Вы находитесь на странице: 1из 18

Pearl GTL

Project

LINDE ENGINEERING

Shell Project No: HP-3000-QAT

Project Document Number: T-4.305.139

Purchase Order Number:

2MH127

Tag/Item Number(s):

0E-2091 A
0E-2091 B
0E-2091 C
0E-2091 D
0E-2091 E
0E-2091 F
0E-2091 G
0E-2091 H
0E-2091 J
0E-2091 K
0E-2091 L
0E-2091 M
0E-2091 N
0E-2091 P
0E-2091 R
0E-2091 T
0E-2091 U
0E-2091 V
0E-2091 W
0E-2091 X

Unit(s):

ASU

PCWBS:

Contractor Project No :

Project Rev.: O

0E-2092 A
0E-2092 B
0E-2092 C
0E-2092 D
0E-2092 E
0E-2092 F
0E-2094 A
0E-2094 B
0E-2094 C
0E-2094 D
0E-2094 E
0E-2094 F
0E-2094 G
0E-2094 H

Page 2

5887

QATAR SHELL GTL PROJECT (PEARL)


C2 AIR SEPARATION UNITS CONSTRUCTION

Issued for Company Comments

OD

MEY

AG

ICC

Issued for Review

OD

MEY

AG

IFR

Issued for Internal Review

OD

MEY

AG

IIR

GAMA
Rev.

Project
Rev

No.

No.

Date

Prepared Checked Approved


By
By
By

Description

Status

ORIGINATOR

Document Title:

METHOD STATEMENT NITROGEN FILLING,


CRYOGENIC VAPORIZER

LINDE ENGINEERING AG

Document No.

Contractor

Gama Qatar Co. W. L. L.

GAM

MTS

PRE

GTL

002

Org.
Code

Doc.
Type

Disc.
Code

Geogr.
Area

Seq.
No

Rev.
No

Project Document Number: T-4.305.139

LOC470
Vendor Code

Rev No.: O

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

TABLE OF CONTENTS
1

INTRODUCTION ____________________________________________________________________ 5
1.1
1.2

GENERAL ____________________________________________________________________ 5
SCOPE AND PRECAUTION _______________________________________________________ 5

HSSE ____________________________________________________________________________ 5

REFERENCES _____________________________________________________________________ 6

DEFINITIONS ______________________________________________________________________ 6

RESPONSIBILITIES _________________________________________________________________ 6
5.1
5.2
5.3
5.4

SITE MANAGER _______________________________________________________________


FSI MANAGER ________________________________________________________________
CLEANLINESS & PRESERVATION ENGINEER _________________________________________
LIFT SPECIALIST ______________________________________________________________

RESOURCES ______________________________________________________________________ 7
6.1

EQUIPMENT & MANPOWER _______________________________________________________ 7

6.1.1
6.1.2
7

EQUIPMENT________________________________________________________________ 7
MANPOWER _______________________________________________________________ 8

METHOD OF EXECUTION _____________________________________________________________ 8


7.1

PRE-COMMENCEMENT WORKS ____________________________________________________ 8

7.1.1
7.1.2
7.1.3
8

6
6
7
7

WORK PERMIT _____________________________________________________________ 8


TRAFFIC MANAGEMENT PLAN ________________________________________________ 8
EQUIPMENT AND PERSONNEL________________________________________________ 8

MEASURING AND FILLING PROCEDURE __________________________________________________ 8


8.1
8.2
8.3

GENERAL ____________________________________________________________________ 8
ASSEMBLY AND CHARGING ______________________________________________________ 9
DISASSEMBLY AND DELIVERY ____________________________________________________ 9

