Annexure - 1

SCHEDULE OF RATES
SERVICE CONNECTION CHARGES FOR NEW OVERHEAD CONNECTION
Category
Proposed by MSEDCL $
Approved by MERC $$

Sr.
No.

a
b
c

SERVICE
CONNECTION
CHARGES

VARIABLE
CHARGES

SERVICE
CONNECTION
CHARGES

VARIABLE
CHARGES

Rs.

Rs.

Rs.

Rs.

500
790

15
20

500

NIL

1000

NIL

1030

30

1620

40

3170

130

2500

NIL

4790

210
6500

NIL

8950

420

12290

590
12000

NIL

L.T. Supply
Single Phase
For load upto 0.5 kW
For loads above 0.5 kW &
upto 5 kW
For loads above 5 kW &
upto 10 kW

Three Phase
Motive power upto 7 HP or
other loads upto 5 kW
Motive power above 7HP but
upto 21 HP or for other loads
above 5 kW but upto 16 kW
Motive power above 21HP but
upto 67 HP or for other loads
above 16 kW but upto 50 kW
Motive power above 67HP but
upto 107 HP or for other loads
above 50 kW but upto 80 kW
Motive power above 107HP but
upto 200 HP or for other loads
above 80 kW but upto 150 kW
H.T. Supply

H.T supply upto 500 kVA

15000

H.T supply upto 1000 kVA

30000

20 per kVA for


excess load
above 1000 kVA

a
b

20 per kVA for


excess load
above 500 kVA
-

$ - As per Annexure-D of MSEDCL's response letter dated 10th April 2006.


$$ - As per Commission's order dated September 8, 2006 (Case No. 70 of 2005).

Note - i) In case MSEDCL permits an applicant to carry out the works through a LEC, a rate
of 1.30% of the normative charges will be applicable towards supervision charges.
ii) In case of extension of load, the normative charges will be applicable on the total
load (existing as well as additional load demanded) as per the load slabs indicated above.

36/40

Annexure-2
SCHEDULE OF RATES
Service Connection Charges for new Undergrond Connection
Sr. No.
Category
Proposed by
Approved by
MSEDCL (Rs.)
MERC (Rs.) *
(inclusive of material
1
L.T. Supply
COST OF MSEDCL)

a
b

a
b

2
a
b

Single Phase
For load upto 5 kW
For loads above 5 kW & upto 10kW
Three Phase
Motive power upto 27 HP or
other loads upto 20 kW
Motive power above 27HP but
upto 67 HP or for other loads
above 20 kW but upto 50 kW
Motive power above 67HP but
upto 134 HP or for other loads
above 50 kW but upto 100 Kw
Motive power above 134HP but
upto 201 HP or for other loads
above 100 kW but upto 150 kW
H.T. Supply
H.T supply upto 500 KVA
H.T supply above 500 kVA

150 #
300 #

500 for loads


upto10kW #
1500 for loads
above 10kW &
upto 50kW #
4500 for loads
above 50kW &
upto150 kW #

2000
4000

8000

14000

30000

45000

@
@

175000
195000

* - As per Commission's order dated September 8, 2006 (Case No. 70 of 2005). The normative rates
approved are inclusive of material cost.
# -MSEDCL has proposed normative charges with annotation that the consumer
is required to bring all service connection materials.
@ - MSEDCL has not proposed any charges for underground HT supply.
Note - i) In case MSEDCL permits an applicant to carry out the works through a LEC, a rate
of 1.30% of the normative charges will be applicable towards supervision charges.
ii) In case of extension of load, the normative charges will be applicable on the total
load (existing as well as additional load demanded) as per the load slabs indicated
above.

37/40

Annexure - 3
Cost of Meter and Meter Box**
( Applicable in case consumer opts to purchase the meter from
MSEDCL & in case of Lost & Burnt Meter)
Sr.
No.

Type
1
2
3
4
5

Single Phase Meter without box


Single Phase Meter with box
Three Phase Meter without box
Three Phase Meter with box
H.T. TOD Meter

Cost as proposed
by MSEDCL in Rs. *
700
1000
3110
3710
5227

Cost as approved
by MERC in Rs. @
700
NIL #
3110
NIL #
5227

( Applicable in case consumer opts to purchase the


metering cabinet/cubicle from MSEDCL)
6

C.T. operated metering cabinet


includung CTs, MCCB & meter
a) 50/5 A
b) 100/5 A
c) 150/5 A
d) 200/5 A
e) 250/5 A
H.T. Metering Cubicle including
C.T. & P.T.
a)11kV
b)22kV

22400
22400
22360
22360
22360

22400
22400
22360
22360
22360

67958
108731

67958
108731

** - All meters are required to be provided by MSEDCL at its own cost.


# - Metering box is to be provided by MSEDCL at its own cost.
* - As per Annexure-D9 of MSEDCL's response letter dated 10th April 2006.
@ - As per Commission's Order dated September 8, 2006 (Case No. 70 of 2005).

38/40

Annexure - 4
Sr. No.

5
6

MISCELLANEOUS & GENERAL CHARGES


Particulars
Proposed by $
MSEDCL (Rs.)
Installation Testing Fee
Low Tension Service
a) single phase
b) three phase
c) High Tension Service
Reconnection Charges
Low Tension Service at cutout :
a) single phase
b) three phase
At overhead mains :
a) single phase
b) three phase
At underground mains:
High Tension Supply :
Changing location of meter
within same premises at
consumers request
Testing of meters
a) single phase meter
b) polyphase meter/RKVAH meter
c) LTMD(with or without CTs)
d) Trivector meter
Replacement of meter card
for HT consumers
Penalty for Hormonics
variation above normal limit
of 3 %

Approved by $$
MERC (Rs.)

25
50

25
50

200

200

50
150

25
50

100
500
1000
5000

25
50
50
300

100

100 **

100
300
500
500
25

100
300
500
500
NIL

One percent of
monthly bill per
every one percent
of increase
Administrative charge for Cheque bouncing

Not approved #

Rs. 250/a) Upto Rs. 5 lakhs


Rs. 500/- per cheque
irrespective of
b) Above Rs. 5 lakhs
Rs. 1000/- per cheque
cheque amount
8
Temporory Supply Hiring of Meter Charges
a) Single Ph.
100/month
NIL
b) Three Ph.
250/month
NIL
# As the matter pertains to Tariff, the Commission in absence of any substantiated
proposal, does not accept proposed penal charges.
$ - As per Annexure-K of MSEDCL's response letter dated 10th April 2006.
$$ - As per Commission's order dated September 8, 2006 (Case No. 70 of 2005).

** - Inclusive of material, labour and all other costs etc.

39/40

Annexure - 5
Application Registration & Processing Charges
Sr. No.
Particulars
Proposed Rate ( Rs.) *
Rural
Urban

Approved by**
MERC (Rs.)

1 New connections/Change of name/


Reduction or Enhancementof Load/
Shifting of service/ Temporary
connection
a) Single phase

25

50

25

b) Three phase

100

100

50

c) LT(Agricultural)

50

50

50

d) HT supply upto 33 KV

1000

2000

1000

e) EHV Supply

5000

25000

2000

* - As per Annexure-L of MSEDCL's response letter dated 10th April 2006.


** - As per Commission's Order dated September 8, 2006 (Case No. 70 of 2005).