Corrected baseline programme for delay analysis


Loginorregistertopostcomments

22replies[Lastpost]

Tue,2005050323:36

NeilTait

Ivescannedpreviousstringsbutfoundnothingrelevant.Heresthescenario,commentsand
referencewelcomebasedonexperience/acceptedprinciples:

Offline
Joined:31Jan2001
Posts:29
Groups:GPCUnited
ArabEmirates

Onourprojectwearequitesimplyutilisingthebaselineprogramme(ContractProgramme)
fordelayanalysis/assessment.Despitethebaselineprogrammehavingbeenapprovedit
wassubsequentlycleartoallpartiesasworkprogressedthattherewerevarioussequencing
errorssomofwhichwereontheasbuiltcriticalpath(tobeexpectedinany2000+activity
programme)
Opportunityexistedunderthecontractfortheerrorstobecorrectedinarevisedprogramme.
Despiterequestforsuch,thisapproachwasnottakenupduringthecourseoftheworksfor
variousreasons(note,arevisedprogrammethatcontainsanelementofprogressisdifferent
fromacorrectedbaselineprogramme).
Unfortunatelyitisonlynow,atthetailendoftheproject(beyondsubstantialcompletion),
thattheclaimresolutionhasreceivedtheappropriatecommitmentfromthevariousparties.
Withhindsight(asbuiltknowledge)thevarioussequencingerrorscontainedinthebaseline
programmehavebecomeevidentandthecontractorhasputforwardanapproachwherebya
correctedversionofthebaselineprogrammeisutilisedfordemonstration/assessmentof
delay/EOTentitlement.
BygoingdowntheroadofacceptingpostworkcorrectionstothebaselineprogrammeIm
fundamentallyconcernedthatsuchaprogrammeisnotdefinedunderthecontractandthat
suchaprogrammecouldproveunfairtothepartiesinvolvedi.e.intheprocessofcorrecting
theprogramme,concurrentactivitieswillberesequencedinseries,whichiforiginal
completionobjectivesaretobeachievedwillrequiresqueezingthecriticalpaththiswill
potentiallyyielddatesthatareearlierthanthosepresented/anticipatedduringthecourseof
theworkandwillalsopresentasbuiltprogressdelaysassociatedwithactivitydurationsthat
arenowreduced.
Beyondmyfundamentalconcerns,thereareofcoursedoubtsoverwhatwouldbedeemed
acceptablecorrections.Impossiblewouldwarrantacorrection,butImpracticalmaywellbe
somethingdiscoveredonhindsightthatneedstobelivedwithonthebasisthatitisnot
impossibleandhasintheorybeensequencedandpricedakathebaselineprogramme.
Doesanyoneouttherehavedirectexperienceorpointsofreferencewithregardspreparing/
acceptingacorrectedbaselineprogramme(postwork)fordelayanalysis?Isitanaccepted
industrystandard?

Top

Printerfriendlyversion Loginorregistertopostcomments

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

Sendtofriend
1/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

REPLIES
#1

Sat,2009101718:53

RolandTannous
Offline
Joined:15Oct2009
Posts:84
Groups:GPC
Lebanon

HeyMike
welldidntmeananyharm.Ididntevenpayattentiontothedate.
:)
Regards

Top

Loginorregistertopostcomments
#2

Sat,2009101714:06

MikeTestro
Offline
Joined:14Dec2005
Posts:3948
Groups:Asta
Powerproject,Building
InformationModelling,
ContentModerators,
GPCIndia,GPCUnited
ArabEmirates,GPC
UnitedKingdom,
PendingGuild
Members

HiRoland
AlittlewordofadvicetoanewPPmember.
Toresurrecta4yearoldthreadmaybeconsideredbadmannersbytheoriginatorand
contributors.
PleaserespondwherealivedebateisinprogressgoandhavealookatLetsChallenge
Spiderandseeifyoucanaddanythingtothatforumandretainyoursanity.
Bestregards
MikeTestro

