Tsunami Reconstruction Project, A&N Administration

CHALLENGES OF CONSTRUCTION in A&N ISLANDS

>

Islands arc scattered over 550 lems

>

Distance from main land - 1 200 kms

>

All construction material require


transportation from Main land

>

Jetties at Chowra, Tcrrcssa, Katchal &

Nancowry can not handle cargo ships.


23 out of 27 sites require transportation

through stevedoring

>

Stevedoring quite risky during rough


weather conditions.

>

Limited working season - 4-5 months

>

Sites scattered over large distances


without proper road connectivity

CONSTRUCTION OF PERMANENT SHELTERS IN A& N ISLANDS


STATUS REPORT (AS ON 31.08.2007)
The details of Island - wise & Agency-wise houses under construction in various Islands are as under:

CI'WI)

South Andaman

Little Andaman
Car Nicobar

5941

NGO

214

609*

82?

908

100

1973

Teressa

506

Katchal

315

Kamorta

518

Nancovvry

269

Chowra

$46

Little Nicobar

1 II

Great Nicobar

995

TOTAL

965

APWD

7966

506

518

269

346

3941

315

TOTAL

111

995

1122

709

9797

MATA have curtailed their commitment from 100 units to 50 units.

These 50 units have now been assigned to APWD (on 14.5.2007)


* NGO's arc constructing only 709 houses, asagainst there initial commitment of about 2500

COMMON FACILITIES AT PERMANENT HOUSES


In addition to water, electricity and sewerage networks, internal roads, following community buildings
are being simultaneously constructed asa part ol permanent housing project:

AREA OF EACH UNIT (sq.mtr.)

NUMBER

Primary School

200

20

Middle School

500

2500

PHC

150

23

Veterinary Dispensary

250

400/150

1/8

250

80/100

32/15

40

43

190/300

31/15

Recreation/ Youth Club

50/80

28/15

Neighbourhood Shopping

50/80

30/15

Police Station

300

F:irc Station

300

45

90

Higher / Senior Secondary School

Market

Adult Learning Centre


Birth 1louse
Death I louse
Community I lall

Qtrs. For Police, 1lealth Centre & School Staff

ISLAND WISE STATUS OF CONSTRUCTION OF PERMANENT HOUSES


AS ON 31.08.2007 IS AS UNDER:

1. SOUTH ANDAMAN
SUIHiR STKUCTURi: AT HAMBOOFI.AT

Following agencies are constructing 873 units in South Andaman as per details given below:

12lunits

CRS-CARITAS

HCC

1 52 units

Mata Amritanandamayi Math

50 units

CARL India

286 units

APWD

214 units

Foundation Work: The status of Foundation work is as follows:

Excavation

639

78%

Concrete Pedestal

615

75%

Grade Beams

573

70%

fixing of Nuts and Be )lts

522

65%

Target date for completion ol foundation at all sites is Dec. 2007.

Super Structure Work: The plan for erection of superstructure has been finalised by all
the NGO's. 'lenders for 164 units have been accepted by the CE, APWDand the tenders
are under process for award. Fabrication ol steel lor superstructure work ol NGO's is in

progress at Port Blair and Kolkata. Targetdate ofcompletion is April 2008. Progress ofthe
houses allocated to CARE has been extremely unsatisfactory, flic CARE representative
has committed to take urgent steps to improve the performance on theground.

Community Buildings:

Community Hall, Sub center and Primary schools are to be constructed as part of
permanent shelters, fenders lor the communilv buildings have been launched by APWD
and target date ofcompletion is April, 08.
Development Works:

Terrace development & formation of internal roads have been completed in all the sites.

Black Topping completed in 6 out ol 9 sites. For balance sites, work to be completed by
November'07. Work for culverts, retaining/ breast walls and drains are progressing in
a phased manner by engaging multiple agencies simultaneously. Work lor provision ol
Water Supply has been commenced at some of the sites. Work is likely to be completed

by October '07. Tenders for External Electrical works have been finalized and work has
commenced at Bamboo llat site. Work scheduled to be completed by December '07.