QUALITY ASSURANCE ______________________________________________________________ 10

10

ATTACHMENTS ___________________________________________________________________ 10
10.1
10.2

JOB SAFETY ANALYSIS ________________________________________________________ 10


TAGS AND SIGNS (SAMPLE) _____________________________________________________ 10

GAM-MTS-PRE-GTL-002

Page 4 of 10

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

1 INTRODUCTION
1.1 GENERAL
This document describes the methods proposed to be used for checking the pressure of and
filling with nitrogen (as required) of Cryogenic Vaporizer as part of the preservation activities at
ASU area that shall be carried out as part of ASU Construction works of Qatar Shell GTL Plant
(Pearl) in Ras Laffan Industrial City (RLIC) of Qatar including similar works up to the time of
commissioning.
The preservation shall be performed at ASU Area. The nitrogen filling and tagging activities
shall be carried out by GAMA QATAR in coordination with the Contractor.
All parties (LINDE Contractor, GAMA Logistics, Mechanical and FSI disciplines) involved
in the preservation of the Cryogenic Vaporizer will conduct minuted coordination meetings as
required.

1.2 SCOPE AND PRECAUTION


N2 (Nitrogen) is hazardous, especially in confined spaces. All measures will be taken prior to
start of operations.
During the work on and in the vicinity of open flange connections, care will be taken so that
dust and moisture can not get inside the equipment.
Nitrogen filling will be performed by the GAMAs Cleanliness and Preservation Engineer.
The methodology will be presented to the Contractor and will be approved prior to execution.
Wind intensity and velocity is to be taken into consideration. It is important in order to be able
to decide if certain works can be carried out safely.
Area influenced by the operation of the man-basket will be taken into consideration.
Competency of personnel to execute the works on the equipment will be assessed.
Availability and safety of man-basket, operator, hand-tools, measuring equipment, connectors,
hoses and the N2 Bottle will be ensured.

2 HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan
Industrial City and International standards, codes, LINDE ENGINEERING AG and QSGTL
and/or its PMC requirements and instructions.
In addition all employees and GAMA subcontractor employees on site will have gone through
GAMA Qatar Site Safety Induction, LINDE ENGINEERING AG Site Safety Induction and
QSGTL Safety induction for site safety, health, environmental and security prior to resuming
work activities at site. Other training courses (i.e. Working in Confined Spaces, Working at
Heights, etc.) will be attended as required by LINDE ENGINEERING AG or QSGTL and/or
PMC.
Risk Assessment will have been prepared by the Risk Assessment Team (RAT) ranking the
hazards associated with project works and control measures to be taken to mitigate the
hazards to an acceptable level.
Each scope work or task will have a completed and approved Job Safety Analysis (JSA)
GAM-MTS-PRE-GTL-002

Page 5 of 10

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

identifying the potential hazards and control measures that will be implemented to protect
people and environment.
The JSA (RA) will be used by Supervisor as the basis of conducting his daily TSTI meeting
and his weekly Tool Box Talk.
For additional safety requirements for a particular or specific task please refer to the JSA
prepared for that task.
All personnel will have PPE required for their specific tasks in addition to the minimum PPE
(coveralls, safety goggles, safety shoes, high-visibility vests, gloves) at site at all times as
required.

3 REFERENCES
T-4.233.760

T-4.233.891

T-13.376.921
T-13.377.539

:
:

Cryogenic Vaporizer Steam Heated-O2 Vaporizer and


Condensate Vessel
Cryogenic Vaporizer Air Heated N2 Vaporizer Preservation
Procedure
Preservation of New Equipment, Technical Specification
Flawless Start-up

4 DEFINITIONS
Company
Contractor
Sub Contractor
Contract
QCP
ITP
QA/QC
HSSE
JSA (RA)
FSI
CA

:
:
:
:
:
:
:
:
:
:
:

Package Unit

CV
ASU
MSDS

:
:
:

QSGTL and/or its PMC


Linde Engineering AG
GAMA QATAR Co. W.L.L.
QSGTL Pearl Project C2 ASU Construction Works
Quality Control Procedure
Inspection and Test Plan
Quality Assurance / Quality Control
Health, Safety, Security and Environmental
Job Safety Analysis (Risk Assessment)
Flawless Start-up Initiative
Construction Area
Major components assembled at the manufacturers plant e.g.
Linde Engineering AG
Cryogenic Vaporizer
Air Separation Unit
Material Safety Data Sheet

5 RESPONSIBILITIES
5.1 SITE MANAGER
The Site Manager will provide inputs to the project execution plan to ensure that strategies &
philosophy of the project are properly addressed.

