Академический Документы
Профессиональный Документы
Культура Документы
Claimant
Defendant
----------------------------------------Ms. Fiona Sinclair QC (instructed by Pinsent Masons LLP) for the Claimant
Miss Anneliese Day QC (instructed by Dentons UKMEA LLP) for the Defendant
Hearing dates: 29th September 2014
--------------------Judgmen
obliged to refer the dispute to the DAB. On 26 August 2014 EMS applied to the
RICS (the nominating body named in the contract) for the appointment of an
adjudicator. Mr John Wright, a partner in Goodman Derrick, was duly appointed.
9. On 27 August 2014 EMS issued this application. It was represented at the hearing by
Miss Anneliese Day QC, instructed by Dentons, and the Council was represented by
Ms. Fiona Sinclair QC, instructed by Pinsent Masons. Both counsel made careful,
cogent and persuasive submissions for which I am very grateful.
The contract
10. The contract was made on the FIDIC General Conditions of Contract for
EPC/Turnkey Projects. This is one of a suite of three standard forms of contract
(known as Books) issued by FIDIC in 1999. The other two are Conditions of
Contract for Construction and Conditions of Contract for Plant and Design-Build.
11. Clause 1.1 of the Conditions defines the DAB as:
The person or three persons so named in the Contract, or other
person(s) appointed under Sub-Clause 20.2 [Appointment of the
Dispute Adjudication Board] or Sub-Clause 20.3 [Failure to Agree
Dispute Adjudication Board]
12. The FIDIC Contracts Guide, published in 2000, makes it clear that each Book
describes a dispute resolution procedure which may be applicable to most contracts
for which the Book was intended to be used. But it then goes on to say that the most
appropriate Book may not be the Book which contains the dispute resolution
procedure which is to be preferred. As one might expect, therefore, the parties have
the choice of choosing a dispute resolution procedure other than that in the Book
which otherwise appears most appropriate to their particular project. The Conditions
of Contract for Construction provide for a full-term standing DAB, where the
member or members are appointed before the start of the works. The other two Books
provide for the ad hoc appointment of a DAB following the issue by one of the parties
of a notice of intention to refer a dispute to adjudication.
13. Although Ms. Sinclair did not accept this, in my view it is clear that this suite of
contracts provides for two mutually exclusive types of DAB: a standing DAB named
in the contract, or an ad hoc DAB appointed following a dispute. I cannot see how
the contractual provisions can be interpreted or operated so as to permit two types of
DAB to be in existence at the same time, or even to be alternatives.
14. The crucial clauses in the present dispute are sub-clauses 20.2 to 20.8, the relevant
parts of which I will have to set out below at some length:
20.2
20.2.1
20.2.2
20.2.3
20.2.4
20.2.5
20.2.6
20.2.7
20.2.8
20.3
20.3.1
(a)
...
20.3.2
20.4
20.4.1
20.4.2
...
20.4.3
20.4.4
20.4.5
20.4.6
20.4.7
20.5
Amicable Settlement
20.5.1
20.5.2
When notice of dissatisfaction has been given under SubClause 20.4 above, both Parties shall attempt to settle the
dispute amicably before the commencement of court
proceedings. However, unless both Parties agree otherwise,
court proceedings may be commenced on or after the fiftysixth day after the day on which notice of dissatisfaction
was given, even if no attempt at amicable settlement has
been made.
20.6
Final settlement
20.6.1
...
20.7
20.7.1
(b)
(c)
20.7.2
20.8
20.8.1
(b)
15. In addition, the following clauses were referred to in the parties submissions:
1.2.6
1.4.1
The contract also provided that marginal words and other headings were not to be
taken into consideration in the interpretation of the Conditions.
The submissions of the parties
16. Miss Day relied strongly on the opening words of sub-clause 20.2.1, submitting that
the sub-clause contained a mandatory requirement to refer disputes arising under the
contract in the first place to adjudication in accordance with sub-clause 20.4.
Accordingly, she submitted that the Councils issue of proceedings following EMSs
notice of intention to refer a dispute to adjudication without either invoking or
cooperating in the adjudication procedure was a breach of contract.
17. Miss Day submitted also that if the Councils interpretation of sub-clause 20.8.1 were
correct, sub-clauses 20.2 to 20.7 would be rendered redundant. She said that such an
interpretation cannot have been the intention of the parties.
18. Miss Day relied also on a comment in the FIDIC Contracts Guide, which said:
... the first paragraph of Sub-Clause 20.2 requires a DAB to be
appointed within 28 days after a Party gives notice of intention to
refer a dispute to a DAB, and Sub- Clause 20.3 should resolve any
failure to agree the membership of the DAB. The parties should thus
comply with Sub-Clauses 20.2 and 20.3 before invoking Sub- Clause
20.8. If one party prevents a DAB becoming in place, it would be a
breach of contract ...
19. Miss Day submitted also that clause 20.8 was to deal with circumstances in which a
DABs appointment has expired or, for some other reason, the parties have agreed to
terminate the DABs appointment, or there has been a breach of contract by one party
so as to entitle the other party to refer the matter straight to court.
20. Ms. Sinclair submitted that sub-clause 20.8 was in effect an opt-out that enabled a
party who did not wish to have the dispute resolved by adjudication to refer the
dispute directly to the court. She relied strongly on the concluding words of the first
sentence (or otherwise) and submitted that this covered any situation where a DAB
was not in place either after a dispute had arisen or at the time when the party
wishing not to adjudicate had commenced litigation.
21. Ms. Sinclair pointed out that since the parties could not be under a mandatory
obligation to achieve the appointment of an adjudicator - perhaps because in good
faith they could not agree on the identity of a suitable adjudicator - the word shall,
where it appeared in clause 20.2.1, must necessarily be directive or aspirational, rather
than mandatory.
22. She submitted also that for a DAB to be in place there must be a DAB that is
empowered to resolve a dispute. She pointed out, correctly in my view, that the
source of the DABs authority was the Dispute Adjudication Agreement. She then
submitted that since the wording of this agreement stated expressly that it was not to
be effective until both its terms had been agreed by the contracting parties and the
adjudicator and the agreement had been signed by each of them, it could not be in
place until this had been done. In my view it is clear that, in the absence of any
agreement to the contrary, the Dispute Adjudication Agreement is to be in the form set
out in the Appendix to the Conditions (because that document is incorporated by
reference into the Dispute Adjudication Agreement).
23. Ms. Sinclair submitted that, both as a matter of language and the express provision in
clause 1.2.6, the phrase or otherwise was wide enough to include a state of affairs
where the Dispute Adjudication Agreement had not been concluded.
24. In relation to the provisions of sub-clause 20.4 to sub-clause 20.7 as a whole, Ms.
Sinclair submitted also that they were unenforceable for lack of certainty. She
identified what has been described as the gap in those sub-clauses, which arises
when the DAB has made a decision and one party has given a notice of dissatisfaction
- with the result that the DABs decision, whilst binding, is not final. The problem
then is that if the unsuccessful party refuses to comply with the decision of the DAB,
as it is required to do by sub-clause 20.4.4, the only remedy (it is said) available to the
other party is to refer the dispute occasioned by the refusal to comply to yet another
adjudication. This can have the effect, Ms. Sinclair submitted, that the party in
default can embark on a course of persistent non-compliance with DAB decisions and
thereby deprive the other of any effective remedy.
25. Ms. Sinclair points out that this problem has been recognised by FIDIC and I was
referred to erudite articles by Prof Niall Bunni and Taner Dedezade, a barrister
employed by Corbett and Co, which set out the difficulties that it presented.
26. In my judgment, there is a short answer to this. Whilst the point may be arguable in
the context of the standard FIDIC Books which include an arbitration clause, it loses
its force where the arbitration clause has been removed - as in the present case. The
articles to which Ms. Sinclair referred were concerned with the limitations on the
powers of arbitrators in this situation (in particular, whether or not they could order
specific performance), the type of award (interim, partial or final) that is or may be
appropriate if the DABs decision is to be enforced and the whole question of the
delay that would be involved in resorting to arbitration.