Top

Loginorregistertopostcomments
#3

Sat,2009101700:03

RolandTannous

Ifindthe"ButFor"principletobehighlysubjective,andamethodthatshouldbeapproached

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

2/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Offline
Joined:15Oct2009
Posts:84
Groups:GPC
Lebanon

withcaution.
Ithasbeenusedalotoftimesfrombothpartiestoaclaimtostatethat"butfor"mydelayon
Xactivitytheotherpartywouldhavedelayedtheprojectanywaybecausehedidntmobilize
hissubcontractorforactivityYontime.Bystatingthatthefirstpartyisreallyviolatingthe
conceptsofCPMbyforgettingthatinalotofcasesitcouldbethatthedelayonactivityX
gaveactivityYmorefloatandthereforethelatemobilizationofthesubcontractoronthat
activitydidntcauseanycriticaldelaystotheprojectandcouldamounttothecontractorjust
pacingthedelayonactivityX.
Ofcourseeverythingsaidabovewouldntbeaproblemifbothexpertsreallyknowwhat
theyredoingandifyouendupincourt,forthejudgetoreallybeintunewiththesubject
becauseinthispartoftheworldmostjudgesdont.
Regards

Top

Loginorregistertopostcomments
#4

Wed,2005051110:13

DavidBordoli
Offline
Joined:8Apr2002
Posts:416
Groups:Building
InformationModelling,
GPCApplicants,GPC
UnitedKingdom

Adrian
Yourgraciousnessisnowmakingmefeelguiltyforbringingyoursliptoyourattention.
IthinkHisHonourJudgeHumphreyLLoydQCmadeasimilarslipinBalfourBeatty
ConstructionLtdvLondonBoroughofLambeth[2002]soweareingoodcompanybut
againthatalldependsonthedefinition,JudgeLLoydsdefinitionsmayhavebeendifferentto
ours!
WecangetverypedanticifwearenotcarefulandtalkaboutatimeimpactanalysisorTime
ImpactAnalysisforinstance.Literally,Ithinklowercasesignifiesanymethodthatanalyses
timeandimpactwhereasuppercaseisaspecificmethod.Similarly,atimeslice/windows
analysisandTimeslice/WindowsAnalysis.
Again,theseareonlymyinterpretationsofthemethodsbutIthinkyourdescriptionisofa
windows/timesliceanalysis.MyviewisthatthetechniquesarebroadlysimilarbutTIAleads
toamorerefinedanalysisasitdealswithindividualeventswhereasTimesliceAnalysis
potentiallydealswithwhatevernumberofeventshappenwithintheselectedtimeperiod.I
tendtothinkthereisaspecificwayofanalysingthedelaysusingTimesliceAnalysisbutuntil
wegetarevisionoftheProtocolmaybeweareallstillalittleinthedark.
Regards
David

Top

Loginorregistertopostcomments

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

3/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

#5

Wed,2005051109:37

AdrianArcher
Offline
Joined:26Nov2002
Posts:10
Groups:PetroChem
/Oil&Gas

DearDavid,
Faircall,yourequiteright.Toomanycommentatorsuse"TimeSlice"and"TimeImpact"
interchangeablyandIfellvictimtoittooIwasreviewingajudgementthatdidexactlythat
whenIdraftedmysuggestionsforNeil.
Agreedthat"TimeSlice"isanothertermfor"Windows."Iknowitasmarkingtwodatesona
programmethatboundaneventandanysuitablemethodofanalysismaybeappliedwithin
thattheatre.Sameforyou?