5.2 FSI MANAGER


The FSI Manager is responsible for the overall management of the Preservation Team to
ensure that safe and effective operations are conducted and properly documented.

GAM-MTS-PRE-GTL-002

Page 6 of 10

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

5.3 CLEANLINESS & PRESERVATION ENGINEER


He will be overall responsible for planning and safe execution of the whole job including:
Organizing of equipments, material and tools needed for the job.
Confirming the preservation location.
Assigning skilled personnel for the job.
Conducting TSTI with the concerned work force prior to start of work.
Ensuring that relevant work permits and Method Statement for the job are obtained prior to
start of work and made available at site.
Conducting of activities to be carried out for the work in a safe manner as per this method
of statement.
Tagging of the vessel(s) and keeping the records. Records are auditable by Company.
Conduct inspection and surveillance.
Notify to Contractor engineer for inspection as applicable.
Ensure that all Contractor and Company regulations are followed.
Ensure that all personnel involved are in safe working condition at all times.

5.4 LIFT SPECIALIST


Shall be operating the man-basket (if and as required), to achieve a safe measuring and filling
of N2 gas in the Cryogenic Vaporizers.

6 RESOURCES
6.1 EQUIPMENT & MANPOWER
A list of equipment and manpower is given below.

6.1.1 EQUIPMENT
Manometer
T-piece
Hose
Gas Pressure Regulator
Atmospheric Monitoring Equipment
Nitrogen Bottle
Holding Clamps
Hand Tools
Full PPE and Safety Harness
Aerial Platform/ Manlift/ Man Basket

GAM-MTS-PRE-GTL-002

Page 7 of 10

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

6.1.2 MANPOWER
Site Manager
FSI Manager
Cleanliness & Preservation Engineer
Man-Basket Operator
HSSE Personnel
Helpers

7 METHOD OF EXECUTION
7.1 PRE-COMMENCEMENT WORKS
7.1.1 WORK PERMIT
The measuring of internal pressure and filling with Nitrogen gas of the Cryogenic
Vaporizer starts with the preparation of Method Statement and issuance of a Permit to
Work.

7.1.2 TRAFFIC MANAGEMENT PLAN


Area will be soft barricaded and secured.
Access road to operation area and enough space for movement of man-basket during
operation will be arranged and made available.

7.1.3 EQUIPMENT AND PERSONNEL


All equipment shall be inspected, tested and approved by the CONTRACTOR.
All equipment and tools shall be available at the site.
All personnel shall be inducted and trained before they commence work on site and
have sufficient knowledge.
All personnel shall be competent to execute all the works pertaining measuring N2
pressure and filling as required of Cryogenic Vaporizer.

8 MEASURING AND FILLING PROCEDURE


8.1 GENERAL
The Cryogenic Vaporizer is filled with N2 gas to avoid oxidation of internals and needs to be
kept at this state during storage and after erection up to the time of commissioning.
The N2 pressure will be checked at intervals of one month by the CONTRACTOR, and will be
refilled as required to achieve 0.5 bar internal pressure.
Observations will be properly recorded, and copies will be forwarded to COMPANY.
The vessel(s) (Cryogenic Vaporizer) and or the container will be tagged appropriately after
GAM-MTS-PRE-GTL-002

Page 8 of 10

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

each inspection and/ or refilling to reflect the status of preservation. (See Attachment-2 for
samples).

