Академический Документы
Профессиональный Документы
Культура Документы
.._
_ . _
__
vl'(.. ....................
"
Gt. v
~A-l.S
, M.HM'1
ti
.t
THE CANTILEVER'
CONSTRUCTION
OF
PRESTRESSED CONCRETE
BRIDGES
Jacques Mathivat
Translated by
Mrs C. J. Emberson
A Wiley-lntersciencePublication
.......... -..... ..
'
~lfil\;lf
~ L~~M
'.
.._.-.-.- ..
~.- ....-
.-.-._.--
---
--_.'._--~
'_.4
--1-_,,--__ ~ ..
__J.
- .- -
--
__..
IJ
.
J
9fL.""iI c~t=
Ij
~~~~"fO!'at.e~~~~~
~
~ N;1:}r.]~ .6J:::A\~
.........:-,. ,
..'
.-~
"
. _
__ ..
.. _
__
__
_........:.-:...-_~J
_.. _.O'..
LIST OF CONTENTS
TG385.M3713 1~83
624"~3.~.
82-23744
............................... ,
vii
Foreword
"
Mathivat, Jacques
The cantilever constniction of prestressed concrete bridges.
1. Bridges, cantilever '2. Concrete beams
3. Prestressed concrete .
I. Title II. Construction par cncor~Ucment des ponts en beton
precontraint. English
. i-,\' . .
,.'
624' .35
TG38S
21
33
47
S4
76
79
95
or
'Hog .........................................
9. Special Problems in Design and Calculation of Decks . . . . . . ..
Chapter 3 Delip for Deck StabDity during Construction
2
13
97
J02
......,..
J26
126
J30
,..
J43
J59
..
J77
J90
J90
,._...
_ ..
"""",,,~'
_..J
vi
C.:onlents
2. Construction by Mobile Concreting Carriage Carried by the Deck
3. Other Construction Procedures using in situ Concreting of the
Segments
190
.................................
Advantages of Precasting .. . . . . . . . . . . . . . . . . .
.
Segments with Glued Match-cast Joints
.
Segment Precasting Methods
..
Methods of Segment Placing
.
S. Problems specific to Segments with Match-cast Glued Joints
6. Limits and EvoI ution of Construction by Prefabricated Segments .
1.
2.
3.
4.
209
212
2~.2
212
219
264
267
270
270
272
27S
..... ..... , .....
4. History and Inventory or Br.idges with Multipleinclined Cables . 278
5. Field of Application of Cable-stayed Bridges-Aerodynamic
3. Spacing of Stay Cables
Stability
...........................
282
314
Bibliography
Index
or
....................................
.........................................
FOREWORD
232
333
336
The advantages of this type of bridge which have led to its rapid development
are essentially four in number.
First, the elimination of the arch. which means that noodwaters and con
tingencies arising from burst dnrns can be accommodated. as the waterway is not
impeded. Thi~ technique is well suited to the use of very high piers, the construc
tion of which has become more economieal through the use of sliding formwork.
Accordingly it has competed with. and virtually eliminated, large concrete arches.
Secondly, the scgrncnts can be prefnbricntcd, where the number required is sut'
ficiently large to make this worthwhile. Prefabrication has several advantages
the segments being factory made are of superior quality to those made at site and.
by the time they are ~rcctcd, a considerable amount of shrinkage has already
taken place, so that the prestressing is applied to hardened concrete.
The speed of operation permitted by this procedure should be noted; with
segments cast in place, it is normal to complete two sections per week on each
beam, or in exceptional cases two pairs per week; with the prefabricated method,
three to four sections a day can be achieved.
vii
Foreword
viii
Finally, the net cost has permitted successful competition with steel in what was
once its exclusive domain. Furthermore, one should note the use of the technique
for railway bridges and the possibility of extending its application by the use of
lightweight concrete.
Foreword
ix
the experience accumulated over a period of abOUI fifteen years. It will be of the
greatest value to civil engineers and should lead to further advancements.
MARCEL HUET,
In the realm of major works the design concept is intimately bound up with the
construction methods, and mention should be made orthe essential role played by
contractors in the rapid and constant development of prestressed concrete bridges
'
built by the progressive cantilever method.
. .!
As always in the engineer's art, progress comes from the exploitation of the
valuable feedback given by each achievement, the analysis of difliculties
encountered and the incidents overcome, either during the building phase or when
the bridge is in service. The following four points can be mentioned, to which the
greatest importance should be attached:
-
the continuity of the cable ducts, the correct evaluation of friction losses,
and the quality of grouting of the prestressing cables;
the spreading of the concentrated loads in the prestressing cables;
the introduction of a temperature gradient in the actions applied to the
structure;
and the redistribution of the hyperstatic stresses caused by concrete creep.
......
: ... ~.
,CHAPTER ONE
GENERAL BACI<GROUND
Bridges faU into three categories according to their longitudinal supporting
structure, namely girder bridges. arch bridges and cable bridges (suspension
bridges and cable-stayed bridges). They can also be designated either by the main
component(s) o[ their cross section such as reinforced concrete slab bridges. T
beRm bridges. box girder bridges. ctc.... or by the position or these componen ts
with regards to the roadway: bridges with beams below carriageway, bridges \v1th
side beams.
None of these classifications adequately fits the large prestressed concrete
bridges in which the method 0/ construction determines both design and calcula
tions. It is therefore common practice to group large prestressed concrete bridges
in four main types. each of\vhich corresponds to a standard building method:
-
This book deals exclusively \vith cantilever construction; thi~ process has been
developed extensively in the last twenty years and at prescnt ;t encompasses ~
broad spcctrurn which includes 1110st or t he major prestressed concrete bridges.
2
Spnt19't19 on 0 pier
.. /
Concrete ~eQmenl~
""
General background
p
roweU'/l9 cobles
e-.L:"~
conslruction
Fig. 1.1
Diagram
showin~
~
the principle of cantilever building
~'~~"'" .
~.~ '~~""
The segments may be concreted in situ in mobile forms. They can also be
prefabricated. transported and set into place with the appropriate lifting devices.
Fig.
2 HISTORY
"
.; ~. ~~
..
....
"::""\.'
Past history
2.1
,....
.'.
The concept of building a structure cantilevered from its supports is not new and
has been in the mlnda of builden almost from the,bcginnina oC con.truction.
The tirst cantilever bridge. were indeed timber bridges. In his writinp, Cacsar
mentions Gallic works built with tree trunks set orthogonaUy In horizontal rows,
the latter being tilled with boulders acting as counterweights (lig. 1.2). Structurcs
of this type can still be found in China, India and Tibet.
"
Fig, 1.4
_-:C:"'~'.
...
, j:'
In moro recopt dmes, in 1811, the American engineer Thomas Pope designed a
timber bridpwit!t.a 5~O'm span. This would have had a very shallow arch rcsting
on two qJllOIJry .butm~nts from which it would have been built as a cantilever
structure by assembling prefabricated components (tig. 1.3).
. Fig. 1.4 shows the building methods conceived f, r this project.
:,r ..,.
...,.......
. . ~~.:.o\, . ,......4y
\l,.
Fig. 1.2 Cantilevered timber bridge (an impression from the art historian Viollet
Le Due)
or
Overturning moment
due to weight of ~
centrmg
i
i
Fig. 1.5.
f'
f:
...
"
,i_
t'
Genttal background
Rio Peixe in Brazil by the cantilever method. The reinforcing bars of the deck
were extended by threaded sleeves as the concrete \vork progressed.
Other works followed both in France and abroad. Caquot designed the biggest
cantilever reinforced concrete bridges in France, notably the bridge at Donzcrc.
having a centre span of no Jess than 100 m (fig. 1.6).
This method has not been extensively developed, however, on account of the
large amount of reinforcement needed to ensure the adequate strength of the
cantilevers, and to contain the large incidence of cracki,ng in the top su rface of th,e
deck.
2.3
:_t.
,),
i~"'!!!1
:...........-.,:..::::~~.--.:-- --C-~.
Fig. 1.7
..~~-~
.,...,."
General bQckgroulld
of the approach viaducts and were supported by the main piers. which extended
above the arch abutments. The central section of the arch was then built on a
centring weighing 200 t, assembled at the bottom of the canyon and lifted by
cables fixed to the ends of the already built arch springers (fig. 1.10).
However, it was Dr Flnsterwalder in Germany who inaugurated the cantilever
method, with the construction of the prestressed concrete structures of
Oa!dulnltcln and NC4:karrens (1950-1951). During the same period. the con
tractor, BouSliron, aI,O used this method for the construction of the railway
bridlO of 1. Voulto over the Rhone (1952) (fig. 1.11). From that date, the evolu
tion or cantilever CODltru~on accelerated. The period 1952-1953 saw the con
struction of .truct~OI u.~g prestresllng rods by the contractor Dycke,rhojJ and
Widman. in QcrmanY. l'hcy used travelling concreting skips supported by the
cantJ1evon (WOrm. brid,e over the Rhine, 101-, 114 and 104m SpaMi Coblenz
bridge oyer Ihe.Moselle, 102, 114 and l23m spans) (figs. 1.12 and 1.13). In
France, the first cantilever construction by In situconcreting of the segments was
on the Chazey bridge over the Ain (three spans, 41.2, 57.6 and 41.2 m long
,,...;It....:...
.' nn
.~
't, ::
"
Fig. 1.8 (0) and (b) Construction of the Marn~ bridges
/.
. ..:::::::;:::- .
/'
_______
..
. ..
CobleF
.. ..
.. .
-n-'
. \\.\'.7_~obleD
'-c.
",-.- .
/./
!
/
\ \~ ,
.>.. . . . .~
~'
,..........,
I .....;
.f '.
. . .............:.......,.,.='"I-~"",.
. l~ .'
_.~........ ;:~t~,
....~;~ti
..
- -..,.. Cable E
-...:..
.:.~>.~;~!
Timber fromo
wilh sloo' Ii"
',A\
Fig. 1.9 Construction of the arch springers of the Caracas-La Guaira motorway
viaducts
Fig. 1.10 (a) and (b) Positioning of the centring and keys of the midspan section
- "'~:~-~"":-
.........
-',",""'.
__
Genera/background
...
.
~,~
~'''''''n'''''''''
-'--''''''''''''''t--''''''~'''''------''''''''~r
!,~:~':. . _.:.
~ :;. .i.. ~.: 1 '~"j~~.,,,;
~ .2""'~d.:
. ""'~x_~""""',4'~':'::'~'"\I:"''1'-'''-I<'''i-''.'''f.!''''~!J~';'''' .'.'
347.00
~w.~w~
I....... ~I
3~.OO
10200
._-_.. _-_.- ~I
11400
12300
. .
~'
~ ~:"
~~
IZRtI
. . . . .
Fig. 1.14
Savincs bridge
!-4-~'1 counterwtf9hl
.;;rr
I
CS
;,
other structures:
-
~:~!,~
10
II
Genera/background
::'~~~'~~<~1j~':.,.,'."",,:,
~~tilt~~~
(b)
. :"',':'
OiJlCI ~dle
Fia. 1.15
."-'
mobile forms
".
.,', '~k"I~".:'Ii ..
.
W..
.,.",'
.
Another step was made when prefabrication was introduced into cantilever
construction. The first French bridge to be built by the cantilever method with
prefabricated elements was the Choisy-Ie-Roi bridge over the Seine. The joints
were glued, the elomcnts integrated by prestressing. The bridge has three con
tinuous spans, 37.5. 55 and 37.S m long. It was built in 1962 by the contractor
Campenon Bernard. Since then, Campcnon Bernard have built several other
similar structures: the Pierro-Benite bridge over the Rhone, the upstream and
downstream bridies of the Boulevard Peripherique over the Seine, the Blois bridge
over the Loire and the viaduct linking Oleron island to the mainland (total length
2862 m)(fig. 1.17).
.- .. _
..,..,...... _ ~ ~ J
)3
12
Genera/background
13
~~~~tf\f~7it~~_,~~%:;".::.~
.. ('
(a)
~jlr.p"~
Fig. 1.1 6
;;
n'
1~,
t~
\~
~:I
'-,
!',
r ~~
Choisy-Ie-Roi bridae
This new construction method was soon used widely, and abroad some
spectacular structures were built in this way: the Chnlon viaduct near Lausanne
and the Rio Niteroi" Bridge in Brazil (totkllength 8 km). Recently several bridges
j""
..
Cantilever techniques are likely to find new openings in years to come in the
design and the assembly of cable-stayed bridges. Brotanne bridge, below Rouen,
already sets a precedent, its 320 m main span is the IBtlest prestressed concrete
span to date. The central part of this structure consists a cable-stayed bridge
built by the cantilever method from the towers, using the multiple cables which
were arranged in a fan shf,.pe.
or
Fig. J. J 7
14
I~
Genera/background
.--- .
i.'
<
3.2
Fig, 1.18
;.
~
.....: .....
'f'
. ~~r.;
~~--""""""""'':'~'
16
Genera/background
17
Spans (metres)
o
Prefabricated beams
10 20 30 40 50 GO 70
--
--
Con'ileve
I-
1_ _ _
Incrementolfounchinq
1_
Self - launChing
-
--I
-_
- ..
-~
C4!ntring
140.00
..,..
13.76
-
-~
~l-
19.Q2.LJ~
Fig. 1.20 Field of application of the processes used to build major prestressed
concrete bridges
524.70 .
~30i---r-: 10.45
. 'MI .. _.I.~
-..
~ t*11
2Q8.00
71.00...._ _
4.40'
La
4,,4.3,ji 4A
00..
.1
',:,.,.-",
L,.;'1::'~
:.> . '"_
Fig. 1.21
.1'.-."
..".
Bendorf bridge
the Hikoshima Ohashi bridge in Japan which has a main span of 236 m;
the Urato bridge, also in Japan, which has a main span of 230 m (fig. 1.23);
the bridge linking the Karor and Babefthuap islands Bast or the Philippines
the GennevilJiers bridge across the Seine with a 172 m span (segments con
creted In situ);
ments);
(I) For historic reasons the Maracaibo bridge is worthy or mention because, ror I long
time. it ~as the pre~tressed concrete bridge with the longest span. Built with severa! cable
stayed bays, its construction did not. however. involve CAntilever techniquea to I sig
nificant extent. .
140.00
..,
_ 5500~.
"
9.OQJl.
-I
~ Normal ronge
l. __ ~ Exceptional ronge
9.Q,44.35
63000
24000
.Moq,t
Urato bridge
V:"
.. .'..;'::;'..,
~.
"
:;~~ ~ .
. :.. 1
~/1~J':~
.:...
~;\:~~~
:"
....
~: .~':
Generlll background
19
girder. A similar method was used for the construction of the B3 motor\l,'ay
viaducts in Paris, with spans of approximately 38 m.
The use of lightweight aggrega/es (expanded clay or schist) in the concrete by
rcducina the dead wciaht of the deck can also permit a more economical construc
tion of large spalll built by the cantilever method.
Several structures have already been built in ligh/weight concrete in Germany
and mainly in HoUand. where several have spans around ISO m:
-
Lightweight concrete
Fia. 1.25
Ottmarshcim bridge
the Bonhomme bridge across the river Blavet, a structure with sloping piers.
with a 18S m opening and with a 146 m deck span between piers (segments
concreted in situ) (fig. 1.24).
20
In France, the Ottmarsheim bridge is the first large cantilever structure in liabt
weight concrete.
CHAPTER TWO
DECK DESIGN
I METHODS OF CONSTRUCTION FROM PIERS AND ABUTMENTS
1.1 Cantnever construction generally starts from the main supports of the
J./.l
'
22
Deck design
23
Wind or construc;lion
loodinQ
ttttttttt
QverlurninQ ......+-..
momenl{
iii
I Iii
i '\
ik...\!1
SeQment
Contilever
BALANCED STRUCTURE
--
BALANCED STRUCTURE
r--
::0
"
'C
.Q
>.
III
/ Conlilever seclion
J:!
..,.....,-;,.;I'""""'..-..
vk7
...
__ Temporory
]
support
1) ~
oc .....
--'Ip-J'L.+I.LI~~_-LL"_
Fig. 2.2 Using tcmporary supports
I'
Supplemenlory
support
~1103 ..f
g _.
J
+' I"
,03.,.
o
+I
,_
t"'J
.!:!
:II
U.
-::
structurcs, when the centre span passes over a river or a highway which pre
cludes the use of staging. The bank spans arc then concreted in silu on the
centring and the centre span is built by the cantilever method (fig. 2.4).
Structures built by this method include the bridge across the Rio Tocantins
(Brazil), the bridge across the Rio Cuaiba (Brazil), the Goncclin bridge across
tho river Isere, and the Port de Bouc bridge across the Aries canal.
(c) Counterloading or anchoring one cantilever span whilst building the adjacent
span. This case more usually arises when building main river spans when the
shore (or bank) spans are short. There are two possible solutions:
The first solution is to ballast the end of the bank cantilever or to provide a
counterweight (fig. 2.5). The bridges at Lacroix-Falgarde and Croix-Luizet,
~I
.1 8
h,
/i
11]
nil/II
illill
...,
24
Deck design
25
Pre5lressed
if~
''lie-rod
Prestressing
/,
'coble
I'
. 1--PreSlress,ngcoble
....... 1
SlOQing
$uppclrt ,.
Support
ground). The I~ngth of the tie rods' must be sufficient to ensure that the
angular movements of the rods due to linear variations of the deck do not
cause excessive fatigue stresses due to bending at the hinge points. On this
account the components of the cables (steel wire or strands) are usua/ly
arranged In a single row located in the axis of the hinge.
The mortise-and-tenon anchorage consists of extensions of the webs of the
deck beams (forming the tenon) which slot into recesses fonned in the abut
ment (acting as mortises) (fig. 2.8). The bearing plates which allow free
horizontal movement of the deck nrc fixed between the top of the tenon and
the top element of the mortise in the case where the restraint is constantly
against an uplift of the deck.
downwards, the double restraint is adopted, the bottom bearing plates, which
are placed after the top plates have been fixed, being forced against the
The abutments of the Givors bridge, together with those of one of the two
the structural capacity of both the abutment wall mortises and tHe tcnons.
The deck reactions at the abutment must be calculated using a 50% overload
"::>;;~:::::~~::~~~~::.
Downword mtroinl
l I,
Fig. 2.6
Ii'
iii
Double restrOlnt
:J-'-
26
Deck design
27
LONGITUDINAL SECTiON
Slllfenin9 membrane
I
,
freSlrnsillQ cobin
i_
..:~~~~~::::;~~: :'~::.:::~:.::.;,.:.::
1
I11I,'
il
Abutment
(a)
8~t30
(a)
SECTIONAL PLAN
Pr'
'J()+f.
3~5
"r
30
llOT/CABLE ~ 1l0YCABLE
~ ~ J
.~f'F"i 1,
12Tl~
71
31ZT15
t fl f
5 ill f&:?l -,
--'
7\~-_:
nTI5
(b)
(b)
Fig. 2.9 (a) and (b) Example of mortise and tenon anchorlle
of the deck on the abutment. it is expedient to build the centre span in light
weight concrete whilst the bank spans and the abutment springings are built
in traditional concrete (fig. 2.11). Such a solution was adopted for
Onmarsheim bridge and is planned for a structure across the Donmere canal
at Tricastin (fig. 2.12).
