Академический Документы
Профессиональный Документы
Культура Документы
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Rottal Burn
WFD Mitigation
measure
Waterbody ID
Designation
Description
The Rottal Burn has a steep catchment of 17.05km to its
confluence with the River South Esk. The final 1km of the
Rottal Burn between Rottal Lodge and its confluence with the
River South Esk was realigned and straightened soon after the
1830s. In this final reach the steep catchment meets the South
Esk glen. This reduces the gradient and results in deposition of
bed material. The bed of the channelized burn was continually
aggrading and sediment was sediment was being deposited at
the confluence with the River South Esk. In response, sand, gravel
and cobbles had been dredged and and used for agricultural
embankments (up to 2.2m above field level) to reduce the
frequency of flooding of the surrounding fields. In 2003, the
stretch was dredged again, destroying the existing habitat.
The River South Esk and its tributaries are designated for
Atlantic salmon (Salmo salar) and freshwater pearl mussel
(Margaritifera margaritifera). Although spawning habitat was
present in the burn, the lack of variation resulted in low numbers
of juvenile salmonids and any fry produced were often washed
out of the burn by spate flows. Working with the supportive
Click Here
to view details
5812
SAC
Project specific
Fish, Habitat,
monitoring
Macroinvertebrates, Plants,
Birds, Morphology
1.8
(page 1 of 5)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Design
1
Old channel
closure to be
reinforced using
root ball logs
B9
55
Up
ne
zo
r
pe
Figure 1.8.1
11kV
overhead
power line
New bund
using excess spoil
Existing channel
to be infilled
Small backwater
to be retained
Knoll
(high ground)
M
New bund
using excess
spoil
New
confluence
e
on
z
er
w
o
L
(M
id
on
ez
l
d
yg
sh
ar
ss
ra
lan
or
ist
ic
ali
nm
t)
en
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 5)
1.8
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Figure 1.8.2
Typical cross section showing a simple
approach to the channel design
Approximately11m
Approximately 0.3m
Approximately 1:3
Approximately
1m
K.MacDougall/Fraser Murdoch
1.8
(page 3 of 5)
Three panoramas showing the development of the middle reach 2011 to 2012
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
K.MacDougall
RRC
Substrate previously dredged from the burn and won from the
embankments was placed on the bed and banks of the newly
excavated channel to an approximate depth of 0.3m. The median
gravel size was 60mm with the range of material being fine
sand to large cobbles. In thirteen locations, additional gravel
was placed to a height of 0.3m above the surrounding design
substrate level (Figure 1.8.2). These locations were where features
were expected to occur and were intended as source material
for natural processes to use to shape the burn.
Fine silt and sand transportation from the site works into the
River South Esk was a major concern, with the rivers designation
for freshwater pearl mussel. Measures taken to mitigate this
included straw bale silt trapping and allowing time for vegetation
to establish before the new channel was connected.
By cutting the new channel through the low lying, rush dominated
wetland vegetation, very little vegetation establishment was
needed in this middle reach. Careful turf stripping, storage and
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 4 of 5)
1.8
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
1
Subsequent performance
The new channel was tested by a number of significant flow
events, including a large spate just 36 hours after being diverted.
This was followed in mid-October 2012 by one of the largest
floods in 10 years.
As predicted, the upper reach has been more morphologically
active, with new sediment supplying the formation of gravel bars.
There has been some local erosion which has allowed a greater
variety in channel width and depth to develop. In the middle
reach, sand and gravel bars have formed and connectivity
with the adjacent floodplain and wetland area has increased.
Erosion has varied significantly depending on the bank material
(peat, sand or gravel) showing that accurate prediction of
channel adjustment is hard to achieve, and that sufficient
space needs to be given to allow change to occur.
Bank erosion and channel adjustment are also leading to the
erosion of the new upper bund. The main area to be monitored
is close to the power lines. Should any stabilisation be necessary,
this would be achieved through addition of further woody
material.
K.MacDougall
RRC
Contacts
Marshall Halliday, Esk Rivers & Fisheries Trust
MMHVIENNAHORN@aol.com, 07769 655499
1.8
(page 5 of 5)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
1
1.9 Reconnecting a remnant meander
River Rother
River Rother
WFD Mitigation
measure
Waterbody ID
Click Here
to view details
GB107041012810
Description
Designation
Project specific
Fish, cross sections,
monitoring
fixed point photograpy,
water levels,
macroinvertebrates,
macrophytes
None
Key
Figure 1.9.1
Design diagram
Canal cut
Original course of
River Rother restored
1.9
(page 1 of 4)
Excavation omitted
along this bank section
to protect mature trees
Bridge abutments of
ancient towpath bridge
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
metres above local datum
8
7.5
7
6.5
6
5.5
5
4.5
4
-8.00
Key
Straight reach
Bend
-6.00
-4.00
-2.00
0.00
2.00
4.00
6.00
8.00
Design
The canal cut was never designed to carry the river flow so it
was decided to seal it off with an earth bund, just upstream of
the old lock. This mimicked the function of the old lock gates.
The entire river flow could then be diverted back into the
historic course around the loop.
The reference point for the channel restoration design was
a survey of the loop carried out in 2002. Additionally, the
narrowest cross sections of the main River Rother channel
were referenced against the cross sections collected from the
loop and compared with channel dimensions sized by a
geomorphologist.
The bank top width was determined by on-site observation of
two stone abutment walls from an ancient bridge that provided
a reliable representation of the historic channel width.
RRC
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
1.9
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
1
Expert judgement and field observation was supported by a
model to inform the more detailed channel design However it
was impractical to excavate the complex shapes optimised by
this model. Therefore the loop was excavated to one of two
basic cross-section designs, namely bend apices and straight
reaches, while points on the transition between them were
interpolated (see Figure 1.9.2). The bed level was set to reflect
existing conditions in the River Rother at each end of the loop
and to improve connectivity with the floodplain during high
flow events. A large scrape was excavated to create wading
bird habitat and to provide clay for construction of the bund.
In order to prevent undermining of the stone abutment walls
(which were of archaeological significance) at the downstream
confluence, sheet piling was driven down to bed level across
the river and a bed check created from a base layer of coarse
locally-sourced sandstone. At the entrance to the loop a ford
was created for farm traffic and to serve as another bed check.
It too was dressed with gravel to mimic a natural riffle.
A new gravel riffle was also constructed upstream of the site to
replace a riffle that had formed in the canal cut, which became
obsolete once the cut was sealed off. New gravels totalled
9,000, labour 13,000 and plant hire costs totalled 28,000.
The isolation of the canal cut left a long still water lagoon that
provides valuable off river wetland habitat, which helped to
achieve the overall biodiversity aims of the project. The old
RRC
Figure 1.9.3
Overlays from cross sectional surveys, (viewed downstream),
of loop section 4A, (see Figure 1.9.1),
illustrating post-construction channel adjustment.