8.2 ASSEMBLY and CHARGING


Read the dials supplied on Cryogenic Vaporizer and record the readings.
If the readings are below 0.5 bar (50 kPa/ 7.25 psi/ 0.5 atm) fill as required.
Perform Gas Testing if the Cryogenic Vaporizer is in a confined space.
Adjust the filling nozzle to properly connect with filling equipment.
Position the N2 Bundle securely on ground.
Do not expose the N2 Bundle to direct sun-light for elongated durations.
Operate and position the man-lift so that the measuring and filling operation can be
performed safely and effectively.
Remove the plug on the Ball Valve on a suitable charging nozzle.
Attach the T-Piece on the Ball Valve.
Install the Manometer on one of the free ends of the T-Piece.
Connect the hose to the other end of the T-Piece.
Connect the other end of hose to the Isolation Valve. Ensure the Isolation Valve is at
closed position.
Connect the Isolation Valve to the Gas Pressure Regulator. Check that Gas Pressure
Regulator is at its lowest setting.
Connect the Gas Pressure Regulator to the N2 Cylinder .
Turn the Ball Valve (existing valve on the vessel) open.
Record the internal pressure displayed on the Manometer.
If it is less than 0.5 bar, open N2 Cylinder valve slowly to avoid pressure shock.
Increase output of the Gas Pressure Regulator to 0.5 bar. Turn the Isolation Valve
slowly to open position.
Check the Manometer to read 0.5 bar.
Turn the Isolation Valve off, when 0.5 bar is reached.
Turn the Ball Valve on the vessel off.

8.3 DISASSEMBLY and DELIVERY


Disconnect the T-Piece from the Ball Valve.
Plug the Ball Valve with the previously removed plug and use a gasket to ensure
tightness.
Dismantle the arm of the Ball Valve and using a duct tape attach on or near to the Ball
Valve to alleviate future operations.
Affix (if missing) an A4 size easily readable danger notice (supplied) on all sides of
the vessel or on to the door of container, as required to ensure visibility at both sides of
the vessel.
Affix (if missing) an A4 size easily readable warnings (supplied) on all sides of the
vessel or on to the door of container, as required to ensure visibility at both sides of the
vessel.
Affix (if missing) an 10cm X 10cm size easily visible safety signs (supplied) on all
sides of the vessel or on to the door of container, as required.
Store the N2 Bundle as instructed on MSDS.

GAM-MTS-PRE-GTL-002

Page 9 of 10

Doc. Title

Q A T A R

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Date/Rev. No :

9 QUALITY ASSURANCE
A Quality Assurance System shall be operated conforming to related standards.

10 ATTACHMENTS
10.1 JOB SAFETY ANALYSIS
10.2 TAGS and SIGNS (Sample)

GAM-MTS-PRE-GTL-002

Page 10 of 10

Q A T A R

JOB SAFETY ANALYSIS / RISK ASSESSMENT

JSA Number: T-4.305.139

NEW

Page No: 1 of 5

REVISED

Job being analysed: NITROGEN FILLING, MOLECULAR SIEVE ADSORBER


JSA Members: Mr. Oguz Baskoylu, Mr. Emre Yazc
Department/Section doing JSA: HSSE & Mechanical Dept.
Job Performers: Mr. Osman Davaslgil, Mr. Seyfettin Bayrak
Normal Approvals:
Name
Signature
Date
General job requirements / Common Personnal
Protective Equipment.
JSA by:

Job Supervisor:

Mr.Emre Yazc

23.09.2008

Mr. Osman Davaslgil

23.09.2008

Additional Approvals (Determined by Job Supervisor in correlation with LINDE HSSE Manager).
Name
Signature
Discipline Superindent(LINDE)
SHES Representative(LINDE)
OTHERS (List Below):

Date

1. The following Personal Protective Equipment


shall be worn while installing manbasket: Approved
coveralls, safety glasses, safety helmet, safety steel
toe shoes and gloves.

2. Permit To Work.

Approval required for hazardous work detailed in the LINDE work permit procedure.
Changing conditions and emergency procedures: Stop work. Switch of equipment.Supervisor directs personnel to nearest and safest muster point considering wind direction. Supervisor counts all employees. Missing
employees are reported to LINDE HSSE Dept. When all clear is given check with LINDE HSSE before returning to work.
LINDE EMERGENCY TELEPHONE NO.

HSSE MANAGER:
RLIC HOT LINE :

583 40 72
474 88 88

Note: 1) If any of the tasks involves biological, physical or chemical hazards, then The LINDE Industrial Hygienist must also approve the work.
2) Use additional sheets as necessary.
3) Details on safety (PPE,Hazard etc) and environmental requirements can be found in LINDE and shell Safety and Environment Procedures.

