The phases

Sanction

Basic Engineering
By ENGINEERING

Project Execution
by EPC CONTRACTOR

2013 Herv Baron

Conceptual evaluation
+ Pre-Project
By COMPANY

Sanction

HERVE
BARON
Design

Installation

Procurement

Manufacturing

Construction
& erection

Inspection &
tests

Shipping

Hand-over

2013 Herv Baron

HERVE
BARON

The multiple sides of a Project

Project Control

PROJECT

2013 Herv Baron

Human Resources Management

HERVE
BARON

The multiple sites of a Project


Home office (Paris)
Project management
Detail Engineering (part)
Procurement

Engineering Sub-Contractor
(India)
Detail Engineering (part)

Shipyard (Korea)
Hull Engineering & Fabrication

Satellite office
Detail Engineering (part)

Fabrication yard (Nigeria):


Fabrication (part)

Installation, commissioning, start-up

Shipyards (Singapore &


Malaysia)
Topsides Fabrication & Integration

2013 Herv Baron

Offshore (Nigeria):

HERVE
BARON

Project

Engineering

Procurement

Construction

2013 Herv Baron

HERVE
BARON

Project

Engineering

Procurement

Construction

2013 Herv Baron

HERVE
BARON

The facilities design basis


Infrastructure:

Feedstock and products flow


Feedstock composition
Battery limit conditions
Equipment Spare

Pressure (bar)

Process facilities:
50

Administrative and technical


buildings

45
40

Control room

35

Access road

30

Site fencing, gates, check point

25
20

Performance:

15

Products specifications

10

Energy efficiency, emissions

Design criteria:
% of over design

5
0
-85

Utilities:
Electric power supply
Other utilities

-80

-75

-70

-65

-60

-55

Environment data:
Min/max temperature
Rain/snow fall
Wind
Geological conditions

Process control
Fire/gas alarm
Public address, LAN, PABX

Applicable codes and standards:


International standards
Local rules

2013 Herv Baron

Systems:

HERVE
BARON

Engineering
in the Project

Design basis:

Documents for Construction:

- Functional
requirements

Construction drawings &


specifications

- Client
specifications

Engineering

Documents for Purchase:


bill of quantity & specification

- Design codes
2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

Process simulations

2013 Herv Baron

HERVE
BARON

Thermodynamic
calculations

2013 Herv Baron

Process Flow
Diagram (PFD)

Heat & Material


balance

HERVE
BARON

Equipment list

2013 Herv Baron

HERVE
BARON

Equipment
duty

2013 Herv Baron

HERVE
BARON

Process data sheet

2013 Herv Baron

HERVE
BARON

Process Flow Diagram (PFD)

2013 Herv Baron

HERVE
BARON

Piping & Instrumentation Diagram (P&ID)

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

Piping &
Instrumentation
Diagram (P&ID)

HERVE
BARON

Process control

2013 Herv Baron

HERVE
BARON

Emergency shut down

2013 Herv Baron

HERVE
BARON

Emergency relief

2013 Herv Baron

HERVE
BARON

Operating manual

2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

Rotating machinery

2013 Herv Baron

HERVE
BARON

Pressure vessels

2013 Herv Baron

HERVE
BARON

Heat exchangers

2013 Herv Baron

HERVE
BARON

Packages,
Fired Equipment

2013 Herv Baron

HERVE
BARON

Process data
sheet
Mechanical
data sheet

2013 Herv Baron

HERVE
BARON

Material Requisition

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Fire fighting

2013 Herv Baron

HERVE
BARON

Passive fire protection

2013 Herv Baron

HERVE
BARON

Fire & Gas detection layout

2013 Herv Baron

HERVE
BARON

Environmental Impact Assessment

2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

Equipment supporting
structures

HERVE
BARON

2013 Herv Baron

Piping supporting
structures (pipe-racks)

HERVE
BARON

2013 Herv Baron

Structural design

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

Structural
drawings

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Architectural drawings

2013 Herv Baron

Equipment layout
drawing

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Layout/
principles

2013 Herv Baron

HERVE
BARON

Layout/consideration for all networks

2013 Herv Baron

HERVE
BARON

General Plot Plan

2013 Herv Baron

HERVE
BARON

Piping Layout
drawing
2013 Herv Baron

HERVE
BARON

3D modelling

2013 Herv Baron

HERVE
BARON

3D model clash check

3D model review
2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Piping Design

