Вы находитесь на странице: 1из 39

PRE - FEASIBILITY STUDY

DEVELOPMENT OF HYDRO SCHEME


ON COED GWERN STREAM

Client: CAT Holdings Plc


Consultant: Nick Jeffries, Engineer
CONTENTS
Page

EXECUTIVE SUMMARY……………………………………………………… 4

1. INTRODUCTION……………………………………………………………. 6

2. REPORT STRUCTURE…………………………………………………….. 6

3. SITE DESCRIPTION………………………………………………………… 6

4. SURVEY DATA ……………………………………………………………...10


Topographical survey
Hydrological survey

5. SYSTEM DESIGN……………………………………………………………. 11
Civil Works
Electro-mechanical Equipment
Grid Connection

6. SYSTEM OPTIONS…………………………………………………………. 13
Methodology
Summary of Turbine Options
Optimising the system
Turbine Choice
Pre-fabricated options

7. COSTS v. REVENUE…………………………………………………………19
Revenue
System Costs
Errors
How payback period may be reduced

8. CONCLUSIONS……………………………………………………………… 24

9. RECOMMENDATIONS……………………………………………………… 24

BIBLIOGRAPHY

APPENDICES

A - Topographical and Hydrological Survey Data


B - Typical Run-of the River Arrangements
C - Detailed Spreadsheets
D - Expected Feed in Tariffs
E - Performance Envelopes for Different Turbine Types
F - Efficiencies of turbines at partial flows
G – Performance of Cross Flow Turbines at partial flow

Nick Jeffries, REBE Module 3 Hydro 2|Page


List of Figures, Tables and Photos

Site Location Plan

Photo 1 – Typical section of stream with natural cascades and underlying bedrock
Photo 2 – Single Phase and three phase grid connection near to proposed site

Figure 1 – Basic Layout of Civils Structures


Figure 2 – Process to determine power/energy output for different systems
Figure 3a – Energy v. flow at different pipe diameters
Figure 3b – Power v. flow at different pipe diameters
Figure 4 – Energy Output v Flow from Hydra and Low Flow Data

Table 1 – Key Characteristics of Coed Gwern Stream


Table 2 – Flow Data for Coed Gwern Stream
Table 3 – Small v Large Turbine – Pros and Cons
Table 4 – Typical Design flows v CFs for micro-hydro-systems
Table 5 – Power, annual energy output, penstock diameters and design flows
Table 6 – Optimization of system for max annual energy output
Table 7 – Specific Speeds including approx. runner diameter for impulse turbines
Table 8 – Comparison of energy output from Francis and Cross Flow
Table 9 – Annual Revenue - ROCs v Feed-In Tariff
Table 10 – Annual Revenue for different penstock diameters
Table 11 – Estimated Costs for different system options
Table 12 – Costs v benefits for choosing bigger systems

Nick Jeffries, REBE Module 3 Hydro 3|Page


EXECUTIVE SUMMARY

The site proposed by the Client for the possible development of a hydro scheme, to
generate annual cash revenue through sales of energy to the National Grid, is attractive
from the very outset. This is due to the Client’s ownership of the land adjacent to the
stream, the good vehicle access via a parallel gravel track and through the close
proximity of a grid connection.

The attractiveness of the potential scheme is further enhanced after a brief desk study
and site investigation reveals:

• Good height difference (head) head difference – more than 10m


• Constant flow – average 200l/s
• Solid bedrock - i.e. good foundation for Civils works.
• Likely low ecological concerns
• Imminent introduction of feed in tariff incentives

The characteristics and topography of the site would suit a run-of-the river scheme. This
would comprise several structures that divert water from the main stream (while
maintaining a compensation flow), remove any debris, convey water to the turbine, and
return water back to the stream. The engineering works would include: intake and weir,
forebay structure with debris screen, penstock pipe and the powerhouse containing a
turbine, generator and control systems. Finally a tailrace that returns the diverted flow to
the stream.

To export the power generated to the local grid – an inverter will convert the DC to AC
current, and a buried/overhead cable connection will convey the energy to the grid.

Based on the measured head, distance between intake and powerhouse, annual
variations in flow and the choice of penstock pipe – it is possible to generate a matrix of
power and energy outputs. As the Client wants to maximize annual revenue we can then
optimum to suit this governing criterion.

Optimization of system for max annual energy output


Pipe Diameter Peak Power Annual Energy Annual
(mm) (kW) Output (kWh) revenue

250 4.1 19058 £4,383

300 6.3 24353 £5,601

350 9.3 27876 £6,412

400 10.1 30393 £6,990

Turbine choice can be assisted by considering that the stream discharges approximately
80% of its annual volume during a 4 month ‘spatey’ period. Therefore it is easy to see
that for maximum energy output - high efficiency turbines are preferable over turbines
that maintain output over a large range of flow.

Nick Jeffries, REBE Module 3 Hydro 4|Page


An estimate of costs reveals a range of capital outlays between £40, 000 – 80,000, from
the smallest to the largest options. Pipe costs represent between 36 – 51% of the four
options considered. Running costs have been estimated as between 1.5 – 2.5%of
capital costs - giving payback periods between 12.5 and 14 years.

These costs and revenues represent an idea of the scale and time duration of the
investment. In the detail design stage, these will be firmed up as more accurate data on
flow variations and construction costs is collected.

A number of ways in which the cost/revenue situation could be improved have been
suggested including – specifying cheaper materials and equipment, client labour force
used to undertake some of the work, scheduling of maintenance in summer, limit output
to avoid potential grid connection cost issues, use of recycled materials or materials from
other CAT sites, use students and volunteers from nearby CAT to design, install and
supervise works.

If the Client decides to proceed with the project, then flow monitoring should begin
immediately. EA, DNO and adjacent landowners should also be contacted at first
opportunity, to identify any potential issues.

Nick Jeffries, REBE Module 3 Hydro 5|Page


1. INTRODUCTION
CAT Holdings Ltd (“the Client”) has recently purchased an area of land in mid-Wales
which it plans to develop into a Survival Training venue in preparation for Energy
Armageddon. The Client has appointed Nick Jeffries (“the Consultant”) to assess the
potential of developing a hydro scheme on a stream which runs through their site.
The Client’s wish is that the scheme can generate annual cash revenue that will
contribute to the future running costs for the Survival Centre.

