Академический Документы
Профессиональный Документы
Культура Документы
design brief
AUTOMATED MONITORING AND FAULT DETECTION
Summary
facility manager to performance
Commissioning,
retro-commissioning,
re-commissioning,
and
and money.
CONTENTS
Introduction
Benefits of Automated
Monitoring
14
Automated Monitoring
Packages
17
23
Conclusion
24
Glossary
25
26
Notes
27
Introduction
Building commissioning is the systematic process of ensuring that a
buildings systems are designed, installed, and tested to perform
according to the design intent and the building owners operational
needs. The commissioning process can be applied to new and existing
buildings and covers the building envelope, plumbing, and all energized
systems (lighting, HVAC, refrigeration, life-safety, occupant transport,
and specific processes). Commissioning is an iterative process of
communication, observation, actively testing components and systems,
and recording results. Traditionally, it has been conducted over a set
time period by a team of specialists who understand the design,
installation, and operation of these systems. If applied to existing
buildings, it is often called retro-commissioning (first application) or recommissioning (second and subsequent applications).
The commissioning of new buildings is most effective when considered
throughout the planning, design, construction, and post-occupancy
stages. Integrating commissioning into a new building project provides
the opportunity for the best initial performance, which the owner can
use as a guideline throughout the life of the building.
Post-occupancy commissioning (including retro-commissioning and recommissioning) usually are performed because some aspect of building
performance, such as occupant comfort or energy use, has exceeded the
baseline performance that should be achieved. Post-occupancy
commissioning is the process of systematically re-evaluating the
performance of the building systems. Simply tuning the building
controls is often a cost-effective means of returning the building to its
design performance. But commissioning of existing buildings often
identifies components or systems that should be repaired or replaced.
Repair and replacement offer the opportunity to install higher efficiency
equipment or improve operations by improving the controls for systems.
Often comfort is improved, and energy use or demand is reduced.
A key limitation to commissioning and retro-/re-commissioning is that
each one is a periodic service, and building performance usually tends to
drift away from the design baseline over time. Also, retro-/re-
PAGE
PAGE
Table 1.
Level
Building Control
Description
Control Access
(Local, Remote)
Control System
Characteristics
Operator Interaction
With Controls
Commissioning Technology
1 Independent,
separate control of
components and/or
systems
Local
No or little data
storage
Manual control of
component and
system operations
2 Integration of
control under
on-site supervisory
software
Local
Automated control of
on/off schedules and
setpoints
3 Level 2 plus
connection via
phone line
4 Level 3 plus
Internet technology
Level 3 plus
alarms to remote
pagers, cell
phones, and
email
Level 3 plus
embedded
diagnostics in local
controllers and/or
diagnostics at
supervisory level
Level 3 plus
information to assess
maintenance
requirements
5 Level 4 with
outside input for
utility demand
response (weather
and load
information)
Same as Level 4
Level 4 plus
automatic load
management and
information to assess
predictive
maintenance
Faults are conditions that are outside of design intent and may include
conditions that waste energy, increase electric or natural gas demand,
and may result in comfort complaints. In addition to detecting faults,
automated monitoring systems may also diagnose faults and provide
information about possible causes.
Automated monitoring can provide operators with information that
allows them to focus on the root causes of comfort complaints and energy
waste. It also can be a very valuable adjunct to retro-/re-commissioning
projects by providing insight into equipment deficiencies at the
beginning of the project. Table 2 summarizes the key characteristics
associated with commissioning, retro-commissioning, re-commissioning,
and automated monitoring.
PAGE
Table 2.
Retro-Commissioning
Re-Commissioning
Auto-Monitoring
Application
New Construction
All applications
Timing
As early as possible
i.e. pre-design
Occurs in response to
under-performance or
problems in the building
systems
Occurs periodically or
in scheduled intervals
as part of the O&M, or
in response to specific
operating issues
Purpose
Ensures building
systems will perform
optimally
Ensures building is
still performing
optimally, maintains
level of previous
commissioning
Continuously
maintains optimal
performance
Frequency
Every 3-5yrs
Once installed,
provides continual
commissioning for the
life of the building
Cost6
$0.05-$0.40/ft2,
median is $0.27/ft2
Benefit6
$1.00/ft2 energy
saving with a median
payback of 4.8 yrs.
One time non-energy
benefit = $1.24/ft2
Similar to retro-,
depending on
frequency
PAGE
Retro-Commissioning
Cost Savings
Retro-commissioning of existing
condition may reduce energy costs because the proper amount of outside
air would have not been heated or cooled, but this is clearly at the
expense of good indoor air quality. Also, during periods when the outside
air temperature is within the economizer range, free cooling would not
be available. Automated monitoring can detect this problem quickly and,
in some cases, provide a diagnosis of what caused the problem.
compensate for the added cold air and the indoor air temperature would
ambient temperature would drop and the hot water coil or heater might
is possible that coils might even freeze. Significant energy waste can
PAGE
LEED Accreditation
For building owners pursuing accreditation under the USGBC LEED
rating systems, automated monitoring systems may help qualify projects
for credits under the Energy and Atmosphere (EA) and Indoor
Environmental Quality (EQ) categories. For the New Construction
(LEED-NC) rating system, automated monitoring systems could apply
to the following.