(d) By means of temporary support strutting beams. enabling the sections of a
cantilever span to be built symmetrically from each end in pairs. This
particular solution implies that the deck is built as a succession of segments
built symmetrically to the axis of each span. A temporary steel girder span
ning the gap (a Bailey bridge for instance) supports the formwork and the se!f
Fig. 2.10 (a) and (b) Structures spanning the Seine at Putcaux bridge. Longitudinal
section and detail of the abutment prestressing
Li9htweiCJht concrete
Tradltionol cone/ere
A "1.7 to t.8
Fig. 2.11
_ ...
_-... J
....... ~
Deck design
28
29
Framewark suppart beam ( Bailey bridge 1
203.00
~
30.25
>'''~.
I ,
\.
Supparl pedestal
142.50
3025
Ughlweighl concretl
.. \
l:25.25 ..,P
roo
,.~"..::"._.- ~~.
~
=n~::::;!fS
'50
Sirutting beam
....
(0)
(e) By proceeding with cantilever construction on one cantilever once the next
cantilever has been connected to the adjacent deck beam. This solution is
onen adopted when the widths of adjacent spans vary. This solution has the
disadvantage of entailing an arrangement of cables which becomes more
complicated if th~.cantilever length greatly exceeds half the span.
/./.2
Cantfle~'er COllstructlon!rom
tire abutments
(a) temporary supports set in front of the abutmenls (lig. 2.14) as adopled for the
8asse-Combelle nnd Pierre-l3cnite bridges;
(b) by the abutment self weight acting as coumerlveight.
TOP VIEW
In most cases the bank span cantilever is embedded in the abutment. and thus
forms a stable unit (fig. 2.15). The abutment is Ihen said to be balanced.
The bridgc across the river Reallon, Verberie bridge, Bonpas bridge and the
viaduct ofle Magnan (fig. 2.16) are examples of this type.
The deck can also be fixed nexibly at each end by means of a shorl balancing
l---
L-==~::~
~
i- r-j--
8I
A
1
r - - - - - - - - - -..!.[--.. .-J
~. r'-+--'-'-d>r-._._._._.t-H._I__ ~=l--__
~. L.
rlt.
~---r---*
Ballast
(c I
AnchoraQe in abutment
30
Deck desigt'
31
Leon concrete infill
Balanced abutment
I..
....... ; /
41.25
Ii
1:JI=r
~l-r
.i'::::~::~:;:~:::~::::::::::=:::::::::~::::::::~
NlOpre~,
btOrirl91
( c) Verb"i, bridge
(c.:) Vcrbcric
briulIC
2000
'.--"'-'~;-4.
6000
_._..
~.
I
Sond'9(O",1 fim/l9
.j
span incorporated into the abutment. In this case. free movement of the deck is
ensured either by rubber or sliding bearings or by tie rods-with double hinges
(liS. 2.17).
Tho deck mUlt then be anchored or tied to the abutment since the uplift reac
lion is opposed by the dead weight of the abutment-which is eventually
baUuted-or by the resistance of the foundation. It then becomes necessary to
48.50
I
15.00
\
50-';: 14.50':
-\
r ......:--
.
~\
;\
-----__ ---k..Q.:&i::,.-&:r~n:_-~;~:~
--------- ;)-1 0
r._ ---------=---i~
...
i ~
It
15.00
(bl
Double- hinqed I'e-,od
3.00
Fig. 2.17
. _
':"".'!'.. l....
Ie.
32
Deck design
Anchoring span
~.~
t~.~\~,\
....
;. J~;;'<~
~'<'
~~.:: .;:~~
AnchOr piles
~"
15.40
1.2 Cantilever constnactlon can be carried out rrom temporary staging but this
Is exceptional
This method has occasionally been used to join. prefabricated elements forming
the ends of the decks near the abutments (fig. 2.21), for example at the
downstream bridge of the Paris Boulevard peripherique.
The' overpasses of the Lyon~renoble motorway were also built with precast
segments joined in a similar way (see Chapter Five).
24.50
Mer the construction stage, the cantilever beams must be interconnected to com
plete the fmal structure. The designer can choose between a number of solutions ~
- - - Tetnf,)OtOry support
\ Foundotion
Fig. 2.19 Temporary fixity (in the case or hinged arches)
The easiest solution is to make up the deck with equal cantilever beams intercon
nected by sliding hinges (fig. 2.22 and 2.23). These hinges transmit a shearinK
force (in the case of an imposed load on one cantilever only) and ensure free
expansion of the bridge by allowing longitudinal displacements of one cantilever
beam in relation to the other. The continuity 0/ deflection-but not that of
rotation-is then restored at the time of connection (fig. 2.24).
34
Deck design
35
#
Shd'nej h'"ges
"
...... ...
.iiii-f
i!
~:~{
~~
Fig. 2.22-Syslems wilh hinged canlilcvcrs-<liagram I
~......
I
~I I I
I I I I I
~~
(0)
IT
,...._.J.Lt
Temporary cables
""
r=====rr==
..
~IIIIIIII
.lJ?
:
1/2
1r
:J
1'# { .
...;....
Shd,n9 hJn9U
=:ll
,
;-e
.(
__ __ ._-,-.. __
--t_'
Fig. 2.23
Wat.r t'llhtnns
Pavemen' 10101S
JlI I I
Rods orrollers
, ~:.
~~\,..==
~"
~,.
:;,;"
.....,;.
Fig. 2.21 (a) anc (b) Assembly of the Left Bank segments of the downstream
bridge of the Boulevard PeriphCrique
'1~
.-~'
Fig. 2.24
'_"---"~'''W
36
It should be noted that in the case of bridges with multiple spans, the introduc
tion of a sliding hinge at the cen tre of each span requires the building of each
cantilever into the abutments so as to maintain structural stability when subjected
to asymmetrical loading. In this type of struct'Jre the lengths of the end spans are:
either approximately half the length of intermediate spans when the bridge con
sists solely of balanced cantilever beams on piers (fig. 2.22); or approximately the
length of intermediate spans when the bridge deck also involves cantilevers built in
at abutments (fig. 2.23).
Structures of this design are obviously simple as they are statically deterl1tlllate
under the combined effects of self-weight and prestress and become statically
indeterminate only with respect to superstructures and additional toads once the
central hinge has been incorporated. This makes design calculations easier as the
statically indeterminate forces for each span thus amount only to the vertical reac
tions transmitted by the hinges. Moreover, after taking into account the per
manent load, irrespective of the additional loading arrangement, these structures
exhibit bending moments of constant sign. This results in a considerable
simplification in the profile of the prestressing cables.
Nevertheless, this system has many disadvantages: a lower ultimate strength
than a continuous structure. as each hinge behaves as a plastic hinge with a zero
monlent of resistance; hinges are difficull to design and construct as they are
delicate components with poor long-term performance; a multiplicity of expansion
joints; risk of uplift of the deck over the abutments, when the span of the end bay
is approximately half that of the adjacent bay-this can necessitate having the
deck integrated \vith the abutment or the use of ballast (see paragraph 1.1.1.2(e);
finally, and most important, progressive settlement of cantilevered ends during the
nrst years of the working life of the structure, deformations caused by shrinkage,
creep of concrete, and relaxation of prestressing tendons.
Even though the break brought about by this deflection in the longitudinal
profile of the carriageway does not affect the mechanical properties of the deck, it
is an inconvenience as far as the appearance of the structure and the user's
comfort are concerned since both are highly sensitive to the slightest
discontinuity.
The extent or this hrcak in J1rofitc can be reduced to n certain extent by estimat
ing accurately the denection of the cantilevers and compensating for it by an
initial compensating camber at the time of construction (fig. 2.25).
This initial compensating camber will be visible at the completion of the
structure but it can be anticipated that after roughly three years, or thereabouts.
the bridge \viU have attained the expected longitudin;tl profile.
The d~13yed deflections in bridge structures \vith central hinges are of course
reduced when the structures are built using prefabrication techniques if the beam
elements are used after a suitably long lapse of time.
Sliding hiltges may also be replaced by sliding conllectiolls which allo\v for the
Deck design
37
Initiol compensating hog
+ -- - _
_-- -- -_u
Fig.2.25
Sliding hinge
Sliding connectIon
&m
Fig. 2.26
Bored moving
piston
--
'~t't17/J
'
Stationary cylinder
Fig. 2.27
38
39
Deck deslgll
Prestressir\9 cobles
.,7!l.1.~
2.2
i
i
.'
!
I'
' - the bridge across Rio Ulua (Honduras) with three spans (60, 120 and 60 m
respectivdy) and with a suspended span of 36 m;
- the bridge across the Rio Parana (Brazil) with a main structure of eiaht
bays of 109 m span and with suspended spans of 4S m.
I'
- -1:
--:':'-~~-..~
by the reduction by half of the break in the longitudinal prom~ whose extent
is already decreased by the smaller span of the cantilevcfs. S~pcnded
Suspended span
Fig. 2.31
Cantilever joint
..
Mfl
&_
2
~
~
':~~'~"'~Y~
.~
.
-~..-"""
~
-----~.
------':::::~12
-----
Mt/
<D
Vi'1!p/2
T
Suspended.
spon
/~.
.'.-
Hinged cantilevers
Contilev.r~ w,th suspended span
of some wt t9ht
span
--
4S
'36
=-= 0.30
120
Fig. 2.32
. ~J
Reduction in support bending moments
".,,_. ,..,~t.~~_:4~tIf:;~
40
+*.
fa
~
I
:.
1/3
J!.
Fig. 2.33
J.
Deck design
41
are requited for the suspended span in addition to the equipment for cantilever
construction.
1/3
2.3
This ratio is as high as 0.90 (=49.7 /SS.3) at the Saint-Jean-de-Maurienne bridget but
this hardly belongs to the category of cantilevering. This arrangement can be justi
fied for a three bay structure when the end spans must be very short, amounting
to approximately one-third of the centre span (fig. 2.33). Uplift forces above the
abutment can be appreciably reduced by bringing the cantilever joints nearer to
the pier.
The suspended span usually consists of independent I-beams or T-beams of the
same number as the webs of the cantilever cross-section (fig. 2.34).
Apart from the above advantages, this structural form retains the same
disadvantages (Io\ver ultimate strength, multiplicity of expansion joints) as the
system with centrally hinged cantilevers.
Moreover.. it leads to the use of two different types of plant: launching girders
Keying segment
-.
.I
RIO ULUA
Sus~tnded
16
...
..:,~
4)lloO
~
CD
-~
S5tI 2.10 ii 2.
+16.
.'
.
.
.
lJ
-
orIl1~~8
--"1-40 ' 30
-
-4,
15 or
,30
.- C
I.
25:0
0'
beam
2'
II 2.10
...,...--...---...
~I
8.10
RIO PARANA
12.50
.., ,..
t20or40
~[.- . _40
Jl
~
.g
&tl
200r
I.
+19
-f
_f
..
12.05
,-rel
14~ I
1.201~
...
f6
.I~.I
-15
2.75
GO
.....
Suspended beam
'Boxbeom
Fig. 2.34
Transverse cross sections of the bridges across the Rio tnua and Rio
Parana
.
I
I
Fig. 2.35
Box beam
1,1
Iii
..
I.
;
r:
.
'
... f
The ver/ical deflections in a continuous structure are indeed far smaller than
those met in' hinged structures and the continuous structure also removes the
disadvantages incurted by breaks in the longitudinal profite.
For instance, the vertical deformation caused by a uniformly distributed live
load will be four times lower for a continuous structure with constant flexural
stiffness and made of a very large number of identical spans, than for the same
structure with central hinges.
This difference in behaviour of the two forms of structure, together with the
influence of precasting techniques, is demonstrated by the centre span of the
Choisy-Je-Roi bridge across the Seine, where the deflections at centre span have
been calculated for two extreme bases of design: an in situ concrete beam with
central hinge and a precast continuous beam. These deflections are summarized in
the table below.
Figure 2.36 shows, for both bases of design, the cantilever deflection curves of
the centre span under dead load and prestressing forces. The two diagrams of
figure 2.31 show respectively the long-term deformations of both forms of
structure under constant load, and their instantaneous deformations under
additional loads. From figure 2.36, j.t transpires that the behaviour of the t\VO
structures is similar in their statically determinate phase. Deflection y and the
rotation 8 of the cantilevers are slightly lower in the structure with a central hinge,
for which the prestress compensates a larger proportion of the dead load moments
(82 instead of 58%).
42
Loads
Ely
46
-38
in sllll
3
,3
3.6
3,6
2.4
-2.0
38
2.0
-22
-1.2
3 .
3.6
0.4
- 8
4.596
,t ".,cture
::
0.4
15
0.8
27
1.4
42
2.2
22'
1.1
4.5
4.5
0.8
16
1496
4.5
I.S
Addition aJ loads
4.5
- 7
+ 2
~
ADDITIONAL LOAD
~~
0
0
11
1.S
-4
4.5
7
7
0.8
UQiZ]i
.A. .. A l i A . ,,41
P,"tr'lsed connection
~
Pi... ~31
0.8
0
20mmt-1---------~~
1---------40mm...
50mm'
Continuous precast
structwe
'
Thus. when submitted to imposed load, continuous structure,s are three times
stifTer than articulated structures.
These results i11ustrate the superiority of continuous structures:
due to the low valu, qf the longlerm deformations which must be taken
into account when determining the initial compensating camber. These
deformations may be upwards. as in the case of the Choisy bridge. due to
the size of the intesr,lion prestress of the centre span;
owing to the lis' drastic consequences 0/ a lack ofprecision ill the eSlima.
lion of the modulus of de/ormation of the concrete, or of the prestressing
force.
The above table ShoWI that with continuous structures, a 10% variation in the
value of prestress in the beams has an influence upon the shape or the cantilevers
prior to'~ssembly three times less than with hinged structures.
10mmt-1--_....::
in situ
ContfnUOU$" preco$t
30mm
deformations
Structure v.ith no
load (final)
30mm l
,'rue'ure co,t
DELAYEO DEFORMATIONS
Y I 8
MPa) (mm) (dc&rees)
~~'
Structure with no
load (initial)
Long-term
Omm.
43
Hi~
I
leE I
Deckde,;gn
l
finally, and above all, deformations subsequent to assembly may affect the
general levels but no longer h~ve any effect upon the relative slopes of the
two cantilevers. Creep notwithstanding. the continuity of the longitudinal
profile can no Ionser be subsequently destroyed.
Deck design
44
:::.:....
~.
:1
I
Keying segment
Integration cables
(a) Keying segment concreted after connection or the two mobile gantries
.1
.,
\.
I
!.
il
I.
;1
d
t,
it
Integration cables
.i
.;
I
(b)
II
I'\
I,
I
I'
Keying joint
-j
I"
Inlegrolion cables
,/Ke y joint
1
,j
4~
by a joint which will be concreted when establishing continuity (fig. 2.38(a)). The
size of this joint may vary between several hundred millimetres and approximately
2 metres (the overall dimension corresponds with the space occupied by the
tensioning jack of the cantilever beam cables for the last concrete segments. t\
similar arrangement will be adopted if the cantilevers consist of precast elements:
a joint 80 to 100 mm .thick will be left between the opposite faces of the two
cantilevers and will be concreted at the time of integral connection (fig. 38(d.
With this arrangement the placing of a central segment acting as a keying elemenl
may occur.
The continuity of the structure is ensured by prestressing cables (integration
cabies) tensioned after hardening of the concrete, of the segment, or of the keying
joint. These cables which are mostly located in the lower flange of the beam
produce statically indeterminate reactions which must be taken into account when
designing the bridge. The bending moments due to linear phenomena (variations
of temperature and moisture, shrinkage effects) may be increased if construction
takes place with large differences in temperature occurring between the upper und
lowcr nangcs of the cantilevcr. As temperature conditions cannot remain constunl
during the hardening period of the cantilever concrete, the ends of the opposing
cantilevers must be provisionally fixed on top of one another by it mechanical
dcvicc (structural sections nnd steel joists) to avoid the disruption of thc joint.
TIlUs, continuous systems arc ultimately statically indeterminate under self
weight and prestress and their degree of indeterminancy is higher than that or
hinged systems.
On the other hanu, as with any continuous construction, it is necessary 10
permillongitudinal expansion of the bridge by cll,reful consideration of the support
conditions. without creating high bending moments at the piers. This problem can
be solved either by the flexibility of the piers themselves, or by using elastomeric
bearings or sliding supports. Bearing design and the infrastructure of the piers best
suited for cantilever construction will be considered again in Chapter Three.
With very long structures with multiple spans one has to incorporate joints in
the cantilevers or suspended spans to ensure free horizontal movements. These
expansion joints are commonly placed 300 to 600 m apart (fig. 2.30).
It is advisable to position these joints not at mid-span but in the area of points of
l~
025 to 030
":!
tl
Inlegration cabl"
.'
I
Cantilever joint
'
~it-r9t~
.
'
I
I.
,J,
,j,
.i.
,I
46
Deck design
zero moment (that is almost at quarter-span) to reduce the magnitude of the defor
mations. This was done at Oleron viaduct, at la Seudre viaduct and, more
recently, at the Saint-Cloud bridge.
In order to permit cantilever construction of the beams including the expansion
joint, the latter is locked provisionally; prestressing cables pass through and are
removed at the final phase. The calculations made for the Oleron viaduct show
that, under permanent loads, vertical deformations are thus decreased in the ratio
of 3 to 1 and angular changes in the ratio of 15 to L These ratios become 2.2 to I
and 3 to 1 respectively under imposed loading (fig. 2.40).
The diagram in figure 2.41 corresponds to the case of a continuous bridge with
a large number of equal spans of constant inertia (span l), containing one hinge; it
represents the curve of deflection of the hinged span under a uniformly distributed
live load of 10 kN/m (=1 tim), for various hinge positions. It is seen that when the
distance between the hinge and the nearest support is about 0.2 I, the deflection
curve of the hinged structure can be compared with the deformation curve of the
continuous structure.
To round ofT the survey of hinged and continuous systems, attention is drawn
to a special case: the Chillon viaduct in Switzerland, over 2 km long. The
structure expansion is accommodated by special joints similar to sliding hinges
and located at the centre of certain spans. These joints arc fitted with devices
maae of steel parts fixed to one cantilever and sliding into the other by means of
sliding and oscillating supports (fig. 2.42).
47
0.11
0.21
03t
05t
04/
0.7t
06/
0.8/
'--=
'" _._,
hlnlle
S pon w,'hout
..
~:.,,+--.:t.::::p~.,.--r--r
~....
Art.0.31
~.
,.
I /'
,
I __
,~,,...
0.91
,.,'
/.,;/
./
I ./
1'1"'/
~.'~.JI /'1"",)//
.
Art.
O.4t '~~
I /
Arl.O.51.
"'.
Fia 2.41
\,./
"u,
3 SPAN DISTRIBUTION
3.1
., 2.
II
c
.2
7.
Fig. 2.40 Deck deformations under imposed load as a function of hinge position
(Oleron viaduct)
Whenever possible, the lengths of standard spans are equal and the deck consists
of a group of identical beams (fig. 2.43). What should then be the lengths or the
end spans?
