Академический Документы
Профессиональный Документы
Культура Документы
16.02.2007
12:26 Uhr
Seite 1
SLAB TRACK
SYSTEM BBPORR ELASTICALLY SUPPORTED TRACK BASE PLATE
16.02.2007
12:26 Uhr
Seite 2
GENERAL
Length
Width
Depth
16 cm (16 / 24 cm)
Openings
91 x 64 cm (top)
87 x 60 cm (bottom)
Weight:
50,00 KN (gross)
51,40 KN (using Vossloh 300-1)
Types:
Linear (R>3697 m)
Radii (R=200 up to 3697m)
Railway/suburban railway/underground
Rail: 60E1 (E2) / S54 / S48U
16.02.2007
12:26 Uhr
Seite 3
50
concrete joint
sealing
compound
upper edge of
the track 0.00
8 16 23
elastic
layer
30
2
ASSEMBLING
50
1.800
1.800
30
2
block out
1800/700
18
18
-0.47
concrete subbase
1.836
-1.32
tubbing segment
-1.55
drainage piping
incline concrete
Block out in track base plate for pump shaft longitudinal section
640
60E1(E2)
elastic
track bed
80
240
160 80
393
473
concrete joint
sealing compound
elastic layer
reinforcement
640
650
650
650
650
650
Horizontal loads
Side shock H = 100kN, but horizontal force in
a mounting axle H = 60 kN; effects of starting
and braking
Reinforcement
Proportion of steel approximately 6 % - mild
steel 550, in case of mild steel 500 appropriately higher
920
650
Vertical loads
Freight train UIC 71
Heavy load train SW 0 acc. UIC 776-1E
Speed v = 250 km/h (A) respectively v = 330 km/h
Axle weight Pmaxstat. = 250 kN at v = 120 km/h
Wear out per support point:
Qdyn = 125 x 1,67 x 1,25 = 261 kN
650
5.200
If a modified concrete joint sealing compound without reinforcement is used (> 4 cm), a construction height of > 43,3 cm
60 E1 (E2) can be achieved if necessary. This ensures the
essential flexibility, for example, to optimise cross sections of
tunnels and bridges or to realise track lowering in order to
obtain a bigger cross section (clearance) in already existing
old tunnels (for example Arlbergtunnel and Tauerntunnel).
Unlike sleeper systems, track base plates can provide big
block outs, for example for revision and bearing shafts wherever needed. Block outs of 1,80 m x 0,80 m have already
been utilized in the tunnel of the north-south-connection in
Berlin. By reduction of the track base plates, cable crossings
of 250 mm width can be planned.
Quality of concrete
Track base plates
C 30/37 / XC3 / XF3 / XA1L / GK 16 / F 52
Concrete joint sealing
compound > 8 cm
C 25/30 / XC3 / XF3 / XA1L / GK 8 / F 73 (scc)
C 25/30 / XC3 / XF3 / XA1L / GK 16 / F 73 (scc)
Concrete joint sealing
compound > 4 cm
C 55/67 / XC3 / XF1 / XA1L / GK 4 / F 73 (scc)
Weather conditions
Besides the safe carrying of the loads of the
railway traffic, the absorption of environmental
influences (temperatures) and the discharge of
surface flood water has to be secured reliably
on a long term basis. The track base plates are
connected with each other only by the passing
through tracks enabling a length compensation
within the 40 mm wide joints. Therefore any
deformations caused by temperature cannot
cause any damage. Furthermore the joints can
also be used for drainage.
16.02.2007
12:26 Uhr
Seite 4
MODE OF OPERATION
The bedding necessary for the load distribution on the track is
guaranteed by the elasticity of the track mounting. In addition
the elastic rubber granulate layer, amounting to approximately 10 % of the total elasticity, has the effect that high forces are
well distributed and causes a reduction of the stress in the
multi-layered system.
Portal crane
Bedding of the supporting points and track base plates under traffic load
bedding measured in 6 MP /
calculated according to stress application
0,00
-0,50
bedding in mm
-1,00
-1,50
-2,00
-2,50
-3,00
-3,50
-4,00
MP1
MP2
MP3
MP4
MP5
MP6
MP7
MP8
MP9
free bearing
stressed track
under consideration for plate bedding
PRODUCTION
Laying
The laying of the track base plates, which have a width of just
2,40 m (2,10 m), is normally done with portal cranes. This
enables the plates to be lifted forwards in the smallest possible space. In addition, no reloading or intermediate storage is
necessary, because the plates can be taken directly from the
transport wagon. In the case of islands or missing track connection, the take over and the laying of the track base plates
by lorry with loader arm is the usual practice.
In any case, the track base plates are being laid at the destination with an accuracy of + 1 cm in order to minimize the
work needed to adjust them.
Adjustment of tracks
After the partial spreading of the tracks positioned at the side,
the work of adjusting the final track begins by using a M36spindle. This method guarantees precise track set accuracy in
setting the track requiring no further correction.
Adjustment work is further reduced by an adequate track
geometry of the track base plates. Therefore the time involved
for the adjustment is reduced by up to 50 % in comparison to
other slab track systems.
16.02.2007
12:26 Uhr
Seite 5
DAMAGE CONCEPT
Concrete
According to the space available, the concrete joint sealing
compound is applied either directly or through a hose pump
up to a maximum of 500 m. The use of a self-compacting concrete joint sealing compound enables a holohedral embedding
of the track base plate. As a result of the vibration-free concreting process (without vibrator), the fine-tuning of the track unit
is not affected. Furthermore, it is possible for these slab tracks
to be installed in a short railway block (example: East-WestConnection Berlin 2002) due to the fast setting process of the
scc-concrete. The concrete joint sealing compound is adequately reinforced in order to limit wide cracks.