Muchobligedandmanythanks,
AdrianArcher.
PickavanceConsultingLimited

Top

Loginorregistertopostcomments
#6

Wed,2005051107:41

DavidBordoli
Offline
Joined:8Apr2002
Posts:416
Groups:Building
InformationModelling,
GPCApplicants,GPC
UnitedKingdom

Dearall
ApologiesforthisnonconstructivepostingbutIdliketogetbackonmyhobbyhorseof
nomenclatureanddefinitionsofmethods.
Withrespect,IamsurprisedatAdriansmisappropriationinanotherwiseexcellentresponse.
Inmyextremelyhumbleopinion(!)whatAdrianreferstoasTimeSliceisinfactTime
ImpactanalysisandisthatmethodwhichisrecommendedbytheSCLandtosomeextent
byhisorganisationschairman,KeithPickavance,inhisbookDelayandDisruptionin
ConstructionContracts.
TimeSliceanalysis(orWindowsanalysis)issomethingdifferentandisnotmentionedinthe
SCLProtocol.Anunexpectedomissionconsidering,inmyexperience,itisafrequentlyused
methodofanalysis,atleastintheUK.
Regards
David

Top

Loginorregistertopostcomments
#7

Sun,2005050819:04

UriShachar
Offline

Guys,
InmostcasesIwouldhaveastrongpreferencetoleavethebaselineprogramme(Contract

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

4/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Joined:11May2003
Posts:82
Groups:GPC
Australia

programme)unaltered,especiallyifitwasagreedorapprovedoracceptedor
acknowledegedbythePrincipal.Thereshouldbeaverystrongcasefortemperingwithsuch
programme.
Extendingthedurationoftheprojectdueto,say,omissionintheProgrammeisparticularly
problematic,asthePrincipal,hadtheproblembeingknownatthetimepriortosigningthe
Contract,couldhavesignedwithadifferentContractor.

Top

Loginorregistertopostcomments
#8

Sun,2005050814:24

PhilipJonker

Iamacuallvplayingagameclledcossacks2whichisbmindbloring

Offline
Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

Top

Loginorregistertopostcomments
#9

Sun,2005050814:20

PhilipJonker

IcouldevenquoteKhalilgibran

Offline
Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

5/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Top

Loginorregistertopostcomments
#10

Sun,2005050814:18

PhilipJonker

TherbidsomespaceforNapoleonhere,aswellasEinsteinqndrsuntsu

Offline
Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

Top

Loginorregistertopostcomments
#11

Sun,2005050814:13

PhilipJonker
Offline

hi
Andrew,thefunhasbegunmletthemprovethereisnoroomforpragmatibmonthesite
regards

Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

6/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Top

Loginorregistertopostcomments
#12

Sun,2005050808:30

Andrew
Flowerdew
Offline

Smallclarificationonlastpost
Iftheassumptionswerereasonableandapparentlypossible,givenwhatwasknownatthe
time........

Joined:14Dec2004
Posts:958
Groups:GPCUnited
Kingdom

Top

Loginorregistertopostcomments
#13

Sun,2005050808:25

Andrew
Flowerdew
Offline
Joined:14Dec2004
Posts:958
Groups:GPCUnited
Kingdom

Hiall,
Withoutknowingthedetailitishardtojudgeoradvisebutiftheoriginallogicassuptions
madewerereasonableandpossibleATTHETIMETHEYWEREMADEthenthecontractor
probablyhasastrongcase.Ifso,followPhilipsadvice,siteveryoneroundatableanddoa
deal.
Itsoftendifficultwithhindsight,nowknowingallthefacts,totakeyourselfbackintimeto
whenthecontractbeganandthinkofwhatwasorwhatwasnotknownatthetime,butthat
isyourstartingpoint.

Top

Loginorregistertopostcomments
#14

Sun,2005050804:07

JohnHerbert

hi,

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

7/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Offline
Joined:14Feb2005
Posts:4
Groups:Building
Services/E&M,GPC
HongKong

FromtheOPandclarificationitseemsthatthecriticalissueistheunforeseen
delay/sequencingerrorandhowdoesoneassessthatwiththebenefitofhindsight?
Allpartiesviewedtheprogrammeanddidntspottheproblem,thereforeitisreasonableto
believethatthecontractualviewmentionedbelowiswellsupported.
Assumimgtheworst,i.e.goingtocourt,onecouldbegintheassessmentfromthe"oversight
point",howeverasyoupointedoutitwouldmostlikelybenefitthecontractor,andinmyview
rightlyso.
Assumingabaselinebeforetheoversightwouldnotbeadvisedinmyview,fromthe
contractorsviewonecouldeasilyrestatethatthesequenceproblem(includingCPactivities)
wereonlyuncoveredatalatestage,andunforeseenbyallparties.Iguessthatnobody
stoodupatthatpointanddiscussedwiththecontractorforthecostimplicationtoaccelerate
theworkstomeetthedeadline.
.......justmy2cents
cheers,