ANSI B31.8 (for gas pipelines and


compressor stations)

2013 Herv Baron

HERVE
BARON

Piping Design

ANSI B31.8 (for gas pipelines and


compressor stations)

2013 Herv Baron

HERVE
BARON

Thickness (mm) Number of passes

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Isometric drawing

2013 Herv Baron

HERVE
Piping
BARON

Pre-fabrication

2013 Herv Baron

HERVE
BARON

Piping General
Arrangement drawing

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Standard Pipe Support


drawings

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Material Selection

2013 Herv Baron

HERVE
BARON

Material Specification

2013 Herv Baron

HERVE
BARON

Material Specification

2013 Herv Baron

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Instrument data sheet

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

Process Control System

HERVE
BARON

System architecture
drawing

2013 Herv Baron

HERVE
BARON

Mechanical Equipment Control

2013 Herv Baron

The instrumentation hardware

HERVE
BARON

Instrument room
Marshalling

Controller

cabinet

cabinet

Control room

VDU

PT

JB

Process
line

CPU

LAN
Secondary cable
Multi cable

2013 Herv Baron

HERVE
BARON

Telecom and PAGA layout

2013 Herv Baron

Building detail drawing/

HERVE
BARON

Cable routing drawings

2013 Herv Baron

Cable list

HERVE
BARON

2013 Herv Baron

Cable routing inside


technical room

HERVE
BARON

Project

Instruments&
Control

Layout
& Piping

Process

Engineering

Procurement

Construction

Electrical

Equipment

Civil

Safety

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

Electrical consumer list

HERVE
BARON

Electrical Load
Summary
2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

General One
Line Diagram

2013 Herv Baron

HERVE
BARON
Generators

Single line diagram

Switchgear

Transformer

2013 Herv Baron

HERVE
BARON

Electrical equipment layout

2013 Herv Baron

HERVE
BARON

Electrical
Control System

2013 Herv Baron

HERVE
BARON

Process design
PFDs
H&M balance

2013 Herv Baron

HERVE
BARON

Process design
PFDs
H&M balance

Process
data sheet

Equipment specification

2013 Herv Baron

Rotating
Pressure vessels
Fired equipment
Heat exchangers
Packages etc.

HERVE
BARON

Process design
PFDs

P&IDs

H&M balance

2013 Herv Baron

HERVE
BARON

Process design
PFDs

P&IDs

H&M balance

Piping
Instrumentation

Process
data sheet

Equipment specification
Vendor
drawings

Layout
Civil
Electrical

2013 Herv Baron

Rotating
Pressure vessels
Fired equipment
Heat exchangers
Packages etc.

HERVE
BARON

Process design
PFDs

P&IDs

H&M balance

Piping
Instrumentation

Process
data sheet

Equipment specification
Vendor
drawings

Layout
Civil
Electrical

2013 Herv Baron

Rotating
Pressure vessels
Fired equipment
Heat exchangers
Packages etc.

HERVE
BARON

Electrical

Layout

Vendor
Piping

Instrumentation &
Control
Process

Civil

2013 Herv Baron

HERVE
BARON

What the
Vendor
supplied

What
Engineering
designed

2013 Herv Baron

HERVE
BARON

Field Engineering

2013 Herv Baron

HERVE
BARON

For more information and


to get on top of Engineering in hours, not years!
A unique synthesis and
reference manual
200 pages, 250 illustrations

To browse the book:


http://goo.gl/dfDrS

To order with a 30% discount:


http://goo.gl/J3TkE

HERVE
BARON

Project

Engineering

Procurement

Construction

2013 Herv Baron

HERVE
BARON

Procurement

2013 Herv Baron

HERVE
BARON

Procurement / Steps

Inquiry (Call for Tender)


Short listing
Bid analysis
Clarifications
Negotiations
Purchase Order
Expediting
Inspection

Warranty Period

2013 Herv Baron

Delivery

HERVE
BARON

Procurement / Supplier selection criteria


Technical Compliance
Price
Qualification of supplier
Schedule
Load of workshop
References
References with final Client
Financial situation