The desired outcome of this pre-feasibility study is

• to state whether such a scheme is viable or advisable


• to describe its main features
• to estimate potential revenue and anticipated capital and running costs

The result should be that the Client has enough information on which to base a
decision whether to develop a micro hydro scheme.

2. REPORT STRUCTURE
The report starts by presenting the results of an initial desk study and site visit
carried out by the Consultant. The purpose of this first assessment was to decide
quickly whether it was worth proceeding to the more in depth pre-feasibility study i.e.
if there were any technical or policy constraints which could fundamentally affect the
viability of the scheme.

The next section looks in detail at the physical characteristics of the site, particularly
its hydrology and topography - important in determining the available flow and head
for the future scheme as they are the key parameters for calculating potential energy
output. Any likely abstraction limitations set by the local planning authorities will be
considered here.

Having defined the site - the report will go on to describe the structural components
of a micro-hydro scheme and look at various options based on different turbines
types and other system components. Each of these options will be analysed to
produce estimated annual revenue. Costs will then be estimated by considering
capital outlay for installation as well as the anticipated running costs.

This information will be presented as a table of cost v revenue for each option – that
will show the scale of required investment and the approximate payback period.

The report will finish by recommending the next steps in the development of the
scheme.

Nick Jeffries, REBE Module 3 Hydro 6|Page


3. SITE DESCRIPTION
The site is located in a forest near to the A487 above the village of Penterperthog
near Machynnleth. The stream flows approximately NW – SE down the steep sides
of the River Dyfi Valley collecting run-off from its mostly forested catchment. The key
characteristics of the stream are set out in Table 1.

The section of stream between the proposed intake and powerhouse varies in width
between 1.5 – 3 m and ‘funnels’ through the forest 2 – 5 m below the level of the
access tracks. The length of this section is about 200m and the fall about 10m. There
are a number of natural rock cascades (see photo1) which reveal solid underlying
bedrock. The SW side of the stream is generally steeper sided, however along much
of it there is a natural shelf which could be used to support the future penstock.

Ownership of the project site is on the SW side by the Client and NE side by the
Forestry Commission.

Access to the site is via forestry track which runs on both sides along the entire
section proposed for the scheme. A National Grid overhead power supply cable is
located along the A487 about 200-300m below the proposed powerhouse location.

Table 1 – Coed Gwern Stream


Key Characteristics
Stream Name Coed Gwern
Stream Length 3 – 3.5km
Fall ~ 1 in 10
Terrain Pine forest
Catchment Area 3 km2
Rainfall (approx) 2300mm (from Wallingford - Hydra)
Runoff (approx) 1500mm
Annual mean flow ~200l/s
Total Annual run-off ~5 million cubic metres
Source: OS maps, initial walkover survey and data from an initial Hydra1 model.

Assuming design flow is 50% annual mean, the power output would be 10kW. On
this basis as well as the favourable access and grid connection - the Consultant
has recommended that the Client proceed to a pre-feasibility study.

Environmental
The stream runs through land in the SW corner of the Dyfi Forest. The flora is
typically pines, other trees, ferns, lichens and mosses (see photo 1). The land is
managed on both sides by the forestry commission for timber production. The stream
is fast flowing and emanates from run off 3km upstream, and does not seem to have
any significant aquatic fauna. All in all the section of stream appear to be of low
ecological value and therefore unlikely to produce any significant issue in an
Environmental Assessment, beyond the standard requirement of maintaining a base
flow throughout the year.

1
Hydra is a flow modeling software from CEH Wallingford.

Nick Jeffries, REBE Module 3 Hydro 7|Page


Site Location Plan

Forestry
Commission Land
Proposed

Intake

Penstock
Client’s
Powerhouse Single Phase
Land
G id C
Grid Connection
ti

Site
Access
3 – Phase
Grid Connection

SITE LOCATION PLAN


Photo 1 – Typical section of stream with natural cascades and underlying bedrock

Photo 2 – Single Phase and three phase grid connection near to proposed site

Nick Jeffries, REBE Module 3 Hydro 9|Page


4. SURVEY DATA
4.1 Topographical survey
A topographical was carried out on the 21st September by the Consultant’s survey
team. The results have been included in Appendix A1. The survey was closed with
an agreement of 0.2%, within the allowable 1% error.

Based on these results, a static head = 10.2m will be used for the initial design.

4.2 Hydrological survey


A hydrological survey was undertaken to understand the flow regime of the stream,
and enable an appropriate design flow to be selected for the scheme. If the Client
decides to go ahead with the project, flow monitoring will be recommended to allow
more precise measurements to be collected.

For the survey – three approaches were taken:

• Hydra modeling in the Consultant’s office using OS Map Data


• Flow data2 for the nearby Dyfi River was scaled down to the project
catchment area.
• A Low Flow survey was commissioned from CEH Wallingford.

Having compared the data available, in particular the methodology and correlation
with Hydra, Low Flow data was selected as the basis of the energy output analysis
(see Appendix A2).

Table 2: Flow Data for Coed Gwern Stream


% Exceedance Flow m3/s
Q5 5% 0.666
Q10 10% 0.466
Q20 Basin Area:    3.199km2
20% 0.287
Base‐Flow Index:  0.44 
Q30 30% 0.202 Annual Mean Flow:  0.198m3/s 
Q40 40% 0.149 Q95:      0.023 m3/s 
Q50 50% 0.114  
Q60 60% 0.087 Data source: CEH Wallingford 
Q70 70% 0.065
Q80 80% 0.045
Q90 90% 0.03
Q95 95% 0.023
Q99 99% 0.014

Note: Q95 – the flow that the EA will likely require to be kept in the stream for
ecological and aesthetic reasons.

2
http://www.nwl.ac.uk/ih/nrfa/webdata/064001/g.html

Nick Jeffries, REBE Module 3 Hydro 10 | P a g e


5. SYSTEM DESIGN
Small hydro schemes can be divided into 2 categories: impoundment (i.e. with dam)
or run-of the-river. For this project –there is no natural lake, the valley shape is steep,
narrow and forested –so an impoundment structure would be inappropriate.