I
PAGE
EA credit #6: Documenting Sustainable Building Cost Impact information from automated monitoring systems also can be used to
meet the requirements listed for this credit.
PAGE
EQ credit #7.2: Thermal Comfort: Permanent Monitoring System this credit requires measurement and trending of temperatures,
relative humidity, and CO2 or air speed at locations selected
according to the impact on occupant comfort. Automated
monitoring systems can be designed to handle these tasks.
PAGE
Building System/Component
Decision
Fault Detection
Measurements
No Fault
Fault
Passive Fault
Diagnosis/
Isolation
No Action
Required
Tolerate
Proactive
Diagnosis
Pro-Active
Diatnosis for
Fault Isolation
Request a Repair
and Continue
Tolerate?
No
Reconfigure
the Controls
No
Reconfigure
Controls?
Fault Diagnosed
Reconfigure
Fault Evaluation
Operate
Safety
Availability
Energy/Cost Impact
Comfort
Environmental
Impact
Alarm/
Shutdown
Continue to
Operate?
No
Detecting Faults
Regardless of the fault detection method used, faults are detected when
the comparison residual (actual value minus predicted value), exceeds a
predefined threshold. Not all values come directly from readings, some
variables are either calculated or characteristic values, such as outside air
quantity or coefficient of performance for an air conditioner. Regardless
of the source of the variable, it is important to use a dynamic model for
predicted values. HVAC systems are inherently dynamic due to
changing indoor and outdoor conditions. Using a fixed value as a
comparison will result in either too many or too few faults being
reported. For example, if facility staff were measuring efficiency and
comparing it to a fixed minimum value, the result would not be accurate
because efficiency changes with input conditions. For this reason, the
detection algorithm should run a dynamic model. This could be as
simple as using a formula to change the threshold based on inputs or a
real time simulation of the whole system.
PAGE
10
Diagnosing Faults
Diagnosing faults is a much more sophisticated process than detection.
Detection is as simple as fault or no fault, diagnosis may require an
analysis of multiple faults (passive diagnosis), or require manipulation of
the system itself (active diagnosis). Many times a fault is detected but its
cause cannot be determined without observing the system through a
wide range of conditions or modes. Using the proactive measure, modes
can be forced and a conclusion reached in a relatively short amount of
time. Passive diagnostics may take considerable time for the system to
cycle through the required conditions or modes on its own.
The cause of some faults can be determined as soon as they are
discovered. For example, if a large pressure drop is found across the air
filter, the diagnosis would be a clogged air filter (assuming the sensor is
functioning properly). On the other hand, triggered faults that are a
result of calculated values typically need further testing to determine
their origin. For example, the monitoring system might detect a
potential sensor error, but is unable to pin point the error among three
different sensors return air, mixed air, and outside air. A proactive
system could wait until the building is unoccupied to force modes that
reveal the diagnosis. Through the BAS, the diagnostics program could
initiate 100 percent outside air and compare both mixed air and outside
air, then switch the dampers for 100 percent return air, and compare the
return air and mixed air. By isolating the different sensors and
comparing them, the faulty sensor should reveal itself. Figure 2 shows a
proactive FDD decision tree for a faulty sensor.
PAGE
11
Temperature
Sensor
Problem
Proactive Diagnostics
Temperature Sensor Problem
Sequential
Operation
Close Outdoor-Air
Damper Completely
Shut (100%
Recirculation)
Close Return-Air
Damper Completely
Shut (100%
Outdoor Air)
Is Mixed-Air Temperature =
Return-Air Temperature
Is Mixed-Air Temperature =
Outdoor-Air Temperature
Equal
Equal
Mixed-Air and
Return-Air
Temperature
Sensors OK
No
No
Mixed-Air and
Outdoor-Air
Temperature
Sensors OK
If Both
Tests Fail
Problem: Return-Air
Temperature Sensor
Problem
Problem: Outdoor-Air
Temperature Sensor
Problem
Problem: Mixed-Air
Temperature Sensor
Problem
PAGE
12
PAGE
13
PAGE
14
Table 3: Lookup Table for Diagnosing Damper Faults, Created by Actively Calibrating the Damper System8
Outdoor Air
Damper
Signal
Normal Operation
(% Open)
Outdoor Air
Fraction
Supply Fan
Power
Consumption
(Watts)
Outdoor Air
Fraction
Supply Fan
Power
Consumption
(Watts)
Outdoor Air
Fraction
Supply Fan
Power
Consumption
(Watts)
10
0.15
1,550
0.05
1,560
0.15
1,500
20
0.25
1,450
0.08
1,600
0.25
1,400
30
0.40
1,350
0.15
1,625
0.40
1,300
50
0.60
1,250
0.20
1,650
0.60
1,200
70
0.75
1,150
0.40
1,750
0.75
1,100
100
1.00
1,000
0.70
1,800
1.00
1,000
PAGE
15
Figure 3. Decision Tree to Detect and Diagnose Outdoor Air Damper Faults
Validate Sensor
Measurements
No
Are Sensor
Measurements
Good?