Key
Design
2005
2006
2009
8
7.5
7
6.5
6
5.5
5
4.5
4
3.5
3
Right bank
Left bank
10
15
20
1.9
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
25
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
RRC
RRC
RRC
Subsequent performance
Virtually all of the initial bare banks had established a good
cover of vegetation two years post-construction (2006). Mature
woody vegetation retained during the project has contributed
woody material to the channel, and species diversity of the
floodplain has increased significantly, with many bird species
regularly utilising the newly created wetlands.
The fish community of the restored loop was consistent with
that of the wider Rother catchment. Higher than average
populations of bullhead (Ameiurus nebulosus), chub (Leuciscus
cephalus), brown trout (Salmo trutta), grayling (Thymallus thymallus),
sea trout (Trutta morpha trutta) and barbel (Barbus barbus)
have been observed. The stone bed check structures at the
upstream and downstream ends of the loop have acted as
spawning grounds for many of these fish species.
Monitoring of the site between 2002 and 2009 indicated a
positive performance of the technique. Changes were observed
in cross-sectional area (see Figure 1.9.3) suggesting a dominance
of erosion over deposition in the loop. There was no significant
(more than one metre) lateral channel change between autumn
2004 and a survey in 2006, but small-scale channel adjustment
has been widespread. Therefore it can be concluded that the
pre-restoration issue of sedimentation in the loop has been
resolved and that the newly-excavated channel is slowly adjusting
to a more natural, and desirable, form.
RRC
Contacts
(page 4 of 4)
1.9
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Braid Burn
WFD Mitigation
measure
Click Here
to view details
Waterbody ID
Designation
3500
UWS
Project specific
Figure 1.10.1
Planform of the Braid Burn through Inch Park
Flood bund
Description
The re-meandering of the Braid Burn at Inch Park was a small
component of a wider flood alleviation scheme promoted by
the City of Edinburgh Council, designed to protect against a
1 in 200 year flood, with additional allowance for climate change.
The scheme utilised the flood storage capacity within Inch Park
and so provided an opportunity to promote biodiversity and
create habitat along the river corridor. The site is an Urban Wildlife
Site (UWS) within the Edinburgh Urban Nature Conservation
Strategy and delivers parts of Edinburghs Local Biodiversity
Action Plan (BAP) 2010-2015.
Inch Park is a well used recreational resource within the city,
adjacent to a large shopping centre, residential properties and
a primary school. The park has a mix of mature woodland and
individual trees along with amenity grassland and is maintained
1.10
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Design
Approximately 80% of the restored course was newly dug and
20% was made up of the retained channel, the banks of which
were reprofiled.
None of the brick and concrete sections of the existing channel
were incorporated into the new design. These were all broken
down and in-filled. Densely graded rock (lumpstone) of 0.075m
to 0.3m was imported and used to form the riffles and shoals.
Gravels for the new channel were recovered and re-used from
the sections of the old course which were to be in-filled. It was
deemed that over time natural processes would transport
substrate, invertebrates and flora to the new sections of the
burn. The hydraulic conveyance of the new naturalised course
is at least as great as that of the lined channel, ensuring no
increase in flood risk upstream.
As a precautionary measure coir matting was pinned in place
along the channel margins and the first stage flood bund, to
help protect the clay and soil banks until vegetation established.
AECOM
Figure 1.10.2
New Braid Burn channel and reprofiled banks
Section AA (see Figure 1.10.1)
49.0
48.0
47.0
Temporary
bank protection
(coir matting)
Original ground level
46.0
45.0
Approximately 3.2m
Approximately 5.5m
AECOM
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
1.10
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
The gently sloped banks provide additional capacity and promote the
natural processes of sediment transport and vegetation colonisation
February 2009
AECOM
AECOM
Subsequent performance
Following the works the river corridor is significantly wider,
with a sinuous channel and more natural appearance. Riparian
vegetation has colonised the banks and wider corridor, which
now has a diversity of height, form and texture that was not
present prior to the works.
AECOM
1.10
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
The shoals around the meanders have trapped significant
quantities of fine silt during high water events and vegetation
has begun to colonise the sediment, disguising the lumpstone
structures. Gravel has been transported out of some parts of the
new meanders and replacement with gravel transported from
upstream has been slow. At one location a less dense lens of
sandy clay within the channel has eroded to form a small cascade
and pool.
Informal footpaths have developed along both banks of the
burn and are well used. Following the works the burn has
become an integral part of Inch Park that brings ecological,
aesthetic and recreational benefits to the area. In 2011 the
scheme won a commendation for environmentally sustainable
construction in the Saltire Societys Civil Engineering Awards.
The coir used to protect the first stage bund from erosion was
a fairly dense weave matting which prevented all but the most
vigorous species from penetrating. Natural colonisation of the
bund was therefore slow. Coir matting with a more open weave
would have allowed more rapid colonisation by a wider range
of species. The coir matting used along the immediate margins
of the burn worked as designed, quickly becoming covered
by sediment.
Environmental Impact Assessment (EIA) ecological surveys
(including bat, otter, badger and tree) were carried out before
works commenced in order to establish the potential impacts.
Routine inspection is carried out by the City of Edinburgh
Council to monitor on-going morphological processes and to
assess stability. This indicated that the new pool and cascade
were stable and as a result this feature was retained. Planting
within the meanders captures litter and other debris which
passes downstream during high flow events. It is periodically
necessary to clear this. Himalayan balsam has been noted
following the works and continued invasive species management
is being carried out.
The new course of the Braid Burn through Inch Park after two years. Marginal
vegetation has established well and natural processes have enhanced the
in-channel morphological features that were created May 2011
AECOM
Contacts
Peter Robinson, AECOM
(page 4 of 4)
1.10
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Highland Water
WFD Mitigation
measure
Waterbody ID
Click Here
to view details
GB107042016720
Designation
SSSI, SAC, SPA, Ramsar,
National Park
Description
Many rivers in the New Forest National Park were improved for
grazing by cutting straight drainage channels during the 1850s,
resulting in the abandonment of a network of historic woodland
streams. These new channels had steeper gradients leading to
down cutting and erosion of the underlying sands, gravels
and clays.
One example of this degradation is on Highland Water, a small
headwater sub-catchment (4.9km2) of the Lymington River. Prior
to restoration the channel was up to 1.2m deep and 4m wide
restricting the natural seasonal flooding of the surrounding forest.
The previously wet woodland and mire habitat had dried out
and the increased channel size presented a barrier to the freely
roaming forest animals.
1.11
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
Design
A35
Key
Works storage area
Site access tracks
Existing drainage course
Restored watercourse route
Public roads
Forest roads
The work was was carried out in the following stages (See
Figure 1.11.2):
Firstly, selected bankside trees on the existing channel were
felled in order to create access for machinery. This also had
benefits for landscape, aesthetics and ecology, as retaining a
straight line of trees would have looked out of place in the
forest environment.
Accumulated leaf litter and wood from the existing drainage
course was then carefully removed and retained for reuse on
site. In places a new channel was dug using an excavator, but
only where no obvious channel could be found. The creation
of idealised features was avoided, but some areas were more
extensively cleared to create deeper pools to maximise gains
for fish.
Gravels were transferred from the existing to the restored channel.