Run-of-the-river systems have a number of possible arrangements (see Appendix B).


Those that could be considered in this scheme are: (a) open channel, (b) combined
channel/penstock or (c) penstock only. Channels are normally only suitable for
countries where labour is cheap compared to pipe costs, or for a particular
combination of topography, river alignment and terrain.

For this project the most appropriate system would be for a penstock only – fed by
an intake/diversion structure and piping water directly to the powerhouse.

5.1 Civil Works


Civils works are those structures required to divert water from the main stream (while
maintaining a compensation flow), remove any debris, convey water to the turbine,
and return water back to the stream:

• Intake and weir – controls the amount of water taken from the stream
• Forebay structure and screen – removes debris and delivers water to the
penstock
• Penstock – pipe that conveys water to the turbine. Needs to be able to
withstand the pressure of the water plus an allowance for ‘surge’ pressure.
• Powerhouse – contains the turbine, generator and control systems
• Tailrace – returns the water to the river

Figure 1 – Basic Layout of Civils Structures

Source: http://www.energyhimalaya.com/sources/images/

Nick Jeffries, REBE Module 3 Hydro 11 | P a g e


5.2 Electro-mechanical Equipment
A turbine and generator convert the energy of the flowing water into electricity. The
equipment will be located in the powerhouse. The shaft speed of the turbine should
be 1500 or 3000RPM to match the frequency of the grid frequency (50 Hz). If it does
not, then there will be a requirement for a gearbox or for a belt drive between the
turbine and generator.

Turbine types are discussed in section 6.4. Generators can be either the more
expensive synchronous type or for small systems the cheaper asynchronous or
induction type.

The powerhouse will also contain electrical wiring, a control system, and potentially
an inverter (see next section) and transformer to match the electricity output to the
frequency and voltage of the grid.

5.3 Grid Connection


The nearest grid location appears to be a single phase line on the main road serving
the buildings at the entrance to the site. There is also a 3-phase power line on the
other side of the Dyfi River (see Site Location Plan and Photo 2). There will need to
be either an overhead or buried cable connecting the powerhouse to the nearest
junction box of the grid.

If a synchronous generator is used a grid tie inverters (or synchronous inverters) will
need to be included to convert DC to AC current and synchronise output allowing it
to feed into the grid. If an inductor generator is specified (more likely) then either an
electronic soft start or mechanical drive will be required to get the generator up to
synchronization speed and then a DC-AC inverter to allow a connection.

Before the initial connection, assuming the system output is below 16A/phase3, an
approval process will need to be undertaken by the DNO to check it conforms to the
G83/1 Regulations.

3
Equivalent to approximately 11kW output for 400V 3-Phase generator.

Nick Jeffries, REBE Module 3 Hydro 12 | P a g e


6. SYSTEM OPTIONS
The sizing of a micro-hydro system will be determined mainly by the Client’s
intended end use for the electricity generated. For a standalone system where
electricity is used only in local buildings or processes, a smaller turbine may be
selected that provides a steady supply for a longer period of the year, whereas for a
grid connected system where all of the electricity is exported, a different system may
be specified.

Table 3 sets out the advantages and disadvantages at the extremes of each site’s
potential generation range.

Table 3 – Comparison of Small v Large Turbine


Turbine Size
(kW)
(proportional to Advantages Disadvantages
max possible
output)
-More efficient - More expensive
-Peak output higher -Lower capacity factor4
-In seasonal countries output -Longer periods of non-
Large may match demand curve generation
-Greater overall electricity
output
-Good for standalone systems -Less efficient
-Provides a more consistent - Requirement for ballast
supply of electricity resistor or other way of
Small
-Cheaper dumping energy
-Higher capacity factor

For this project the Client has stated that the intention is to sell all the energy
produced to the local grid to gain as much cash revenue as possible. Therefore the
governing factor for turbine sizing will be:

Maximize total annual energy (kWh) output

6.1 Methodology
The selection of the correct turbine size is carried out using an iterative process (see
fig 2) that calculates power (kW) output and the corresponding energy outputs (kWh)
for a range of design flows.

The scope of the analysis is expanded by considering different pipe diameters (D) for
particular flows. Varying D will change the working head, H, driving the design flow –
thereby changing the power and energy output. The result is a matrix of maximum
turbine power output, annual energy production and pipe diameter which enables
revenue and system costs to be estimated thus allowing the cost-benefits of different
systems to be compared (see Appendix C).

4
Capacity Factor = [Energy Generated/yr (kWh/yr)]/[Installed Capacity (kW) x 8760]

Nick Jeffries, REBE Module 3 Hydro 13 | P a g e


Figure 2 – Process to determine power/energy output for different systems

If we adopt the British Hydro Association’s guideline5:

“ for a good return on investment on micro-hydro systems aim for a capacity factor (CF)
of 50 – 70%”

This corresponds approximately to the design flows shown in table 4:

Table 4 – Typical Design flows v CFs for micro-hydro-systems


DESIGN FLOW (Qo) CF
Q mean 40%
0.75 Q mean 50%
0.5 Q mean 60%
0.33 Q mean 70%
source: BHA

We can now begin to calculate power and energy outputs.

5
Pg. 10 Mini Hydro Guide, BHA

Nick Jeffries, REBE Module 3 Hydro 14 | P a g e


6.2 Summary of Turbine Options
Table 5 below is a summary of the key outputs from the analysis (for detailed
spreadsheets Appendix 3). The highlighted values are the maximum annual revenue
for each pipe diameter at the specified flow.

Table 5 – Power, annual energy output, penstock diameters and design flows

Design
Flow
100% 75% 50% 33%
(%
Qmean)
Pipe Max Annual Max Annual Max Annual Max Annual
Diameter Power Output Power Output Power Output Power Output
(mm) (kW) (kWh) (kW) (kWh) (kW) (kWh) (kW) (kWh)

250 0.0 0 0.1 160 4.0 14706 3.9 17735

280 0.5 1244 4.9 13636 5.6 20459 4.4 19955

300 4.8 10912 6.8 18889 6.2 22702 4.6 20821

350 10.4 23782 9.3 25884 7.0 25688 4.9 21973

400 12.8 29338 10.4 28903 7.4 26976 5.0 22470

Notes:
1. An abstraction regime limited turbine flow to 50% above Q95. This is more rigorous,
than typical limits of 25% to ADF, and 50% above ADF.
2. The pipe diameters selected were those sizes commonly available from pipe suppliers
3. Assumed partial flow efficiency – 75% - in later calculations this is further refined to
match established performance curves.