Target date ol completion ol developmental works is April 2008.


Sanitary System:

Eco-lriendly Sewerage Disposal System (SDS) with bio-gas as by-product is being

Month wise Roll Out Plan for South Andaman is at Annexure 'A'. The first batch of 54

implemented as part ofthe Project at all sites having more than 50 numbers ofunits.

houses will be ready lor allotment by end ol Oct. 2007.

Curtailment of number by NGO's:

NGO's had initially committed 2397 Nos. of houses which was subsequently curtailed to just 709 houses. The surrendered houses where cither reassigned to APWD & CPWD as per the
details given below:

INITIAL

PINAL

CRS-CARITAS

480

221

HCC

054

152

22.06.06/31.08.06

APWD

MATA AMRD'ANANDAMAYI MATH

100

50

14.05.07

APWD

CARE INDIA

954

286

12.09.06

APWD

CASA

672

nil

14.08.06

CPWD/APWD (100)

ISM & SALVATION ARMY

137

nil

22.06.06

APWD

2. LITTLE ANDAMAN

SUPERSTRUCTURE ERECTION AT ONGE TIKRY IN LITTLE ANDAMAN

1973 units arc under construction in Little Andaman by the following agencies:

CRS-CARITAS

100 units

APWD

908 units

CPWD

965 units

The work in three non-tribal sites has recommenced with elicit from 9.1.07, after having
been suspended temporarily due to unfortunate law and order incidents at Hut Bay.
Due to this, the completion has been delayed by 3 months. Work for 25 units at Netaji
N.igar site No.2 could be started only on 5.6.2007 due to landdispute.

Foundation Work: The status of Foundation work is as follows:

Excavation

173 3

88%

Concrete Pedestal

1704

86%

Grade Beams

1532

78%

Fixing of Nuts and Bolts

1244

63%

The work for foundations is in progress. Target date of completion of foundation


work is November, 2007.

Super Structure Work: The plan for erection ofSuperstructure has been Finalised by all
the Agencies. CPWD has completed the erection of 40 units at Onge Tikrv. Sheeting and

walling work is in progress. Fabrication of steel for superstructure work of CPWD and
APWD is also in progress. Target dale ol completion lor all the sites is May 2008.

Community Buildings: Community Hall, Health Sub center and Middle Schools are
coming upas a part ofthe project. Target dale ofcompletion isJuly 2008.
Development Work: Terrace development S; formation of internal roads is in progress.
Work of roads, culverts, retaining/ breast wall, and drains is in progress in a phased
manner bv engaging multiple agencies simultaneously lor speedy completion. Material
mobilization isin progress for ihe Phase wise works of Water Supply, Sewer lines. Septic
Tanks& External Electrical works. Target date of completion isJuly 2008.

Sanitary System: Eco-friendly Sewerage Disposal System (SDS) with bio-gas asby-product

is being implemented as part of the Project at all sites having more than 50 numbers of
units excepting Ilarmindar Bay.
Month wise Roll Out Plan for Little Andaman is at Annexure 'A'. The first batch of

50 houses will be ready for allotment bv end of Sept., 2007

Super Structure Work: The work of erection of 100 superstructure units is in progress

3. CAR NICOBAR

and the fabrication ol superstructure is also in progress at Vi/ag since November 2006.
3941 units arc under construction in this island by CPWD
Foundation Work:

The status of Foundation work is as follows:-

Target date of completion of shelter work is June, 08

Community Buildings: Fenders accepted lor all thevillages.. Iargel date of completion is
June 08.

%>

Excavation

3857

I)

Concrete Pedestal

3728

96%

Development Work: Tender lor Sewer lines and Septic Tanks for all villages finalized.

Grade Beams

3620

92%

Target date of completion is June 2008. Under ground cable laying is in progress and

Fixing of Nuts and Bolts

3583

91%

Material mobilization is in progress for Installation of Transformer and D. P. Structure S:

External Electrical distribution works. Target date ofcompletion isJune 2008.