Flow was diverted from the existing to the restored channel, section
by section (See Figure 1.11.2) from one crossing point to the
next moving down the reach. Adopting this phased approach
enabled a controlled diversion of the flow into the new channel,
reducing the risk of initial channel instability occurring.
The existing drainage course was then in-filled using a mix of
8,000 tonnes of hoggin (as dug sand and gravel mix) and 800
tonnes of firm clay by-product, both sourced locally.
1. Selected bankside
trees felled
6. Fill finished proud to
deter surface water flow
re-opening channel
Brock Hill
Brinken
Wood
Great Huntley
Bank
Highland
Water
Poundhill
Inclosure
0
Blackwater
200
400m
Figure 1.11.1
Map showing plan of restoration works at Warwickslade
3. Gravels transferred
to the restored
channel
Pre-restoration
profile
Existing drainage
course
Restored
profile
Restored course
Figure 1.11.2
Stages of technique implementation
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
1.11
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
1
The clay was packed tightly at 10m intervals and at construction
crossing points to prevent seepage. The rest of the channel
length was then in-filled, with excavator movements helping
to compact the fill as they moved across the site.
Fill levels were finished slightly above the surrounding ground
level to deter any surface water channelling along the fill, which
had yet to settle. This could have led to re-opening of the
filled channel.
Dead wood was scattered across the site to aid the rapid recovery
of the landscape and stop the route becoming a straight path for
humans or grazing animals. Turfs removed from the existing
course were used to reinforce bends and cut-off points to
reduce the risk of erosion immediately post-construction.
Finally the soils, ferns and small plants which had to be removed
from the banks during construction were re-used to dress the
finished work across the project area.
Sketch design diagrams were developed to provide an overview
of the works. However, in this fragile habitat it was essential
that that the contractor was sensitive to the local conditions,
therefore most of the detailed project works decisions were
made using on-site expert judgement.
Alaska
1.11
RRC
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Restoring Meanders to
Straightened Rivers
The reduced in-channel capacity of the restored course raised
concerns about flooding onto the A35. A pool close to the road
was widened to reduce the flood risk in this location, which
would have caused major disruption.
An innovative tramway system was devised to enable materials
to be moved along the line of the channel, even during poor
weather, with no appreciable impact on the heavily designated
forest habitat.
Project costs comprised plant hire and labour (106,500),
and infill materials (108,000).
Subsequent performance
The newly restored channel has been left to develop naturally and
no post-construction adaptation has been necessary. A variety
of morphological features and in stream habitats have been
re-established and floodplain connection has been restored
through more regular bank overtopping. This has helped to re-wet
the surrounding woodland habitats. These enhancements have
been quantified by a recorded improvement in SSSI condition
scores for the area.
The use of high quality infill material was crucial to the success of
the scheme. At other locations where a similar technique had been
used the redundant channels had been in-filled with poor quality
material, which left them vulnerable to erosion and re-opening.
Alaska
Alaska
Alaska
Contacts
Will Bond, Alaska Environmental Contracting Ltd
info@alaska.ltd.uk, 01929 463301
(page 4 of 4)
1.11
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Enhancing Straightened
River Channels
River Somer
WFD Mitigation
measure
Waterbody ID
Designation
Click Here
to view details
GB109053022250
Project specific
monitoring
None
Habitat survey, fish,
invertebrates
Design
Description
The overall aim of this project was to improve an over-wide
and heavily silted reach of the River Somer running through
Midsomer Norton High Street. This involved removal of three
small weirs and constructing a new sinuous channel that had
sufficient morphological dynamics to remove the need for
regular de-silting, reducing maintenance costs and disturbance.
Project objectives included: constructing a sinuous channel
using local materials (including accumulated silt); providing
diverse habitat features for fish (especially wild brown trout
(Salmo trutta), plants and invertebrates native to the River Somer;
improving the aesthetics of the reach within the town centre;
increasing the opportunity for local people to encounter a
range of river wildlife; and involving the local community in
construction and long term maintenance.
The existing Midsomer Norton Flood Alleviation Scheme and
flood relief channel was exacerbating the build-up of sediment
by diverting higher flushing flows around the town centre
reach. However, this also presented an opportunity to create a
design which was not heavily constrained by flood risk concerns,
since the High Street typically only received local surface
floodwaters.
3.10
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Enhancing Straightened
River Channels
3
Downstream
culvert
Weir 1
removed
Riffle
Footbridge
Weir 2
removed
Figure 3.10.1
Plan view of new channel design
re
s
War memorial
Le
n
gt
16
7m
et
Footbridge
Figure 3.10.2
Cross section through riffle AA
Pool
Figure 3.10.3
Cross section through berm BB
0.9m
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
3.10
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Enhancing Straightened
River Channels
Silt is used to fill the marginal berms ready for planting 2011
Subsequent performance
In June 2012 the first formal post project assessment and
maintenance visit was carried out. This was to assess the condition
of the channel against the original project design and aspirations
in terms of ecology, aesthetics, resistance to flood flows, flow
patterns, siltation and routine maintenance by volunteers.
This assessment indicated that the berms were intact and in good
condition despite several high flow events. Plant communities
had matured well, providing a diverse marginal habitat.
Kick samples revealed that aquatic organism diversity has
3.10
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Enhancing Straightened
River Channels
Maintenance, carried out by volunteers from the Friends of
the River Somer group, has helped to keep the channel free of
litter and nuisance species such as buddleia (Buddleja davidii),
dock (Rumex hydrolapathum) and nettles (Urtica dioica).
Contacts
Luke Kozak, Woodland Water & Gardens
lukekozak@gmail.com, 07791 607969
dominiclongley@hotmail.co.uk, 07770803512
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 4 of 4)
3.10
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
4
4.8 Bank protection using root wads
River Dulais
River Dulais
WFD Mitigation
measure
Waterbody ID
Description
The River Dulais (Afon Dulais) is a tributary of the River Towy,
and is an important spawning habitat for migratory fish. The
river had a history of instability and planform adjustment,
with a channel cross section up to fifty per cent wider at this
location than upstream reaches. Unrestricted grazing, by
sheep and cattle, had resulted in a loss of bankside vegetation.
Figure 4.8.1
Plan showing position
Designation
Click Here
to view details
GB110060036250
SAC, SSSI
of root wads
Parallel to
the flow
Parallel to
the flow
Parallel to
the flow
20 to
the flow
20
Salix
20
4.8
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Design
Salix
Salix
Salix
Figure 4.8.2
Planform showing installation
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
4.8
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Salix
Anchor trench
(filled)
Wooden
pins
Previous eroded
bank line
Reinforced
geotextile matting
Figure 4.8.3
Bank protection utilising root wads to
protect the base of the bank from erosion
4.8
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Subsequent performance
Stabilisation of a complex outer meander bend has been
achieved and each of the root wads installed has grown well.
Monitoring encompassed HABSCORE and electro-fishing
surveys, which were undertaken by the Environment Agency
Wales just after construction in 2004 and again in 2006. Three
sites were surveyed within the project reach, and a further three
upstream to act as controls. At each site two semi-quantitative
and one quantitative electro fishing surveys were carried out
to determine population estimates for Atlantic salmon (Salmo
salar) and brown trout (Salmo trutta) fry and parr.