6.3 Optimising the system


If we plot the relationship between annual energy output (figure 3a) and peak power
output (figure 3b) against flow for each of the pipe diameters, we see that maximum
annual energy is actually achieved at the optimum flow conditions shown in Table 6.

Table 6 – Optimization of system for max annual energy output:


Pipe Optimum
Peak Net Head
Diameter Flow % QMean
Power (kW) (m)
(mm) (cumecs)

250 0.063 32% 3.9 8.08


300 0.09 45% 5.8 8.55
350 0.132 67% 8.7 8.65

400 0.132 67% 9.5 9.43

Nick Jeffries, REBE Module 3 Hydro 15 | P a g e


Figure 3a – Energy v. flow at different pipe diameters

Energy Output v Flow

35000
Annual Energy (kWh)

30000

25000

20000

15000

10000

5000

0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45
Flow (cumecs)

Figure 3b – Power v. flow at different pipe diameters

Power v Flow

16
Power (kW)

14

12
10
9.5kW
8.7kW 8
5.8kW
3.9kW
6

4
2

0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45
Flow (cumecs)

400mm 350mm 300mm 250mm

An interesting and useful result from this optimization stage is that in most cases, as
annual energy output reaches its maximum value, peak power output has reduced. The
corollary of this is a smaller turbine (less cost) and larger output (more revenue).

Nick Jeffries, REBE Module 3 Hydro 16 | P a g e


6.4 Turbine Choice
The type of turbine is based on a number of factors but can be narrowed down by
considering the available head in the system:

• Low head sites – Francis, Propeller, Kaplan


• Low - Medium head – Crossflow, Banki
• High head – Pelton, Turgo

The precise selection of turbine within the overall design is an important step to realizing
the optimum potential from the scheme. To assist in this process graphical tools can be
used such as the performance envelope (see Appendix E); or a conceptual quantity
called ‘specific speed’, Ns , that is a function of turbine shaft speed (RPM), power output
and head:

Ns = 1.2 RPM √kW


H1.25
For Ns =
12 - 30 Pelton;
20 - 70 Turgo;
20 - 80 Crossflow;
80 - 400 Francis;
340 - 1000 Propellor and Kaplan.

Table 7 – Specific Speeds including approx. runner diameter for impulse turbines
Shaft Speed (RPM)
Pipe Diameter
(mm) 400 600 800 1000 1500

250 70 104 139 174 261

300 79 119 158 198 297

350 97 146 194 243 364

400 92 138 184 230 344

Approx. Runner
280 186 140 112 75
Diameter (mm)

The results suggest either a Francis or Crossflow turbine, however there are significant
overlaps between different turbine types and therefore other factors need to be
considered to refine the choice, such as:

• Cost
• Availability
• Flow variability
• Performance of turbine at variable flow rates

Crossflow turbines are accepted as cheaper to fabricate due to their comparatively


simpler structure. Although their efficiency at peak output is lower than other turbine
types, they have a better performance over a range of flow conditions compared (see

Nick Jeffries, REBE Module 3 Hydro 17 | P a g e


Appendix G). Francis turbines have a higher efficiency in the 60 – 100% Design flow
region, but their performance drops off sharply below 50% design flow.

If we apply the efficiencies from the efficiency v. flow graphs (appendix F) to the design
data for the optimum conditions (table 6), we can compare outputs from Francis and
Cross Flow turbines:

Table 8 – Comparison of Outputs from Francis and Cross Flow


Francis Crossflow % Difference

400mm kWh 30393 29877 1.7%


kW 10.1 9.0
350mm kWh 27876 27404 1.7%
kW 9.3 8.3
300mm kWh 24353 22794 6.4%
kW 6.3 5.5
250mm kWh 19058 17976 5.7%
kW 4.1 3.7

As water flow corresponds to power (kW) and volume discharged corresponds to energy
output (kWh), then knowing that our stream discharges approximately 80% of its annual
volume during a 4 month ‘spatey’ (high flow) period of the year – it is easy to see that for
maximum energy output - high efficiency at higher flow is more important than
maintaining output at lower flows.

6.5 ‘Off the shelf’ options


A number of manufacturers have responded to the increase in demand for micro-
turbines by producing a number of low cost, modular, off the shelf systems using
standardized parts for fabrication. Examples of such systems include Toshiba ‘E-Kids’6
and The Ossberger Turbine7.

The advantages claimed are:

• Flexible application
• Rapid assembly
• Simple installation
• Lower construction costs
• Reduced O and M costs

These are fairly innovative systems, which in the case of Toshiba may still not be
competitive in the European market as they are only assembled in Japan. However if
demand in Europe continues to increase, it may mean that these systems become viable
when the project reaches detail design stage.

6
http://www.tic.toshiba.com.au/product_brochures_and_reference_lists/ekids.pdf
7
http://www.ossberger.de/cms/en/hydro/the-ossberger-turbine/

Nick Jeffries, REBE Module 3 Hydro 18 | P a g e


7. COSTS v. REVENUE (for detailed calculations refer to Appendix C)
7.1 Revenue
The potential revenue from generating renewable energy is set to increase
significantly as the new feed-in tariff (FIT) incentive scheme is due to come into
effect in April 2010, replacing the existing ROC8 scheme.

FITs oblige utility companies to pay a premium rate set by the government, for each
kWh produced by RE systems. The rate is significantly above the market rate for
conventional power generation (see Appendix D – for provisional rates). The effect
on potential revenues for a range of annual kWh outputs is set out in Table 9 based
on a FIT rate of 17p/kWh compared to the existing ROC system that pays 2 ROCs
for every MWh of electricity. ROCs currently sell at about £45/ROC (ref:
http://www.nfpa.co.uk/ auctionprices.html). At these rates the potential increase in
revenue amounts to 53%.

