter 5:
"Additional requirements for gravity drains".
8.
SEPTIC TANKS
CTI - 28/10/98
AR/SR
4/4