No marked differences were observed in fish densities between
the two survey occasions, with some sites showing a reduction in
fish numbers. However, it should be noted that the post-scheme
surveys were undertaken just one year after the works and
the full benefits are not likely to be realised until several years
after implementation.
Salix
Salix
Contacts
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 4 of 4)
4.8
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
River Rother
WFD Mitigation
measure
Waterbody ID
Designation
Click Here
to view details
GB107040013670
Project specific
monitoring
SSSI
Fixed point photography
Cain Bio-Engineering
Description
This tidal section of the River Rother has undergone many
centuries of river management for land drainage and navigation.
The channel is characterised by long stretches of deposited
littoral sediments. These preferentially deposit on the inside of
meander bends with resultant erosion through rotational slips
on the opposite (outer) banks. In some places breaching of the
flood embankment is a concern.
4.9
(page 1 of 3)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Design
A traditional brushwood mattress technique more commonly
used on chalk streams was specified, to trap suspended sediment
during tidal exchange and so stabilize the bank.
This technique can be used in estuarine environments with
high sediment loads where the area is within the normal tidal
range. The process of sediment deposition infills the mattress
structure. Anaerobic conditions then develop which suspends
decomposition of the internal woody skeleton, providing
long-term integrity. There is nearby historic evidence from
earlier stabilized areas that natural wood has remained intact
for some 100 years.
Hardwood sweet chestnut (Castanea staiva) posts were used
(minimum diameter of 0.125m). These ranged from 2.1m up to
4.5m in length to allow for the variation of the eroded bank
profile and to ensure that at least 1.5m of each post was driven
into the bank. The posts were installed in a 1m grid along a
200m section of bank, with an average width of 11m (see Figure
4.9.1) by a long-reach excavator. A hazel (Corylus avellana)
brushwood mattress was then laid between the posts, using
3m to 4m long brush. Brush was installed to extend slightly
beyond the last posts at the toe of the structure, to encourage
sedimentation in this critical area by increasing roughness.
Cain Bio-Engineering
Figure 4.9.1
Cross-section of brushwood mattress design
Brushwood
mattress infill
Accreted
bed profile
4m AOD
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 3)
4.9
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
4
Brushwood laid between posts to form
a matrix to trap suspended sediment 2005
Cain Bio-Engineering
Subsequent performance
Fixed point photography has shown that after seven years this
technique is continuing to prevent erosion, with vegetation
developing well, especially at the top of the bank.
Some of the brushwood became compressed by the weight
of accreted sediment, leaving the netting standing proud
above the brushwood. Cutting holes in the netting around the
posts would enable it to settle with the compressed brushwood.
Cain Bio-Engineering
Cain Bio-Engineering
Cain Bio-Engineering
Contacts
Simon Cain, Cain Bio-Engineering
4.9
(page 3 of 3)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
5.6 Fixing whole trees into the river bank for flow diversity
River Avon
River Avon
WFD Mitigation
measure
Waterbody ID
Designation
Click Here
to view details
GB108043022350
Project specific
Fixed point photography,
monitoring
habitat mapping,
RRC rapid assessment
method
Figure 5.6.1
Plan of the works
Description
Remove two willow limbs
and coppice three willow limbs
Though the site was within a well wooded corridor, the river
had little in the way of bankside trees and the resultant lack
of woody material input, along with historic dredging, had
contributed to the lack of physical habitat diversity in the river.
Design
A303
Large whole trees were installed on the left and right bank
either side of A303 over a disrtance of 850m (see Figure 5.6.1).
Remove one
Poplar hybrid limb
5.6
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
s e
re al
et sc
m to
5
1. wn
y 1 ra
el t d
at no
im n
ox sio
pr en
Ap dim
is
(th
Crucifix Method
Firstly a cross-shaped trench was excavated. Then the tree to
be placed in the stream was attached to another shorter
section of timber using a mortise and tenon joint and high
tensile wire (see Photograph1), forming a crucifix shape.
Finally the completed structure was lifted, using a long
reach excavator, placed into the excavated trench (see
Photograph 2) and then backfilled.
4560
um
im
in
um
im
in
5m
3.
5m
0.
at
el
y2
Approximately
0.4m diameter
ro
xim
Figure 5.6.2
Plan and cross-section
Natural England
Ap
p
of crucifix anchoring
2
Trees jointed in cross fashion
and bound with high tensile wire
Bank to be well compacted
on reinstatement
Steel bar ends have washer on
and burred to hold tree
40mm
Detail of washers
3m
End of steel
bar burred
Washer to
hold tree
Natural England
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
5.6
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
5
M
im
in
um
Direction
of flow
Steel cable
Diameter and rating
to suit
90
A
0. ppr
4m o
x
di ima
am te
e t ly
er
5m
1.
Ground anchor
Figure 5.6.3
Plan and cross-section
of Ground anchoring
45 60
M
um
im
in
5m
3.
Ground Anchoring
High tensile steel cables were attached to the
main trunk and a narrow trench dug into the
bank to accommodate the cable. Using a long
reach excavator, the tree was lowered into its
trench and backfilled.
Steel cable.
Diameter and rating
to suit
Ground anchor
Staking
This was used where the river banks were soft.
The end of the tree trunk to be used was
sharpened and then pulled horizontally into
the bank (using the long reach excavator),
embeded by approximately 2 metres.
In all cases the trees were pinned to the river bed
with 3m long, 40mm diameter reinforced steel
bars to ensure that they did not move or pull
free from the bank. Holes were drilled into the
trunk before it was placed in the river. The structure
was then pinned into place by the excavator
bucket, pushing the bars through the pre-drilled
holes into the river bed to a depth of 2m. The
steel bars were a requirement to get flood defence
consent for the work. However, understanding
of how much achoring is required has improved.
Natural England
5.6
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Subsequent performance
Reach-scale mapping of all sites was undertaken including
fluvial audit, physical biotope mapping, river corridor survey
and repeat photography. Results showed that the installation
of woody material has created greater flow variability. There
are now areas of marginal dead water and faster flowing water
creating more varied habitat. Sediment accumulations are now
concentrated at the channel margins rather than on the channel
bed along the main flow path. This is keeping the gravel bed
clean for spawning habitat and provides silty marginal habitat
for brook lamprey.
spp.) and water mint (Mentha aquatica). The low gradient and
deep channel remains a limitation on the extent and diversity
of macrophyte growth within the channel.
The aquatic plants are annually managed by cutting throughout
the River Avon catchment. The fishing club initially reported
problems for their weed cutting boat, so in some reaches 1.5m
to 2m was cut off the outer ends of the submerged trees. In
other places they have been trimmed where they protruded
above water level to reduce snagging of fishing lines and the
cut weed.
RRC
Trees installed on
the right bank.