Table 9 – Annual Revenue ROCs v Feed-In Tariff


REVENUE
Feed-in
ROCs Electricity
kWh/year Tariff ROC FIT
Value (6p/kWh)
(17p/kWh)
10000 £900 £1,700 £600 £1,500 £2,300
20000 £1,800 £3,400 £1,200 £3,000 £4,600
40000 £3,600 £6,800 £2,400 £6,000 £9,200
80000 £7,200 £13,600 £4,800 £12,000 £18,400
100000 £9,000 £17,000 £6,000 £15,000 £23,000

If we apply FIT to Table 6, we can generate a table of annual revenue for our
optimum conditions:

Table 10 –Annual Revenue for different penstock diameters


Pipe Diameter Peak Power Annual Energy Annual
(mm) (kW) Output (kWh) revenue

250 4.1 19058 £4,383

300 6.3 24353 £5,601

350 9.3 27876 £6,412

400 10.1 30393 £6,990

Assumptions
1. 4% reduction on final output for breakdown or maintenance days
2. Turbine efficiency at peak output – 90% Francis; 80% Cross flow
3. Partial flow efficiencies – see table in Appendix G

8
Renewable Obligation Certificate

Nick Jeffries, REBE Module 3 Hydro 19 | P a g e


4. Gear box/belt drive efficiency – 97%
5. Generator efficiency – 95%
6. Grid tie inverter efficiency – 95% (from Fronius – see Appendix E)

7.2 System Costs v. Revenue


In order to analyse the financial viability of a hydro scheme it is necessary to
compare revenue to costs. Costs can be divided into:

• Capital costs
• Running Costs
• Annual revenue

At the pre-feasibility stage it is difficult to ascribe precise costs to all elements of the
design and operation. However it is possible to start building up a first estimate - by
costing some key items accurately, comparing to similar completed projects and
using established industry guidelines. This will at least enable options to be
compared and the scale of required investment to be understood:

Table 11 –Cost for different system options


Peak Power Output (kW) 4.1 6.8 9.3 10.1

Pipe Diameter 250mm 300mm 350mm 400mm

%
CAPITAL Capital
C1 Planning Design £5,000 £5,000 £5,000 £5,000
C2 Management and Finance £1,500 £1,500 £1,500 £1,500
C3 215m pressure water pipe £15,171 £23,753 £30,506 £38,246
C4 Other Civil Works £8,000 £8,000 £10,000 £10,000
C5 Electro- Mechanical £4,152 £6,886 £9,006 £9,781
C6 Distribution of Electricity £4,000 £4,000 £4,000 £4,000
C7 Contingency 10% £3,782 £4,914 £6,001 £6,853
£41,605 £54,053 £66,013 £75,379

RUNNING
R1 Insurance 0.5% £208.02 £270.27 £330.07 £376.90
R2 Annual Inspection Fixed £150.00 £150.00 £150.00 £150.00
R3 Maintenance Fixed £300.00 £300.00 £300.00 £300.00
R4 Rates 0.4% £166.42 £216.21 £264.05 £301.52
R5 Administration Fixed £55.00 £55.00 £55.00 £55.00
Cost per year £879 £991 £1,099 £1,183

REVENUE
Expected annual revenue £4,164 £5,321 £6,091 £6,640.87
Less Running Costs £3,285 £4,330 £4,992 £5,457

Pay back (yrs) 12.7 12.5 13.2 13.8

Nick Jeffries, REBE Module 3 Hydro 20 | P a g e


Assumptions
1. C1, C2, C6 and R2, R3 and R5 – assumed to be the same for all options.
2. C3 – Class B U-PVC pipe from - http://www.epco-plastics.com/
3. C5 includes Turbo-generatorset (http://www.swithenbanks.co.uk/); grid tie
inverter (http://www.brightgreenenergy.co.uk/fronius_inverters.asp) and an
allowance for control systems.
4. C1, C4, C6, C7 have been estimated and scaled according to size o f scheme.
5. Overall running costs – guided by industry norm of 1-2% of capital cost/year for
running costs.
6. Insurance and Rates percentages – adapted from DTI, 1999

The above economic analysis, which is a fairly cautious, straight-line payback


calculation, has been carried out to demonstrate the basic ‘attractiveness’ of the
scheme. The Client now has a better appreciation of the scale of investment and the
duration involved to recoup this investment.

By way of validating our estimates – the Consultant is aware of a similar (9.5 kW)
scheme9 in Northern Ireland on a site which had particular special structural cost
issues that cost £78, 000 to install and commission.

If time and scale is acceptable to the Client, then the next project stage should
include a more sophisticated analysis that incorporates accurate costs based on
actual quotations and measured drawings as well as the application of discount and
bank interest rates. Table 9 shows the kind of data that may be considered in such
an analysis.

Table 12 – Costs v benefits for choosing bigger systems


4.1kW 6.8kW 9.3kW 10.1kW
Pipe costs as % of
36% 44% 46% 51%
overall costs
Revenue as % of
10.0% 9.8% 9.2% 8.8%
capital costs
Increase in capital cost
- £12,448 £24,408 £33,774
from cheapest option
expressed as % - 29.9% 45.2% 51.2%
Increase in revenue
compared to cheapest - £1,157 £1,927 £2,477
option
expressed as % - 27.8% 46.3% 59.5%

9
Designed and constructed by NewMills Hydro, Carrickfergus, N.I. Cost and size of scheme provided by
Managing Director of New Mills Terry MacGuire during phone conversation on Fri 27th Nov.

Nick Jeffries, REBE Module 3 Hydro 21 | P a g e


7.3 Errors
Flow
Annual energy output is sensitive to small changes in the variables used to calculate
it and also in the way the data is presented. This is illustrated when comparing the
effect of using flow data from Low Flow model compared to Hydra model when
calculating energy. Both sets of data are presented as a series of stepped
increments (see Appendix A2), the difference being that more steps have been
included in the Hydra data set.