Internal feed-back

2013 Herv Baron

Annual turn-over

HERVE
BARON

Procurement

2013 Herv Baron

HERVE
BARON

Expediting

2013 Herv Baron

HERVE
BARON

Expediting

2013 Herv Baron

HERVE
BARON

Inspection

2013 Herv Baron

HERVE
BARON

Inspection

2013 Herv Baron

Shipping
HERVE
BARON

2013 Herv Baron

Shipping
HERVE
BARON

2013 Herv Baron

Shipping
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Project

Engineering

Procurement

Construction

2013 Herv Baron

HERVE
BARON

Earthworks

2013 Herv Baron

Pipeline
HERVE
BARON

2013 Herv Baron

Pipeline
HERVE
BARON

2013 Herv Baron

Roads
HERVE
BARON

2013 Herv Baron

Buildings
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Civil Works

Sand
Aggregate

Cement
Admixtures
2013 Herv Baron

HERVE
BARON

Civil Works

2013 Herv Baron

HERVE
BARON

Civil Works

2013 Herv Baron

HERVE
BARON

Civil Works

2013 Herv Baron

HERVE
BARON

Civil Works

2013 Herv Baron

HERVE
BARON

Civil Works

2013 Herv Baron

HERVE
BARON

Pre-fabrication

2013 Herv Baron

Erection
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Underground networks

2013 Herv Baron

HERVE
BARON

Plant erection

2013 Herv Baron

HERVE
BARON

Steel structure erection

2013 Herv Baron

HERVE
BARON

Equipment installation

2013 Herv Baron

HERVE
BARON

Equipment installation

2013 Herv Baron

HERVE
BARON

Piping Pre-fabrication

2013 Herv Baron

HERVE
BARON

Piping erection

2013 Herv Baron

HERVE
BARON

Piping erection

2013 Herv Baron

HERVE
BARON

Field Instrumentation Installation

2013 Herv Baron

HERVE
BARON

Electrical equipment connection

2013 Herv Baron

HERVE
BARON

Cable pulling

2013 Herv Baron

HERVE
BARON

Arrangement of Technical rooms

2013 Herv Baron

HERVE
BARON

Cable connections

2013 Herv Baron

HERVE
BARON

Other Systems Field Equipment Installation

2013 Herv Baron

HERVE
BARON

Control room consoles installation

2013 Herv Baron

Testing
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Commissioning
Handover System

Sub-System
Document Folder

Circuit

Elect Equip

Mech Equip
Instrument
Loop

Instrument
Cable

Instrument
Tag

2013 Herv Baron

Junction
Box

HERVE
BARON

The multiple sides of a Project

Project Control

PROJECT

2013 Herv Baron

Human Resources Management

HERVE
BARON

Project Organisation

Project
Manager

Engineering
Manager

Project
Engineers

Procurement
Manager

Discipline
Engineers

Process

Civil

Instrumentation

Electrical

Expediters

Inspectors

Construction
Manager

Contract
Manager

Scheduling
Manager

Cost Control

Construction
Superintendent

Construction
supervisor

Construction
superintendent

Construction
supervisor
2013 Herv Baron

Equipment

Purchasers

Project Control
Manager

Site Manager

HERVE
BARON

Project procedures

2013 Herv Baron

HERVE
BARON

Project temporary facilities

2013 Herv Baron

HERVE
BARON

Project temporary facilities

2013 Herv Baron

HERVE
BARON

Project temporary facilities

2013 Herv Baron

HERVE
BARON

Project temporary facilities

2013 Herv Baron

HERVE
BARON

Project temporary facilities

2013 Herv Baron

HERVE
BARON

Construction Procedures

2013 Herv Baron

HERVE
BARON

2013 Herv Baron

HERVE
BARON

Quality Control

2013 Herv Baron

HERVE
BARON

Quality Control

Temperature

Sampling
Slump
2013 Herv Baron

HERVE
BARON

Quality Control

2013 Herv Baron

HERVE
BARON

Cost Control

2013 Herv Baron

Insurance
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Contracts

P.O.
P.O.
Purchase
Orders

P.O.