Top

Loginorregistertopostcomments
#15

Fri,2005050612:33

PhilipJonker
Offline
Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

HiAndrew,goodtoseeyouarestillaround.
HiNeil,
SomethingImissed,inyourfitstpostthefirstsentence,therewasathread,"Asbuiltcritical
path",Ithoughtyouwereawareof.Obviouslynot,asypuhavenotreferredtoit.Thereis
someinterestingreading,probablythelongestthreadtohaverunonthePPsite,maybe
somebodycancomment?
Thepointisletsbepractical/pragmatic,andgoadifferentroute,whichthe"legaleagle
planners"seemtoavoid,astheirincomederivesfromthere,andtalktoeachotherie
client/contractor/middleiman,andresolvetheissuesinacivilisedmanner.Admitour
shortcomingwhicheversideofthefencewesit.Ifyoumakeamistakeadmittoit,andfixit.
Ihaveoverthirtyyearsexperience,andIstillhavenotlearnteverything.Youprobablyneed
thirtypeoplewiththirtyyears,andyoumightgettohaveabasicunderstandingof
everything.Foreveryactivitywedotheremightbe10+methods,sowhoarewetocriticise
somebodyelseslogic,unlesswehavetwentyexperiencedpeople,andthenthejokeis
somebodycanthinkupabettermethod.
Regards

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

8/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Philip
Top

Loginorregistertopostcomments
#16

Fri,2005050608:27

Andrew
Flowerdew
Offline
Joined:14Dec2004
Posts:958
Groups:GPCUnited
Kingdom

Niel,
BothPhilipandAdrianssuggestionshavemanyvalidpoints.Althoughyouobviouslywishto
minimiseyourworkcontentbutwedonotknowthevalueoftheclaimandhencehowmuch
effortthecontractormaythinkitsworthspendingontheclaiminordertopersueit.Itmay
besubstantialandhencehemaywishtospendconsiderabletime(andmoney)onitifhe
believesitwillhelphiscase.
Oneofthequestionsthatneedstobeaskediswhythecontractor(andpossiblyothers)
thoughttheoriginallogicwascorrectandwhysubsequentlyitwasfoundtobewrong.The
legalphrase"whatwasoroughttohavebeeninthecontemplationofbothpartiesatthetime
ofmakingthecontract"isfundamentaltocontractlawandprobablyhasadirectbearingtoall
orpartofwhatyouareconsidering.
Iknowthisdoesnthelpyoupickananalysismethodbutdontshootyourselfinthefootby
choosingamethodbasedonwhatwillsaveyourselfwork.Itmightcostyou(ormorelikely
yourclient)alotinthelongrun.

Top

Loginorregistertopostcomments
#17

Fri,2005050608:05

JoshiNiraj
Offline
Joined:12Feb2005
Posts:27
Groups:Building
Services/E&M,GPC
UnitedArabEmirates

Jonker
IfthesaidchangescorporateinthebaselineschedulewithmutualunderstandingasTait
explainedthenwherejeopardisego?