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T-4.305.139

JSA Number:
QT- 4.xxx.yyy
A T A

Q A T A R

Job Performers: Mr. Osman


Davaslgil, Mr. Seyfettin
Bayrak
ITE
M

ACTIVITY
Using of Manlift

HAZARD / POTENTIAL
CONSEQUENCES

1,1

Initial Risk

P C

CURRENT
CONTROLS

RISK
RANK

Mechanical Breakdown

Equipment shall be serviced


1.1.1.1
maintained and inspected as per set
maintenance and inspection program.

Ensure equipment to be provided


with controls of the dead man type,
which only allow movement of the
machine to take place whilst they
are actually being operated.

1.1.2

Ensure E-Stop is in place through the 1.1.1.2


control system.
Perform equipment daily check prior 1.1.1.3
to use.
Supervisor shall ensure that work will
be properly supervised as per work
method statement.

Dead man controls automatically


return to the neutral position.
Appropriate trained & certified
persons only to use equipment.

1.1.4

1.1.5
Improper use of
equipment

1.2.1

3 #####

ADDITIONAL
CONTROLS

1.1.1

## 3 ##### 1.1.3

1,2

SCOPE : METHOD STATEMENT FOR


NITROGEN FILLING, CRYOGENIC VAPORIZER

1.2.2
1.2.3

Ensure an emergency stop should be


provided on the platform control
panel.
Manlift shall not be used as cranes or 1.2.1.1
jacks unless they have specifically
been designed for this purpose by
their manufacturers.
Leaning out of the platform will not be 1.2.1.2
allowed.
Colour code sticker to be available on 1.2.1.3
the equipment.

Residual Risk

P C

3 #####

3 #####

Ensure equipment is inspected,


approved & colour coded as per
colour code chart.
Current inspection sticker must be
in place.

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T-4.305.139

JSA Number:
QT- 4.xxx.yyy
A T A

Q A T A R

Job Performers: Mr. Osman


Davaslgil, Mr. Seyfettin
Bayrak
ITE
M

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

1,3

Initial Risk

P C

CURRENT
CONTROLS

RISK
RANK

Untrained personnel

1.3.1

1.3.2
B

3 #####

## 3 ##### 1.3.3
1.3.4

1,4

Fall of personnel

1.4.1

SCOPE : METHOD STATEMENT FOR


NITROGEN FILLING, CRYOGENIC VAPORIZER

5 #####
1.4.2

Ensure platforms must only be used


by authorized personnel who have
been trained in the operation of the
type of platform in use.
Initial training should cover operating
principles, machine controls and
environmental conditions, which are
likely to be encountered.
Training and practice in this type of
work undertaken is essential.
Ensure that equipment operator is
certified by third party, valid
certificates.
Safety harness shall be provided for
the use of all personnel working from
mobile work platforms so that in the
event of any advertent movement of
the platform they are working from,
they will not be thrown from it.

ADDITIONAL
CONTROLS
1.3.1.1

1.4.1.1

Boxes, hop-ups or ladders will not be 1.4.1.2


used to gain additional height or reach
from the platform of manlift machine
work platform.

Residual Risk

P C

Ensure supervisor/foreman who


will be using the manlift should be
particularly aware of the hazards
which may be encountered whilst
using these machines and of the
precautions which may be taken to
eliminate or minimize the hazards. A

3 #####

3 #####

4 #####

Discuss working at height hazards


in TSTI.

Supervisor shall ensure that work


will be properly supervised at all
times as per work method
statement.

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T-4.305.139

JSA Number:
QT- 4.xxx.yyy
A T A

Q A T A R

Job Performers: Mr. Osman


Davaslgil, Mr. Seyfettin
Bayrak
ITE
M

ACTIVITY

HAZARD / POTENTIAL
CONSEQUENCES

1,5

Initial Risk

P C

CURRENT
CONTROLS

RISK
RANK

Overturning of Machine

Ensure no excessive force by the


operator on the platform by
introducing an element of side load.

