ACKNOWLEDGEMENT
TABLE OF CONTENTS
Table of Contents
Airport Express Metro Link, Delhi __________________________________________________
0 Project Objectives __________________________________________________________________
1
Overview ________________________________________________________________________
1
Project
___________________________________________________________________
lifecycle
1
Cost
____________________________________________________________________________
Time ____________________________________________________________________________ 3
Performance _____________________________________________________________________ 3
Project Planning ____________________________________________________________________ 4
Project Manager __________________________________________________________________ 4
Work Breakdown Structure __________________________________________________________
5
Budgeting and Cost Estimation ________________________________________________________
6 Scheduling
________________________________________________________________________ 8
PERT/CPM _______________________________________________________________________
8 Slack Calculation __________________________________________________________________
9 Crashing ________________________________________________________________________
10
Project Monitoring and Control_______________________________________________________ 12
Challenges Faced _________________________________________________________________ 1 2
Responsibilty Divison ______________________________________________________________
12 Responsibilty Matrix
______________________________________________________________ 13
PROJECT OBJECTIVES
Project Objectives
Delhi Airport Metro Express will deliver a safe, swift, reliable and eco-friendly mode of
transport between Central Delhi and IGI Airport. Our services will be consistent, easy to use
and will recognize the diversity of our customers. We will achieve this by engaging the best
people who will be trained, managed and developed to the highest standards.
OVERVIEW
The project has been implemented on a Public Private Partnership (PPP) model by Delhi
Airport Metro Express Private Limited (DAMEPL). DAMEPL is a Special Purpose Vehicle (SPV)
to develop, operate and maintain the Delhi Airport Express Line (DAMEL). The Delhi Airport
Express shareholders are Reliance Infrastructure Limited, and Construcciones y Auxiliar de
Ferrocarriles, S.A. (CAF) of Spain with 95% and 5% stake respectively.
Reliance Infrastructure Limited led consortium has been selected through the process of
international competitive bidding to undertake the implementation of this prestigious project.
The Concessionaire is executing the entire project except the civil works for viaduct, tunnel
and stations, which has been done by DMRC.
PROJECT LIFECYCLE
Dec 7 2009
Delhi Airport metro express line to be mapped onto GIS
Apr 18 2010
Jan 07-09 2011 Commissioner for Metro Rail Safety (CMRS) inspects Airport metro express
Page 1
PROJECT OBJECTIVES
Line---no faults found---DMRC happy with the 2-day inspection
Jan 13 2011
Page 2
PROJECT OBJECTIVES
Aug 16 2011 All six stations open, Airport metro now fully functional
Aug 19 2011 Airport metro launches new card for infrequent travelers
Aug 22 2011 Now, Airport Metro train service every 15 minutes
Sep 14 2011 Free feeder bus service for airport metro
Sep 20 2011 Commuters can now buy tokens with credit cards and debit cards
Nov 14 2011 Water Seepage disrupts Airport Metro
Dec 15 2011 Speed trial of Airport Metro Express
Jan 14 2012 Wi-Fi introduced in Airport Metro Express
COST
The total cost estimated to bind this project was Rs.57 billion of which Rs.28.85 billion was
paid by Reliance infra. After crossing the deadline given cost of Rs.7.5 billion were spent extra
every day.
TIME
The project was completed in 39 months but the estimated time was 35 months. The project
was initially launched on February 23
rd
the metro started working within a few days due to some problems like no baggage trolleys
for heavy luggage, it was delayed for 4 months and was re launched later.
PERFORMANCE
After re inaugurating it, it worked for 4yrs and 3 month straight after which due to the cracks
in the bridges because of the irrelevant speed of the metro the project was again stopped
for some time.
Page 3
PROJECT PLANNING
Project Planning
PROJECT MANAGER
Three major questions face the project manager:
1. What needs to be done?
2. When must it be done?
3. How are the resources required to do this job going to be obtained?
Project manager is responsible for organizing, staffing, budgeting, directing, planning, and
controlling the project.
Mr. Anil Ambani, Founder of Reliance Infrastructure took up the task of Airport Express Line
proposed by DMRC with great enthusiasm. He decided that he will be the Project Manager for
this Product. He has gone through many sleepless nights; He reunited his best team to form
an excellent product. Project manager taking the complete responsibility for this project
turned this project into a lifetime achievement.
Project Manager generated a Task sheet with a complete Timeline and how these
things should be done.
Page 4
PROJECT PLANNING
WORK BREAKDOWN STRUCTURE
Page 5
Page 6
The total cost of the project exceeded the budget allocated and also due to several
miss-happening and rebuilding done, the total cost of the project kept increasing.
With the current fare reliance is expected to recover his investment with the time coming.
Reoccurring costs were the reason why the project exceeded budget.
SCHEDULING
Scheduling
PERT/CPM
Activities
1.
2.
3.
4.
5.
6.
7.
8.
9.
Time
Star
Activity no.
1
2
3
4
5
6
7
8
9
Critical Path
Page 8
Predecessor
1
2
3
2
5
4,6
7
8
Early start
0
9
16
21
16
19
26
28
33
1-2-3-4-7-8-9
9 months
7 months
5 months
5 months
3 months
6 months
2 months
5 months
6 months
End
Early finish
9
16
21
26
19
25
28
33
39
Late start
0
9
16
21
17
20
26
28
33
Late finish
9
16
21
26
20
26
28
33
39
Critical Time:
Slack
0
0
0
0
1
1
0
0
0
39 month
SCHEDULING
SLACK CALCULATION
Page 9
SCHEDULING
CRASHING
Activity
Normal time
Crash time
7
7
4
1
2
6
2
Normal
cost(billion)
4.5
6
2.86
6
3
5
2
Crash
cost(billion)
7
6
3.3
7.8
6
2
2
1
2
3
4
5
6
7
9
7
5
5
3
6
2
8
9
5
6
5
4
4.12
3.4
7.51
8.4
Page 10
Cc/month
1.25
15.47
5.76
11
-
0.40
SCHEDULING
Crashing Act 1 by 2 months and Act 9 by 2
months: New cost= 36.88 + (1.25*2) + (2.5*2)
= 44.38 billion
New critical time=39-2-2=35
months No change in critical path!
Crashing activity 3 by 1 month:
New cost=44.38 + (0.44*1)
=44.82 billion
New critical time=35-1=34 months
Same critical path! (Both paths equal)
Crashing Activity 5 by 1 month:
New cost=44.82+ (3*1)
Page 11
RESPONSIBILTY DIVISON
The team was divided into many parts:
Mr. Shah the sales department manager
Mrs. Neelima gautam construction manager
Mr. Abhinav Rana electricity department
Mrs. Anju Bhatnagar cost estimator
Mr. bhatiya quality engineer
And finally the project manager: Mr. Avinash Mukharjee
Page 12
RESPONSIBILTY MATRIX
Page 13