Submerged with
branches just
protruding out
of the water
January 2009
RRC
RRC
Contacts
Jenny Wheeldon, Environment Agency/Natural England Adviser,
formerly Avon STREAM Project manager
Jenny.Wheeldon@naturalengland.org.uk, 0845 6003078
(page 4 of 4)
5.6
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
5.7 Felling and placing trees for habitat and flow diversity
River Bure
River Bure
WFD Mitigation
measure
Waterbody ID
Designation
Mill Farm
Figure 5.7.1
Plan of the River bure
in the Blickling Estate
Phase 1
2008
Footbridge
Ch
ur
ch
Ro
ad
R B
ure
Phase 2
2010
100m
Description
The aim of the project was to re-establish the natural river
processes interrupted by past management and to provide
morphological, hydrological and habitat diversity. The project
was completed in two phases. The project was low cost, used
on-site materials and had minimal impact on the riparian
zone.
The River Bure at Blickling National Trust Estate had been
historically altered for milling and, more recently, meanders
were cut off at the end of the 19th century. The local channel
gradient is moderate (between 1 in 300 and 1 in 800) and the
river has a gravel bed with a significant overlying silt layer in
an over-widened channel. The river is flashy, prone to high
flows during and after heavy rain especially in the winter. The
riparian and adjacent land is well wooded, with alder and willow
carr and remnants of ancient woodland.
(page 1 of 3)
Click Here
to view details
GB108049007170
Project specific
Fish, macroinvertebrates,
monitoring
plants, sediment transport
and distribution, flow velocity,
substrate characteristics,
Woody material (entire trees) was felled into the channel in as
natural a form as possible to increase flow variability. It was
envisaged that the trees would either create scour or trap
mobilised silt and sediment. Marginal deposition would eventually
vegetate and stabilise creating a faster flowing, narrower
channel with clean gravel substrate.
Design
Woodland
5.7
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 3)
5.7
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
5
Subsequent performance
Up to 2013 the technique has had no negative outcomes and no
adaptive management has been necessary. There is a possibility
that some of the material may move so the site is visited by the
National Trust countryside staff a few times a year, especially
after high flows, to see if there are any issues. So far no significant
movement has occurred, despite significant flooding which
occurred in March 2013.
Dave Brady
Dave Brady
Contacts
Dave Brady, National Trust
(page 3 of 3)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
River Darent
WFD Mitigation
measure
Waterbody ID
Designation
GB106040024222
Project specific
monitoring
Alconbury Environmental
Click Here
to view details
None
Invertebrates, vegetation
Description
The River Darent in the Dartford area has been heavily modified
over many years, including changes to channel planform, the
implementation of land drainage schemes and abstraction,
leading to an over widened channel. Prior to restoration this
section of river, two miles upstream of Dartford, was very uniform
with a shallow gradient. The natural substrate is dominated by
gravel but had become overlain by silt. Flow and habitat diversity
was limited with negative impacts on fish and macroinvertebrate
communities.
The aim of the project was to demonstrate that the processes
that sustain a healthy chalk stream could be restored and the
habitat protected during drought periods. This was to be
achieved in a cost-effective way by re-working the in-channel
gravels to form a low flow channel. The restoration work
contributed to Chalk Rivers Biodiversity Action Plan (BAP) targets
and complemented the implementation of the Darent Action
Plan (1992).
5.8
(page 1 of 3)
Alconbury Environmental
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Figure 5.8.1
Sequence of gravel
redistribution and planting
Figure 5.8.2
Indicative cross sections
Section A
Iris planting
Section A
Highest point of ledge
upstream of pool
Section B
Pool
Section B
Deeply excavated pool
Section C
Run at head
of pool
Pool
Section C
Shallower scrape to keep
bed highest here
Section D
Existing
bed level
Replanted water crowfoot
Section D
Replanted water crowfoot
in low-flow channel
Pool
Ripariain trees and banks
untouched bed modifications
done with machine in channel
Approximately 6.5m
Design
All of the bed modifications were carried out from within the
channel, so that the banks and trees were left untouched. The
channel was re-profiled using a long reach excavator creating
a sinuous channel, with pool and riffle sequences, still within
the confines of the original channel.
The excavator accessed the river where there were suitable
gaps between trees and the creation of gravel berms at these
points enabled the excavator to exit the river without damaging
the completed work.
A low flow channel was created by moving small amounts of
gravel in a meandering path. Part of the bed was kept at a higher
elevation to create a sequence of riffles.
In other areas more significant quantities of gravel were
redistributed enabling pools to be created. Pools, spaced at
approximately 20m intervals, were designed to be self-cleaning.
Gravels were placed upstream of each to narrow the flow and
increase velocity to induce scour in these pools.
Slack
Approximately 6m
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 3)
5.8
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
5
The whole of the construction phase was supervised by the
designer who was on site throughout the work and provided
instructions to the excavator driver.
Existing bankside trees with large root systems acted as natural
deflectors and provided a variety of marginal habitat. A small
amount of planting was carried out, including water crowfoot
(Ranunculus spp.), yellow flag (Iris pseudacorus) and purple
loosestrife (Lythrum salicaria). The water crowfoot was sourced
locally from the Darent.
Subsequent performance
Photographic evidence shows that the in-channel features
created as a result of the works have been maintained over
the subsequent seven years and are still present. However, no
detailed morphological assessment has been undertaken. Clean
gravels can be seen throughout the reach and the low flow
channel, pools and riffles provide improved fish habitat.
Comparison of pre and post-works invertebrate monitoring,
using the Proportion of Sediment-sensitive Invertebrates (PSI)
method, demonstrates an overall improvement in the composition
of species indicative of good chalk stream habitat conditions.
A significant increase in the numbers of less silt tolerant species,
for example blue-winged olive mayfly (Ephemerella ignita), has
Contacts
Tom Cook, Environment Agency (South East)
5.8
(page 3 of 3)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Inchewan Burn
WFD Mitigation
measure
Waterbody ID
Description
The Inchewan Burn is a tributary of the River Tay SAC and
flows through the village of Birnam. The upstream section retains
much of its natural character, though in a heavily forested
valley. The catchment is steep and flashy which has caused
flooding in Birnam in the past.
Designation
Click Here
to view details
150290
Project specific
monitoring
None
Hydraulic habitat, fish
A.Pepper
RRC
5.9
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Design
The method statement for the works was a simple concept
based on utilising the gradient of the degraded reach (1 in 14)
to form a series of step-pools, replicating as closely as possible
the upstream bed form (Figure 5.9.1).
A schematic of the reach illustrating the repeat step and pool
features (all varying in boulder arrangement) helped to guide
the contractor. Further guidance was provided using the
upstream reference site to aid discussions with the RRC and
the supervising local ghillie.
Figure 5.9.1
Schematic of step-pool sequences
RRC
Step
Pool
Pool
Step
Step
0.5m
concrete toe
Keystones pinned
to concrete toe
14m
Shoal
Step
0.5m
Minimum 0.5m
Pool
Step
Concrete bases
minimum 0.5m below
final stone and cobble level
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
5.9
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
5
This meant that the contractor only had minimal fixed dimensions
(the number of steps, step drop and distance between steps)
to guide the placement of boulders, and the instruction to make
it resemble the upstream template reach as far as possible.
First, the wire from the disintegrating mattressing was removed.
The cobbles that had been transported downstream were
retained for reuse. The work was carried out during a dry period,
with all of the low flow in the burn routed through a 0.5m
diameter pipe.
The large boulders required for the bed were sourced from local
field stone piles. These were lowered in to the burn and placed
using a system of levers and pulleys. The largest (0.5 tonne) were
used as keystones, mimicking the upstream channel where
the largest boulders were integral to the step features, retaining
the smaller interlocked boulders (the step) behind them.
The high gradient meant that there was a need to ensure that
the keystones did not move. For this reason, a buried concrete
base and steel pins were used to fix the most critical bed elements.
Where concrete was to be used to bed-in the steps, it was
specified to be buried at least 0.5m below the stone and cobble
base to ensure that it remained unseen (Figure 5.9.1).
SEPA
5.9
(page 3 of 4)
SEPA
SEPA
The vertical concrete right bank (i.e. the road bridge footing)
was constructed with a 0.5m wide toe which had previously
been hidden beneath the wire mesh bed. This stepped ledge
needed to be hidden by the new works (for aesthetic reasons
and to prevent undercutting) and therefore provided a secure
foundation for locating a number of the keystones. The boulders
and concrete ledge were both drilled and the boulders then
fixed in place with resin and steel pins.
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Immediately after
completion
December 2007
Boulders were also placed along the gabion basket left bank
retaining wall, partly to hide the gabions but also to protect
them from the abrasive throughput of bed material which
had destroyed the Reno Mattress base.
RRC
Subsequent performance
In December 2007, the local ghillie observed salmon, sea
trout and brown trout (Salmo trutta) swimming through the
reconstructed section of the burn and upstream once more.
The work has made a dramatic improvement to the aesthetics
of the reach, which is appreciated by regular users of a footpath
close to the river bank.
Monitoring by the University of Stirling in 2009 compared the
hydraulic habitat and fish density in the unmodified upstream
reach with that of the restored reach. This showed that hydraulic
habitat had been successfully restored and that juvenile salmon
and brown trout were colonising this reach. However, passage
upstream was being impaired by the shallow masonry culvert
bed beneath the railway.
The success of the scheme was in part a result of basing its
design on the upstream reference reach. This provided a visual
template for restoration which could be easily understood as a
shared vision by the design engineers, stakeholders and contractor.
Contacts
RRC
jock@salmon-fishing-scotland.com, 07968145033
Click
Here for Reference
Martin Janes, River
Restoration
Centre Material
rrc@therrc.co.uk, 01234 752979
(page 4 of 4)
5.9
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
River Valency
WFD Mitigation
measure
Waterbody ID
Designation
Click Here
to view details
GB108049007170
None
Removed
sewer crossing
New wall
Relocated
revetment wall
New railing
New
Lower Bridge
River widened
on the south bank
into grass verge
Extended bridge
parapets
Widened river channel
adjacent to the Riverside Hotel,
replace and extend footbridge
Retained
revetment
Figure 5.10.1
Plan of Boscastle
River Jordan
bypass outfall
Main Bridge
River Jordan
outfall
New flood
defence walls
Description
Boscastle village is located in a steep sided and narrow valley
through which the River Valency flows down to the harbour. In
2004 an intense storm centred over the small wooded catchment
caused massive erosion of sediment and river-side trees. This,
combined with high flows, inundated the village with water
and debris causing extensive damage.
The village is of great historic value and is a main attraction
for visitors to North Cornwall. The river itself is the centrepiece
of the village. The process of Enviromental Impact Assessment
(EIA) and landscape appraisal led to the best enginering design
that would deliver the multiple flood risk, landscape and
environmental objectives.
Enlargement of the river channel offered the only viable way to
reduce flood risk and improve the flood capacity and sediment
conveyance of the river. The scheme aimed to demonstrate
best practice in achieving this sympathetically, so avoiding a
deep geometrically uniform channel. The channel was designed
in such a way that it simulated the natural features found higher
up in the undisturbed reaches of the river by engineering
features into the excavated bedrock.
5.10
(page 1 of 4)
Halcrow
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Start of
car park upsteam
Transition
into harbour
Plunge pool
under bridge
Over dig
Transition
below Jordan
into original
Regraded at 1:45
River Jordan
outfall
Mean
Mean
14
pr
Original bed
Spring tide
level
or 1:4
ey flo
f vall
ofile o
12
aded
regr
file of
pro
:45
bed 1
2.5m mean
depth
10
8
6
Existing
main
roadbridge
4
Regraded bed
New bridge
00
100
Rivers Agency
Deposition here
post-project
16
0
300
200
400
500
Chainage (metres)
l
tica
Ver face
pe
1 Main fracture
Slo
North wall
South wall
Design
ctu
Fra
re l
ine
lines evident in
direction of the
natural rock
dip slope
Slope
Bed
Figure 5.10.3
Simplified plan of the river channel showing the
effect of natural fracture lines within
the rock break
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
5.10
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
South wall
Pool
Ledge cut
back towards
wall at pool
(embayment in
quartz)
Down slope
Channel walls
constructed with
masonary facing
to retain original
character. All stone
recovered from
debris screening
Halcrow
Weir slope
down in
direction of
dip slope
Full ledge
width 1m
pe
Slo
Weir crest
at prescribed level
Figure 5.10.4
Schematic plan of weir and
pool in quartz strata
Cascades with pools below were formed along the bed with
nominally 0.2m drops at 9m intervals to approximate the
1 in 45 gradient. Excavation was only undertaken under the
supervision of an experienced river engineer, enabling every
aspect of the final topography to reflect the specific nature of the
rock in situ as it was worked. The alternative of trying to detail
the bed profile for the contractor would have been impractical.
Halcrow
5.10
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Subsequent performance
The re-profiled river has performed well during the years since
completion. The excavated profile has remained stable, as have
the individually sculpted cascades, pools and embayments. Within
the latter a good diversity of flow characteristics provides niche
habitats, with some gravel in sheltered eddies as well as small
beaches. It is also visually attractive, enhanced by the sound
of the cascading water. This contrasts markedly with the flat,
featureless river bed that existed before.
Halcrow
Halcrow
Contacts
James Burke, Environment Agency
(page 4 of 4)
5.10
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Managing
Overland Floodwaters
Burn of Mosset
WFD Mitigation
measure
Waterbody ID
Downstream breach
of embankment
Designation
Click Here
to view details
23021
None
Project specific
monitoring
Confluence with
Rafford Burn
Embankment constructed
to prevent flooding of water
onto adjacent fields
Figure 6.4.1
Plan view of the sediment
Floods
acretion area
Upstream breach
of embankment
Sediment accretion
area/outwash fan developing
at upstream breach
Description
The Burn of Mosset is a small but geomorphologically active
gravel-bed stream that drains an area of 49km2. It flows
northwards through the town of Forres before entering
Findhorn Bay. Forres has had a long history of flooding from
the burn, with six events causing serious property damage and
disruption within the last 50 years.
This upstream storage area, the focus of this case study included
an extensive natural sediment accretion zone. It has a large
capacity to store sands and gravels and also retain large
woody material. This will reduce the risk of sediment blockage
or damage of the dam control structure from sediment or
large wood respectively.
6.4
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Managing
Overland Floodwaters
Design
Two breaches of the existing embankments (see Figure 6.4.1)
were created to allow flow to spill out across the floodplain.
Their locations were selected using LiDAR imagery to identify
low areas of land suitable for the course of the temporary
basic channel, which was constructed to ensure that there
was no interruption in migratory fish passage.
The overall aspiration was to then allow natural processes to
develop a multi-thread watercourse. Initially the upstream
breach in the bank was set to maintain 80% of the lower flows
in the existing channel, and protected using thirty tonnes of
locally sourced granite placed within the breach opening.
This was to ensure that species within the existing channel
could continue to use the available habitat whilst the new
watercourse continued to develop.
Royal Haskoning
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
6.4
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Managing
Overland Floodwaters
Scot Avia
Subsequent performance
Approximately one year after the banks were breached in
September 2009 the channel experienced an estimated 30m/s
flood flow (of the order of a 1 in 10 year event). The stone
protection at the upstream breach was partially washed out, as
anticipated. The breach enlarged such that the majority of the
flow was diverted along the new route after the flow subsided.
The result was rapid development of river features, including
the formation of an outwash fan (see Figure 6.4.1). Some ecological
degradation has occurred in the short term, as the old channel is
now dry except during very high flow events.
6.4
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Managing
Overland Floodwaters
Royal Haskoning
Royal Haskoning
Contacts
Matthew Hardwick, Royal HaskoningDHV
(page 4 of 4)
6.4
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
12.1 Restoring an on-line lake to a chalk stream
Babingley River
Babingley River
WFD Mitigation
measure
Click Here
to view details
Waterbody ID
Figure 12.1.1
Planform of Babingley River
Silt deposition
in bays with
additional
ecological
benefits
Designation
Downstream section.
Lower energy reach
requiring intervention
to establish low flow
channel and expose
gravels
Redundant
channel
now dried out
GB105033047620
None
Project specific
monitoring
Fish, Invertebrates,
Vegetation (post- project only)
Upstream section.
Higher energy reach retaining less silt.
53
B11
0.6m wide
culvert
1.15m high sluice boards
removed from culvert entrance
Description
The Babingley River rises from chalk springs above the villages
of Flitcham and Hillington in North West Norfolk. The Hillington
site is located close to the source and includes an impounded
online lake known as the Broadwater. The aim of the project was
to revert the lake back to 420m of river. This would resolve the
water quality issues in the lake, remove barriers to fish passage,
including eel (Anguilla anguilla), provide additional spawning
habitat for wild brown trout (Salmo trutta). The sluice boards
used to impound the lake were removed, lowering the water
level. This concentrated the flow and enabled the river to cut
a new channel. However, lowering the water level created a
barrier at the upstream weir, which was addressed by a pool
and traverse fish easement.
This low cost river restoration technique was possible at this
site as the landowner owned both sides. The rural location of
the site, and lack of infrastructure downstream, meant that
flood risk modelling was not considered necessary.
Existing weir
at upstream
extent of site
Design
The work was designed to use the energy of the river to cut
and form the new channel. The works were carried out in
three distinct phases;
1.Controlled removal of downstream sluice boards
Six sluice boards, 1.15m high in total, were located at the
downstream extent of the reach where the river flows
through a 0.6m wide culvert. These maintained the water
level in the impounded lake. The boards were removed
using a staged approach enabling the lake level to be
lowered in a controlled manner and allowing the amount of
sediment released downstream to be regulated.
Original lake extent
Water level
prior to works
New
water level
1.15m
Figure 12.1.2
Typical cross section of
new channel in downstream section
12.1
(page 1 of 4)
Change in flow
dynamics after boards
removed results in the
formation of a low
flow channel
Approximately
4m
These techniques were developed to suit site specific criteria and may not apply to other locations
Drained silt
becomes colonised by
vegetation helping to
stabilise the banks
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
Environment Agency
Environment Agency
Existing weir
structure
0.3m
Figure 12.1.3
Pool and traverse fish easement
1m
0.3m
1m
0.3m
Main flow
Rock rolls at an
offset angle to
reduce velocities
Environment Agency
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
12.1
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Mitigation
for Barriers
12
3. Installation of deflector boards
After the sluice boards were removed and the water level
lowered, the river began to cut a new channel into the silt.
In the upper reach, where the gradient was steeper, the river
was left to naturally continue this process. In the downstream
reach the gradient was less and lacked the energy necessary
to continue cutting into the remaining silt. The installation
of a series of deflectors created pinch points that have
concentrated flows sufficiently to cut down to the hard bed
and create pool and glide sections. Twenty deflector boards
were installed facing in an upstream direction over a 200m
stretch.
The deflectors were generally installed in pairs, some opposite
each other and some offset. The locations were determined
by working with the river. Hillington Fly Fishing Club was
responsible for this work so the addition of the deflectors
did not contribute to the Environment Agency project cost.
Environment Agency
Subsequent performance
The upstream section of the restored river was quick to expose
hard bed, and braided channels have formed here. The combination
of newly exposed gravels and improved flows has increased
the amount of available spawning habitat.
12.1
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Mitigation
for Barriers
12
Environment Agency
Environment Agency
Contacts
Andy Sadler, Environment Agency (Anglian)
(page 4 of 4)
12.1
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
12.2 Step pool cascade fish pass and culvert bed improvement
Lodge Burn
Lodge Burn
WFD Mitigation
measure
Waterbody ID
Click Here
to view details
GBNI1NB030301223
Description
Designation
Project specific
Fish, River Corridor Survey
monitoring
(pre-project only)
hydromorphology
None
Design
The works were carried out in four key stages;
1. Flow management; works to install the step-pool cascade
and improve the culvert bed had to be conducted in the dry.
A fully isolated dry working area was achieved by sandbagging
and over-pumping.
2. Modify culvert bed; the culvert had to be enlarged to
incorporate the loss of capacity and increased roughness of
the new cobble bed. The culvert bed was carefully excavated
0.3m below the existing level.
Stainless steel baffles (0.15m high) were secured across the
culvert at 2.5m intervals to prevent scouring of the placed
bed material.
Rivers Agency
12.2
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
Rock size
to be approximately
rectangular to form weir
- rock size may vary
Concrete infill/bedding
recessed below
top of rock
0.3m
Min 1.0m
0.25m
0.25m
Lamprey ramp
0.3m wide concrete
with embedded
0.1 0.2m diameter cobbles
Flood wall
Terram 1000
separation textile
Top level
as shown on plan
for each crest
0.3m
0.25m
Figure 12.2.1
Typical Cross-section
through Cascade
12
Rivers Agency
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
12.2
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
4m
3m
Reinforced concrete
weir with
stone cladding
Terram 1000
separation geotextile
along length of fish pass Original bed level
2m
Original concrete
ramp demolished
to required level
1m
Notch level = 1.50
Figure 12.2.2
Longitudinal Section
through Cascade Fish Pass
Figure 12.2.3
Overal plan of
Cascade Fish Passage
12.2
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
49.04m
43.04m
42.54m
37.04m
31.04m
25.04m
21.65m
19.04m
13.94m
13.04m
0.00m
Chainage =
0.00m
AOD
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
Rivers Agency
12
Subsequent performance
This project is a good example of what can be achieved to
improve fish passage in a very confined space. The new pass
has had a positive response in terms of aesthetics.