It m~t fU'lt be remembered that with a structure of a given length resting On its
abutments by means of simple supports, the optimum end span is not equal to
one-half the standard spans. For instance, in the case of a cast in situ three-span
bridge. from the point of view of the distribution of bending moments in the
structure. the economical value of the ratio between end span and centre spaD is
bctwe= 0.75 and 0.80. With a similar structure built by the cantilever method and
prestressed, otha- factors must be taken into account, namely the mode of
application of the dead load, the prome of prestress with its statically indeler
minate efTects, and the method of construction adopted for the part of the deck
..
:",~~
48
T
T
s~~n91 B~o~
0.651
I.
, (..
lq50~
Deck design
49
When the connection of the end span occurs after that of the adjacent span, the
c:nd result will be the same provided that the reactions on piers and abutments are
adjusted by jacking and adjustment of relative levels of the bearings.
3.2
Even when it. is not possible to give equal \'ailies to all the spans, cantilever cons
truction pro~des considerable flexibility in span distribution.
J.2.1
Fig. 2.43
close to the abutments. From experience one finds that the above mentioned ratio
must be selected between 0.65 and 0.70. Similar conclusions can be applied to the
end spans of structu res with multiple spans.
In the case of such a span distribution (solution a), the ends the structure do
not tend to rise under dead load and prescribed highway loading, the abutment
reactions remaining broadly positive.
In reverse. if the' end spans are appreciably longer than half the adjacent spans,
building the part or the deck included between the end of the bank beam and the
abutment requires the use of falsework or temporary supports.
If. on the other hand, the end span is close to half the adjacent span, construct
ing the deck is made easier since it is fully cantilevered. However, special arrange
ments must be taken to avoid the deck hogging over its abutments (solution b).
As seen in paragraph 1.1.1.2(c) these arrangements can be made either by
ballasting the end segments or by anchoring the deck to the abutments. In
practicc, it is advisable to give end bays the smallest possible span compatible
with the preservation of positive reactions on the abutments, in order to avoid
involving a device to stppress uplift. This usually amounts to extending the
cantilever of the end span by one or two segments which may be made by the
cantilever method before connection to the adjacent span, without using
temporary supports, the stability of the cantilever being temporarily assured by
coun terweigh ts.
When the structural form of the deck is a continuous beam and the connection
of the end span is made before that of the adjacent .pan, the weight the extra
segmentJ bunt by the cantilever method balances the upward reaction at the abut
ment due to permanent load and to imposed load (increased by 1.5), as if they had
been built on centring (soluti,on c). The structure is .,lin statically determinate.
once the pro\isional fixing to the bank pier has been released.
or
If the structure spans a gap where local conditions (such as river clearance) deter
mine a span L of the central bay and where smaller end spans (length I) are found
preferable because of their lower cost, the transition will be effected easily by an
intermediate span). equal to the arithmetical means of the spans L and I (fig. 2.44)
or \vill be close to that value.
A~t(L
+ I)
The Oleron viaduct and Saint-Andre-deCubzac bridge across the Dordogne arc
two examples of this type of structure (fig. 2.4 5).
IA a 1/2(L+/ll
Fig.2.44 Structure with two standard type spans
or
....,
I(
1..
4l5190~ 1........
36.70
F,ig.2.45
74.05
5x95.30
~ ... 4x57.90.. I ~
74.05
36.70
so
Deck design
51
3.2.2
Generally, if the structure crosses a wide. deep valley it may be desirable for
aesthetic reasons to make the spans vary regularly to match them to the apparent
height of the piers (fig. 2.46). The spans [, of the structure are governed by the
following condition:
(a) Variation in the length of the standard segments by overlapping the formwork
..
panels.
(b) In the case of the cast in situ deck; variation in the length of the pHecap which
I: (_1 1+ 1 i, -
=0
d, + (-I)"d.
/.1
in which d: and d. represent the lengths of the portions of the end spans built on
slaging. Tho: lenglhs of the differenl beams are equal to:
Figure 2A i illustrates this case. With the nine-span structure shown the span
lengths arc indeed such that:
20 - 34 + 40 - S2 + 60 - 52 + 40 - 34 + 20 - 4 - 4 = 0
and the lengths orthe beams 2 and 3 IIrc equal respeclively to:
;; = 2(34 - 20 + 4)
= 36 m
Thus. with the viaducts of the B3 motorway whose spans were constantly variable
due to tho exceptional congestion at ground level a 10 cm lolerance in length of
lhe precast segments together with the use of standard 3.4 and 2.5 m segments
made possible spans between 27 and 52 m.
Similarly, at the Saint-Cloud bridge-where foundation conditions required a
short transitional span of 46 m between the structure spanning the Seine, which
included spans ranging from 90 to 100 m, and the 66.9 m span standard bay of
the access viaduct-it was, however, possible to construct the whole bridge by the
cantilever mothod by adding tcn precast segments at the end of the cantilevered
beam 0( pier P II (Ii 2.48) after connection with the balanced cantilever bellO' of
pier P12.
The Givors bridge across the Rhonc. and the GcnneviJlicrs across the Seine
::r
_I'
3.2.3
66.90
P9
Structures with ullequal alld cOllstanlly l'ariable spans can be built by the
'I'
6690
-_-_-:.-:.~r~~_~~9m8n'$
ilDL
.,,4600'1_-19JL_
PIO
PII
P12 ~r~---~.:':"'.:
.-:
;. ,Q (A., . .';.,.... %l'~
;30 00
~~!
4 32
~II
)0
36
I
)0
I ..
44
)0
i ..
60
)0
60
)0
IE
44
)0
I~
36
32 4
)0
I ..
I r---:
1SQbJ ~.l=fEr
20
34
40
52
60
52
40
34
20
300.00
110.00
20.00
"I. I.
110.00
'\
130.00
.. ..--.
~.".--~;'!.\l1lF'~
__
..
::=:Jt::4:
~~'.
..... _I;> c.+~~~---~'"
. _~ ._..__ \72.00
--_12~1
W:S&;U___
= \
-
$I
(b)
._.!!_29~.
..~!
cU.st>.iIC,
$1aQ8
2nd$l0Qt
Fig. 2.49 (a) and (b) Construction of the Givors and Gennevilliers bridges
52
Deck design
53
both have a short centre span between two large spans. The cantilever construc
tion of these structures made it necessary for the cantilever beams on either side of
the short bay to be made in two stages as shown in figure 2.49. With such proce
dures it is necessary to rest the cantilever beams on simple supports during the
second stage of construction in order to avoid the transmission of high bending
moments to the piers.
Webs
3.2.4
Finally, it should be noted that the difficulties described above are increased if the
structures are skew or curved and consist of two or more parallel beams.
With skew bridges (lig. 2.50) it is necessary to determine the length u of the
precast segments so that the joints of the different parallel beams coincide. This
result can be achieved by selecting u as equal to a multiple or a submultiple of the
displncement 0 due to the skew, or by building asymmetrical pier segments.
If the skew varies from one support to the next it should first be ensured that
the location of the transverse prestressing cables is compatible with the position of
the joints whilst leading to as regular a distribution of prestress as possible. The
prestressing cabt~ spacing e must then be a multiple of 0.
With curved bridges similar problems must be faced and arc made more severe
by the trapezoidal shape of the precast segments resulting from the need to keep
joints perpendicular to the longitudinal axis of the bridge (fig. 2.51).
Abutme"
s~men:s
==:t-=--=--=t.=__ -
I,!-
Transverse prestress,ng
cables
Trope,o'dol
segment
II
d\+d!.,
Tronsv~rse
connect,ng Jo,nt
54
4.1
Cross-section type
The transverse section best suited to cantilever, construction is the box for the
following reasons:
)
~
l,
II:
(a) On the one hand, due to the construction procedure adoptcd, the bending
moments arc negative over most of the spans and very lar" in the rClion of
the supports. As the bottom flanges must withstand high compressive forces,
it is preferable to make a lower slab continuous betwcen webs; this disposition
of material also allows the designer to take advantage of the intrinsic
torsional strength of the box.
(b) On the other hand, box structures have a good mechanical efficiency
(approximately 0.6) and a value of IIltilllate stre"gt" which depends less on
the grade of concrete than 7:'sections. Thus, if at the tUllC of failure the force
in the cables is equal to Fr , the depth of concrete in compression is
y ~ F,/bR br for a given value of the concrete crushing strenath R.,. In the
case of a box bealn. the depth y is generally low on Dccount of the large value
of the width b of the lower flange and the lever arm z is not reduced
drasticaUy if Rbr does not achieve the expected value (ft 2.'2). With T
beams" the depth y is close to that of the flange nnd a drop in R,., entails cOin
pression in the \veb and, as a result, an appreciable reduction in the lever ann
z and consequently in the ultimate strength.
(c) Finally. elastic and d.vllalnic stability of the bridge during cantilever construc
tion is ensured luore satisfactorily with a box-section structure. which oOcrs a
higher torsional rigidity. than a structure of open section. In service, the
torsional rigidity Jessens the rotation of the transverse section under eccentric
loads. It improves the distribution of imposed loads between the various
zT:l-O~'
zt.------""'-----.l
Ilf
L
il
"
,1;
ss
Deck des;g"
1-C>
'''~I
OJ
W-
if
___._..
5.40;
I
-1-1170
~~6~
Fig. 2.S3 Structure with a T-beam in the centre-span region
-'--4,95
t:tf
ar
. . . . ""
a
bl
I':
.i
if
/)-//
;~
;.
I~
/)/3
Fig. 2.52
Ultinl~te
1;,
dJ
Fig. 2.54
c=J~
---r:;r
,180
r_
56
4.2
Box beam with two webs, each 400 mm thick. prestressed by cables made of
12 :\0 12.7 mm strands (4J = 70 mm)
Total thickness of \vebs: 800 mm
Effective thickness: 2(400 - 70) 660 mm;
Box beam with three webs, each 290 mm thick
Total thickness of webs: 870 mm
Effective thickness: 3(290 - 70) == 660 Mm.
I:
The two box beams are comparable as far as shear strength is concemed but
using the box beam with two webs implies a saving of 7/81 == 8% in the volume of
concrete in the webs. or approximately 3% in the total section of the beam. On the
other hand, the prestressing cables can be anchored in the depth
the webs
(thickness: 400 mm). whereas, with the three-webbed cross section. because of the
insufficient thickness of the individual webs. the cables must be anchored either in
the bottom \\eb flange junctions, or in a specially provided boss.
The h'eb spacing is, however, limited by the resistance of the top flange slab to
transverse bending under live load. The cantilevered portions of the top flange
must also be modest in order to avoid transmitting very high local bending
moments to the webs (fig. 2.56). The induced moment m1 , which increases with
13m<'~'8m
1<13m
Fig. 2.57
18m"'~25m
the relative rigidity of the webs, is fortunately maximum in the span when the
beam depth is at its lowest and shearing force is usually negligible.
The number and the/onn of the cells depend above all on the deck (fig. 2.57). If
this width does not exceed 13 m, the single-cell box beam with two webs is con
ventionay used. The webs may be either vertical or sloping (fig. 2.58). The latter
arrangement improves the architectural appearance and reduces the weight on the
foundations, at the cost of requiring more elaborate mobile rormwork or more
complex precasting forms if the beam depth varies. This arrangement also
decreases the weight of the bottom nange in the region where the latter has a
minimum thickness for construction reasons.
It is becoming increasingly common to use a single-cell box beam with t\VO
webs for deck widths exceeding 13 m. One of the most spectacular structures of
this type is the Felsenaubriicke in Switzerland with a cross section width of
26.2 m. It comprises a single-cell box beam with two webs of a constant thickness
of 0.50 m (fig. 2.59). It is to be noted, however, that the Swiss code is less strict
or
4=t
un
LT LIT
It is generally advisable to minimize the number of cells which make up the cross
section. as each cell requires additional formwork. This leads to a significant
spacing between webs: approximately .s to 7 m. Moreover, it is more economical
to provide a small number of thick webs since each web includes a thickness of
concrete 0 (corresponding to the deduction of the diameter of the prestressing
ducts) \\'hich takes no part in shearing resistance and impairs the performance of
the section in flexure. Furthermore, thick webs make easier the positioning of
cable anchorage cones, ancNmprove conditions for the plaein. or concrete.
57
.Deck design
~r
Arc t9 a: 1 to'!
5
Fig. 2.58
j=o
29:gg:29
r
~.
T"
T
22
m(~
Fig.2.56
aaar- '
'25 I.
3YJ
,20
50
8.00
6J
..-/'1
r-'55
700
i~-
4gi
~ -- ..373
!~i
Fig. 2.59 Single cell box beam with two webs of constant thickness
58
than the French regarding the transverse eccentricity of the military vehicle
hishway loading.
The side cantilever of the Felsenaubriicke amounts to 7 m with a depth of
0.55 m at the root.
Beyond J8 In the association of two single-cell box beams connected by the
deck slab permits a deck width up to 2S m; this covers the majority of current
requirements (e.g. the Givors bridge and the Blois bridge) (fiS. 2.60). A few very
large bridges may include three box beams such as the Saint-Jean bridge at
Bordeaux (fig. 2.61), but with these structures, which are generally motorway
bridges, it is usually preferred to design two independent parallel bridses each
with two beams. separated by a central reservation (e.g. the upstream and
downstream bridges of the Boulevard PCripherique in Paris) (fig. 2.62).
When the deck width is between 13 and 18 m, a particular problem arises. If a
wide box beam with two webs i~ not adopted, a box beam with three w,bs appears
in theory to be best suited, but often this type of section is not economical because
of design problems, for the difficulties in mobile formwark, or far the preeasting
equipment (cellular forms and segment-handling equipment).
Deck desig"
:~
....
S9
_ _
..........
! 340
. .
, ~
-~
110-
2660
,,;s_-t
r:lj.'" --,
-'
~---
250
3.79
I~
900
Fig. 2.61
...
900
eo
32
120
1580
....-----_.
-------J-.1- ..--_.
.,1.' ,'.(~-~...
--I
1580
--
o
1_.
:.:
---!
I.
3'50
So
8.00
".1.
-0
COG)
Q)Q)
I.
-~l
\~I
"'1
t
If')
9.00
-.1 ..
8.00
I~eof' ~ I
17.16
till(
....
4'20
(0)
!~
-!
220i
...
tr.,.
j
:
.
fr!
laW..,..
\
o
o
.....
I.D
4.50
I~I
4.00
~I
( b)
Fig. 2.60 (a) and (b) Cross-sections of the Givors and Blois bridges
L-.. I~
------1----
_'000.
11. 38
I
~
__._._. ~!
60
There are, however, se\'eral examples of this type of arrangement, including the
Oissel bridge (fig. 2.63) and the Joinville bridge across the Seine (fig. 2.64) and the
viaducts of the Paris BJ Sud motorway (fig.2.65), with structural sections of
17.2, 19.0 and 15.25 m width respectively.
This section is also used with wider decks (I > 20 m) as in the Genncvilliers
bridge across the Seine (fig. 2.66).
:
-0
19.00
..- .:
52:
- -
--
Warm air
rc:r:t:J
19.00_-1
A A _ . ~ __
Rib
Iocotioni
l~
~36
ill.
:1
I~
61
Deck design
18 1
I ---'t22C
~I
9.48
Fig. 2.67
L/3
6.03
15.25
10(
~l~"IIi1lJiii111i1i11liiilii1l'"
L
Fig. 2.65
9.~O
.1
....
19.55
Another solution is to use a single-cell box bealn with two webs including a
cellular top slab or transverse stiffening ribs (fig. 2.67). The first scheme allows
large cellular lateral cantilevers and may be an advantage with structures liable to
00 tdTcctcd by frequent icing. as the different cells of the section produce thcrm:1I
storage and may be used' in undernoor heating of the carriageway slab. The.:
Chillon viaduct in Switzerland has a cross section of this type (fig. 2.68). The
strength or the web in local bending induced by the force concentrated at the
cantilever lower nange was examined carefully; it was necessary to increase the.:
\veb reinforcement.
The second scheme seems more advisable and the author proposed it for the
construction of the Saint-Andre-de-Cubzac bridges across the Dordognc
(fig. 2.69). This choice resulted from comparative surveys of different section ~
.,
fI
;:r
40-..
o
o
13.00
III
1610
...- ~50.
ai
1564
I
._--~--"-
5~...
Fig. 2.66
______.__ ~_r_
120
9.2~~t~_--ill
JL~
1-.( ...
500
~:
62
1660
I~
63
Deck design
16.10
I"
250
1-4.--...:Q9__ ._1
~
14
6bo
7.78
Fig. 2.69
.lU9.-...._. _ ..,.
27.60
such as: two box beams each with two webs, a three-webbed box beam. and II
two-webbed box beam with a ribbed upper slab.
Taking into account the nonnal width of the decks (equal to 16.6 m), and the
need to reduce this width to 14.3 m for one of the access viaducts. this solution
proved to be both the most practical, as far as construction was concerned, 11m!
most attractive, economically speakina.
As compared with a structure consisting of two box beams, it has the
advantage of avoiding transverse prestress, which is always costly for such
widths, and of eliminating the concreting of the junction slab. Also, it considerably
simplifies deck bearings and foundations.
Finally, it has a better mechanical efficiency than the three-webbed box beam
and leads to a simpler design of mobile formwork or precasting moulds.
This type of transverse section, used for the first time in the construction or the
Saint-Andrede-Cubzac bridges, has been used since in several structures which
have all incorporated precast concrete seaments; these are: Sa/Ii"""",, bridge in
Denmark, a 16.1 m wide bridge (fig. 2.70). In this bridae an improvement has
been made in the design of the joints between precast segments. The contact sur
faces of the half ribs were reduced by means of a lining laid out in the forms in
order to secure a high average compression of the joint to be glued, wbich helped
towards satisfactory gluing when the segments were connected. It had been
suggested that a structure plaMed for construction in Denmark, the Vejle Fjord
bridge (fig. 2. 71), ~hould be built with a 27.6 m wide deck with a ribbed top slab
but this project was subsequently abandoned.
Finally, one can envisage designing a multicellular deck with two vertical
central webs and two sloping webs. This cross-section would provide high
torsional rigidity, and the shape of the side cantilevers would provide economiclll
Fig. 2.71
._.
. .
?5J9
._.
.. ~.
...
01'.
.11810 50 ~
Fig. 2.72
_.e.5.L-__...:
Cross section of la Viosnc viaduct
..
~.
--_._........
64
Deck design
16.00
.----------1.. . .
~f\----r~
L-J V ~ :
HOflZonloloddiloon
~IOddition
Fig.2.73
Standard section
20.40
Standard sectIon
Widening
Metro \iaducts at Marne-Ia.. Valle"e with decks made or precast segments usually
11 m wide; they reach 16 m at the Neuilly-Plaisance Metro station owing to the
addition of side cantilevers (fig. 2.73).
This solution was also adopted for the Saint-Cloud bridle across the seine both
for architectural reasons and on account of the highly curved plan (R = 350 m) of
the structure which prompted the designers to seek a structure with high torsional
rigidity (fig. 2.74).
4.3
In an urban environment bridges are often found witb an increased width at their
ends, to allow for the addition of s1iproads or for traffic management at an
intersection.