Top

Loginorregistertopostcomments
#18

Fri,2005050604:37

PhilipJonker

HiNeil,

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

9/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

Offline
Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

Ihavebeenonbothsidesofthefenceinclaims,andevenasacontractor,Iwouldsaythat
makingchangestoanapprovedprogrammewouldjeopardiseyourowncase.
Regards
Philip

Top

Loginorregistertopostcomments
#19

Fri,2005050604:16

NeilTait
Offline
Joined:31Jan2001
Posts:29
Groups:GPCUnited
ArabEmirates

Philip&Adrian,
Thanksforthetimeyouhavetakeninreplying.
Philip,contrarytoyourstatementtheprogrammewasntsuspecttobeginIdidsaythat"...it
wassubsequentlycleartoallpartiesasworkprogressedthattherewerevarioussequencing
errors...".Otherwise,yoursteadfastpositiongetsthethumbsupfromcertainquartersofthe
office.
InthisinstanceIrecognisetheneedforanassessmentthatneitherpenalisesnorbenefitsthe
contractorinanunfairmanner.Myconcernwasthatbyadoptingacorrectedbaselinethis
wouldbenefitthemunfairly.Howeverlikewise,itisevidentthatbystickingwithabaseline
thatcontainserrorstheymaywell(will)beunfairlypenalisedasitwouldyieldcertainevents,
thatdidhaveanevident(asbuilt)criticalimpact,asbeingnoncritical.
ThealternativeanalysistechniquessuggestedbyAdrianarewelcomeandIsuspectofferthe
solution.Mypreferencefortheasplannedimpactedtechniquestemsfromitssimplicityand
theavoidanceofhavingtobuildanasbuiltprogrammecompletewithasbuiltlogic,as
opposedtojustasbuiltdates.
Onceagain,thanksforyourfeedbackandsuggestions.
Regards

Top

Loginorregistertopostcomments

Fri,2005050602:34

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

#20
10/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

AdrianArcher
Offline
Joined:26Nov2002
Posts:10
Groups:PetroChem
/Oil&Gas

DearNeil,
Fromwhatyoudescribe,Iseeanumberofpossiblewaysforyoutoproceed.Forgivemeif
ImtoolongwindedindescribingthedifferenttechniquesbutIdontknowatexactlywhat
leveltopitchmysuggestions.
Itisntuncommonforeitherpartytoadisputetointroducea"corrected"baselinebyone
partytoadispute.Theoutcomesyoudescribesoundterriblyfamiliarthe"corrected"
baselineneverexistedduringthecurrencyoftheworksandwashenceneverfollowedthe
"corrected"criticalpathscouldbeprejudicialtoonesideortheotherargumentsover
reprogrammingtoovercometheimpracticalaswellastheimpossible.
YoullnotethatIkeepputting"corrected"ininvertedcommas.Thatsbecauseonemustbe
mindfulthatnoprogrammecaneverforecasttheworkswithcompleteaccuracyand,assuch,
itcanneverbe"correct."Besttreatanyclaimofpossessinga"correct"or"corrected
baseline"withoutrightcynicism.
Iwouldntworryabouttheprogrammebeing"approved."Fromwhatyouvedescribed,the
contractencouragesupdatesandrevisionsandevennowyourContractorwantsto"correct"
it.Therearealmostnocontractformsthattreattheprogrammeasanimmutable,contract
document.Ifbothpartiesnowagreetochangetheprogramme,sobeit.
Iunderstandyoureadoptingthe"asplannedimpacted"technique.Thistechniquehowever
assumesthatthatoriginalbaselineisrelevantandafairrepresentationoftheworksfortheir
entireduration.Thisisfineforsimpleprogrammesofadozenactivitiesorsobutyour2,000
activityprogrammehasgrownwellbeyondthelimitsofthistechnique.
Youfeartheriskthatconcurrentactivitieswillberesequencedundera"corrected"baseline.
Thisisinevitableonalargeprogrammeanycorrectionswillshiftwholetrainsofactivities
pasteachother.Imremindedofamediationinwhichtheothersidesexpert,insistingonthe
"asplannedimpacted"model,hadtotrytoexplaintothemediatorwhyasingleadverse
weathereventwasimpactedonadozendifferentactivitypathsandonadozendifferent
days,notoneofwhichmatchedtheactualdateoftheevent!
Itispossibletostudytheworkswithan"asplannedimpacted"modelbutyouwouldneedto
treateverysingledeviationfromtheoriginalbaselineasaneventforimpacting.Thatisthe
onlywaytoensurethatasinglebaselineprogrammecanrepresenttheworksfortheentire
durationoftheworksbutIwouldntwishthatonanyone.Imthinkingyourprogramme
simplysoundstoobigtohandlean"asplannedimpacted"analysis.
Youcanhoweveravoidtheproblemsofforcingonebaselineprogramme,originalor
"corrected,"torepresenttheworksforalloftheworksandthatstotryadifferent
technique.
Themostinterestingandfrustratingthingaboutretrospectivedelayanalysisisthe

