Академический Документы
Профессиональный Документы
Культура Документы
xls
Summary
$0
$0
$0
$0
$0
$0
$0
$0
Payback (years)2
NA
$0
$0
$0
$0
Payback (years)2
(1)
Option B Break-Even3
$0
Option C Break-Even3
$0
This model assumes that payments are made at the end of each period and discounted back
to the system production date. This model does not evalute the financial impacts of any
system buyout options.
1
Payback is equal to the number of years it takes for the PV Cost of the selected option to
become equal to or less than the PV for Option A - Status Quo.
2
The Break-Even calculator computes the rate of Annual Increase in Retail Electricity (per
kWh) required to make the PV Cost of Option A - Status Quo equal to the PV Cost of the
selected alternative Option. This can viewed as the minimum rate of retail electricity cost
increase required for the selected Option to provide a lower PV Cost than the Status Quo.
3
1 of 4
269259747.xls
Summary
KEY ASSUMPTIONS
System Production Date
6/1/2009
Required Field
Y Anticipated system production date
Term (years)
Y Term for the PPA agreement and the financing period; must be expressed in integers from 1 through 50.
$0.00
$0.00
$0.00
$0.00
N Upfront rebates or incentives per watt to buy and install the system, if applicable
Y Installed cost of the system net of any upfront rebates or incentives.
Y Anticipated first year electricity production in kilowatt hours derived from a source such as PV Watts.
0.00%
$0.000
0.00%
Y The retail electricity cost per kWh the Agency currently pays PG&E
Y Anticipated annual rate of increase in the retail electricity cost
Discount Rate
0.00%
Y Discount rate used to calculate present value (Agency's assumed earnings rate or opportunity cost of capital)
0.00%
N This field may be left blank if the Agency elects to purchase the system with its own funds without any financing
arrangements (ie. Agency does not borrow money to pay for the system)
0.00%
0.00%
0
Y Anticipated annual cost of an Operations & Maintenance contract expressed as a percentage of the installed cost (applicable
Y to Option B - Agency Buys System).
Y Anticipated cost per KW to replace the solar system inverter in year 15 (applicable to Option B - Agency Buys System)
$0.00
0.00%
N This field may be left blank if the Agency determines that no incremental staff costs would be incurred to manage the
Operations & Maintenance contract (applicable to Option B - Agency Buys System).
N
0.00%
N This field may be left blank if the Agency determines that there are no project management costs to install the system
(applicable to Option B - Agency Buys System)..
$0.000
0
N This field may be left blank if the Production Based Incentive (PBI) credit is not applicable to the Agency (applicable to
Option B - Agency Buys System). Please specify the number of years the incentive credit is available.
0.00%
N This field may be left blank if the Agency determines that there are no project management costs to manage the PPA vendor
to install the system (applicable to Option C - Agency Enters into PPA Contract).
$0.00
N This field may be left blank if the Agency determines that no incremental staff costs would be incurred to manage the PPA
contract (applicable to Option C - Agency Enters into PPA Contract).
$0.000
0.00%
Y Electricity rate paid under the PPA in year 1 (applicable to Option C - Agency Enters into PPA Contract).
Y The annual inflation factor applied to the PPA rate (applicable to Option C - Agency Enters into PPA Contract).
2 of 4
269259747.xls
Summary
3 of 4
If you are experiencing Excel error notifications when running this model, please make sure the following Add-Ins are selected:
From the Tools Menu ->Add-Ins, select the following options: