NORTHERN RAILWAY

No. NR/KRCL/ORH/140515
Office of the
Date: 14.05.2015
AXEN/C/CHENAB
SEN (CIVIL)/Chenab,
KRCL, Kauri.
Sub: Left over works and points raised regarding
Officers Rest House by CE/North/Northern Railway
during design team visit dated 13/04/2015.
Under reference the subject matter, it is submitted that the
several shortcomings and defects were found in the newly
constructed Officers Rest House which were raised by the
CE/North/Northern
Railway
during
design
team
visit.
Shortcomings and defects are as under:

ROOM
1

ROOM
2

Fixing of curtain rods for doors


ii) Fixing of net over exhaust fan to avoid insects.
iii) Latches (Kundi) installation of the bathroom ventilation & window
NO
panels
iv) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.
Paint and Putty splashes on floors and walls of the room and
bathroom.
ii)
Elimination
of the gap between window shutter and window frame.
NO
iii) Fixing of net over exhaust fan to avoid insects.
iv) Latches (Kundi) installation of the bathroom ventilation & window
panels
v) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children..
vi) Fixing of curtain rods for doors

Fixing of net over exhaust fan to avoid insects.


Latches (Kundi) installation of the bathroom ventilation & window
panels
NO
iii) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.
iv) Fixing of curtain rods for door.
v) Bathroom taps leakage
ii)

ROOM
3

ROOM
4

ROOM
5

ROOM
6

i) Paint and Putty splashes on floors and walls of the room and
bathroom.
ii)
Elimination
of the gap between window shutter and window frame.
NO
iii)Fixing of net over exhaust fan to avoid insects.
iv)Latches (Kundi) installation of the bathroom ventilation & window
panels
v) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.
vi)Fixing of curtain rods for doors.
i) Paint and Putty splashes on floors and walls of the room and
bathroom.
ii)
Elimination
of the gap between window shutter and window frame.
NO
iii)Fixing of net over exhaust fan to avoid insects.
iv)Latches (Kundi) installation of the bathroom ventilation & window
panels
v) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.
vi)Fixing of curtain rods for doors.
vii)
Installation of grill in window frame
viii)
Leakage of WC flushing system
i) Paint and Putty splashes on floors and walls of the room and
bathroom.
ii)
Elimination
of the gap between window shutter and window frame.
NO
iii)Fixing of net over exhaust fan to avoid insects.
iv)Latches (Kundi) installation of the bathroom ventilation & window
panels
v) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.
vi)Fixing of curtain rods for doors.

ROOM
7

NOi) Fixing of curtain rods for doors.

ROOM
8

NOi) Fixing of curtain rods for doors

ii) Elimination of the gap between window shutter and window frame.
iii)Fixing of net over exhaust fan to avoid insects.
iv)Latches (Kundi) installation of the bathroom ventilation & window
panels
v) Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.
vi)Bathroom taps leakage.
ii) Fixing of net over exhaust fan to avoid insects.
iii)Latches (Kundi) installation of the bathroom ventilation & window
panels
iv)Latches (Kundi) installation at the middle of the bathroom door panels
for easy access to children.

It is requested that the above mention issues shall be fixed at


the earliest.

(Manish Kumar)
SSE/Works /Chenab
Northern Railway