27. However, these problems disappear when the contract provides that the forum for
final resolution of any dispute is litigation, and not arbitration. I can see no reason
why the court could not intervene at the instance of one of the parties by ordering
specific performance of the obligation to comply with a decision of the DAB.
Alternatively, if it were to be argued that the proper or only remedy for this was by
way of a further adjudication, the court could enable the aggrieved party to secure
justice by refusing a stay of any court proceedings that it commenced. I therefore
reject Ms. Sinclairs submission that the relevant provisions in this contract are
unenforceable.
28. As to Ms. Sinclairs argument that there can be no DAB in place if a Dispute
Adjudication Agreement has not been concluded so as to be effective, whether
because the parties have been unable to agree the adjudicators fees or that it has not
been signed by the parties and the adjudicator, I think that Ms. Sinclair was disposed
to accept that, in the absence of any agreement between the parties, the effect of
incorporating the Appendix to the Conditions as the terms of the Dispute Adjudication
Agreement was that all the relevant terms of that agreement would be in place save
for agreement of the adjudicators fees. In my view, there would be an implied term
of that agreement - reflecting the common intention of the parties to it - that the
adjudicator would be entitled to his or her reasonable fees and expenses.
29. Both counsel referred me to a judgment of Hildyard J in Tang v Grant Thornton
[2013] 1 All ER (Comm) 1226, in which he had to consider the enforceability of a
dispute resolution clause. At paragraphs 56-58 he said this:
[56]
[57]
[58]
30. I agree with these observations. In this case I consider that the only missing
ingredient, the rate of the adjudicators daily fee, is one that can readily be assessed by
the court in default of agreement. Courts such as this one are well equipped to assess
what is a reasonable level of fee for an adjudicator in this type of situation. In this
case the adjudicator put his proposals to the parties in respect of his fees and neither
party challenged them. I doubt if the court would have much difficulty in concluding
that the figures that he proposed were reasonable (although I am not expressly
deciding this).
31. As I have already mentioned, Ms. Sinclair also relied on the requirement for the
Dispute Adjudication Agreement to be signed by all the parties before it became
effective. I see nothing in this. If a party without good reason refused to sign the
agreement, I cannot see why it could not be compelled to do so by an order for
specific performance at the suit of one or more of the other parties. I therefore reject
Ms. Sinclairs submissions that the contract is unenforceable.
32. Reverting to sub-clause 20.8, my conclusions are clear. First, the words if a dispute
arises ... and there is no DAB in place apply to a situation where there is no DAB in
place at the time when the dispute arises. If it were otherwise, as Miss Day pointed
out, the provisions of sub-clauses 20.2 and 20.3 could never have any application
because, by definition, under those sub-clauses there has to be a dispute in existence
before the process of appointing a DAB can begin. Thus in every case where subclause 20.2 or 20.3 applies there will be in existence a dispute but no DAB. Thus,
since under sub-clause 20.8 sub-clause 20.4 is disapplied, on Ms. Sinclairs approach
to the construction of sub-clause 20.8 there can never be a reference of a dispute to
adjudication in any contract which provides that the DAB is to be appointed in
accordance with the provisions of sub-clause 20.2 or sub-clause 20.3.
33. It seems to me that sub-clause 20.8, which is in the same form in all three of the
FIDIC Books, probably applies only in cases where the contract provides for a
standing DAB, rather than the procedure of appointing an ad hoc DAB after a dispute
has arisen. Ironically, Ms. Sinclair said that the position was precisely the opposite:
in her skeleton argument she submitted that the parties could prevent clause 20.8 from
operating at all by appointing a standing DAB. I have to confess that I did not
understand this point, but it shows that Ms. Sinclair was not suggesting that the fact
that, depending upon the dispute resolution procedure chosen, sub-clause 20.8 might
not have any application was fatal to what I would otherwise consider to be the
correct construction of the conditions.