A variation in the deck width may be facilitated by one of the follo\yjng
processes:
(a) Width variation of the side cantilevers (fig. 2.75(a.
Deck widening
(b) Variation in the width of the reservation between box beams when there arc
several of them (fig. 2.7S(b.
(c) Addition of one or more extra webs (fig. 2.7 Sc).
Additional webs are usually built once the box beam has been made continuous
they are constructed either by means of special mobile formwork, sliding on th
beam or by formwork suspended from two beams or falsework supported a
ground level.
The first solution was used a~ la Banquiere viaduct at Nice (fig. 2.76 and 2.77
whilst the second was adopted at the CoJlecteur bridge over the Seine at SainI
Denis, and the last was employed for the Connans bridge across the Seine. \V c1:
may also be precast as those of the upstream bridge of the Boulevard Peripheriq u
across the Seine (fig. 2.18).
66
Deck design
67
47.52
/
OouJbe J
~.
/a
~
VARIABLE
Fig. 2.76
Section B8
VARIABLE
Fig. 2.78
~ _~........
...
',
,,-
.......... ~-~.""-~
68
o
\ ~a
90
~
~wed9'
90
Cf
J1T:~a
btr~a
"""'
VH
tl
= /(0- ~)
in position
Fig. 2.79 (a), (b), and (e) Wcb arrangcment in relation to the flanlcs
Deck design
{
M,
t ----
2 - 20(0 _~)
H. J:
~:
0:
=t l
t2
In a deck with variable stiffness the critical sections with respect to shearing for'
are generally situated at approximately onesixth span.
The use of prestressed stirrups, which induce a vertical compression in the we
permits an increase of the value of the permissible shear stress t b and a decrea
of the web thickness a. Prestressed stirrups are made of single win
monostrands, or of bars, positioned in sleeves and grouted to prevent corrosi<
(fig. 2.81). Some monostrands are supplied directly from the works in pins.
sleeves and coated with a corrosionproof grease.
Anchorage
4.5
Active ,anchO,age
Webs must provide resistance to shearing forces and permit proper placing of the
concrete as well as. fairly often. the anchorage of prestressing cables. Thcy musl
therefore have the following characteristics.
Bar
Manowires
Area prestressed verticolly
Sleeve (4), l
4.5.1
where t~
Zone of anchorage
bybondi"9
A,..t:"'I')''''.l~ rY1".".I"~
-_._-
- nr
)0r0i.!,.
, I
. I
,"'21~~!q
~1:1:~I~
~~:III~
Areo prestressed
vertocolly
:~i~!~
.I
".~
~- ~
box beams
~I~I
Strcssed stirrups
70
The stirrups made of bonded wires or strands used with prefabricated webs arc
more economical due to the fact that no sleeve is needed ('1 co 0).
Variations of depth in the beam also result in a reduction of the shearing force,
thanks to the effect of the vertical component of the compression in tho lower
flange (the so-called Rcsal correction). When variations in heisht are Important it
. is usually possible to maintain a constant web thickriess along the length of the
beam and this greatly simplulCs the formwork.
Sloping cable profiles in the region of the supports reduces still further the shear
force because of the vertical component of the prestressing force.
a)
where ~I
+ 2(20 + ~t + ~I + 60)(mm)
Deck design
71
The above condition Is often inadequate with webs of great depth. It is indeed
Clsential that the concrete fills the form adequately over the whole depth of the
web. Concretina ports set half way up the forma and towards the inside of the box
beam mako placina easier. When the webs are sloping vibration can be Improved
by luidinl the internal vibrators inside latticed ducts.
Ouyon sullests an empirical formula for webs with a depth less than 6 m:
a;> 36 + 50 + +(mm)
In this way we have 240 mm for a depth of S m and cables 12 ~ 8. Ifthe webs arc
Inclined at a large angle to the vertical, it is advisable to increase the values liven
in the above formula.
With depths equal to 6 m, or slightly higher, it does not seem sound to go below
300 mm if the webs include 12 T 13 cables (Pont du Bonhomme: webs of 300 mm
for a depth oJ 7 m). and below 240 mm if there arc no cables in the webs.
Boyond 7 mth. Ouyon formula can be replaced by:
a~-
Stirrups (t/>.)
:!
I' ~
"
22
80 +
~(mm)
Coble (t/>l
4.5.3
!
Concreting shoft
( for vibrations)
--Web face
An adequate thickness allowing for the anchorage cables, if these are stoppeo of
at the surface of the segments in the depth of the webs. Approval certificates gi\'t
for each prestressing procedure, minimum values. to be observed, apart frorr
special arrangements (end plates, wire wrapping, elc.).
These values are equal to 230 mm with 12 ~ 8 cables and to 360 mm witl
I:! T 13 cables (approximately I.SD; D being the external diameter of tho
anchorage).
72
beams, the upper flange is fIXed to the webs because of the presence
or the lower
nange which acts as a tie rod and thus laterally restrains the webs (fig. 2.83).
As a result, the upper flange whose dimensions are determined by its resistance
to transverse bending under live loads, may have quite large spans (commonly 4
to 6 m) without needing excessive thickness or excessive transverse reinforcement.
It is, nevertheless, a pity that the strength of flanges is grossly underestimated
by present codes \vhich take no account either of moment redistribution or of the
formation near ultimate load of concrete arches braced by transverse cables,
although this has been proved by numerous experiments. The transverse flange
must include substantial chanifers at the web junction (fig. 2.85).
The chamfer I improves the fixity of the flange-web cOMection and makes the
flange line divert from a straight line facilitating the use or transverse cables with a
rectilinear or a slightly sinusoidal outline.
,
I
Fig. 2.83
73
2L
3
7T7'
t
\
Crocks
\ Crocks
Transverse
presfresstnq
coble
Concrete arch
Fig. 2.84
(I _~)
I,
where the thickness to of the nnnge is a variable dependent on L. Guyon gives lhe
formula below which is valid for French loading conditions and i~ in accordance
with elastic theory
,,,
\
Deck design
/0
4.7
(m)
10
mm
2.5
160
3,0
180
3.S
4.0
4.5
200
5.0
5.5
220
(!:-36 + 100). mm
This rormula gives thickness values which arc too high when spans arc longer
than 4.5 m. It increases the deck dead weight without useful purpose. We prefer
adopting the values shown in the table below, which are still higher than minimum
permissible values.
either as a voided slab, as in the case of the access viaduct of the Tagt
bridge (fig. 2.86)
or as a ribbed slab. as with Saint-Andre-de-Cublac bridge (fig. 2.69).
Span and thickness (I') of the nange
The thickness t' of the lower nange is usually determined by the cover required for
the prestressing cables placed there; the minimum thickness is approximately 2.5e
(, is the diameter of the duct of the cables); it is 140 mm for 12 ~ 8 cables, anc
180 mm for 12 T 13 cables (fig. 2.87). When there is no cable in the lower fla nge
its thickness can.be reduced to 120 mm (example: Coblenz bridge-fig. 2.88). J~
74
._
TIl - ~~
LJ
Ir
VI -
1-4'50
L____
51.0 0
Fig. 2.86
',. t
fL'
" .
! cp
20.40
411
-35
7.00:
I
I'm.
4.52
---
720 )0
I.
I
720)0
.lzI.37_-_ _tZ50
J
' I.
In the area of illlermediale supports the thickness of the lower flange is deter
mined by the permissible compressive streSS under working load on the lower
fibres. Its thickness may then range from several hundred millimetres to more
than 2 metrC$ (2.4$ in the Bendorf bridge (fig. 2.89. It should be noted, however.
that an occasional drop In the strength or the concrete in the lower flange docs not
seriously affect the overall safety of a cantilever bridge; it docs not usually depend
on the value of the ultimate moment at the support. but on the ultimate capacity
ur the midspan section. Ncar failure. which happens at midspan. the sections close
to the supports are actually subjected to forces hardly greater than those applied
to the bridae In service.
The lower flange is usually rigidly jointed to the webs by means of heavily
inclined chnmfers to avoid interference with the placing of the concrete. If the
chamfer angle is less than 45 0 openings must be left in the formwork to permit
internal vibration (tig. 2.90).
4.8
'
0q
_....:
T 3,-t
t
I 01
a::=:.qj
cptl
-------..
5.00
16~
."l
Ti"
---
fO.5cp or 3cm
",
_J
-"~'.,.
..
3066
1000
-j
" i
I .
75
Deck desigtl
Equivalent thickness (E) is the thickness of a slab with a solid rectangular section
I~
Inlerior form
l=:I i
76
",""'!~
/'
I;
"
I
,j
iI
,I
...-
7Ck
:.,...-036
!/
H
II
j
~+
~~~t
-=r
.....
....30
.",
"0
q;::::::::=
40
50
60
70
80
90
100
110
120
130
140
lm(m)
Fig. 2.91
I la~oix-Fal'3rde bridge. 2 Goncelin bridle across the river Isite. 3 SamtJean bridle It Bordeaux
(C 01. .. BOUflesVlltnce brid,e. , La Pyle bridle. 6 Oissel bridle. 7 o;VOtl brid,e. 8 Mallusc brid,e.
9 S~ond bridle across the river Adour It Du. 10 MouUnsJes..Metl bridle (CD). 11 Bridle .cross the
1~ Pierre-Simard Street bridge It Brest. 16 ChoisyteRoi bridle (CD). 17 Coutbevoie brid,e (CD).
21 JI.:\"isy bridge. 21 8oap.. brid,e. 23 Bridae actou tht river Adout at BIYOftft1. 24 Boulevard Peri
phc:sque upstream bridae. 25 Blois bridae. 26 Atlmon bridle. 21 Tours bridle. 28 BOIUI-Sllnt Andeol
bricic. 29 ConfJans (CD). 30 Bridae across the river Oardoft. 31 La Se'*c viaduct. 32 ChiUon viadutt.
33 Les Spams viaduct (CD). 34 Saint-Andri-dc-Cubzac viaduct. 350ene\fllliers bridae. 36 Orleans
bri':.e. 37 JoinvilJe brid,e. 38 Le Mllnan brid,e. 39 Viaduct ddte Canadians (CD). 40 Viaducts of'the
So\.;~'em B3 motofWay (CD).
having the same volume of concrete and the same usable surface as the deck
under consideration.
Figure 2.91 shows the equivalent thicknesses a number of existing structures
for which the average spans (ratio of the overal11ength to the number of spans)
have been plotted as abscissae.
or
11,
110./'
Fig. 2.92
soffif
Most of the existing bridges belong to that category: they include a cu rye(
soffit with either a parabolic or a hyperbolic variation \\'hich correspond
practically \vith the shape 'of equal strength of the cantilever' beams under self
weight (fig. 2.92(a. With some structures the soffit curve is cubic, but this optioJ
often results in insufficient depth around the quarter-span point (fig. 2.92(b). As i
reminder only, we shall mention decks with a linear variation of depth \vhicl
requires a beam unit at midspan, which within the medium span range can b
justified only for aesthetic reasons, (fig. 2.92(c.
The ratio of depth at supports to span, or slenderness ratio hi/I usually varic
between one-sixteenth and one-twentieth; the economicaJ optimum
approximately one-seventeenth.
In theory the deck depth at midspan may be zero if the structures conccrnc(
have hinged cantilevers. Even in this case, however, it is necessary to provide (
minimum depth of 1 m (from 1 to 1.4 m) to be able to position the hinge. If th,
deck is continuous, traditionally a minimum depth of J.6 m has been required tc
permit access inside the box beam for the removal of formwork, tensioning of pre
stressing cables, checking of the structure and, on occasion, the siting of services
In practice, the depth at midspan (h o) remains in the range one-thirtieth to one
sixtieth of the span.
It will be seen in paragraph 9, however, that, taking into account both therma
effects and the redistribution of stresses due to creep. usually leads to an increas,
in the depth at midspan above the minimum value.
Decks with variable depth have the following advantages:
I
Rectilinear
Parabolic soffit
,",
/,/
_0
~i
11
.,.,,'
-c------
\I
!I
,~'
. / ,..,
~,"././
C
2' _.~;f""" OJ7...,.,..........
7 ~~''''''''o20",.",.'''''''
.. C : J
u 16 S3 ~oo23.t9;otZ .. ~"",..'
o~
til
o-'~!f: ~~ 300 02,,26.s 025
32
... ""
- _10'11 0 39 .--0-028 t2 11
13 02
,~-18
0
C :;'OJ'
,-",~21~~001-'~
C3J
BraCIng
_ :;",::,,/ ..,."."," 38
C SQ
"
'~J~/
:-0
C 9:)1
.:!
7'
oJ
Deck des ig 11
Despite all this, an architectural trend has recently led bridge designers to us
decks of constant depth, more especially with urban bridges or with multiple spa:
structures with low headroom above ground or water.
Constant depths are more convenient for the passage of services: water, ga~
nnd so forth.
78
79
Deck design
Settlon
00
~~'~'~~I"ltll''..I~~'I''~I!&I''III~~~''I~~
Fig. 2.95
Stiffener
I'i
1';'1
:i
;1
I;
Con5tont depth
(Choisy-Ie-Roi bridge)
(0 )
( b ) Semic;onslonl depth
(Pierre - Benit. bridge)
( e )Voriobl. d.pth
( Boulevard ~iphirique
downstreOll\ bridg.)
.'fO, .
Fig.2.96 Chamfers of the Pierre Benite bridge
the pier (fig. 2.9S). It should be noted that, in this case, the structure shows a con
tinuous soffit in elevation, parallel to the cantilever; the chamfers are thel
unobtrusive. When seen from a distance, the deck therefore appears to be of con
stant height.
The Saint-Jean bridge at Bordeaux and the Pierre-Benite bridges near Lyor
were designed according to this principle. Figure 2.96 illustrates the continuity (
the soffit line.
6
6.1
Fig.2.94 Chamfers in the downstream bridge of the Boulevard Pcriphcrique
h_."~
"-''"'': .
.t.,.,
i"
80
81
Deck design
<D{
Fig. 2.97
Cabling arrangement
Fig.2.98
ep{ 7;. o.
the beams and placed as the construction progresses with a view to resisting
the rapidl y increasing negative moments due to selfweight. These cables are
tensioned symmetricaDy on each side of the pier.
Structures with hinged cantnevers involve this type of cable only.
(b) Integration cables (I), placed near the mid-spart of each span, to achieve deck
continuity and to withstand the resulting bendina moments.
I
1
or the cantilever
The number of cables in each group is designed to live the resultant eccentricity
required to provide the moment of resistance for the deck; cables (If) are usually
the most numerous.
The number of cables (B) is primarily controlled by the ultimate strength
requirement of the structure when the spans adjacent to the span under considera
tion are subjected to imposed load (fig. 2.98).
The amount of steel required for longitudinal prestress varies for standard
spans, bet\veen 20 and 30 kg per square metre of serviceable deck area.
If the number of cables required in the section at the support and in the mid
span section is kno\vn at the preliminary design stale, an approximate estimate of
the quantity of prestressing steel will be obtained by livinl each cable type an
average length equivalent to 0.52 I for the cantilever beam cables and O.SO I for
the integration cables (I is the span under consideration) (fig. 2.99).
SOl
i..
.
Fig. 2.99
6.1
~I
The cables for the balanced cantilever beams are designed to match the nega ti ve
bending moments caused by the con~truction of the cantilevers. and to join each
segment to the part of the deck already completed with the distance away from
the support.
.
As the number of cables required decreases it is possible to stop off some cables
at each segment. The cables anchored in the segments beyond the one under cons
truction will be threaded at a later date.
In the construction of bridges by the cantilever method it is advantageous to
use longitudinal prestressing tendons strong enough to avoid overcrowding. The
bars used in some countries have the twin drawbacks of lacking strength as well
as that or lacking the flexibility to follow the required profile.
Cable strength does not need to be too high, however, as the number 01
cantilever beam cables in each web must at least be equal to the number of seg
ments to be prestressed (except in the case of segments with more than two webs)
Furthermore, over-strong tendons require special care to ensure concrete bearifl)
slrrn,lh under the anchorages, and effective diffusion of the concentration 0
prtslressing force. Several mishaps with prestressed concrete bridges have beer
due to an abnormal concentration of anchorages in an individual section.
The strength of tendons commonly used in the longitudinal prestressin g 0
cantilever bridges currently varies between 1000 and 1600 kAT (10k N = 1 t
(working load or cable).
82
There are two possible arrangements for the profile of the cantilever beam
cables depending on whether they follow a sloping line in the webs (inclined
cabling) or whether they stay in the upper flange (horizontal cabling).
Deck design
COftI'rvclto"
83
plUIt."
T_"" cob.ts 12 T 1) +
A~
"
..
:~;~~
.;.:.:;;.;;...........-''*oIw;.,,;~~
BOO:
"'1'9'01101\ pt"l""
Four'.." 12 T I) CObltS '01,1' 12 .. 8
tOtlu
1j;'rSI"Q
-4,
II.
30
.16 stirrup
welded to Ihe plate
Duet
Active stirrup
Anchorage
'-L/ II L...--
Steel plote
Passive stirrups
Suspended port
JOint
Fig. 2.101
..
84
Deck design
85
the slope of the cable is varied and is a maximum near the supports; this gives a
corresponding reduction in shear stress in the area where shear force is a
maximum (fig. 2.107).
If the deck is of cOllstant depth the profile of the cantilever beam cables
(fig. 2.108) is simply transferred from one segment to the next. This applies to the
integration cables if they are taken up into the webs (figs. 2.108 and 2.109).
In several recent structures, however, instead of positioning the anchorages of
the prestressing cables at the surface of the joints between segments. they have
been set in bones or ribs located inside the box beams (see Chapter Five.
paragraph 1.2.2). This solution has advantages. First, cable tensioning, anchorage
and grouting can take place from the inside of the box segments in optimum con
ditions of comfort and safety, without incurring the risk of operating various
~d
t['
Actr.e stlttUP
f.
:Ii
-Anchoraqe
n+1
On-1:>QIJ >an +1
Upper cable
'---~
!d
n-1
'
-I
~- :-
td
"
Fig. 2.107 Standardized cabling--deck or variable depth
Cantilever beam cable$
AnChOtOqe
~
I~
-.
5e9menl
:'_~/
,~",~~"~",,,--
......
9'OO,...
..
~,;~ ""..~~~
"... .:J,'
__ ..
- I
, , ',
"Ii
1/
.I
'-''
/I
InteQrolion cobin
Thirteen lZcjlecoblu
EiqhllZcjI 7 cables
./
'Two lZ.8cotlt\
~~
1_
EJ4!'ltttl\ 12 T 13 cobtts
Tw,lv, tZ.Scobltl
l,n
7cotJ.,
per segmen'
1Z.8cobles /
Thr~1Z4>
124>8 cobin
Loaped
E"lhllZcjlBcable,
II
II
'!
86
pieces of equipment outside the beam, and they CM be carried out with
mechanized apparatus (fig. 2.110). Furthermore, it permits a reduction of the
number of cantilever beam cables to be stressed at each placing of a concrete
segment to the minimum required to ensure the strength of the cantilevers with
respect to their self weight. The supplementary cables, which arc threaded on and
stressed once the cantilever beams have been connected, may be continuous over
a length greater than one span.