For each data set a different optimum flow and overall energy output is returned:

Hydra Low Flow Difference 


Optimum Flow  0.140 0.132 6.1% 
Annual Energy Output(kWh)  31522 30622 2.9% 

Fig 4 presents this graphically:

Figure 4 – Energy Output v Flow from Hydra and Low Flow Data

Comparison of Energy Output v Flow for Hydra and Low Flow


35000
Annual Energy (kWh)

30000

25000

400mm
20000

15000

10000
250mm

5000

0
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4
Flow (cumecs)
400mm 250mm 400mm Hydra 250mm Hydra

This result is more surprising if one considers the overall volume discharged from the
Hydra model is 0.11% less than the Low Flow model i.e. less potential energy is

Nick Jeffries, REBE Module 3 Hydro 22 | P a g e


generated. The issue highlights the need for accurate flow monitoring during the
project development period.

Pipe Length
The pipe length was estimated using a distance measuring wheel along the
proposed penstock route which is steep, forested and difficult to access.

Pipe costs are significant in the overall costing of the project (250mm - £70/m;
400mm - £180/m), so establishing accurately the length of pipe will be an important
part of the next design stage.

7.3 How payback period may be reduced


The cost/revenue figures presented in section 7.2 are quite cautious; there are
several ways in which the situation could be improved:

• Pipe costs based on information available at this time. Cheaper pipes may be
available.
• As land is private with no vehicle loading, penstock pipe could be laid partly
above ground thereby reducing excavation/backfilling costs.
• If plant and labour is available Client can potentially undertake following
works (with supervision): intake works, installation of penstock pipe,
construction of powerhouse and tailrace
• Calculations include 4% downtime for maintenance i.e. 15 days. If
maintenance is carried out in low flow period this will have only small effect
on energy output.
• Limit output to ~3.7kW (Single phase) and ~11 kW (3 phase) i.e. less than
16A/phase, thereby avoid potential grid connection cost issues.
• Specification of inductor generator over synchronous generator – will be
cheaper and will not require expensive grid tie inverter
• Use of recycled materials or materials from other CAT sites
• Use students and volunteers from nearby CAT to design, install and
supervise works.

Nick Jeffries, REBE Module 3 Hydro 23 | P a g e


8. CONCLUSIONS
The site has several characteristics that point favourably to the development of a
micro-hydro scheme:

• Site owned by Client


• Easy access for construction
• Proximity to grid connection
• Likely low ecological concerns
• Reasonable head difference with constant flow.
• Solid bedrock allows for good foundation for Civils works.

The situation is further enhanced by the expected introduction of the feed-in


tariffs in April 2010 which will create an even more economically sound case for
developing the project.

The estimate of potential revenue from electricity sales against estimated costs
for four different systems suggests a payback period of 12.5 – 14 years for an
investment between £40,000 - 80, 0000. This does not include an allowance for
discount rates.

9. RECOMMENDATIONS
In order to develop the scheme further the following actions are recommended:

• Start collecting accurate flow data. If a measuring weir is used, this can
be incorporated into final design of intake works
• Determine size of investment available
• Think clearly how you would like energy to be used in the future – if
eventually energy is to be used on site this will effect the final design
• Contact Environmental Agency to establish any potential ecological
constraints
• Contact DNO to advise of plans
• Contact Forestry Commission

Nick Jeffries, REBE Module 3 Hydro 24 | P a g e


Bibliography

1. British Hydro Association (BHA), A Guide to UK Mini-Hydro Developments


Version 1.2, Jan 2005.

2. T.Kirk (1999), Small Scale hydro-power in UK. CIWEM, Water and


Environmental Journal. Vol 13. Issue 3. Pages 207 – 212.

3. DTI, 1999 - New and Renewable Energy: Prospects in the UK for the 21st
Century: Supporting Analysis, - http://www.berr.gov.uk/files/file21102.pdf

4. Boyle, G (2004) – Renewable Energy – Power for a Sustainable Future. Second


Edition. Oxford Press.

Nick Jeffries, REBE Module 3 Hydro 25 | P a g e


Appendix A – Topographical and Hydrological Survey Data

A1 -Levels
UP SURVEY  DOWN SURVEY 
Forward  Back  Height  Forward  Back  Height 
3.98  0.1825  3.7975  2.91  0.31  2.6 
3.8375  0.1375  3.7  3.51  0.325  3.185 
3.702  0.375  3.327  1.2325  3.842  ‐2.6095 
3.925  0.55  3.375  0.0325  3.98  ‐3.9475 
3.315  1.415  1.9  0.0325  3.918  ‐3.8855 
0.125  3.715  ‐3.59  0.17  2.8275  ‐2.6575 
0.735  2.91  ‐2.175  1.26  2.77  ‐1.51 
1.328  2.814  ‐1.486 
TOTAL  10.3345  10.311 

A2 - Low Flow and Hydra Stream Data

Low Flow     Hydra 

 %   % 
Flow m3/s  Volume m3  Flow m3/s  Volume m3 
Exceedance  Exceedance 
‐  ‐     2.0%  0.8  504576 
‐  ‐  3.0%  0.7  220752 
5%  0.666  1050149  5.0%  0.58  365818 
10%  0.466  734789  10.1%  0.41  659418 
‐  ‐     15.0%  0.33  509937 
20%  0.287  905083  20.0%  0.26  409968 
30%  0.202  637027  29.1%  0.2  573955 
40%  0.149  469886  39.7%  0.15  501422 
50%  0.114  359510  50.0%  0.11  357303 
60%  0.087  274363  60.3%  0.09  292339 
70%  0.065  204984  70.9%  0.07  233997 
80%  0.045  141912  80.0%  0.05  143489 
90%  0.03  94608  89.9%  0.03  93662 
95%  0.023  36266  95.0%  0.02  32167 
‐  ‐     97.0%  0.02  12614 
‐  ‐     98.0%  0.02  6307 
99%  0.014  17660  99.0%  0.01  3154 
   Total  4926239     Total 4920877 
Difference  ‐0.11% 

Nick Jeffries, REBE Module 3 Hydro 26 | P a g e


Appendix B – Typical Run-of the River Arrangements

Nick Jeffries, REBE Module 3 Hydro 27 | P a g e


Appendix C – Detailed Spreadsheets

Nick Jeffries, REBE Module 3 Hydro 28 | P a g e


Energy Output Estimation, 350mm, 75% Qmean

Catchment area 3.199 sq.km Design Turbine Flow 0.149 cumecs


Annual mean Flow 0.198 cumecs Min turbine flow (% of max flow) 10%
Pipe diameter 350 mm Min. turbine flow 0.015 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 1.85 m
Net head (m) 8.26 m