The work for foundations is in progress at all the sites. Target date of completion of

Roll Out Plan for Car Nicobar is at Annexure 'A'. The lirst batch of 100 houses will be

foundation work in all sites is October 2007.

ready for allotment by end of September 2007.

SUPERSTRUCTURE ERECTION AT KINYUKA IN CAR NICOBAR


-

>

-<

r,

4. CHOWRA

AERIAL VIEW OF CHOWRA

346 units arc under construction in this island by CPWD.


Constraints: Due to extremely rough sea conditions, transportation ol material through

Stevedoring is possible only during two months in a year i.e. February and March. This
year, transportation ol materials could be started only by the end ol March 2007.
Foundation Work:

The status of Foundation work is as follows:

Excavation

144

42%

l>

Concrete Pedestal

138

40%

Grade Beams

138

40%

Fixing of Nuts and Bolts

1 IX

40%

The work for foundations is in progress. Targetdate of completion of foundation work in


all sites is Nov. 2007.

Super Structure Work: The work of erection ol superstructure has been finalized by
CPWD and the fabrication of superstructure is in progressat Vi/ag since November 2006.
Target dale ol completion is August 08.
Community Buildings & Development Works: One tender lor all the community
buildings such as Community Hall, Recreation Hall, Birth House, Death House, Shops,

one Middle School & Health Sub Center and all Civil & Electrical development work is

awarded. Material mobilization is in progress. Target date of completion is Oct. 08.


Roll Out Plan lor Chowra is at Annexure 'B*. The first batch ol 50 houses will he ready lor
allotment bv end of March 2008.
FOUNDATION WORK COMPLETED AT CHOWRA

Ml

FOUNDATION WORK COMPLETED AT KALASI IN TERRESSA

5. TERESSA

506 units arc under construction in this island by CPWD.


Constraints:

i.

All sites are approachable only via sea route and materials
can be shipped to shore only through stevedoring operations.

ii. Transportation of materials from shore to sites is possible only on head loads.

--_--

iii. Being Malaria-prone Island, it adversely impacts morale of stall

JffP^

'
- ,

^*..;-. r ;;

working on the permanent shelters.

1...

- >
'-..-.;*fe^

Foundation Work:

The status of Foundation work is as follows:-

Excavation

506

100%]

Concrete Pedestal

506

100%

Grade Beams

506

100%

Fixing of Nuts and Bolts

506

100%

L_il
1

,_

^
fl^3s

".MBH&MfeMM^^

" ' -

"

Thework for foundations is completed at all the sites.

'JEL.iM

* .-^ - ,'. ' "'

1 '

w^T

_
Jf

'^^"w

"

Ii

Community Buildings & Development Works:

lender lor community buildings and

all Civil & Electrical works in 4 villages accepted on 03.04.2007. Tender for remaining
Super Structure Work: The fabrication of superstructure is in progress at Vi/ag since

4 Villages isdue to open in 2nd week ol Sept. 07. Targetdate ol completion is Sep. 200<S.

November 2006. The work of erection of 96 superstructures is in progress and walling


Roll Out Plan for Tcressa is at Annexure 'B'. The first batch of 10 houses will be ready for

work has to commence. TheTarget date of completion is Aug. 08

allotment by end ol September 2007.

II

AERIAL VIEW OF BENGALI SITE AT TERESSA

i:

FOUNDATION WORK COMPLETED AT CHOTTA ENNAKA

6. KAMORTA

518 units arc under construction in this island by CPWD.


Constraints:

i.

Except three, all other sites are approachable only via sea routes,

ii. Transportation ol materials from shore to sites is possible only on head loads,
iii. Being Malaria-prone Island,

it adversely impacts morale of work force

stationed on the islands.

Foundation Work: The status of Foundation work is as follows:-

f
a

Excavation

431

83%

Concrete Pedestal

428

82%

Grade Beams

384

74%

Fixing of Nuts and Bolts

352

68%

11

_J

The work lor foundations Is in progress at all the sites. Target date ol completion ol
foundation work in all sites is December 2007.