In economic terms the net result is an appreciable reduction in the number of
prestress anchorages. In terms of constructini the speed of placina of segments
increases as the laying of supplementary cables is removed from the critical path.
This type of cabling allows the use of cantilever techniques to build short-span
viaducts (less than 50 m) under comparable conditions-as far as the amount of
prestress involved is concerned-with the construction of entire spans between
points of zero moment on falsework or with mobile formwork.
This is the cable arrangement adopted for the viaducts of the B3 motorway
with its standard spans of 36 m (fig. 2.111).
The bosses are generally immediately below and to tM side of the upper
flange/web junction, so that the thrust resulting from tho anchored cable is divided
between the web and the flange (fig. 2.112). Some bosses are designed so as to
make possible the anchorage of two cables which intersect there (double boss);
other bosses are set into the flanges (inset bosses)(fig. 2.113).
Deck design
87
InltO'0l10n coblt~-Model A
[DOUble bOSS.!]
~ ~
A
t..Q
_IA
'j
Section CC
>
pj
C..JA
Pion seclion DO
/).. J1JIIJ.
LLDlItJ
Fia. 2.112 Bosses
1'"serfSUl
Elevolion
EleOlion
Pion ;nv,ew
Ploninvitw
EP
Fig. 2.113
b()~scs
.,1
I:
I
I
'-1/
8600
l12
88
Deck design
89
Integration cables are designed to ensure continuity between the various cantilever
beams and to oppose extreme moments of opposite sign caused by dead and live
6J.J
either brought up through the webs and anchored into slots cut in the upper
flange (a.) (fig. 2.117).. In that case they overlap with the cantilever beam
cables if the latter are inclined. Because of this overlap, the webs then
contain a large number of sloping prestressed tendons, thus the only shear
reinforcement is nominal reinforcement of small diameter. On the other
hand t the slots in the upper nange give rise to a considerable risk of water
seepage into the cable ducts. It is essential to give particular attention to
their grouting and their scaling (resin sealing).
8 cables
b1
01
A cable~
Fig. 2.116
,.
a2
Integration cables
Anchoring of the
integrotlon coble
~
/
LOWER CABLING ARRANGEMENt
Ji/
/'
.
~I
:1
Fig. 2.117
n,JJ
90
-Or cables in the lower flange which are stopped olfin the bosses protruding
above the lower flange or positioned at the junction with the web
(aJ-these cables have a profile similar to that of the cantilever beam
horizontal cables;
_ Or sinusoidal and acting simultaneously as cantilever bewn tendons at
supports and as integration cables in the span (aJ.
A
__
~,
. _--.-::::-._-_._._._..,....~. I
~~-
I ~!~
:
: i:
AU intearation cables follow, for part of their profile, the median .line of the
lower Oans The latter is curved when the deck is of variable depth and the cables
develop an outward thrust which can incur a serious singularity of stress if provi
sion bas not been made for appropriate reinforcement (fig. 2.118).
The effect of thiS outward thrust is maximum when the lower flange compres
sion H' comes close to zero under the action of imposed loadings. The lower
fiance of the box beam sustains a supplementary vertical stress of 0.03 MPa when
cable. stressed to 1800 kN arc positioned at 0.20 m spacing and have a radius of
A~'
inte9rOhQn cobl,
Slre$5
the section
dlagram.in
i~r.~~
\
i;:;'
91
HI
Integration cables'-
..
L~' -~':-,...::: ~.
\.
Deck design
_0- - - .. _0 .. 0 ... -
lower flange
"
N'
tittftt,tt!
p
Duct
SECTION AA
H'/H'
/~ttt~:,
IR'
.~
"
Thrust of tendon
o~~\ii f1J];:.
F/R
Iii
\,
p~q+t._!i.
R fl'
SJ --:rJ
++++
'"'-...,
Fig.2.118
.-...........
92
f;J~d( l:l~IY
Deck desigll
9J
i;1l,:gr.;::~;
Ih(: :;J1chorat:~,
'<'T"
~:)I\C
lhe.: "';~'it/'k"
':":'!I;::lcd
,I' "'"
I:';,'
t!,,'
"
,I.;'";;.2,12(1!.
TLiS'
,,!:"'-:::~
" .....::'
o:!
the lower flange and the resistance of the passive reinforcement there, The
<. 3.J~
t''''rj.! "~'-I
(:}
i, ..
either stopped off in anchornges placed at the junction hct\\'cr.'1 weh ,!nd
upper naqge (b l );
or extended to the support diaphragms where they are anchored (b ),
Se9ment joint
These cables can be stopped ofT below the upper flange, at protruding bosses
which are concreted using a special form, after construction of the segments,
6.3,] Statically indetermillate moments created by the tensioning oj integration
cables
i'iI;.
~.: ~.i
":;ISI!\~
(,,1';'('.'
:',
! 0');
The statically indeterminate morn~nt5 due to the integration cables arc relatively
;';'.\' ()..er !l'~J'.: 1'( :!i~? k;l)',~!: ,r l':'~ hr;','f~c ~'l"": !".'.,:.,:l.: 6~, '.~ ;v' ~ .. ,.. , ('!' !l".
---=.~
--,
r:Y'
--:.-" - _
~--.
,. -..
,p";,~. ,.:;:-";,,,,~,.~~,-:.,
::,;'~;;"-',,:,::~,
6.4
Examples of cable
"":..;:
~.",--; ..:,!:~~
,
<.: '..... lnft": ......
.,...:!, n':lJst.. ~;
;.;.:.:::'" O(:twCf.".:'
~~~cm~orce~j?~~
-,....
<.
':,.lr~t
=":;'""\
.. :.~ ...
~=-:~jo
Fig. 2,121
'
.. , ' ;. ,.,
,11
e coblU 12 T 13
e cobles
..~ ./ '
'I
r="
;,.
.; .. 11 CU ;)l:'"
iQ;.l-~~~~f{~~~.
4 cobles 12 T 13
<,:.
14130
!~;~,3,~,'_~6,95 ,
Crocks
,,-;
l'~'
..
E,.
Canllieve, beam ptUlteSS,nQ
~! ;
! 2;; ~:tll~sS 1~T~~
~p.I=::~rr-~.
,:;:;_;.
.
;.
.
.
;.:.:
IJ; ....; .. c .'
'
213Coblts 12TI3
, .. , .. ,:' .i' .,
",;.:: ..
Crocks
" jl6'o
..,'-;
F'::!f~~\o:_~d jci~~'
Anchoroges
p(Om::~
....
~._----
Inlfl;'Ofton o't,"eu,,'1
2 " cable, 12 T 13
94
38 (0:11$ 12., 8'"
6 cobles \2 T U
52 cobin 12.8+
2 tabl" \24-8
prtst'ISsint
+ 16cob1tl
20 cobl" 12.8
12 T 1l
... 46 cobles 12 T 13
LkLi"1~""~~' ;..-........1J'~;f !.
..~ __ .I .,!:..:;.l".oC
n
Pc, 5
Fig. 2.124
n3
II
Pl" 4
~,
Integration cables
The be5t solution is still the use of horizontal cables. \vhich give very low friction
(e.8.t the Conflans bridge,. the Rio Niterol bridge, the GCMevilliers bridge). If
cables are Inclined, the ducts can be replaced by still tubes, but in each segment
the cable line must stay in one plane to aUo\v bending of the tubes.
If ducts arc Uled. it is necessary to minimize the number of segments where the
cable Iinc is curvod. It is clearly much easier to align straight ducts and this, in
turu, also facilitatcsquality control of prefabricated segments at the precasting
yard.
6.6 Transverse cable.
In the case of decks with a box beam of relalively snuz/l width (L ~ 16 m). the
tranlvcrse strength of the roadway slab is usually checked by conventional
"'n/arced coner", design. In this case, prestressing is at a disadvantage, because
.of thelarlc number of anchoraaes in relation to the length of the cables.
Prestressing is preferred when the transverse section is madc of a single large
beam or scveral box beams; in this case, prcslre~~ing also assists continuity.
HO\\'CVCf, recent tests have shown that cOMection between beams can also 'be
safely achieved by conventional reinforcement. Depending upon the structure the
quantity of transverse prestressing tendons ranges from S to 7 Jcg/m 1 of deck,
Cou\,cntionul rcinrorccrllcnt per cubic rnclrc of concrete. usuaJly ranges:
-
the stability of the cantilever (fig. 2.125). After connection with the adjacent
cantilever, the tension in the beam tendons is released and the hinge is freed.
6.5
9~
Pet,
Fig. 2.125
Because of the large number ofjoin Is in cantilever construction, friction loss along
the tendons during tensioning is often greater than has been evaluated from
standard formulae. At each joint the ducts have accidental discontinuities in slope
or in curve which must be taken into account when calculating the loss due to rric
tion. These discontinuities are more important in the case of prt!abricated
segments, \vhere the ducts cannot be coupled at the joints. Several methods can be
used to help to reduce the friction loss:
rubber or steel) threaded inside the duct and ensuring its alignment;
correction moments; most frequently, nat jacks are introduced between the
piers and the deck;
introducing temporary hinges, usually at centre span in order to decrease
deck stiffness at the time of integration prestressing-these hinges, placed
in the lower flange, are locked before completion of the structure.
However, the most efficient method consists in creating an ac/ive Ihrust in the
area of the temporary hinge. A hinge in a given part of the deck determines the
96
Deck design
alignment of the line of pressure under the combined effects of self-weight and pre
stressing. This line could pass outside the hinge, if an external force, produced for
example by a Freyssinet flat jack, is applied in a given section. This has two
effects (fig. 2.126):
This adjustment can be used in correcting the longitudinal profile of the structure.
At the end of construction of the Choisy-le-Roi balanced cantilever beams.
compensation and adjustment were made in the connecting section of the central
span.
During connection of the cantilever beams. of the Bonhomme bridge, an adjust
ment was also made. The device included flat jacks. placed at the joints between
webs and flanges (their number and size was such that their centre of gravity
coincided with the section's neutral axis) and concrete wedges placed at the level
of the top and bottom flanges of the box girder (fig. 2.127). The total force in the
flat jacks could develop 22000 kN. The adjustment moment was created by the
curvature of the median line of the cantilevers: this curvature was due to the varia
tion of stiffness of the bridge sections.
1~
Freyss'
~el
flal jocks
~-~l ~- JFWMlh~'
Freyssinel hinge
'\
Cobles
Concrete wedges
'-r""l
I! :
97
205
.~;'
h~
78
'
""'"...."" 9,"
2 Jocks'" 400
Steel plate
28
f;;,2
I.
='.~' '1
~2/. ~. "Ui.".""",,,,
48
.:_~
!
.~.~,,<.~.~~
After connection of the cantilever beams, the deck enters a statically indeter.
98
integration prestressing;
To these deflections are added the long-term deflections due to the creep of con
crete. These do' not create differences in levels at the ends of the cantilevers in a
same span, but create 'continuous variations in the longitudinal profJ.1e of the
structure (generally lowering of the joints). For this reason, they must be
balanced, as are the statically determinate deflections, by introducing init;al co",
pellsaring CQI1WerS in the cantilevers.
The main problem in calculating the cantilever deflections is found in the study
of the long-term behaviour of loaded concrete. The linear Inodulus of elasticity of
concrete varies with time, in relation first, to the age of the concrete at the time of
1---'~2
Ii
S09ment numbers
I_
3T4~5-
----_..... C
"
8.~
,
..---..,
8
............._
"--~---
\.
c'~.
I~
'-\-"---. ..
~.........
84
.. '-\.
b l '"
'. ~ \
..~
\
\
\
Fig. 2.128
Deflection a cantilever
.HE'
u
","';
,,~
CI
II
!I
~"""'''''''Id
I
.:
ol~
II
'"
j-~
Fig. 2.129
- j - - - 4 -1-'- 5 ~
............
;'\..
u-+---u-../.
\
\
"
Q;
:.......--1 '--'-~2---"r--3
0'1\..~", '. \\
"
loading and second, to the duration of loading (see curves in figure 2.156). The
prestressing force also decreases with time, because of gradual losses in the
tendons.
Fiaure2.128 gives the sencral shape of stalically determinate deflections of a
cantilever at each construction stage, without any compensating camber.
Fiaure 2.129 shows the successive deflections which must be applied to a
cantilevert so that it futaUy attains the desired theoretical profile.
The deflections are obtained as follows: The first se&J11cnt is built with an initial
compensatinl camber fa -A.a;;; Oiu; instead of comins to the position OA after
prestressina, the seament comes to Oat During construction of the next scgment Q
moves by a distance AA. and comes to a The end of the segment comes to h', b'
beins such that OAB. =Oa.b'; but if an initial compensating camber.li 0iu is
given to the second IClment in relation to the first one, B comes to b.
La~er b will move to ~, at a distance equal to DB' (fig. 2.130). When the scg
mcnts arc concreted ;n situ inside mobile carriages, it is not very accurate to
adjust the clrrialca before concreting, by referring to the theoretical levels that
they should haytI aceordin. to fi.sure 2.130. This level is suscepti ble to major
variations aecordin. to tho ambient temperature and humidity, and mainly to
solar radiaCion (Ice thermal gradients. paragraph 9.2). It is advisable to make the
adjustment by givins th~ mould an Inll/al angular variation 0' in rclation to thc
previous seamcnt (Cia. 2.131). The curves in fig ure 2.130 can still be used for the
cOlltrol of the deflections of the cantilever beams during construction, but the deck
must be adjusted during the early hours of the morning when thermal gradients
are still snlall. A similar method is used if the deck is built by the assembly 01
precast segments, the mould being placed at an angle. 9' with the precasting form.
Segment numbers
.-4,
........... ~ ..........
~
99
0
\
..---..-......
93' ~ . . . . .
I~
"" I
"
Deck design
II
rf
a1
II
",
\\
\l,~
II
..
~,,~->,.
-' . Ill'
"
...
L%A .ft
100
Deck design
101
Segment numbers
!...-1-~.-2 ~!..-.
3-"1.-- 4
~'
C ---,
,,~/,.
I'H
f
"
'",
b ,//
/1
b'
\,
!1-----
ll~.""-~ I J~
c.n
t~ft118,
~2
~~
"
85
, ...
,,,
__. -L_-~=---T--
~~-=_._
\j!
Ij 8
1,0
c:
::---' -:~.
..
~~
'\.. _.-.... ~.
." J.
l- 10
-""1
-- _.--- -
... .....
---' ----
'.
.. ........
87
,. 1"
Desired compensatIng
cember
\- .. -.- ..
\
f,r)
".~
"
\"'}
",',",.
\
~".
Fig.
\
\
I
...........
"\
~I
.g
I
.,.\
0'
c
g
0:
E'
1/
Fig. 2.130
2.1~
- ----
rl
~ I
..
~
.,
I '
r,---'
j
/+t
00
/+2
j+3
/+4
; 1+9
;+1C ;+11
/.412'
/+22 1+22 /+23 /+23 /;24 /+24 /+2\ /+25 /+26 /+26 /+27 /+27
.g
0'1
.S
~c.J
I
I
r:
However, the deflections are much smaller in this case (about one-half or one
third) as the prefabricated segments are usually stored for a few weeks before
being placed in the structure (fig. 2.132).
If. despite all the controls during construction, the cantilever beams do not
exactly match at the time of connection, it will be necessary to use one of the
fol1o\'Jing remedial solutions:
! --...
~ 2 S em
concre!ed
In
511u
f 5 em
ill the case 0/ difference 0/ level, tilting of the cantilever beams by nat jacks,
8'0
Fig. 2.132
102
:~Slr=ar
~r
: I
I
t
I
I
-I
I
I
I
L;~'
:
',I
...... ,
"'::>'-'"
4IIQ
. ,
KeYln9 JOint
Deck design
103
first. shear stresses principally in the webs of the box girder (shear force;
V):
.
I I
t
. ..;....---a.. ~,
Fii' ~,lJJ
ii'
"
or
and, vertical components of the conlprcssivc stresses (n) in the lower flange
(the de R6JaJ shear (0". YR ).
Under the shear flow.}; created by the torsion, the cross section of the box girder
tenus tu '.way (",. 2. 136). To stop this deformation, it is advisable to give the
diaphragms one of the two triangular forms shown in fig. 2. JJ 7. The diaphragm s
must be open to allow access to maintenance staff and the passage of services.
When the beam depth varies, Scheme ) easily allows the transmission of the
ResaJ shear force. With Scheme 2, in the case of dc'cks of constant depth, large
If the end sections the cantilevers have a difference of slope, only the movement
of the whole length of one cantilever can cure it. Deformation by twisting of the
beam is senerally impossible.
9
R.sultont thrust
DECKS
Cantilever bridge designers currently encounter three main problems which
influence the design and dimensions of a structure:
9.1
;'
Resultant thrust
vl~!v
Because of the high torsional stiffness of box beams, and of the flexural stiffness of
the top and bottom flanges, usually no internal stiffening is needed in decks built
by the cantilever method. Only stiffening above supports and expansion joints is
'~
Fig. 2.1 JS
'~
104
Deck design
105
c-c
A-A
f
c=::
r-'\M,
I
( . t D..Jfl~
C
~ _.
lB~
,-~l ~i~
c
f
f
e 1(1 a
Fig.2.136
..,
M,
2n.
Fz II
IE
a-a
..J
A
: M,l
2,{l
Fig. 2.139
Stiffener
AA
f8
"A!
81
(,"""',J
r, ": r, I
': I, ~
CarrYing e!er"'l:~~
Scheme 2
Fig. 2.137
pipes C~Hl easily ~ plnced on the lo\vcr flange of the box beam. If the supports are
not in the same plane as the \vebs, some prestressing rods together with non
prestressed reinforcement must be inserted to transmit the shear forces to the
supports (fig. 2.138).
TIle Inost sirnple amongst the special segments nre the abutment ,egmtnll; they
usually have only a vertical diaphragm (fig. 2.139). The hinge segments are more
complicated. They comprise two parts: a carrying element and a carried element.
They are both stiffened by a diaphragm inclined in plan so that it forms a diagonal
in tension, thus balancing the support reaction in the deck (fig. 2.140).
Fortunately, there are few hinge segments and abutment segments.
On the other hand, there can be many pier segments. Their design is different
An
according to whether the pier is simply supported or fixed at the pier. In the first
case, the pier segments are similar to abutment segments (fig. 2.14 I). Only two
details differ. First, the forces transmitted are larger: secondly. if the deck is or
variable depth. the vertical component of the force due to the slupe of the lower
vI
ri~. ~.I JS
SUPPllrl'\
not in
(fin. 2.142).
106
8
*
c-c
A-A
:
,
;"
/----
I
\'
I
I
I
'
I"~
~
Fig. 2.141
I"''''
I
\
'----
B-B
*
:sc
I
A.J
AI
Line sUppOrts r
under the
diaphragms
Point
supports
JCrA
I ~~~r::orts
III
3
Sloping diaphragms
TYP' 8-
'r
flr
I
Under asymmetrical loads, the upper and lower flanges of the deck are
stretched by a force T and compressed by force C. If the deck stiffening consists
of two vertical diaphragms placed above each bearing line, the webs must balance
the outward thrust created by T. If, on the other hand, the crossbracing is made of
two sloping diaphragms converging at the upper flange level, thus forming a
triangle, T is divided in two components Fe and FT which follow the directions of
the diaphragms.