34. In addition, I do not accept Ms. Sinclairs submissions about what is meant by the
phrase no DAB in place. The right to refer a dispute to adjudication arises under
sub-clause 20.4.1 as soon as a DAB has been appointed, whether under sub-clause
20.2 or 20.3. It is quite clear from the words final and conclusive in sub-clause 20.3
that the process of appointment is complete once the nominating body has
appointed the adjudicator. That must mean the identification of a particular person
as the adjudicator because the appointing body cannot make the Dispute Adjudication
Agreement for the parties. In my judgment, therefore, a DAB is in place once its
member or members have been duly appointed in this way because from that moment
onwards a dispute can be referred to it. Not even Humpty Dumpty would suggest that
a dispute could be referred to a DAB that was not in place.
35. For all these reasons, therefore, I reject the Councils submissions that sub-clause 20.8
gives it a unilateral right to opt out of the adjudication process, save in a case where at
the outset the parties have agreed to appoint a standing DAB and that, by the time
when the dispute arose, that DAB had ceased to be in place, for whatever reason.
Further, I also reject the Councils submissions that the adjudication provisions in the
contract are unenforceable.
36. Accordingly, I accept EMSs case that the contract requires that the determination of
the current dispute is to be by way of adjudication and amicable settlement under subclauses 20.4 and 20.5 and, only failing that, by litigation.
Should there be a stay?
37. Both parties accept that the court has an inherent jurisdiction, which involves an
exercise of judicial discretion, to order a stay of the claim brought by the Council.
The question is whether this is an appropriate case in which the court should exercise
that discretion in favour of EMS.
38. Ms. Sinclair submitted that any decision by the DAB would almost inevitably
provoke a notice of dissatisfaction from one or other party. Accordingly, to embark
on the fairly lengthy (and therefore expensive) adjudication procedure under the
contract would be a wholly or at least largely unproductive exercise. She submitted
that the dispute raises complex questions of construction and application of
legislation, mandatory codes and standard industry practice and will require extensive
disclosure. She submitted also that the rough and ready process of adjudication is
entirely inapt to resolve this dispute.
39. As to this last point, Ms. Sinclair may well be correct, but that is nothing new: the
complexity of a potential dispute about when the required power output was achieved
was foreseeable from the outset, yet nevertheless the parties chose to incorporate the
adjudication machinery in the FIDIC form of contract. If Ms. Sinclair is right to
describe this type of adjudication as a rough and ready procedure, then both parties
agreed to have it.
40. Nevertheless, I have some sympathy with Ms. Sinclairs submissions. This is not a
case where either party has invested any time or money on the preparation for or
conduct of an adjudication, and so it can be fairly said that it is better to have one, if
more expensive and extensive, dispute resolution procedure than to take the real risk
that this will be required in any event in addition to an adjudication. If no other
factors were in play, I would be tempted to accede to Ms. Sinclairs submissions
because the rival scenarios are quite finely balanced and, if anything, are perhaps
tipped in the Councils favour.
41. However, there is another factor in play. As the authorities clearly show, there is a
presumption in favour of leaving the parties to resolve their dispute in the manner
provided for by their contract: see DGT Steel and Cladding v Cubitt Building [2007]
BLR 371, and the cases referred to at paragraphs 5 to 11 of the judgment.
42. Whilst Miss Day acknowledged that the dispute was clearly difficult because the
parties had not managed to settle it at the mediation, she submitted that it cannot be
assumed that the parties would adopt the same positions in the light of a reasoned
decision from an adjudicator. Alternatively, she submitted that, even if the
adjudicators decision were not accepted by one or other party, it might nevertheless
provide a starting point from which the parties could settle the dispute. She submitted
that it cannot and should not be assumed that an adjudication would serve no purpose.
43. Although, as I have already indicated, on purely practical grounds the pragmatist in
me would tend to favour the contentions of Ms. Sinclair (if all other things were
equal), I consider that the various factors are too finally balanced for me to conclude
that, overall, the Council has made out a sufficiently compelling case to displace the
presumption in favour of adopting the method of dispute resolution chosen by the
parties in their contract.
44. For these reasons, I conclude that the Council has not made out a sufficient case for
resisting a stay. Accordingly, the action must be stayed and the parties left to resolve
their dispute in accordance with the contractual machinery in the light of the matters
discussed in this judgment.