RE: Rain issues at Mastlands, Larry Lane, and Ascot Dr.
Wednesday, May 23, 2012 8:47:13 AM
Craig, could you give Dave a briefing on the notices you have sent.
-----Original Message----From: Ferguson, David
Sent: Wednesday, May 23, 2012 7:54 AM
To: Kashi, Kevin
Subject: RE: Rain issues at Mastlands, Larry Lane, and Ascot Dr.
Kevin,
When were the notices mailed to the property owners?
-----Original Message----From: Kashi, Kevin
Sent: Tuesday, May 22, 2012 5:07 PM
To: Ferguson, David
Cc: Estes, Lesley; Lonestar, David; Pon, Craig; Smith, Lorenzo; Lonestar, David; Amirzehni, Gus
Subject: RE: Rain issues at Mastlands, Larry Lane, and Ascot Dr.
David; per our conversation . Here is a draft of an email to Mr. Denmead.
................................................................
The Creek/roadway restoration near the large driveway close to 62 Larry lane will be addressed by a City contractor
in August (item No.5). Staff has been working with permitting agencies and consultants to facilitate this repair
work. We will have the work completed before the rainy season.
Bird cage. We do not have any record showing the City owns the bird cage or the watercourse surrounding it. The
entire facility is outside of the City's right of way and staff has been cleaning the bird cage as service to the
constituents. Also, notices were mailed to the property owners to attend to this private facility.
If there are other concerns or issues, please contact the City's call center first at 615-5566 and contact me for followup.
................................................................
The Roadway/Creek restoration near the wide driveway (item No. 5) on Larry Lane is up for repair in August when
the water level is supposed to be at its lowest. We have the permits that we need and our contractor is ready to
start.
Walter B. Denmead
wdenmead@aol.com
Tel: 530-4347