To detennine more precisely the behaviour of pier segments resting on a double
line of bearings, different types of crossbracing were studied with the help of
Professor Ghali and Calgary University, for a deck of constant depth, using rUlite
element analysis.
The diaphragms shown in figure 2.143, included verlical and slopillg
diaphragms, with continuous supports under the diaphragms (A I' B1)' or con
==--Web stiffeners
lnF m
l, I
~
8,
Line supports
under the
diophrogms
Fig. 2.142
I"~
If ~I
SIOPin9diOP~.L
Outword pressure
U---~
-, I
'~
I ; I
AZ
Verticof dlophragms
.~,~.~
...
I
107
Type A - Verticol diophr09ms
~ 1
iI'
,-
8Point
~
I
supports
Fil. 2. J43
---
.. _
.",,~
108
'.
I
. ---~I~ '.'
4900
"I'"
89.00
J450
'"
49.00
4F'
- - - - Compression
- - Tension
Inflll
36
~:
.
I
----,----......
lF~
I
.
bJ ~
.....
..t
,J
,...
4.62
.I.
254
.1.
.l~
4.62
i ~\:~\:
Jt-~~~~\ 11
\""'.
or
~\
~I\~\~
,/,/
/'.
"
Vertical diaphragms
the above conclusions remain true; the diaphragms. however. contrihutc to the
lotal strength.
In the cnsc of sloping diaphragl1lS, it can be noted that compressive and tensile
stresses in the \vebs are largely lower than the values calculated by the triangula
tion method described previously. Although the force distribution depends on the
relative web and diaphragm stiffnesses, onc can approximatcly assume thelt the
forces in the sloping diaphragm are about half the applied force; the other half
being trnnsmitted by the webs.
Fqr this type of stiffener, it is advisable to use a more realistic scheme. It Con
sists in dividing the tensile force Teoming from the top slab into two equal parts:
the first part produces direct tensile and compressive forces in the sloping
diaphragm; the second part has the same distribution that has been described in
the case of vertical diaphragms (fig. 2.146). A comparison bet\veen the diagrams
Principolstresses ,n the webs
From a study of the diagram of the principal stresses in the webs. one can dra\\'
a simple scheme of calculation \vhich facilitates the design or reinforcement. In
this scheme, sho\vn in figure 2.145, the tensile force Teoming from. the upper
flange is divided into four equal forces applied at the top the webs; these are
later divided into vertical forces Fa applied above the supports and sloping forces
F: directed along the diagonals of the \veb panels. F. and F'J can be tensile or
compressive forces, according to their position in relation to T. This calc'dation
n1cthod \vas checked on the pier segments of the Saint-Andrede..Cubzac bridge.
They \\'cre fitted \\;th strain gauges. During deck construction the measured
str ains were very close to the strains calculated by the above method.
If vertical diaphragms rest on supports continuous in the transverse direction.
-'I
,.
Fig. 2. J4S
I
I
Ii
.~
('----- ...
:0
T/4
",.L;:?/'"
"
a pITT
T/4
-fi
1-~
). ~//'1\.\~
1
.
775
Celcularl~n scheme
1-,
15.50
775
109
I~6.89 :
~! /f
Ilj~I'~~~:I:III:~~lIjll~!I:'p:ff
::~-~;~
;~.~.~~ ..~;._~~
I
Deck design
- - - Compression
--TenSIon
~
I '.
T/8
-/4
-.~;/c;'"~T/2. -.~r
.-~
I'
!
I
T/8
,'T/c.
../
./
;
;'
'
,/I
\.
\
f
.
\.
t
Fig. 2.146 Sloping diaphragms
110
Fig. 2.147
Deck design
111
of principal stresses in the webs in the cases of vertical and sloping diaphragms,
showl that the principal stresses in the first group are approximately double those
in, the second.
As a conclusion, it may be said that the different stiffener types studied arc all
satisfactory. However, they must be checked for torsional stiffness, and for the
transmission of shear forces at the supports; lastly, the size and reinforcement of
the elements should be calculated by the simple method described above.
A comment should be made concerning precast pier segments. The diaphragm
can, at times, be so large that these precast segments become too heavy for site
linina and handlins equipment. It is then necessary to cut the pier segment into
several pieces, either longitudinally as on the upstream bridge on the Boule
vard Peripherique (fig. 2.147) and on the Saint-Andre-dc-Cubzac bridge, or
horizontally as on the Calix viaduct (fig. 2.148) and the Metro viaduct in Marne ..
la-Vallee (tiS- 2.149). The joints between the subunits still remain matching.
112
11.00
/:1
20
2%
12.00
..
3.90
1.811
':0.
2.'90
Deck design
I.
! I
.9~
1.-..-...._~70. -.-...
Fig.2.149 Metro Viaduct in Marne-la-Vallee. Pier segment
113
I
9.2
or
daily variation of the deck's average temperature does not exceed 6C;
~~\I,~/
~/Ir~~
"".
-w
..
/
(-;-==-,---'--- .._----"'\
-~_.----
I~----.__-_._-_
..,.__..
_~
K68 dn
~rsJ-
11(";1
J?
112
dl"
..,,1(60/ &
Kfj.(J dn
. - h~(;;i
, \dw
..,=_.,
o
K68
ArclgJi10 - 1
/!"0
2h
M: -""'-
i1
18,
~I
I'' '
tT:'
o+b
68
Dfi;:6,.6
'"
--
o,b,c
...,
.,
IK~8'a(-)
ho
-I
Bendi~..~~!~t_~~ stress.~.
''llO~
Temperature ~1
II
---
(ho\
Reed temperature
distribution
Mv'
k'''O
(~)
1J;
<7,
Tcmp~'ll'Urt~ @,
'0
a, EK66k{J
1/1
Fig. 2.151
EKllOk
_ on the one hand, a structure with variable depth is about one and a half
times more sensitive to thermal gradients than a structure with constant.
depth;
_ on the other hand, flexural forces are more important in a structure witn
variable dep!.h when !.he depth variation increases.
Figure 2.153 shows !.he values of bending moments due to a thennal gradient of
50C in several structures, and !.he values of a/ stresses on the deck's iower fibre.
These values correspond to the above observations. The various differences can
be easily explained. The values of the stress 0/, in the Marne-la-Vallee viaduct.and
in the Joinville bridge, are higher than indicated above; but they are three-span
k '0.65
.. k-O.60
2.0
p:
I.e II-- - -
110
I .
zt:1
"0
~
~lt8E:;:t
i>
v"k~
1,0,
1.5
2.5
3.5
h/ho
Fig. 2.152
115
- Marne 10
..
i
.
7S
56
10Z
~.Z
375
-12
0.58
1050
-1,4
0.59
1400
-1.2
19 0.63
770
-1.8
2.1 0.66
725
-1.9
24 063
980
-2 I
2.6 061
1050
-1.7
26 0.60
2270
-2.0
2.7 067
720
-19
l
I
t.~
WoiwY bridge
s;
Joinville brid9'
.5!
.D
.g Orleons brldge
Genev~kers bridQI
t
I.S
f
z.~
102
u
10e
Z.S
liS
S.S
IlZ
u
z.
lZO
N~,mol $!less
tT, (Mpol
062
TI$T
Anvtrs bridge
MoQnDn v,adue:!
Bendlnq momen!
(1m)
T;'T
~.. vioduc:t
11/"0 v/'ll
o
Cl CherlOM ond
: EpOIris viaducts
k-
Moin
ehorocletislics
SlrUClllr"
s;
AveroQe
062
'-
Fia- 2.153
structures, whereas in the above calculations, the span was assumed 10 he full)'
fixed, i.o. the cue of a deck havini an infinite number of equal spans. It must also
be noted that in end spans and in parts of the structure where spans of very
diff~nt Ieniths are adjacent. 0/ can reach 2.5 MPa.
It shall also be noted that a SoC thermal gradient oflong duration usually has a
more severe effect than a short duration gradient which cannot be added to the
imposed loads.
III conclusion. taking into account temperature effects in cantilever bridge
desi&n leads to substantial tensile stresses near the midspan joints of the order of
2 MPa for a deck of variable depth. Under this additional stress the mid-span
section tends to become subcritical and it is advisable to increase its dep!.h, which
in turn diminishes the action of thermal gradients by decreasing the ratio h/ho.
9.3
A final problem often met by the designer is that of the redistribulion 0/ bending
stf'fsses t;tIused by long-Ierm df/ormallons due to creep of concrete. This happens
in slallcally Indeterminate structures whose state of equilibrium changes in the
course of construction; this is the c8:SC with bridges built by the cantilever method.
Attention hal been drawn to the effects of long-tenn deformations of the concrete
by IIOticeabie geometrical variations in the shape of some structures. In particular,
in situ construction of larie cantilever beams has made this evident in structures
.. _" .
.h'
.....
Deck design
114
116
where permanent hinges were kept at the mid-span points since, with time. these
droop progressively.
The reduction of such deformations has been achieved through the introduction
of continuity in the structures. This is why most of the prestressed concrete
bridges built by the cantilever method are now made continuous by rigidly con
necting the ends of opposing cantilevers. In addition. the use of precast segments
which are placed after a suitable aging period, also has a favourable effect upon
the fl1lallongitudinal prortle of the bridge.
Although the continuity of the structure and the precasUng of concrete seg
ments settle the problem of discontinuity and that of the significance of the defor
mations, they do not stop the occurrence of the redistribution of stresses which
creates a difficult analytical problem.
An estimate of these stresses may be obtained experimentally through
measuring the bearing reactions of the structures with time, corrected to take
account of the diurnal variations caused by temperature effects.
To clarify these points consider two cantilevers C and C' connected at time I r
(lig. 2.154). Had the hVO opposing cantilevers not been rigidly connected they
\vould have be~n further deformed by creep under self weight and prestress, and
from the instant I r their ends \vould have sustained rotations (I) and ro' and vertical
deformations! arad!' increasing \\lith time. Rigid connection of the cantilevers has
therefore hindered their long.. term deformations and hence has produced statically
indeterminate forces in the region of the joint which aJter the previous equilibriunl
conditions to set up a new state of stress. It is this redistribution of forces caused
by the noncompatibility of the system with the residual deformations \vhich is
called, some\\'hat unsuitably, adaptatio1' by creep.. Generatty speaking these
stresses amount to a bending moment M(t) which cancels the angular
discontinuity C1) - ro' of the cantilever ends, and to a shear force Jl(t) equivalent to
their vertical deformations/and}'. If the cantilevers are identical and if they have
been built at the same time, their vertical deformations are equal and V(t) is
identicaUy zero.
The force parameters M(t) and Vet) which arise when the cantilevers are con
necled, increase gradually with time asymptotically towards finite limits Mo and
Va' It is generally agreed that these limits should have been reached within 3 to 5
years.
Several methods have been used either to estimate the values or Mo and Vo due
to creep in a cantilever prestressed concrete bridge or to protect the structure
against their effects.
A first enlpirical n'ethod consists in maintaining on the lower fibres of the
beam, in the region close to the connection joint, a residual stress sufficient to
counteract subsequent tensile stress caused by creep_ In most cases the value of
this residual stress is agreed as 2 MPa; this value has been confirmed by the
evidence of more precise calculations and by measurements taken on specific
structures.
Deck design
117
Prrnclple
,[
~l
~jf---- ~-
I <Ie
I> /
v
M.V
M( '-',)
MO
Vo
o
Fig. 2. J 54
An alternative method consists in assuming that all the clements which make
up the struclure are built together over an infinitely short period of time. The con.
crete nrodulus of e/asticUy may then be considered to be constant and equaJ to its
instantaneous value E, (fig. 2. J55).
At any point on the bridge the 12 J stresses caused by the applied load (self
weight and prestress) during the construction of the structure generate strains .,
such that:
",
".-
- E,
~,
Once the structure is completed the decking is still subjected to long-term strains
f./ I , The final strains wiU therefore be equal to:
Ef
= E;.
Ed
JJ8
t -----tIJ+
------l~
C
i~
',f;
__
c'
Df!ck design
-I"
119
Before joining
I <Ie
II,
11 = f:t + &(/ =-
n
c : ..J.
,.
11 2
Ed
After joining
II,
1>1,
= , &t =II,
1
-
E;
+ "1
1
-
Ed
hence:
'il
I~.g
1
l_ttd;H,
1
~CE,-E;
n,
n,
;I
,. ,
;; n,
2
-+
Ed
IE+E:
,.
. + n2 E
i
n an+(n -n)(l-.:!)
,
1
2
1
,.
Fig. 2.155
Approximate method
.~ Ii
4.0
--372
3.5
-303
3.0
Let us suppose n2 is the stress which would arise in the structure, had the load
been applied directly in the final state of equilibrium. Due to creep, the concrete
modulus of elasticity is reduced to a value E/lower than E, and is called the rUlal
modulus. A modulus of long-term elasticity of the concrete may then be deter
mined by:
1
= -.-.-_-
Ed
E,
&d
= Ed
--257
2.0t-,
--222
--200
1.5
"
--1.70
--144
1.0
E1
2.5
0.5
Instantaneous defOl'motions
----.J __
:3l. ,456
Days
Fig. 2.156
Months
9 1152
.-J
l
.
5
..J
Yeors
CD
Deck design
120
tion of its age and of its loading period. It should be noted that the values plotted '
as ordinates are the ratios between the real deformations and the reference defor
mation of 28..day-old conerete subjected to instantaneous loading.
Instantaneous deformations are not affected much by the age of the concrete at
time of loading (newer concrete excepted) and do not vary much. On the other
hand, creep deformations are significantly influenced by the age of the concrete.
For instance, 7-day-old concrete will attain a total deformation almost double of
that of three month old concrete.
As the construction of structures with prefabricated concrete segments is rapid.
the deformations before the cantilevers are joined may be calculated by including
a constant modulus along the length of the cantilever beams. Supposing that the
average age of the concrete segments before completion is 28 days, the ratio E!,
is equal to 0.40. If the average age of the cantilever beams is 100 days before com
pletion this ratio is practically equal to 0.50; this gives:
Is; :
5, +
~ (52 - 51 I: ~
t====
.~
=L,
:s;)
!. ",'"
.-_t_~
"
0:
"
====1
I:"
(51 +Szl
(5,)
II val~e
of S after creep
eolculotion with
ftnOl structure
(S2)
Fig. 2.157
2 ( 5.+Sz1
121
if the cantilevers are built at the same time, the moment due to creep is con
stant along the deck, and is slightly smaller for the precast structure (line 1)
than for the insitu structure (line 2);
if the cantilevers are built one after the other, by in sltu concreting of the
segments, the moment due to creep has a linear variation along the span
(line 3) and is slightly lower at the midspan level;
if the time lag between the construction of the two cantilevers becomes very
long, it seems as if the younger cantilever is supported by the stabilized
cantilever and increases its fIXed end moment. In this case, the creep
moment at the joint between cantilevers d'ecreases even more, but tensile
stresses can appear in the upper fibres of the fixed end section of the older
cantilever;
122
Deck desigll
123
t===
===1
12V
.L - - - - - 1+655
+710
12V
lIV
' I
+945]
11
+1260 ,.
-
12V
-10,---'
.n:~
---P,ecosl deck
't
------_,0
,...+150
Precast
,
0+-------.+120~-
500
+655
+710
lIV
X,
lIV!
--r--
iDS .
Conslructoon dllectoon
:'
!".",
+680:- ,;
I'"
+850r
Call
';';~4
,~ . . ~~
In $1111
"
';-:-+530
+850
"".
Ir ono applies to these cantilevers the simplified rule of the Ministerial Circular
letter of 2 April 1975, the moment is 6600 kNm (=660 tm) this conftrms that this
rule is adequate when the cantilever beams are built simultalleously and rapidly.
especially in the case of prifabricated structures. This rule, which does not take
into accoWlt the eventual age difference between the cantilever beams, seems to
give excessive results for the moments at the connection of the two cantilevers if
they are built one after the other. The results given by this rule have also been
compared with those calculated by the program on the Angers bridge. This
structure has a continuous deck with multiple 8S-m spans. The cantilever beams
were built and joined by moving from one abutment to the other. It was simplified
for the study into a structure with three equal spans fully fixed at both ends. Each
span was built by integration of two unequal cantilevers comprising respectively
11 and 12 segments. This asymmetry led to a sloping creep moment diagram
(Fig. 2.159),
Two hypotheses have been considered: a precast deck, as it was built, and a
cast ill situ deck. It can again be noted that the asymmetry of construction has
less effect in the case of cast ill situ decks. The specified rule also expresses the
asymmetry of the cantilevers, but gives in both cases a higher value than
calculated by the computer program.
The variation of moment due to creep in the joint section in relation to time,
shows that more than 90% of the total moment is reached after 3 years in the case
+690'"
....
/nsli'lldeck
_ the three lines representing the moments due to creep in in situ cantilevers
cross at a point n situated on the side of the younger cantilever.
~'
'>"':+485
. Spec,f,ed ,ule
\ .. \';00
--.
.~
Conl,lt:vc:t lIc.:um
10,111 12 s89menls
Contoleve, .wlth
11 St9mtnlS
Fig. 2.15 1)
124
Pr7tdeck
500
,--
400
".""
_~_--------T--------
---
//
///
~300
I
I
200
100
fer
Time
1000
fc2 500
1500
3yeors
~.160
Fig.
Ang~rs bridg~-nft~r
2000
5yeors
Day
n'(\fl1cnt~ nri~('.
I'(ll~nlinl
125
be higher than calculated. This is because the long-ter," deformations after Con
nection are most probably underestinldted.
The overall defonnations of a cantilever are equal to the difference between the
deformations due to self-weight and those due to prestressing. But, generally, the
prestressing tendons are' grouted at about the time of connecting the cantilevers
together. The grouting by bonding the tendons to the concrete modifies the
mechanical characteristics of the section; in particular, it decreases the prestress
ing lever arm. From this, it results in the long-term deformations of the
cantilevers increasing by a large amount. The calculation, made for. the Angers
bridge cantilevers, with a steel/concrete modular ratio of 7, showed a 30%
increase in the deformation.
Making the section homogeneous (by bonding of the prestressing tendons)
leads also to a change
the equilibrium of internal forces in each section: this
may be regarded as a local adapla/ion by creep. Lastly, losses due to friction
along the tendons are not well understood and are often underestimated during
cantilever cnl15lruction. Consequently. this Icnds tn u decrease in the cflicicncy of
or
means that the overall behaviour of the cantilever beams, under self-weight and
prestressing. is satisfactorily expressed by the calculation scheme. But where do
the crccp
Deck design
While waiting for research and tests which, no doubt, \viIJ increase in the next
few years. to improve our knowledge of the behaviour of cantilever bridges. it can
he m~~\lnlcd thnl lnkin~ nccnunl or the cUlllltlalivc nction of rhtrtn:JI crfC<.:fs lind
l'l'lTP I" l o"hstrihuf;ul1 IIIOUlellls, nc~un.lif1g to the <":;"~tlla,. 01 1 I\pril JC)75. ha~ lwo
il1l1llt!tli{llt!
consequenceso
It is necessary:
Nome of the S:'':~ure
48
2.5
AncJers bridqe
85 t
95.3
48
90
La
46
(J"
( '.IIl)
( ,)
(Mpo)
~90
8.6
-11
640
2.4
-1.5
-1
t70
5.4
-1.1
74
200
5.1
-1.1
~-
Bro'onne brid;&
~._-_
l
0
2.5
5.5
St Andre de Ct.;ozac bridge
Access Vloduct
--,._-_.-...