16.02.2007
12:26 Uhr
Seite 6
BASE STRUCTURES
TUNNEL FLOOR
BRIDGE
1,5%
Balast
2%
Ballast
Concrete blocks
Track axle
Tunnel axis
Track axle
1.600
1.520
86.0
1.700
3.300
66.0
1.730
Bridge axle
1.680
1.570
74.0
94.0
Ballsting
45.5 32.5
78.0
+0,18
SOK 0.00
16.02.2007
12:26 Uhr
Seite 7
Longitudinal member
Track 60E1(E2)
Cross member
EARTH STRUCTURE
The laying of earth structures is done on a load distribution
plate or a hydraulically bond supporting layer. Based on the
high degree of prefabrication of the track base plates and the
relatively small grouting openings, quality influences due to
weather conditions are kept fairly low. This also applies to
mounting on bridge constructions.
Rail axle
Essential differences occur due to the rather high deformation, by disfigurement or shrinkage, caused by temperature
differences, subsidence, or traffic loads as well as creep and
shrinkage. Especially at the bridge joints deformations can
cause unacceptably high track tension and lifting of track supporting points. In such cases special track-crossing constructions are necessary in order to reduce deformations to an
acceptable extent. For example, on the 25 bridge girder systems of the east-west-connections, a total of 50 special trackcrossing constructions were built, and twelve joining areas
were directly built over with slab tracks (on extensive sliding
bearings).
Partial
Absorbing plates
drainage pipe
made of concrete
drainage material
DN 200
ballast
Track axle
Concrete joint
sealing
comound
Upper edge
of track
0,00
Bitumen cating
Balast,
granulate 1
washed
49
2:3
Steel concrete distribution
plate d = 30 cm
6%
20
2.40
-0.80
20
Soil exchange
Bitumen cating
WU concrete (C25/30)
210
Elastically supported
track base plate
210
Steel wedge
Track 60E1(E2)
49
Concrete
Bearing
4x longitudinal member
79.2
70.6
Cross member
Bearing
79.2
16.02.2007
12:26 Uhr
Seite 8
Track axle
Elastomer mat
Concrete block
Elastomer mat
Due to the low height of the system (> 47,3 cm), mass spring
systems without troughs can be produced for low construction heights, for example 25 Hz on approximately 50 cm. On
the bridges of the main station Lehrter Bahnhof, a softer elastomer was applied in the centre of the concrete blocks area,
unlike in the side areas, in order to avoid punching.
Application of elastomer
16.02.2007
12:26 Uhr
Seite 9
blockages, track magnets and conductor rails. In areas of frequency control, the reinforcement can be insulated against
outside influences.
Noise absorber
Section A-A
Guard rail
Track magnet
Adapter plate
Thread rod
Compensating plate
Anchorage device
Base plate
Elastomer
base plate
Section B-B
Blockage
Conductor rail support REHAU
height adjustable
Adapter plate
Compensation plate
Adapter plate
Elastomer base plate
Compensation plate
Section C-C
Coated reinforcement
for example using AGROVAN 209
Additional equipment of the track slab system BB-PORR sectional view + top view
16.02.2007
12:26 Uhr
Seite 10
sterreich RZ 17220
Section A-A
Section B-B
65
60
60
ca. 60
ca. 30
6.5
65
24.5
Concrete subbase
Hydralically
bond foundation
Upper edge
of foundation
Upper edge
of foundation
Slabtrack
Ballast
Slabtrack (FF)
Track base plate
Ballast
15 reinforced concrete sleepers
2,60 m long
15m
Trackform 60E1(E2)
2.800
2.400
60
65
65
60
Ballast with
standard sleepers
60
60
Elastically bonded ballast 30.00 m - 35.00 m
22.8 m
Surface bonding includes strip along sleeper ends, 0.2-0.3 m wide and 0.2-0.3 m deep
30.00 m - 35.00 m
Transition area slab track / ballast (Germany) longitudinal section, top view + sectional view
10
16.02.2007
12:26 Uhr
Seite 11
REFERENCES
REFERENCES
parts and because its application has now been maintenancefree for over 17 years.
PROJECT
YEAR
SPECIFIC FEATURES
Langenlebern
1989
Tauerntunnel
1992
Helwagbrcke
1993
TRACK LENGTH
264 m
2.629 m
52 m
Galgenbergtunnel
1996/1997
Rmerbergtunnel
1997
638 m
Zammertunnel
1998/1999
4.477 m
Kaponigtunnel
1999
By-pass Melk
1999/2000
11.040 m
11.170 m
9.042 m
1999/2000
Siebergtunnel
2000/2001
S7-Rennweg Airport
2001/2002
3.250 m
4.865 m
9.880 m
Blisadonatunnel
Tauerntunnel
2002
2002/2003
3.730 m
12.902 m
Unterwaldertunnel
2003
2.480 m
Junction Rohr
2003
1.691 m
Junction Wagram
2003
2.870 m
4.690 m
Lehrter Bahnhof
2001/2002
(east-west-connection)
Lehrter Bahnhof
(north-south connection)
8.944 m
2004
2.650 m
Pistentunnel S7
2005
1.412 m
Lainzer Tunnel
2006/2007
under construction
4.550 m
Arlbergtunnel
2007/2009
under construction
20.812 m
TOTAL
124.038 m
11
16.02.2007
12:26 Uhr
Seite 12
Fotos: PORR-Archiv
The reference brochures of the PORR Group (from ABAP Nr. 217 on) can be downloaded from www.porr.at