required for protection, measurement and balancing of the current of the three phase generator.
These panels are installed between generator and step-up transformer of the power plant.
Test conducted:
Functional testing of the complete assembled panel.
Continuity test and 3.3 KV test on wiring.
HV Test at power frequency at 28 KV RMS for 1 minute
VT ( Voltage Transformer) Cubicle
These cubicles are similar to LAVT cubicle except provision of LA & SA (Lightening arrestor &
Surge capacitor). These cubicles are used when the system requires large no. of voltage
transformer for metering, protection and synchronization circuitry of power generating unit