MOln choroc'erlstlCS
_..--.,- -- _------_
Mognon vIaduct
~_
..
.....
I
-_.
l~,
.....
120
-"-._-_ ..
Fig.. 2.161
I
- -------
2tl
585
-1.6
-210
..
100
_-
7.8
+0.4
....
-18
first. lu incrc:lsc the be:Ull depth :tl the point ur connection of cantilevers;
second, to maintain some residual compressive stress on the scction lo\\'cr
fibres. near the connection point, even in the case of imposed loads. of
nround 3.5 to 4.0 MPa. This leads to an increase in longitudinal prestress
ing force of approximately JO(X).
127
~WH-
"",.oL
---I
o~
'O... i
CHAPTER THREE
amplitudes of the deck reached 400 mm and it was necessary to stay the ends of
the cantilevers by crossed cables to the abutments.
For r"u/rispan structures or for shorl piers, the linear movements of the con
crete (due to shrinkage, creep, thermal and moisture variations) combined with the
statically indeterminate effects of longitudinal prestress, coupled in turn with the
effects of pier stiffness, give rise to such bending forces as to rule out the use of a
flXed link between deck and supports to transmit them to the foundations,
The structure takes the form of a continuous beam resting on bearings (rubber
plates, Teflon,.,.) \vhich allow longitudinal movements of the deck. It then
becomes necessary to ensure the stability of the deck during construction, One
can either provide temporary fIXity between the deck and the piers, if these have
sufficient flexural stiffness, or use temporary supports placed near the piers (see
paragraph 4).
"
T\vo particular types of pier structure provide a similar result, while being
better suited for cantilever construction of the deck. These are flexible piers and
piers with a double line of neoprene bearings.
ts
'0.
!
,i
.
U
~
1 / ) "
I
i,
;:
. ~f~.
\~
en.!. '
~,',~
t .,,.;:- :1~ ~
'j
;,;
<\I'"
.f15
..
88
8.,.,
to
,_.
GL
~.. '
~,
:t~ it
...J,..;
'0-
It')
an
_.....
~~~
~
1tl
N;
f..i
.~
~~
~-
....
8 t_.
<:t,
i
..
, I
0'$
.-~
0
u0
L.-~
~
;;;~?
!~~
.m-~~
._-~... ~
N:
=
~
O ::;;;
.~
u..
D_ Q:
.
'8....;
,'1 ~
_
i.
' I / ) '
.,
'0
:0
~~ -~
o
o
~
..
. ~"
'lij:~
t0 ;
~--L1 I'" .
-1 ... _
jl/).
~t
f..-U -L...!
f
~. , . , . . .
8'N
_
._
I
Iri
126
-"'''''.... "''~,.
128
it provides an efficient support for the deck under vertical loads, because of
the twin supports;
.
it has great horizontal flexibility (for longitudinal movements to the
structure}-this resolves the problem of expansion in continuous
structures;
it provides an economic way to stabilize the balanced cantilevers during
construction by simple temporary crossbracing of the diaphragms.
In the final state, the diaphragms are individually flexible enough to accom
modate longitudinal movements of the deck and stiff enough to absorb braking
loads and to ensure the overall stability of the structure; the splaying or the
diaphragms plays an important role in the stability.
When the geometry or the structure allows it-more particularly, in the fre
quent case of a three-span structure-it is more economical to splay the
diaphragms in order to reduce the bending moments transmitted to the founda
tions. If the diaphragms are hinged at both ends, and if their axes converge at
foundation level, the bending moment at this converging point is nil, and the
distribution of stress on the ground is uniform, \vhatever load is applied to the
structure.
\H
H- sectIon pIer
~yo"
Fig. 3.4
Fig. 3.3
129
Fig. 3.5
130
"4'~
l! .
".
"-<"ij. ....,
.,
~....
.",.
,,;II.
~""
'''.lJ
(TO)
F,.,
"
u=
I dx
o i(x)
,
v=
I:; 2i +
~~~
I..:M/f' ,
"'I IrI
~1"" 0
~'
_"~I
"'7\
"Ata'\'or~t==l...- .,------
A !GlA'
l'
i(x)
IV=
I' x=
dx
-
i(x)
2sa~
s= 2s
f" -xd\"
If the diaphragms have constant cross-sections, if S and I are the total cross
seclional area and the moment of inertia of the two diaphragms together, at the
level M'. then:
SQ~
2.1
r'dx
Jo s(x)
Fig. 3.6 Cor.::nuous structure with piers having two lines of neoprene bearings
;= I
(F
131
Let a be the equivalent cross section area of the diaphragm, such that;
2.2
2",,)
0'
B..:AM +BQ
BM + CQ
Ill)
sll)
Ii=
,( I)
v= KN
H
2.2./
In
n\
Fig. 3.7
132
If m, I, II and 111', 1', Il' are the forces in the diaphragms at T and A', the follow..
ing equations can be written:
both ends
Webs fixed at
fiXed at bottom
(b) Conditions
0/ displacement
the displacements
Bresse formulae
(J),
A = 1/E1
B = P/2EI
4: I1r + tx
nrV
tV
Ei
E
E
Jo ---dx=c.o
., ---xdx=
+ tx
Y
a =CJ)ol +
wof
+
Jo B E E
00=000+
C=-(2 + Po)
6EI
o +-+-
111
dx
00
cos cp
9' = co'
= A=
).'
,_ = v-a9
J,l'
8=0
/-1
C = - ( I + 2po)
31
C=oo
a,
= a sin ~ +
8==0
ordinates as follows:
1-'
I )
C=--'(J+-(3+2po)
3El
2po
+_1)
2Po
1)
,,1
Eo
000 being the rotation of the diaphragm AB about B, and E being the
longitudinal modulus of elasticity of concrete,
Similar equations give the displacements w', a', ~' of A'.
A., ~ and 9', A', ).1' are obtained by shifting the
The displacements
9=
(I + 2po )
El
A =I- ( 1 +
/
2po
"i' -:::
s
E
I2
B := EJ
A=-' (1
+ --
. ~=-
/ (. 1)
A=- 1 + EI
2po
t~V
111
and
= \' + aO
By cancelling the unkno\vns in the various equations above, one can calculate 9,
2.2.2
By studying the previous equations, it is found that the system formed by two
vertical diaphragms differs from a standard beam with torsional and flexural stilT
ness characteristics, only by the coefficient Po'
In the case or diaphragms fixed at both ends, this coefficient appears only in the
equation of horizontal displacement u. The behaviour of the two diaphragms is
the same as a beam in the case of vertical displacement u and rotation 9. The same
applies when the horizontal displacement u is caused by a moment only. On the
other hand, ir created by a horizontal force, the horizontal di5plnccmcnts are
greatly increased. (Po normaJly ranges between 30 and 80); this shows the
horizontal flexibility of this type of pier.
This phenomenon is even moore enhanced if the diaphragms arc singly or
doubly hinged, as is shown in the following chart, where the displacement
coefficients At B, C are shown in the case where the terms including l/po can be
neglected.
134
Displacement
coefficients
Fixed
diaphragms
1
1
1/2
Singly hinged
diaphragms
at
at
top
bollom
I
2
2
Doubly hinged
diaphragms
Multiplying
coefficient
111
11/21
Po(lJ/3/)
co
135
'.
Po=6(~f
The previous properties remain qualitatively valid if the piers are sloping.
, 1400
2.3
(0 )
We will now give several examples of prestressed .concrete bridges having piers
with flexible diaphragms.
2.3.1
(bl
28.00
__._--_.- ..._._....
This structure comprises two identical half bridges. Each half has a prestressed
concrete deck with three continuous spans (37.5 m. 55 m. 37.5 m) fixed on two
.,,14.00
...
I
I
I
lb)
136
137
piers. Deck and piers form a symmetrical portal frame. A system of tubular steel
piles, driven into the limestone to refusal, forms the foundations (fig. 3.9). The
superstructure includes, below each box beam, two thin diaphragms fixed at both
ends, sloping at an angle of 0.065 radians to the vertical; their thickness is 0.4 m.
These diaphragms were precast (approximate mass: 2S t). Their axes .met near
foundation level, reducing the bending moments at that level. Fixity between pier
shaft and diaphragms, on one hand, and diaphragms and deck on the other, was
achieved by means of 12 8 mm looped prestressing cables. During cantilever
construction of the deck, the diaphragms were temporarily stiffened by a
triangular steel frame forming the web of a beam, whose nanges were the
diaphragms (fig. 3.1O(b. This steel frame had to be partiaUy submerged inside
heavy fenders acting as shock absorbers; they were plac:ed betWHn the
diaphragms to protect the piers against the impact of floating debris. The system
was completed near the top of the diaphragms, by cross-bracing tubes pre
compressed by nat jacks (fig. 3.1 O(a.
A detailed study of the pier displacement coefficients was made according to
the three following hypotheses:
-!
.E.;,
~I
./I
.
Diaphragm
type
Fixed
Mixed
Hinged
3.98
12.7
Pier
elasticity
C
54.62 973.49
234.02 4670.1
Ek
0.918
0.978
1.026
1.-(
i
'"
..
'ij
:.0
.
:::;
:::Vl
Brakina
load on
deck F
M
Unear
variations
,(~6'" 10')
'M
M '.
'M
+7.4' +24.7
+6.4 +21.5
+5.9 . + 19.7
...;
~)
i1:
.::!
'J
2.4
1.3
0.9
r;
c:
OS
.~
c:
....J
'"
E
ell
-5
.....
o
M: bending moment in the deck above the pier, on the side of the main span
J>(: bending moment at the pier head
Q: horizontal force at the pier head
>
.D
u
.&
""
In the following chart, we show the main results of this study which involves also
the displacement coefficients of the pier and of the foundation piles.
Displacement
coefficients
g'"
./. I~...0
L~
Imposed
load on
central
span
co
C
.r;;
0'
.su
o
Iii
i=
138
!'
139
t-t'~-:--::~
- - - -C=~:1- -t T-t
.
I
I
.1.
_
~
1!l'CX)
~,...::
_ m
_ ,
N -!
RUd
lJi
tf).
~
N:
j,
I.
I;
1"':1
;::1 ~l
'
IN'!
.
Miud
Filed
,
I
Miled
- , - -Hinged
fiinged
Syrr.:Tricol verlicolloods
2.3.2
", ..,..,
--
._--!
3 .. _ .#
300 .
V':""
4.50~
r-r---t:j
, 119.3
'~
I 1178
~~
..
;>"""".'"<4"".,.,.,5:1@;:. ~
DOO . . ._-_
,~
500
_......
140
.
\~;,
Jf1
,;( :?
141
diaphragm thickness varies from 0.60 to 0.40 m; they are inclined symmetrically
at 0.0805 radians to the vertical. They \Vere precast and fixed by prestressing. as
in the previous structure.
:: .~
I'"
'.
. ./:f
740
jo.43
.
i
740
.4g~~_i
33.00
---,
--L
.-.-.... . -.........._-..........
21.00
r-
(b) Piers in the river
Fig. 3.13
J uvisy bridge
2.3.3
This structure. \vhich overlooks Lake Geneva, comprises t\1.'O parallel viaducts
with an undulating line in plan more than 2 km long. There are 23 continuous
spans, in prestressed concrete; the standard spans are 93 or 104 m long. Four
expansion joints separate each viaduct into sections several hundred metres long.
The longitudinal stability of these sections is assured by the abutments and by
fixed piers of special design.
The standard piers comprise two vertical thin diaphragms, 0.80 m thick, 8 m
apart. Their height can reach a maximum of 36 m. The diaphragms are hinged at
the top and fixed at the bottom in the pile cap when the pier height is more than
22 m; the. diaphragms of shorter piers (height less than 22 m) are hinged at both
ends. The fixed piers are stiffened by a longitudinal prestressed diaphragm \vhich
nllows lhc.:nl to absorb the forces induced by braking an~ lincnr movements of the
deck. Because of their spacing, the diaphragms are never under tension and do not
require any prestressing. During deck construction, the sta bility of the pier is
ensured by tcnlpornry steel bracings anchored in the diaphragms by high strength
prestressed bolts.
142
tY
~':
40
-"I~ I
I
.
,
.i.~~~~
III I
~::=ro
. "'._
+. _
Frey$sinel hinges/
I
I
R'
elnforcement for the
s~pport of the lounchin9
ard r
9
Temporary crossbroein9
~I
The MaSDen viaduct. on the Nice bypass on the ~A8 motorway t comprises a pre
16
(tiS. 3.15).
~
Tho pieri ." mlde or double H shaped shaftli the distance between the axes is
12 m. They have a maximum heiJht of 95 m above the valley bottom. The piers
behave 8$ thin vertical plates of variable section, directly flXed on the foundation
footing (fia. 3.16).
Because the structure is situated in a seismic area, the deck is fixed to the west
abutment and transversely restrained on the other piers and abutments, either by
flXing on the shafts for the central piers, or by antiseismic keys positioned at the
neoflon bearinp in the east pier and abutment.
.
stressed conert_
I
I
l3.00
s)
~----'"T 2.00
y
5.00
Rock
~ I
I 'I fl.
:1
,...;.i
-.0~
~y
~+
Fig. 3.14
143
d_ with four
continuous spans (3
x 126 m
and 76 m lona)
Each neoprene bearing is defined by its plaMoo dimensions (at b), its areas S
numbern of its elementary layers and the thickness
of its ele
mentary neoprene layers.
(s = a x b), the
3.2
The shear modulus of dasticity G of the neoprene varies according to the mode of
application of the loading- The usual vaJues are:
G
144
145
~N
;-r
1t
t s
>'
f1
\- - . 1
fi'iii=*
L ,-..
( I
-t s
S n(axb)
Fig. 3.17
--r---r8
/.
Neoprene bearing
;-(/
ts
t!
.iI
Fig.3.18
47
...!?-1~
l?
: :l
"0
.!!
..
~
3.2./
Verti~al deformation
e)
u=c--N
2
..
:Q'
'-ff.rl~~:
~
+:c-_-1
t
o\I')
~ 18la ~
~
r-:
~,~
-r.
91J1~
I
~~L
r
c(~)
~=c(!:)
~
a a2
b b2
0,
o
N
C/l
Q)
..I
v,
---t----_~
r
i o :
<t
.,
,...., Oi
..(),
-.o
...;
Ii:
to
If)
If)
:2
GSa
lie)
u=c--N
2
GSa
N
'
III
146
3.2.2
147
-$- : -i
-$- Ii -$-1 ~p
Under a bending moment M, the upper face of each elementary layer rotates
relatively to the lower face by an angle 6.
(;3
O=c'--M
GSa 4
Supports
where c' is a.sh~pe coefficient depending on the plan dimensions of the bearing. It
expresses the load-spreading effect on the layers of the vulcanized plates. If a is
one dimension in plan. measured perpendicularly to the rotation axis, for a
bearing constituted of n neoprene layers, the rotation 0 can be expressed as
follows:
1:$
-$-
113
8::;c'--M
4
GSa
t1'
T
0.5
0,6
0.7
0.75
0.8
0.9
1.0
1.2
1.4
1.5
10
136.7 116,7 104.4 100.0 96.2 90,4 86.2 80.4 76,7 75.3 70.8 66.8 64.9 63.9 61.9 60
,.... _d
u::;-Q
GS
M=
nE
u=-Q
Id
+ 2",
2"
GS
0=
d
GSpa'
3.3
: III
If. on top of the pier, there are t\VO parallel lines of neoprene bearings nt a spacing
d, partial fixity of the deck with the pier is created. The neoprene bearings, being
distorted under a load Q, and settling under a vertical load (M/pd) due to lr1 (see
fig. 3.19), affect the deformation of the pier.
The rotational stiffness of the neoprene bearings is negligible. Consider f, the
normal force, and m, the moment transmitted to the neoprene bearings when a
with
=--6
C'lliJ
GSpa 2
!=--v
.. cniJ
pGSa
hence M = - n~
(tP-
2c
20
c'
+ -
"-,,~"""-"'''.r,",,,,,,,~
148
;
~ k
'.1 ~
.
Taking an example:
-= I
600 x 6oomm;
d=2Am
c' = 86.2
c = 2.37
11
pGSa
M=-11(;'
A = Ap + A.
B= Bp
C= C
m-f
~
(2.4 2
2 X 0.6
+
2 x 2J 7
86.2
pGSa
=-
1If.)
2
(
3.4
+ C.
Piers with. double line of neoprene bearings have the property, as have piers with
thin concrete diaphragms, of providing efTectivefixity of the deck, while at the
same time allowing freedom to expand longitudinally. Several advantages result
from this fixity: first, the longitudinal bending stresses are reduced in the deck at
midspan, as the change in the bending moment is transferred; at the same time,
the moments at the supports are not increased significantly, thanks to the moment
reduction in the span (see fig. 3.21).
During the cantilever construction of a deck. its stability can be increased by
substitulinll I.:oncrete blocks for the neoprene bearings and by applying a verlical
prestressing force, without having to introduce temporary supports, the use of
such temporary supports being time-consuming and expensive. It is also possible.
hy a jlldicillllS choice of Ihiekness of the neoprene layers. 10 reduce Ihe bending
If the second part of the term in brackets is neglected, i.e. the rotational stiffness
of the bearings, the consequent error is less than 1%. One can then write:
0=
2lice'
pGSa 2 (/2
149
,-
OLERON VIADUCT
Imposed load 6 t / m
. iii iii
ili
iii
i i
r.-'
2n
A. "" c prP
GSa 2
Bn = 0 .
II
&
C =--
"
Moment at
the pier
.1
2p GS
rather is there horizontal movement under moment M. If A" Bp , Cp are the defor
mation coefficients of the pier (including foundations), the total deformation of the
(Moments in 1m )
Fig. 3.21
Oleron viaduct
150
stresses transmined to the pier foundations. Moreover, one can cancel out the
bending moment of anyone point of the pier for a given load cue.
Consider a pier with a double line of neoprene bearings, supporting a con
tinuous deck. For a particular deck loading, a bending moment M is created at the
top of the pier, and if there are no movements at the joints, the bending moment
transmitted to the base of the pier is:
IS I
()
--..
'"
if , if
,
M
M'=M+Qh
Eu=BM + CQ=O
hence:
1.10
B
Q=--M
C
Fixed-end pier
and
Fig. 3.22
Cp + CIt
The value of the coefficient, varies according to the thickness of the neoprene
layer. In the case of no neoprene layer, ~ is negative.
(9 =
Bh I ) .
hI
11.1
I:X = - = 1715
+=0
C. =hBp -Cp
Pier characteristics
h =33 m
I=7.0m~
h
EA p =-=4.71
/
3/
21
C,
2
The moment .\1' transmitted to the base of the pier is nil in the case of
Four neoprene bearings are placed in two lines at a distance 2.4 m apart in
the longitudinal direction.