0.75 x Qmean
Flow ‐ Q95  50% above  Turbine Flow   Compensation  Power Output  Power output 
 % Exceedance Flow m3/s (m3/sec) Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.149 0.518 9.3 4082


10% 0.466 0.443 0.222 0.149 0.318 9.3 4082
20% 0.287 0.264 0.132 0.132 0.155 7.4 6479
30% 0.202 0.179 0.090 0.090 0.113 5.0 4393
40% 0.149 0.126 0.063 0.063 0.086 3.5 3092
50% 0.114 0.091 0.046 0.046 0.069 2.5 2233
60% 0.087 0.064 0.032 0.032 0.055 1.8 1571
70% 0.065 0.042 0.021 0.021 0.044 1.2 1031
80% 0.045 0.022 0.011 0.000 0.045 0.0 0
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 26962 kWh/yr


Breakdown/maintenance (‐4%) 25884 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £5,953
Efficiency  max partial flow
Turbine 84% 75%
Gear Box 97%
Generator 95%
Energy Output Estimation, 300mm, 50% Qmean

Catchment area 3.199 sq.km Design Turbine Flow 0.099 cumecs


Annual mean Flow 0.198 cumecs Min turbine flow (% of max flow) 10%
Pipe diameter 300 mm Min. turbine flow 0.010 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 1.88 m
Net head (m) 8.23 m

0.5 x Qmean
Flow ‐ Q95  Turbine Flow   Compensation  Power Output  Power output 
 % Exceedance Flow m3/s (m3/sec) 50% above Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.099 0.567 6.2 2710


10% 0.466 0.443 0.222 0.099 0.367 6.2 2710
20% 0.287 0.264 0.132 0.099 0.188 6.2 5420
30% 0.202 0.179 0.090 0.090 0.113 5.0 4375
40% 0.149 0.126 0.063 0.063 0.086 3.5 3080
50% 0.114 0.091 0.046 0.046 0.069 2.5 2224
60% 0.087 0.064 0.032 0.032 0.055 1.8 1564
70% 0.065 0.042 0.021 0.021 0.044 1.2 1027
80% 0.045 0.022 0.011 0.011 0.034 0.6 538
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 23647 kWh/yr


Breakdown/maintenance (‐4%) 22702 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £5,221
Efficiency  max partial flow
Turbine 84% 75%
Gear Box 97%
Generator 95%
Energy Output Estimation, 250mm, 33% Qmean

Catchment area 3.199 sq.km Design Turbine Flow 0.065 cumecs


Annual mean Flow 0.198 mm Min turbine flow (% of max flow) 10%
Pipe diameter 250 mm Min. turbine flow 0.007 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 2.13 m
Net head (m) 7.96 m

0.5 x Qmean
Flow ‐ Q95  Turbine Flow   Compensation  Power Output  Power output 
 % Exceedance Flow m3/s (m3/sec) 50% above Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.065 0.601 3.9 1720


10% 0.466 0.443 0.222 0.065 0.401 3.9 1720
20% 0.287 0.264 0.132 0.065 0.222 3.9 3440
30% 0.202 0.179 0.090 0.065 0.137 3.9 3440
40% 0.149 0.126 0.063 0.063 0.086 3.4 2977
50% 0.114 0.091 0.046 0.046 0.069 2.5 2150
60% 0.087 0.064 0.032 0.032 0.055 1.7 1512
70% 0.065 0.042 0.021 0.021 0.044 1.1 992
80% 0.045 0.022 0.011 0.011 0.034 0.6 520
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 18471 kWh/yr


Breakdown/maintenance (‐4%) 17732 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £4,078
Efficiency  max partial flow
Turbine 84% 75%
Generator 95%
Grid tie inverter  97%
Energy Output Estimation, 400mm, Qmean

Catchment area 3.199 sq.km Design Turbine Flow 0.198 cumecs


Annual mean Flow 0.198 cumecs Min turbine flow (% of max flow) 10%
Pipe diameter 400 mm Min. turbine flow 0.020 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 1.63 m
Net head (m) 8.51 m

Q mean
Flow ‐ Q95  50% above  Turbine Flow   Compensation  Power Output  Power output 
 % Exceedance Flow m3/s
(m3/sec) Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.198 0.468 12.8 5603


10% 0.466 0.443 0.222 0.198 0.268 12.8 5603
20% 0.287 0.264 0.132 0.132 0.155 7.6 6670
30% 0.202 0.179 0.090 0.090 0.113 5.2 4523
40% 0.149 0.126 0.063 0.063 0.086 3.6 3184
50% 0.114 0.091 0.046 0.046 0.069 2.6 2299
60% 0.087 0.064 0.032 0.032 0.055 1.8 1617
70% 0.065 0.042 0.021 0.021 0.044 1.2 1061
80% 0.045 0.022 0.011 0.000 0.045 0.0 0
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 30560 kWh/yr


Q95 (m3/sec) 0.023 Breakdown/maintenance (‐4%) 29338 kWh/yr
Qmean (m3/sec) 0.198 Price/kWh £0.06
Feed in tariff £0.17
Efficiency  max partial flow Average Gross £6,748
Turbine 84% 75%
Gear Box 97%
Generator 95%
Energy Output Estimation, 350mm Optimum

Catchment area 3.199 sq.km Design Turbine Flow 0.132 cumecs


Annual mean Flow 0.198 cumecs Min turbine flow (% of max flow) 10%
Pipe diameter 350 mm Min. turbine flow 0.013 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 1.50 m
Net head (m) 8.65 m

Q mean

Flow ‐ Q95  50% above  Turbine Flow   Compensation  Power Output  Power output 


 % Exceedance Flow m3/s (m3/sec) Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.132 0.534 8.7 3798