Super Structure Work: The work ol erection ol superstructure has been finalised by
CPWD and the fabrication ol superstructure is in progress at Vizag since November2006.
Target dale ol completion is August 2008.

Community Buildings: fenders for the all the sitesisawarded. Target date of completion
is August 2008.

Development Work: Tender for Civil works at all sites is finalized. Target date of
completion is August2008.

Roll Out Plan for Kamorta is at Annexure 'A'. The lirst batch of 10 houses will be read)
for allotment by end of September 2007.

13

EOUNDATION WORK COMPLETED AT CHAMPIN IN NANCOWRY

7. NANCOWRY

269 units are under construction in this island by CPWD.


( i mstraints:

i.

All sites are approachable only via sea route.

ii. Transportation of materials from shore to sites ispossible only on head loads,
iii. Being Malaria-prone Island, it adversely impacts morale ol work force stationed
on the island.

Foundation Work: The status of Foundation work is as follows:-

Excavation

111

S4 o

1.

Concrete Pedestal

226

84%

Grade Beams

219

81%

Fixing of Nuts and Bolts

217

80%

The work for foundations is in progress at all the sites. Target date of completion of
foundation work in all sites is October 2007.

Super Structure Work: The work of erection of superstructure has been finalised by
CPWD and the fabrication of superstructure is in progress at Vi/agsince November2006.

Target date of completion is July 2008.


Community Buildings: Tenders for theall the sites is awarded. Target date ofcompletion
is August 2008.

Development Work: Tender for Civil works at all sites is finalized. Target date of
completion is August 2008.
Roll Out Plan for Nancowry is at Annexure 'B'. The lirst batch ol 10 houses will be
ready for allotment bv end of December 2007.

14

FOUNDATION WORK COMPLETED AT WIMCO VILLAGE IN KATCHAL

8. KATCHAL

315 units are under construction in this island by CPWD.


Foundation Work:

The status of Foundation work is as follows:-

Excavation

277

SS"

Concrete Pedestal

267

85%

Grade Beams

265

84%

Fixing of Nuts and Bolts

265

84%

The work for foundations is in progress at all ihe sites. Target date of completion of
foundation work in all sites is October 2007.

Super Structure Work: The work of erection of superstructure has been finalised bv

CPWD and the fabrication ofsuperstructure is in progress at Vizag since November 2006.
Target date of completion is August 08.

Community Buildings: Tenders for theall thesites isawarded. Target date olCompletion
is August 2008.

Development Work: Tender for Civil works al all siles is finalized. Target dale of
completion is August 2008.

Roll Out Plan for Katchal is at Annexure 'A'. The lirst batch of 10houses will be ready
for allotment by end of December 2007.

15

Work at I..axmi Nagar, Gandhi Nagar and Shastri Nagar will commence in

9. GREAT NICOBAR

March 2008 when BRO lair weather road will he available

995 units arc under construction in this island by CPWD.


Constraints:

Foundation Work:

The status of Foundation work is as follows:

Progress of Permanent Shelter is linked to the progress of completion of


North Soulh Road.

BRO has provided fair weather access only upto Joginder Nagar.

Excavation

298

30%

The work at four accessible siles has commenced.

Concrete Pedestal

280

28%

Case submitted lo Forest Department lor Forest Clearance for two out of

Grade Beams

250

25%

fixing ol Nuts and Bolts

206

21%

four siles located in forest land.

F1A study for Kopen Heat &Gandhi Nagar lo beconducted by NIOT

FOUNDATION WORK COMPLETED AT RPRS SITE: IN GREAT NICOBAR

16

The work for foundations is in progress at lour siles. Iargel date ol completion of

Community Facilities and Development Work: Tender for Civil & Electrical work for

foundation work in all sites is October 2008.

Communit) Facilities and Development works lor Campbell Bay, Govindnag.trand Agri.