Good
Is Outdoor-Air
Damper Signal
Correct?
Problem: Control or
Control Code
Correct
Is Actual
Pressure
Drop and Power
Consumption = Expected
Pressure Drop
and Power
Consumption?
Lookup Table for
Normal Operation
No
Yes
OK: OA Damper
Operation OK
No
Is Actual OAF =
Expected OAF?
OAF is OK,
but not the
Pressure Drop
and Power
Consumption
Equal
No
Problem: Damper Problem
Is Actual
Pressure
Drop and Power
Consumption = Expected
Pressure Drop
and Power
Consumption?
Yes
No
PAGE
16
ABCAT
The Automated Building Commissioning Analysis Tool (ABCAT),
developed by the Energy System Laboratory at Texas A&M University,
uses existing hardware in a fully commissioned building to achieve a
baseline measurement for operational energy use. During the calibration
period, the program is running its own simulation model; at the end of
that period, the mean error is subtracted to further calibrate the model.
It then monitors the building and compares the actual inside air quality
and energy use to the calibrated model. When the two values are not
synchronized, a fault is reported by the system.4
ACRx Sentinel
Field Diagnostics Services Inc. created the ACRx Sentinel package to
diagnose faults in small commercial air-conditioning units. The Sentinel
uses custom hardware installed in packaged-HVAC units to monitor
and transmit data to a web server via a wireless modem. The software
analyzes refrigeration and air-side data on a daily basis and reports faults
on a web page, including estimated wasted energy costs.9 The Sentinel
is available for retrofit applications and is likely to be available as an
OEM (original equipment manufacturer) feature that is sold to HVAC
companies within the next few years.
PAGE
17
CITE-AHU
CITE-AHU is a retro-commissioning tool developed from a joint effort
between NIST and CSTB, the French Scientific and Technical Centre
for Building. Designed specifically for AHUs, the program uses APAR
algorithms. CITE-AHU depends on the existing hardware in a building
and taps into the BAS for its interface. By connecting directly to the BAS,
CITE-AHU can perform active tests to force different modes. This
allows the program to more aggressively pursue faults without waiting for
them to happen.3
PAGE
18
DABO
Diagnostic Agent for Building Operators (DABO) was developed at the
CANMET Energy Technology Centre-Varennes in Canada. DABO
requires a BAS because it actively monitors and controls the HVAC
system with four different modules.
Currently, the Diagnostic Agent module is the only part available for
commercialization. The Diagnostic Agent uses expert systems and
pattern recognition to monitor, diagnose, and report faults. The
Adaptive Controller monitors and controls the sub-systems of the
HVAC system, such as VAV boxes and AHUs at optimal levels. The
Building Energy Agent uses inputs from the Diagnostic Agent and the
Adaptive Controller to predict performance and optimize set points.
The Building Maintenance Agent uses outputs from the Diagnostics
Agent to create a maintenance schedule report. The last module in the
circle is the Building Commissioning Agent, which is the active part of
DABO. Using the information from the Diagnostic Agent, it runs a
series of tests and actively changes settings based on the results.5
EffTrack
EffTrack, developed by Efficiency Technologies, Inc. is an automated
efficiency and diagnostic web-based service focused on chiller, boiler,
and plate exchanger efficiency and trending. EffTrack uploads data from
an existing BAS and/or additional monitoring equipment to its servers
and processes the data to provide facility managers the ability to
document, monitor, evaluate, and manage chiller system performance.
Efficiency Technologies has announced plans for future enhancements
that will include advanced chiller charting, internationalization (metric
units), diagnostics, and automated data collection for boilers and plate
exchangers, water treatment analysis, screw chillers, steam driven
chillers, evaporator condensers, air-cooled and rooftop units, air
handling units, and tower systems.
PAGE
19
PAGE
20
INFOMETRICS
Infometrics, developed by Cimetrics, is a remote monitoring service
using hardware and software that access data from the underlying BAS.
Cimetrics personnel analyze the data to find and diagnose faults.