1.5.2

The outriggers or stabilizers, when


1.5.1.2
fitted, shall be fully extended and in
position, before the platform or boom
is raised.
The platform shall not be overloaded 1.5.1.3
exceeding the regulated safe working
load.
Ensure the machine will be located to
the most suitable position for the job
to be carried out before any slewing
takes place.
Slewing of the boom to the extent that
causes the machine to overturn shall
be avoided.
Ensure all vehicle movement to be
guided by competent banks men with
high visibility vests.
Ensure that each piece of equipment
is fitted with an automatic reverse
alarm and beacon or strobe light.

4 ##### 1.5.3

1.5.4

1.5.5

1,6

Vehicle Movement

1.6.1

ADDITIONAL
CONTROLS

1.5.1

## 3 #####
B

SCOPE : METHOD STATEMENT FOR


NITROGEN FILLING, CRYOGENIC VAPORIZER

3 ##### 1.6.2

1.5.1.1

When a manlift needs work in a


congested area, an approval for
the operation shall be obtained
from HSSE dept of Gama/Linde
authorized personnel's.
Considering the effects of the
acceleration and deceleration of
the manlift.
Discuss in TSTI.

Residual Risk

P C

3 #####

4 #####

3 #####

JOB SAFETY ANALYSIS / RISK ASSESSMENT


T-4.305.139

JSA Number:
QT- 4.xxx.yyy
A T A

Q A T A R

Job Performers: Mr. Osman


Davaslgil, Mr. Seyfettin
Bayrak
ITE
M

ACTIVITY
Transportation of
nitrogen bottle

HAZARD / POTENTIAL
CONSEQUENCES

2,1

Initial Risk

P C

Moving of the
nitrogen bottle to the
"filling position" via
man-lift

RANK

2.1.1
A

CURRENT
CONTROLS

RISK

Damaging of cylinder
4 #####

3,1 Dropped bottle

3.1.1
##
C 3
5 #####
#####
3.1.2

Nitrogen filling

4,1

Dropped tools

4,2

Gas Leakage

4,3

Inhaling nitrogen

4.1.1
A

4 #####

4 #####

B
4,3

Handling pressurized
equipment

ADDITIONAL
CONTROLS

Ensure the bottle is securly tied to the 2.1.1.1


vehicle.
2.1.1.2

Ensure that the nitrogen bottle is tied 3.1.1.1


to the basket rails of the man-lift using
metal or plastic clamps.
Barricade and secure the working
area with sign boards to prevent
unauthorized entry.
Ensure that all hand tools are carried
in a tool box or attached to the
personnel.

Perform Gas Testing prior to start of


operation.
4,3,1 Ensure that the operation is carried
5 #####
out in a well ventilated area or out
doors.
4,4,1 Ensure that valve protection cap is in
place.

2 #####

SCOPE : METHOD STATEMENT FOR


NITROGEN FILLING, CRYOGENIC VAPORIZER

Ensure the driver is warned to


avoid abrubt manouvers.
Ensure that the people are
instructed to avoid to drop the
bottle while carrying.
Discuss in TSTI.

4.1.1.1

Install barricades "exclusion zone"


with sign boards indicating
nitrogen filling works in progress to
prevent unauthorized entry.

4.3.1.1

Install "INERT GAS WARNING"


signs, as necessary.

4.4.1.1

Remove protection cap only to


connect the bottle to the filling
point.
Use a check-valve.

Residual Risk

P C

4 #####

A
A

3
4 #####
#####

3 #####

4,2,1

Ensure the regulator is connected to 4.4.1.2


the bottle and operational.
Ensure that the bottle is kept under 50 4.4.1.3
degrees Celcius and not in elongated
direct contact with sunlight.
Ensure that the bottle valve is opened
slowly to avoid pressure shock.
Ensure backfeed is not allowed into
the bottle.

Isolate cylider (bottle) at cylinder


valve when not in use.

Doc. Title

Q A T A R
Date/Rev. No :

GAM-MTS-FSI-GTL-002 Rev. C
Method Statement Nitrogen Filling,
Cryogenic Vaporizer

Вам также может понравиться