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

11/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

explosioninthenumberoftechniquesthatbecomeavailableuponcompletionoftheworks.
Nowthatyourprojectisnearcompletion,youhavetheoriginalbaselineprogrammeandthe
asbuiltprogramme,whichIthinkgivesyouallthereasonsyouneedwhytheoriginal
baselinecantbemadetoapplytoalltheworksforalltheirduration,"corrected"or
otherwise.
Therearetwotechniquesthatcanhelpavoidargumentsoverthebaseline"asbuiltbutfor"
and"timeslice."Bothhoweveropenupdifferentgroundsfordisagreementbetweenthe
partiesindisputeitseemsitsuptoyoutodecidewhichargumentsareworthhaving!
"Asbuiltbutfor"
Thistechniquehassolidsupportfromthecourts.A"live"asbuiltprogrammeisconstructed
that,withverifiablelogic,holdsalltheactivitiesonthedatesthattheyoccurred.Activitiesthat
representtheeventsareexcisedfromtheprogrammetoseewherethecompletiondates
wouldfallwereitnotfortheeventinquestioni.e.,theworkswouldhavefinishedxdays
earlierbutforsuchandsuchevent.
Yourasbuiltrecordsneedtobemorethantheactivitiesasbuiltstartandfinishdates.Youll
alsoneedrecordsthatcanconveyhowtheactivitieswerelinked.Forexample,did"FRP
Mezzanine"drive"FRP1/F"withastarttostartlinkplusalagorafinishtofinishlinkplusa
lag?Ifthereisaneventbetweentheseactivitiesthenthechoiceoflinksmayinfluencethe
eventsimpactontheworks.
Yousaidyouhaveanasbuiltcriticalpathsoyoumightalreadybehalfwaythere.Becareful
thoughsomesoftwareproducesasbuiltcriticalpathsonlybecausetheycanthandleas
builtdatesproperlyandkeepthem"live."Finishedactivitiescanthenaffectfutureactivities
from"beyondthegrave."
Italsohelpsifyourcontracttermsaresympathetictoassessmentofactualdelaysto
completion.Moststandardformssaysomethinglike,"islikelytocauseorhascauseddelayto
completion,"whichisconsistentwiththe"asbuiltbutfor"technique,soyoureprobablyOK
there.
Youhaventmentionedanydisputesoveraccelerationbutthe"asbuiltbutfor"techniquecan
calculatethisaswell.Theeffectsofclaimedaccelerationcanbetestedbyaddinginactivities
thatextendtheprogramme:i.e.,"wewouldhavefinishedmuchlaterbutforallthis
wonderfulacceleration."
Disputesoverthistechniqueusuallyarisefromthechoiceoflogictodrivetheasbuilt
programme.Itsapopulartechniqueformanyreasonsbutprincipallyitsgroundedinfact.
Eventscanbeimpactedontheactualdaystheyoccurredandtheprogrammeisverifiable
fromthesiterecords.Yougenerallydontneedtheoriginal,dysfunctionalbaselineand
thereforeyoucertainlydontneedtotryto"correct"it.