Farm site have been launched and bid is opened On 29th Aug. 2007. Fender for Jogindcr

Super Structure Work: The plan lor erection ol superstructure has been finalised. Fender
for fabrication of superstructure is launched and Technical bid is opened. Financial bid is
opened on 29th Aug 2007. Target date ofcompletion isSept., 08.

Nagar is dueto be received in Oct. 2007. Target date of completion isSept'2008.


Roll Out Plan for Great Nicobar is at Annexure 'B'. The lirst batch of 50 houses will

be ready lor allotment bv end ol Jan., 2008.

FOUNDATION WORK COMPLETED AT RPRS SITE IN GREAT NICOBAR

17

10. LITTLE NICOBAR

AERIAL VIEW OF LITTLE NICOBAR

I I I units arc planned for construction in this island by CPWD.

Constraints:

All the 5 sites fall in reserved forest area for which EIA study and Forest clearance is

required.

Final EIA reports have been received from NIOT and case is submitted lo Forest
Department for 3 sites for Forest Clearance. For balance sites case is under process
lor submission to Forest Department.

Plan for all the I11 units will be finalized on receipt ol EIA/ Forest Clearance.

Due to difficult access, air dropping of construction material is required

IX

ISLAND WISE ROLL OUT PLAN


Ml' 07

ISLAND

OCT-07

NOV (IV

DEC 07

JAN 08

I I II 08

MAR 08

AI'R-08

MAY 08

JUN 08

|UI.()8

1 - ~%

South Andaman

823

144

140

189

100

14

100

36

Little Andaman

965

50

3 30

380

430

348

140

140

105

Car Nicobar

3941

200

400

460

460

500

500

500

321

60

60

60

60

56

41

62

62

40

40

in

42

42

40

36

26

26

100

Chowra

346

Tercssa

506

10

40

46

42

42

Kamorta

518

10

26

45

44

93

Nancowry

269

10

30

40

39

41

II

40

28

Katchal

315

10

40

40

44

38

39

40

32

32

Great Nicobar

995

50

50

100

100

100

100

100

24

1245

1221

1056

1019

947

637

286

178

Little Nicobar

TOTAL

41

II

7966

170

460

961

1135

19

ANNEXURE

Month

Completion of Superstructure

Completion of Superstructure

Completion of Superstructure

(No. of units)

(No. of unils)

(No. of units)

Sep-07

Completion of Superstructure Completion of Superstructure


(No. of units)

50

100

10

(No. of units)

Oct-07

144

50

200

26

Nov-07

140

330

400

46

Dec-07

189

380

460

44

10

Jan-08

100

430

460

93

40

Feb-08

114

348

500

88

40

Mar-08

100

140

500

42

44

Apr-08

36

140

500

42

38

105

500

40

39

Jun-08

U\

36

40

Jul-08

3? I

26

32

26

32

May-08

Aug-08
COMMUNITY FACILITIES
Other Works

Communilv Buildings

April - 08
March

08.

April 08.

April -08

May 08

March

08

March

April -08

April - 08

March

08

08

2.1

annexure:

TERESSA

No. of Units
Month

CHOWRA

315

No. of Units

269

No. of Units - 346

Completion of Superstructure

Completion of Superstructure

Completion of Superstructure

(No. of units)

(No. of units)

(No. of units)

GREAT NICOBAR

No. of Units

995

LITTLE NICOBAR

No. of Units

111

Completion of Superstructure Completion of Superstructure


(No. of units)

(No. of units)

Aug-07
Scp-07
Oct-07

10

40
-

Nov-07

46
-

Dec-07

42

10
-

Jan-08

42

30

60

leb-08

41

40

60

Mar-08

41

Apr-08

62

41

May-08

62

41

Jun-08

40

JuI-08

40

Aug-08

40

39

50

40

28

100

60

100

60

100

60

100

60

100

66

24

COMMUNITY FACILITIES

Other Works

Communilv Buildings

May - 08

Apr-08

Mar-08

Apr-08

Development works

May - 08

Apr-08

Mar-08

Apr-08

J
21

INTERMEDIATE SHELTERS

22