Quarterly reports are created for the client with an energy use analysis,
mechanical system performance analysis, and a set of operational
recommendations prioritized by savings.2
PACRAT
Performance and Continuous Re-Commissioning Analysis Tool
(PACRAT) is an automated monitoring tool created by Facility
Dynamics. PACRAT taps into the existing BAS trend logs to monitor
and analyze the performance of the HVAC system. PACRAT has
three modules:
I
Rooftop Diagnostician
Developed at Pacific Northwest National Laboratory (PNNL), which is
operated by Battelle for the U.S. Department of Energy, this tool allows
facility staff to determine the cause of a malfunction in a rooftop unit or
to monitor performance in order to optimize regularly scheduled
AUTOMATED MONITORING AND FAULT DETECTION
PAGE
21
PAGE
22
Current Development
As noted above, many different organizations are developing automated
monitoring tools, each with a slightly different focus. Most products are
focused on one or more major HVAC components, with the intent of
expanding the scope to create a comprehensive analysis tool that can be
used to detect and diagnose faults throughout the whole HVAC system.
The details of research and development by private organizations are
closely guarded. However, public groups such as CANMET Energy
Technology centre in Canada, NIST, and Annex 40 readily announce
current progress and future development.
PAGE
23
Conclusion
Lack of proper commissioning, inexperienced operators incapable of
handling complicated building controls, and insufficient maintenance,
lead to reduced equipment life and increased operating costs.
Commissioning, re-commissioning, and retro-commissioning require
qualified commissioning personnel for periodically gathering, reviewing,
and documenting performance data. After traditional commissioning has
been completed, the beneficial effects often begin to dissipate.
On the other hand, automated monitoring provides continuous
feedback on building performance and affords the opportunity to
reduce labor requirements and create energy savings. Whether the
installed automated monitoring system is an active or passive FDD
system, nearly all HVAC systems will realize better performance.
Many hurdles still exist for this industry. Public awareness may be the
most significant. Many organizations are investing in this technology
with the hope that these products will be a common part of building
systems in the future. For now, only a few commercial and government
buildings utilize automated monitoring, and these few cases have shown
the concept to be viable. It is only a matter of time before automated
monitoring is installed as a common HVAC tool, and is expanded to
encompass other building systems.
PAGE
24
Glossary
ABCAT
AEC
AFDD
AHU/RTU
APAR
ASHRAE
BAS
DABO
FDD
HVAC
IAQ
LEED
NIST
O&M
OSA
Outside Air
OSAD
OAE
PACRAT
PECI
PNNL
USGBC
VAV (box)
VFD
WBD
PAGE
25
PAGE
26
Notes
1. Brambley, Michael, and Srinivas Katipamula.
Beyond Commissioning. The Role of Automation. Feb. 2005.
Pacific Northwest National Laboratory.
www.automatedbuildings.com/news/feb05/articles/pnl/pnl.htm
2. Building Accountablity. Cimetrics.
www.cimetrics.com/home/infometrics/
3. Castro, Natascha S., and Hossien Vaezi-Nejad. CITE-AHU,
an Automated Commissioning Tool for Air-Handling Units.
National Conference on Building Commissioning, 2005.
4. Claridge, D.E. Engineering and Software Requirement of the
Automated Building Commissioning and Analysis Tool.
Energy Systems Laboratory (ESL) at Texas A&M University.
ESL, Texas A&M, 2005.
txspace.tamu.edu/bitstream/1969.1/2081/1/ESL-TR-05-01-02.pdf
5. Intelligent Building Operating Technologies. CANMET Energy
Centre. Varennes: CANMET Energy Technology Centre, 2004.
cetc-varennes.nrcan.gc.ca/fichier.php/codectec/En/
2004-044/2004-044e.pdf
6. Mills, Evan. Cost-Effectiveness of Commercial-Building
Commissioning. Dec. 2004. Lawrence Berkeley National
Laboratory, Portland Energy Conservation, Energy System
Laboratory.
eetd.lbl.gov/emills/PUBS/Cx-Costs-Benefits.html
7. PACRAT. Facility Dynamics.
www.facilitydynamics.com/Pacwho.pdf
8. Portland Energy Conservation, Inc. Methods for Automated and
Continuous Commissioning of Building Systems. ARTI: 21-CR.
Springfield: US Dept. Commerce, 2003.
9. Rauch, Christopher A. Field Diagnostics Services, Inc.
Acrx.Com. 2002.
www.acrx.com/FieldDiagnosticServicesIncCompanyDescription.pdf
10. Rooftop Diagnostician.
availabletechnologies.pnl.gov/technology.asp?id=58
11. Whole Building Diagnostician. Building Systems Program.
20 Oct. 2005.
www.buildingsystemsprogram.pnl.gov/fdd/wbd/index.stm
PAGE
27
09/2007