EPC
Sub-Contracts
Main Contract

Sub

2013 Herv Baron

Sub

HERVE
BARON

Contracts
Terms and
Conditions
Price
Schedule

EPC

Main Contract

Performance
guarantees
Technical
basis
Specifications,
codes & stds
2013 Herv Baron

HERVE
BARON

Contracts

E
2013 Herv Baron

HERVE
BARON

Contracts

E P
2013 Herv Baron

HERVE
BARON

Contracts

E P C
2013 Herv Baron

HERVE
BARON

Contracts

2013 Herv Baron

+ x%

HERVE
BARON

Construction contracts

Civil

2013 Herv Baron

HERVE
BARON

Construction contracts

Mechanical

2013 Herv Baron

HERVE
BARON

Construction contracts

E&I

2013 Herv Baron

HERVE
BARON

Construction contracts

General
Contractor
2013 Herv Baron

HERVE
BARON

Contracts
Terms and Conditions

EPC

Main Contract

Obligations of the 2 parties

Penalties in case of bad performance


Conflict resolution

2013 Herv Baron

Limit of liability

HERVE
BARON

Quality Assurance (QA)

2013 Herv Baron

HERVE
BARON

Quality Assurance (QA)

2013 Herv Baron

HERVE
BARON

Quality Assurance (QA)

2013 Herv Baron

HERVE
BARON

Quality Assurance (QA)

2013 Herv Baron

HERVE
BARON

Document Control
Document code
1

Installation drawings

Detail drawings

Diagrams

Lists Bill of Quantities

Isometrics

Calculation notes

Specifications

Data sheets

Requisitions
Discipline code
Instrumentation & Control

Civil engineering

Electrical

Project general documents

Mechanical

Safety

Piping & Layout

Processes

Steel Structures

Vessels Heat exchangers

Materials Welding

2013 Herv Baron

HERVE
BARON

Document Control

2013 Herv Baron

HERVE
BARON

Document Control
Client
Documents
submitted
to client

Approval/
Comments

Engineering

Comments

Vendors

2013 Herv Baron

Documents
submission

HERVE
BARON

Electronic Document Management System

Center 1 Sr.
Mgmt

Intranet /
Internet

Center 2 Sr.
Mgmt

Correspondence
etc.

Electronic Document
Management System
Projects

Breakdown
structures

Engineering
documents

Reports
Interfaces

Satellite
Engineering
Center

Vendor
documents
Construction
Site

2013 Herv Baron

Intranet /
Internet

HERVE
BARON

Interface Management

2013 Herv Baron

HERVE
BARON

Scheduling

MONTH
7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
PROJECT SCHEDULE
PLANT START-UP
PIPING PRE-FABRICATION & INSTALLATION
X X X X X X X X X X
PIPING MATERIAL & DRAWINGS AT SITE
PIPING MATERIAL MANUFACTURING & SHIPPING
X X X X X X
PURCHASE OF PIPING MATERIAL
TECHNICAL & COMMERCIAL CLARIFICATIONS
X X
CALL FOR TENDER FOR PIPING MATERIAL
PREPARE PIPING MATERIAL TAKE-OFF
X
PIPING ROUTING STUDIES
X X X
PIPING & INSTRUMENTATION DIAGRAMS (PIDs)

2 3

2
2013 Herv Baron

HERVE
BARON

Scheduling

2013 Herv Baron

HERVE
BARON

Progress Monitoring
How would you measure
progress?

2013 Herv Baron

HERVE
BARON

Progress Monitoring

2013 Herv Baron

HERVE
BARON

Progress Monitoring

2013 Herv Baron

HERVE
BARON

Progress Monitoring

2013 Herv Baron

HERVE
BARON

IT

Today: 3D

15 years ago: 2D

Tomorrow:
3D & data

2013 Herv Baron

IT
HERVE
BARON

2013 Herv Baron

Safety
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Safety

Guard Rail System with Toe


Boards

Planking

Runner

Bearer

Post

Cross Bracing

Longitudinal Brace

2013 Herv Baron

Sill

Safety
HERVE
BARON

2013 Herv Baron

HERVE
BARON

Human resources / career path


Graduate Engineer, 25 years old

Process Engineer

Project Engineer

Engineering Manager/
Deputy Project Manager

Project Manager

3-5 yrs

5 yrs

5-7 yrs

40-45 yrs old


2013 Herv Baron

Note: the career pattern shown here is a very fast track one to the PM
position... One would enjoy oneself just as well taking more time!

HERVE
BARON

Beyond this presentation


Share my new developments
Find my other on-line and classroom training

http://www.toblog.fr/en/baron.html

2013 Herv Baron

Вам также может понравиться