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

12/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

"Timeslice"
ThistechniqueisthedarlingoftheSCLprotocolandderigueurfortheUScourts.Itsthe
mosttimeconsumingtechniquebutgivesthemostfaithfulrenditionoftheworksasthey
progressed,withoutthebenefitofthepartiessometimesprejudicedhindsight.
AndtheContractorgetsto"correct"thebaselinesortof.
Inshort,eacheventisimpactedontoaprogrammethatrepresentsthestatusoftheworks
whenthateventbecameapparent.Eachupdateshouldincludealltheasbuiltdatapriorto
theeventandanydocumentedprogrammerevisionsknowntothepartiespriortotheevent.
Yousaidthattheoriginalbaselinewasshownuptobeunworkableandthisiswhythe
Contractorwantstocorrectit.Ifyouadoptthe"timeslice"methodthentheoriginalbaseline
canberevisedor"corrected"progressively,aseachprogrammingproblembecame
apparent.
Iunderstandyourcontractsupportsupdatingandrevisingtheprogramme.Also,your
Contractorwantstoreworkthebaselineandtheycanjustaslongastheycorrectit
progressivelyaseachprogrammingproblembecameapparentandnotinonealmightyhit,
liketheir"corrected"baselineseekstodo.
Disputesoverthistechniqueusuallyarisefromwhentoimpacteventsandwhentorevisethe
everdevelopingbaselineprogramme.Forexample,iftheContractorclaimsadelayin
receivingasubcontractornominationfromtheEmployer,shouldtheeventbeimpactedonthe
originalprogrammeddateimpactedsuccessivelyuntilthenominationisreceivedoronthe
actualnominationdate?SomejurorsalsogetshirtyaboutcalculatingEOTsonalikelydelay
toprogressinsteadofanactualdelaytocompletion,sometimesaskingwhetheraContractor
actuallyneededtheEOTinhindsight.
Imthinkingyoumightneedtoopenbothsidesuptothepossibilityofadoptingadifferent
techniqueandthenperhapsweighingupwhichargumentsareworthhavingwithyour
Contractor:debateovera"corrected"baselinethatneveractuallyexistedduringtheworks
debateoverthe"asbuilt"logicthatactuallydrovecompletionordebatingwhetheryoucan
barhindsightfromtheanalysisentirelyand"correct"theprogrammeprogressivelyinstead.
Sorryforbeingsoprolixbutgoodluck!

Kindregards,
AdrianArcher.
PickavanceConsultingLimited
Top

Loginorregistertopostcomments

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

13/14

5/7/2015

Correctedbaselineprogrammefordelayanalysis|ProjectControlsplanning,scheduling,costmanagementandforensicanalysis(PlanningPlanet)

#21

Fri,2005050601:44

PhilipJonker
Offline
Joined:7Nov2004
Posts:852
Groups:GPCSouth
Africa,Railway
Construction

HiNeil,
Idonotbelieveinthesocalledasbuiltcriticalpath,norinclaimingwithaprogrammethatis
fixedintheasbuiltstage.Theerrorsshouldhavebeencorrectedproactively,iebeforethe
activitiestookplace,asarevision.AsIunderstandittheprogrammewasapproved,andas
suchshouldformthebasisforaclaim,withoutanyalterations,despitethefactitwassuspect
tobeginwith.IthinkthepointhereisthatitshouldneverhavebeenApproved
Regards

Top

Loginorregistertopostcomments
#22

Thu,2005050522:11

NeilTait
Offline
Joined:31Jan2001
Posts:29
Groups:GPCUnited
ArabEmirates

Top

Mmm,afewdayswithnoresponseImdisappointedatthelackofresponse,butinterpret
thisasmeaninganyoneorcombinationofthefollowing:thosewithexperienceareeitheron
holidayornotreadingthisforumand/orsuchpractiseisuncommonandnotindustry
standard.
Stillinterestedinpersonalexperienceorpointsofreferencerelatedtotheacceptabilityof
correctionstothebaselineprogramme.

Loginorregistertopostcomments

WebsiteDevelopmentbyHuntDataSolutionsandVitalInteractive.CMS:DrupalTHEME:AcquiaMarina

http://www.planningplanet.com/forums/forensicclaimsanalysis/412815/correctedbaselineprogrammedelayanalysis

14/14

Вам также может понравиться