Flooding shortly after construction caused some damage to the
face of the first cascade. Gravel and cobble washout from the
culvert resulted in the infilling of pools, however this material
was removed subsequently by the Rivers Agency. This initial
movement highlighted the importance of incorporating sufficient
self-maintaining processes in pool design (i.e. sufficient flow to
maintain the pool depth), as well as the need to anticipate early
wash-out of excess material. The remaining cobble bed material
within the culvert is now deemed to be stable.
Rivers Agency
Rivers Agency
Contacts
Gareth Greer, Rivers Agency
(page 4 of 4)
12.2
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
12.3 Complete removal of a large weir
River Monnow
River Monnow
WFD Mitigation
measure
Waterbody ID
Designation
Description
Kentchurch Weir, owned by Environment Agency Wales (now
Natural Resources Wales), located within a large private estate,
was thought to be a modern reconstruction of an older weir and
was in the process of breaching. It was decided to completely
remove the weir rather than repair it, also addressing the
adverse effect it was having on WFD objectives including fish
migration.
Click Here
to view details
GB109055029720
None
Figure 12.3.1
Plan View showing the location of
Kentchurch Weir
B43
47
Kentchurch
Kentchurch
Weir
Grosmont
Bridge
Mill
Wood
The Mill
Farm
12.3
(page 1 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
Design
To remove the weir a 20 tonne 360 excavator and a 6 tonne
swivel skip dumper were used. Demolition started with a 3m
width on the left bank which was taken right down to bed level.
Once the weir was breached a line of jumbo sand bags was
used to channel the flow through this breach. This enabled
the contractor to demolish the rest of the weir in the dry as the
impoundments had been de-watered.
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
12.3
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
Breach in the weir on the left looking downstream from within the
previous impoundment 2011
during the works. On the right bank A short length (about 2m)
of weir was left in place, supplemented by some blockstone, to
address the risk of local erosion. Much of the excavated material
was reused locally.
12.3
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
Subsequent performance
The scoping study carried out before the weir removal
constituted the pre-works monitoring, and included habitat
and geomorphological assessments. After the weir was removed
Environment Agency Wales continued monitoring the river as
it adjusted to the removal of the weir and have commissioned
the University of Cardiff, to study the changes in river morphology.
Some anticipated channel adjustment has taken place, some of
which will require intervention in order to prevent adverse
consequences for farmers.
Monitoring every 3-4 months between July 2011 and January
2013 has documented the dispersal of impounded gravel
from the reach upstream of the weir. In addition, transfer of
these gravels downstream has resulted in the growth of point
bar, resulting in decreased flood conveyance.
Alaska
Contacts
Alex Humphreys, Atkins Global
(page 4 of 4)
12.3
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
12.4 Weir lowering and rock ramp construction
River Calder
River Calder
WFD Mitigation
measure
Waterbody ID
Description
Historically a degraded river due to its industrial heritage, water
quality on the Calder has been significantly improved over the
last 20 years allowing coarse fish populations to return. However,
in-channel obstructions have prevented the migration of fish,
including eels (Anguilla anguilla), to approximately 20km of
spawning grounds and habitat further upstream.
Designation
Click Here
to view details
GB112071065490
None
Design
Prior to the works a dive survey established that the weir was in
poor condition and liable to failure. It indicated that there was
extensive sediment deposition upstream of the structure.
A topographic survey established the bed levels upstream and
downstream of the weir which then informed the calculations
to determine the level and spacing of the bed check weirs.
A hydromorphological assessment concluded that the impacts
of the weir removal on sedimenttransport, water levels and the
flow regime would be beneficial. It was established that there
would be no increased flood risk and that there was likely to be
a reduction in flood risk for at least one business due to the
elimination of the weirs backwater effect. The banks were
deemed stable enough to withstand the lowering of water
levels. The left bank was already modified with stone blocks
along the immediate upstream section and the right bank was
gently shelving.
Environment Agency
12.4
(page 1 of 4)
The end sections of the weir adjacent to the wing walls were
left in place to assist with stability. The initial drop in water level
following the weir removal was approximately 1m removing the
impounding effect for approximately 500m upstream.
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
Extent of the
original weir
Reprofiled
weir surface
Section of
weir apron
removed
12
Figure 12.4.1
Plan View showing bed check weirs and
low flow channel
Large stones
placed below each
bed check weir
Combined Sewer
Overflow (CSO)
Section of
sheet pile wall
retained
High voltage
cable
These techniques were developed to suit site specific criteria and may not apply to other locations
(page 2 of 4)
12.4
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
Three bed check weirs, all 0.3m high, were installed in phases
using an excavator, working from downstream up towards the
existing weir structure. This work was undertaken from within
a sheet piled cofferdam. To install each bed check weir a
trench of 1m deep was dug and interlocking 1m3 pre-cast
concrete blocks were set across the channel on aggregate
bedding, parallel to the existing weir. The bed was lowered
upstream of the existing weir. Stones (varying in size from large
gravels to cobbles and boulders) were placed immediately
downstream of each check weir to reduce the risk of scour
causing instability of the structures. Stone armour was also
placed at the toe of the existing weir structure, where scour
had created a void, to help stabilise it. Once the installation of
the bed check weirs was complete, the existing weir was
partially deconstructed.
Figure 12.4.2
Longitudinal Profile AA
Weir apron removed
over full width of re-profiled
section of river
Original weir profile
Bed lowered
Weir lowered
to new profile
Environment Agency
12.4
(page 3 of 4)
These techniques were developed to suit site specific criteria and may not apply to other locations
a n u a l
o f
i v e r
e s t o r a t i o n
e c h n i q u e s
Removing or
Passing Barriers
12
Subsequent performance
The design was developed such that continued maintenance of
the structures should not be necessary. The site now operates
as a full weir removal would have, with the bed check structures
effectively buried and blending well into the natural river bed.
The material used in the rock ramp was selected to withstand
the expected stream power at the site, however exceptionally
high flows over a sustained period during 2012 appears to have
caused significant scour and erosion both above and below
the weir. Flow volumes experienced during 2012 resulted in
velocities capable of entraining the material used for the rock
ramp (the 1 in 50 year return period flood event in June had a
peak flow of 220m3/s compared to median annual flood flow
of 173m3/s).
Once a portion of the material had been scoured out, the uneven
bed surface was vulnerable to further scour and turbulence and
allowed more material to be scoured out during subsequent high
flow events. The issues experienced at this site as a result of
high flood flows highlight the importance of setting the size of
stone used for the stone armouring according to bankfull flows.
Environment Agency
The site after three years. Some of the material entrained during high flood flows has been
carried downstream but the majority has remained in the vicinity of the rock ramp
and is visible near to the left hand bank April 2013
Contacts
Steve Powell, Environment Agency (North West)
jack@ribbletrust.com, 01200444452
(page 4 of 4)
12.4