10% 0.466 0.443 0.222 0.132 0.334 8.7 3798
20% 0.287 0.264 0.132 0.132 0.155 8.7 7595
30% 0.202 0.179 0.090 0.090 0.113 5.2 4598
40% 0.149 0.126 0.063 0.063 0.086 3.7 3237
50% 0.114 0.091 0.046 0.046 0.069 2.7 2338
60% 0.087 0.064 0.032 0.032 0.055 1.9 1644
70% 0.065 0.042 0.021 0.021 0.044 1.2 1079
80% 0.045 0.022 0.011 0.000 0.045 0.0 0
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 28086 kWh/yr


Breakdown/maintenance (‐4%) 26963 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £6,201
Efficiency  max partial flow
Turbine 84% 75%
Gear Box 97%
Generator 95%
Energy Output Estimation, 300mm Optimum

Catchment area 3.199 sq.km Design Turbine Flow 0.090 cumecs


Annual mean Flow 0.198 cumecs Min turbine flow (% of max flow) 10%
Pipe diameter 300 mm Min. turbine flow 0.009 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 1.59 m
Net head (m) 8.55 m

Q mean

Flow ‐ Q95  50% above  Turbine Flow   Compensation  Power Output  Power output 


 % Exceedance Flow m3/s (m3/sec) Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.090 0.576 5.8 2561


10% 0.466 0.443 0.222 0.090 0.376 5.8 2561
20% 0.287 0.264 0.132 0.090 0.197 5.8 5121
30% 0.202 0.179 0.090 0.090 0.113 5.2 4547
40% 0.149 0.126 0.063 0.063 0.086 3.7 3201
50% 0.114 0.091 0.046 0.046 0.069 2.6 2312
60% 0.087 0.064 0.032 0.032 0.055 1.9 1626
70% 0.065 0.042 0.021 0.021 0.044 1.2 1067
80% 0.045 0.022 0.011 0.011 0.034 0.6 559
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 23554 kWh/yr


Breakdown/maintenance (‐4%) 22612 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £5,201
Efficiency  max partial flow
Turbine 84% 75%
Gear Box 97%
Generator 95%
Energy Output Estimation,  250mm Optimum

Catchment area 3.199 sq.km Design Turbine Flow 0.063 cumecs


Annual mean Flow 0.198 mm Min turbine flow (% of max flow) 10%
Pipe diameter 250 mm Min. turbine flow 0.006 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 2.02 m
Net head (m) 8.08 m

0.5 x Qmean
Flow ‐ Q95  Turbine Flow   Compensation  Power Output  Power output 
 % Exceedance Flow m3/s (m3/sec) 50% above Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.063 0.603 3.9 1694


10% 0.466 0.443 0.222 0.063 0.403 3.9 1694
20% 0.287 0.264 0.132 0.063 0.224 3.9 3387
30% 0.202 0.179 0.090 0.063 0.139 3.9 3387
40% 0.149 0.126 0.063 0.063 0.086 3.9 3387
50% 0.114 0.091 0.046 0.046 0.069 2.5 2184
60% 0.087 0.064 0.032 0.032 0.055 1.8 1536
70% 0.065 0.042 0.021 0.021 0.044 1.2 1008
80% 0.045 0.022 0.011 0.011 0.034 0.6 528
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 18807 kWh/yr


Breakdown/maintenance (‐4%) 18055 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £4,153
Efficiency  max partial flow
Turbine 84% 75%
Generator 95%
Grid tie inverter  97%
Energy Output Estimation, 400mm Optimum

Catchment area 3.199 sq.km Design Turbine Flow 0.132 cumecs


Annual mean Flow 0.198 cumecs Min turbine flow (% of max flow) 10%
Pipe diameter 400 mm Min. turbine flow 0.013 cumecs
Pipe length (m) 215 m
Static Head (m) 10.3 m
Head Loss(Pipes/Fittings) 0.79 m
Net head (m) 9.43 m

Q mean

Flow ‐ Q95  50% above  Turbine Flow   Compensation  Power Output  Power output 


 % Exceedance Flow m3/s (m3/sec) Q95 (cumecs) Flow (cumecs) (kW) (kWh)

5% 0.666 0.643 0.322 0.132 0.534 9.5 4141


10% 0.466 0.443 0.222 0.132 0.334 9.5 4141
20% 0.287 0.264 0.132 0.132 0.155 9.5 8281
30% 0.202 0.179 0.090 0.090 0.113 5.7 5013
40% 0.149 0.126 0.063 0.063 0.086 4.0 3529
50% 0.114 0.091 0.046 0.046 0.069 2.9 2549
60% 0.087 0.064 0.032 0.032 0.055 2.0 1792
70% 0.065 0.042 0.021 0.021 0.044 1.3 1176
80% 0.045 0.022 0.011 0.000 0.045 0.0 0
90% 0.03 0.007 0.004 0.000 0.030 0.0 0
95% 0.023 0.000 0.000 0.000 0.023 0.0 0
99% 0.014 0.000 0.000 0.000 0.014 0.0 0

TOTAL 30622 kWh/yr


Breakdown/maintenance (‐4%) 29397 kWh/yr
Q95 (m3/sec) 0.023 Price/kWh £0.06
Qmean (m3/sec) 0.198 Feed in tariff £0.17
Average Gross £6,761
Efficiency  max partial flow
Turbine 84% 75%
Gear Box 97%
Generator 95%
Appendix E – Performance Envelopes for Different Turbine Types

Figure 3 – Performance envelope for different turbines

Source: DBERR Report 2004 and BHA 2008

Nick Jeffries, REBE Module 3 Hydro 30 | P a g e


Appendix F – Efficiencies of turbines at partial flows

Source: Kirk, 1999

Table of partial flow efficiencies - derived from above graph

Qmax/Qo Francis Crossflow


100% 90% 80%
90% 90% 82%
80% 90% 83%
70% 89% 85%
60% 86% 85%
50% 84% 854%
40% 80% 84%
30% 73% 80%
20% 62% 70%
18% 0% 65%
10% 0% 30%

Nick Jeffries, REBE Module 3 Hydro 31 | P a g e


Appendix G – Performance of Cross Flow Turbines at partial flow

Source: http://www.ossberger.de/cms/en/hydro/the-ossberger-turbine/

Nick Jeffries, REBE Module 3 Hydro 32 | P a g e

Вам также может понравиться