Dimensions of each bearing: 600 x 400 m, three layers of (12 + 2).
Deformation of the neoprene bearings:
b
1/
=J
2n
= Ec ~
- - 2 = 0.97
PIC GSa
EB ... 0
nt
EC =E--=915
2pGS
. . ~~ ......~.~
152
-
;s;::.
EA
EA
EB
EC
B2 )
C
3.38
M'
Ek
cp
nil
77.7 x 33
1 - - = 1-----=+0.03
C
2630
The bending moment M' transmitted to the base of the pier is very small (3% of
M). To give the theoretically zero value to M', the thickness of neoprene should be
such thai
ECp
EC =-*860
2
correspondingto 11&'" 34 mm.
The following table indicates the variations of the parameters A, B, C, k in rela
tion to the neoprene thickness.
It can be noted that, in order to eliminate the bending moment at the base of the
pier, the necessary neoprene thickness is 8 mm for a 20-m-high pier, and 34 mm
for a 33-mhigh pier.
3.5 Innuc:nee of the thickness of neoprene bearings on the stress variation in
threespan structure
=-M
Bending moment
diagram in
the pier
(II = 33 m)
= 0.25 -I = 1.18
1I
.5
4.71
77.7
1 715
5.03
77.7
2020
5.36
77. 7
2325
5.68
77.7
2630
6.00
77.7
2935
6.33
77.7
3240
l.le
2.03
2.76
3.38
3.93
4.46
-0.50
-0.27
-0.10
....
....
Ek = E(A - B
Coefficients
,=
153
Bending moment
diagram in a
lower pier
(Ir = 20m)
r,f
.100
l
1
..
fJ
f..
'"'
0 "
10"
'"
,~"
'0'"
.').'
+0.03
...
+0.13
"00
..
'tlUI
_nl'
~;,
-,
iI"
+0.21
., ?O
17
.,
t,
.(1 ~.
l'....
lfJ
....
deck supported elastically on the piers through one, two. three, six or nine
layers of neoprene (12 rom thickness);
deck simply supported at the piers.
The loading cases under consideration are those to which a prestressed con
crete structure is normally submitted, i.e.:
-
to a
to a
other
(load
A(lJ)~
imposed load S I = 6.8 tim uniformly distributed on the end span (load
A(I,:
v.
~
Tnblc I. Bending nl0l11cnt :tllhe top uf the piers in relation to the neoprene thickness
Numbcrofncoprenc layers
0
(fIXed)
92
184
+ 216
+ 106
+ 68
136
+ 174
93
+ 53
- 106
+ 146
-,
M>O
60
+1700
-1420
101
+2017
M<O
-I S81
-1367
Loading cases
-
+ 124
M<O
Loading of central span S 2 = 4.5 tim
Loading of end span S J = 6.8 tim
Braking load 15 t
30
+1440
-1240
97
+ 1 711
+
+
+
+
84
43
86
127
13
+1270
-1120
93
+1509
-+11502
-1226
9
68
27
S4
95
' + 58
+ 19
-
38
+ 77
-1030
90
+1367
6
+
+ 930
- 850
80
+ I 105
+ '20
+790
-740
-1122
-795
74
+941
924
The vaJues have been calculated above the pier axis and at the level of the deck centre tiDe. Units are tnt.
Table 2. Bending moment at the base of the pier in re1ationto the neoprene thickness (tm)
Number
Loading cases
0
(fixed)
31
J
-Ill
+222
+218
+ 13
- 77
+ 154
+167
-157
+314
M>O
+283
- IS
-129
+258
+243
M<O
264
-188
-144
-liS
820'
-435
.;,..198
i97
-207
159
- 74
163
+609
-7N(\
S2.=4.S tim
Loading of end span,
S. = 6.8 tim
Braking load 15 t
Extreme values of
bending mornent
Continuous
beam
+ 404
+ 342
62
202
or neoprene layers
~I
>0
if <0
+ 698
-1243
167
+S77
-51R
G=24m
+ 20
- 60
+120
+140
0
-130
+260
+260
-64
.- 40
-130
47
+ 176
+265
-265
: 170
-400
.558
-380
180
+527
-S50
--624
186
+591
-62(,
0
(S20)
f
780
(.50
v.
156
~I
~I
00
0'"
'.0 '"
"'0
r-o
NN
r ... r l
.~
The resulting bending moments in the structure, under these loading cases are
summarized in Tables 1 to 3.
These "alues cali f'ir some comment.
i:",.:
'
l!
-'"
00
'I') V)
v.
NM
...
<:)
\ON
00
~-.c
-.c
+ +
I I
.!:!
'5
u
>.
.!!
"'0
cor--
...,
"
'0
-00
Cl\r-
00
NN
0""
OV"l
000
O-~
I I
:
c
.g
"'Iv
.!:
~
,~
..
+ +
+ +
CJ\\O
...,N
+ +
I'
'<
':.'
"
' J
(""I
,.,
.~
:;~
..
l\1any striJcturc:-.
hn\'~
hee,'
b~l~!t
with doub;f
!ir.e~
,...
c ;
f"~
+ ...
-,-,
.:;; ':.:;>
;;,.,
~tt'i_
C'.
C"
('0
.:..
.J.
..-\
.21
. .,.
I
E
111:11,'
I: ~:-:---:-:-:-:-:-:
'~
'"
,-_-:---:_-:-:-:-~~
,..;
Temporary cofferdam_III
<:)
".~'~''':''
:0
'"
!-
I'.
1- .. ~;...,:'''''':.l
"!'";:\
1::
~
- i'
(;
:;;
,~
..
""c
:i1
Pf:-:-:-:-:-:-:-:-:-:-:
PI
".;":._.
~R
g 0
Roc~ __.:.
01
I~
i . :
--~
'
',~
Immersed concrete
~a.e.
Ii'" Q, C ."
:iulfi~~lfi
11.50
sc"":
-sea
a.
_ D !.~ea
.. II D"
1!~ ~i:,r
I;:--:---:
"', - .:
~
'0
'";:\
-=
i:.d
:-_. ci-:'LI
fU '
..__,
.
~-~
:,::
aa.
lX::1ni"ri'S.
;:~!. '.:~'II"
ilt'
;'\!'.
"
u."c
!1CC'PP'~:C
1,\
="
c-"
8.
c\.c
c,f
0:..;" ;""':
~;";"';'::"":";'';''~:--~
~.
,
(:;
rlC)C5
.. ~c:t the m~X;ri:~.,,, u~nJi{i:~ t:~,<Jn:el1~. \Vh~~ t;"j-'; :'.'<,.. i~):r 0;-laycr~ "i:1.r:",:~ '-";>~rn
one to six, the m:ni,num bencing moment at ~he support decrc~5es \.' ,-dy
6% and at mid-span increases by 10%. The extreme case of r.i:le iayers
should be avoided as this piling up of neoprene could create instability in the
bearing. Whatever the number oflayers. there is always a good fixing errect of
the deck on the pier, with the advantages mentioned earlier and an important
decrease of the midspan bending moment, for a small increase at the support.
','
," (b) Regarding the piers, there is an optimal thickness of neoprene which leads to
minimal stresses at the foundation level. In the example, the optimal thickness
is three layers of 12 mm, which is similar to the value found for the fixed joint
structure.
157
Fig. 3,23
Roc_-23,OO
158
159
The O/;rOll viaduct has a total length of 2870 m and comprises two span types
only:
The precast concrete deck is continuous over sections which are approximately
300 m Ion,. The deck rests on 45 piers located in the sea.
The deck is flexibly supported over the piers on a double line of neoprene bear
ings. The pieri have a hollow rectangular section, with a wall thickness of 30 cm.
Th, Blois Brldg, crosses the Loire in five continuous spans: (61.5, three x91,
61.5 m Jona). Two parallel box beams make up the precast concrete deck. Their
depth is variable. They are elastically riled on hollow section piers. The deck
forms with the piers a pin-jointed frame (rli. 3.24).
,'.
--l2!9
I~----
..,
The problem,
~~
etF~~f
Z
Q
X
~
IIIII
(bl
Fig. :.1-1
Blois Bridge
WInd
\... ...__.,-_-J
Temporary WO'U lood'nej
'- I
Segment out
01 equ,i1bllum
160
16
Temporary wedge
or
Fig.3.26
4.2.1 The deck ;s rigidly and perlnanently fixed at the piers tolorm Q rigid
frame
.
In this case the stability is ensured by the strength of the piers. Generally, the
strength is high enough to carry the overturning moments during construction as
these are smaller than the moments applied when the structure is in service. Some
times t it is necessary to reinforce the piers. Vertical prestressing can be applied to
reduce the eccentricity. of the resultant forces. If the piers have flexible
diaphragms. it is often necessary to stiffen the diaphragms as on the bridges of
Choisy..le-Roi t Juvisy and Chillon (see paragraph 2.3).
It
Thus, despite the pier's small stiffness, it may be possible to ensure the stability of
the deck (fig. 3.28).
When the de~k is made up of precast segments placed with a launching girder,
the prestressina force may be replaced by the launching girder reaction, when its
central support is not over the central line of the pier (fig. 3.29). An analogous
0
-.. . Prestressing bors
ft
OIO~
I"'"
I
..:... 1._ ..t. I:
1-'
I
, ,/
~OjO~
',/
1"-
+.
Fig. 3.27
Flat locks
.~.
Concrete wedges
Temporary fiXity-Piers with a double line of neoprene bearings
162
163
"'/
Vn
f
[~~ LIITTTI1II-,r-r-.----,---r-~- Vn
Temporary fixing
f---.l.-+-J-- d
tp
",/8. Pd
2
vii
.1
Construction
v"
C#+Pd
2'
it
Construelton
Vii
C
Fig. 3.30
*' -P1.2
,-'
""J[
vnr:~
is'
Fig.3.19
result could be obtained if an asymmetrical segment was built over the pier; the
centroid of the segment would be transferred by the length of half a segment. But
this method would considerably complicate the cabling design (fig. 3.30).
Following the same principle, in the case of curved cantilever beams, a lig
nificant proportion of the bending moment due to the self weight of the cantilever
beams can be equilibrated by a preslressing force, transversely eccenlrlc to the
bearing axis. This method was used for the construction of the Saint-Cloud bridae
over the river Seine. Its balanced system, with SO-m long cantilevers, was
temporarily fIXed on elliptical piers. These piers had a maximum width of 2 m.
The deck being curved, the piers were flexed by the application of a prestressing
force which was eccentric longitudinally and transversely. A simple prestressed
fixing, central or ~ccentrie, may not be sufficient to ensure stability of the
balanced cantilever beams if accidental loads are taken into account, such as the
fall of the mobile concreting equipment. which create high overturning moments.
It may be necessary to cable-stay the piers. The cables would be lightly stressed
and would be able, by their tensile capacity, to ensure the stability of the cantilever
beams. The cable stays would also reduce the compressive forces on the wedges
when the cantilever beams arc only loaded vertically. Such a method was used
during the construction of the Gennevilliers Bridge (see paragraph 4.6).
/
4.1J The deck, ill ilsjillal state will be simpl)' supported 011 piers havillg all
.__e.
....
. ,.,...-.
164
DC?~ ign.(or
, tOO
ChassIs .... -, . ;
;~
Fig. 3.31
==::::E
/
FiJling point
~c
Fig. 3.33
Fig. 3.32
"
0
I
~~
pH = e/2a) 0
N( 1- 2p)
pN + e/2a;> CIa
\Vhatever the solution, the dimensions of the temporary support must be such that
it can resist a compression equal or superior to C/Q.
The single temporary support seems preferable, except in certain special
circumstances. T""o temporary supports need t\vice the amount of material, and
only offer as compensation the possibility of starting the deck construction from
one side or the other of the pier. It has been possible to avoid the use of temporary
:11:
Fixing point
supports during the construction of some structures where the deck was made of
prccnst segments (the Rio Niteroi bridge and the 83 motorway viaducts)_ The
stability of the balanced cantilevers was ensured by the launching girder used for
the placing of the segments. The deck was rigidly linked to the launching girder by
a verticnl frnme, able to resist both tensile and compressive forces (fig. 3.33).
4.3
165
Nor",alloading
deck selr-\\'eight comprising two clements:
(a) theoretical weight of the segments (weight of the segment built or
166
167
4.J.2 Aceidellialloading
Caused by accidents during construction: the fall of the mobile concreting equip
ment during its transfer. or the fall of a prefabricated segment or of its placing
equipment. The weight of these elements must be multiplied by a dynamic factor
of 2. However. one does not consider, during the study of the stabiJityof the
cantilever beams, the fall of mobile equipment during concreting, nor the raU of a
precast segment after its placing and tlxing by temporary prcstressin,.
The stability of mobile equipment during concreting. when ensured by
mechanical devices. must be assessed independently of the strength of these
devices. Similarly, st'ability of the precast segments after placing and before
threading of the final prestressing cables, must be assessed independently of the
strength of the lifting equipment.
4.4
The l1orllialloadi"g conlprises know" loadings and ralldoll' loadings. The cvalun.
tion of random loadings is diflicult as they are closely related to the quaJity and
II
Ho\\'cver, it is thought that the magnitude of the random loading could be taken
as the sum of random differences in self.. weights and site loadings, expressed by a
formula q =!(S) decreasing when the loaded area increases. sinlil:tr to the
unifornllive loading used to represent vehicle loads in bridge design (fig. 3.35).
In the case of a 150 m long cantilever system with a 20 m wide deck, a site
2
Iloading of SO kg/m represents a total loading of 7S .t uniformly distributed on one
II
f/. 50 kg/m 2
-e_l
'CJ '
SLit
f1 {S:
Wind 22 kg/m 2
Fig. 3.34
"
NIH\
S/
L/
-----L---------~l
FiI.3.35
"IC
t~t~t~t~'-i'-t-f::--,t-.~-~~t-t-t-t"""t"""t
1-
:--I
Regarding wind. the french Code of Practice (article 14.2, vol. II, Book 61)
evaluates its loadin. on a normal area as:
100 kg/m J if the construction period lasts less than a month;
125 kg/m l if the construction period lasts more than a month.
168
169
50nocol'o
buiding
q'50kg/m 2
240 0
. . 27~/
.~
""-.. .
~.
./ Pie,0.. ,~
I
Fig. 3.36 Random loadings for the Gennevilliers bridge
If no precise data are given (e.g. tests in a wind tunnel), the angle of the ascending
wind acting on one cantilever only, must be taken as 100 , when the construction
period lasts more than a month. This is equivalent to a 22 kg/m J uniform load.
The wind tunnel testing of a model of the Gennevilliers bridge has shown that this
loading could be an ullderestimate, in the case of an exposed site. The tests have
been carried out on a rigid duralumin model. The model represented a balanced
cantilever system built on the right bank pier. The mobile concreting carriage was
nlso placed on the model (fig. 3.37).
It wu possible to observe the wind loads on the deck and to calculate the wind
vertical components, which would create an overturning moment on the balanced
cantilever system during construction. The Right Bank site had been chosen
I
t
1716
IS
14
13
12
:1
il
I.
2TtCJLJf9
I
I
Measuring poinls
1 234
5 6 7 8
The cantilever beams, during construction, must be assessed for their stalic
equilibrium limit state. This assessment can be made by the new semiprobabiJistic
170
171
N
1860
Sonocotro
building
..
"'-.
/1
.I
Seine
River
!/
'I:
/
90
"
0
./'
.---./
n
/
U/
Wedges
Equivclent pr'$$ur.
:42 k9/m 2
Fi~ ..\.JII
M:lxil1ll1l1l
._11-
o\"l:rtlirnill~ 11101111:111
\hll:
1\'
willd
1:\llIhn!.:1I1
"~VM
1'n:SMII'1:
42 kg/Ill:
theories of safety: the ultimate strength is checked for all the elements which affect
the stability of the balanced cantilever system, by increasing the applied loads and
decreasing the strength of the materials.
If the balanced cantilever system is temporarily fIXed on the pier, for example. it
is secured on two tines of wedges by prestressing cables; one checks that the
cables are not loaded to their ultimate capacity and that the wedges are not
crushed. One can also check that the moment created by applied loads around
one of th<. lines of bearings is less than the ultimate moment of resistance of the
stabilizing elements. If the deck rests on temporary supports, each element must
be checked for its ultimate strength. Among the applied loads. the most severe are
generally the accidental loads and they must be used for the choice of the stabUiz
ing system: temporary fixing. temporary supports. cable stays, etc. It is necessary
that, under standard imposed loads, not factored, the deformations of the
cantilever beams are kept small. To achieve this. it is necessary, in the case of
temporary fIXing on two lines of wedges, that the wedges stay in compression
(fig. 3.40); it is also necessary, in the case of temporary supports, that the deck
does not lift at any of the supports.
Fill. 3.40
4.6
ScrYic~.bilily
limit stille
Cable Slays
H' - tension F', cross secti"on area S'.length I' flexibility X'
I'
=-
ES'
I"
H" - tension F", cross section area S",leneth I". flexibility X" == __
ES"
._ _,f/lf
1731
1
~~ and
1~
M't' are due to the rotation of the pier head. If k is the rotational
H'
--
iI
K{;
K{~:
TP
F*
~;JK
J_
ka~ )
( I + -K'-
"ka
F' - - - F" +
K'
F)
+ 2F)b = 0
2/-"
(4)
()
II
k
K a +b)
k
- nh - - --~- (F - F ) -:- F', --- ad/)
A"
K' 2h
II
0
K'
(6)
=0
(7)
For small values of P, the compression in the link between deck and pier is not
reduced, F = Fo and:
F=P=Fo
Pd
P=Fo
F"
= F~ -
~:
ka
Pd
K' + 2ka~
(8 )
(9)
These equations are valid until p:= Po, Po being such as:
(I)
(2)
F= Fo + l:1F
/0'''. "-" (F
A"'
I::S
F"
1-"
Beyond a value Po of P, Po being such that Mo > Nob (No being the normal force
acting on the pier head), the resultant tends to move away from the axis of the
wedge B* , the deck lifts from wedge B and the tension in cable F is increased.
F> Fo
k a-b
M'!.'=---M"
.
K" 2b
F" >Fo'
K"
The system comprises four unk-nown quantities p', F', F'II, and t:.F and four equa
tions (1), (2). (3) and (4). By replacing l:1F by its value IiF = F"- Fo in the equa
tions (1), (2) and (4), the system is reduced to three equations aHowing the calcula
tion of F. F' and F", Generally K' = K" and Po = I'~" One can then write the
above equations as follo\vs:
(J
>F~
The equilibrium of the balanced cantilever system around the wedge B* can then
be expressed:
F'
I1F" =-Gi\J
K a +b
Mi = - - - M
K' 2b
(a
Fig. 3.41
6F,6.F; and 6Fi' are due to the tilting of the deck around the ~\'edge B* and:
H
Pier(k)
2b
0
k
=-aA1
K' ,
,I
...
~F'
F'
II
(3)
Po
=:: - - - - - - - -
d( I _
2ka'
2ka 2 + K'
(10)
) - b
When P> Po' the compression in the link between deck nnd pier is reduced and in
174
the prestressing cables, the tension F is increased so that F> Fo. The equations
(5), (6) and (7) are used to calculate F, F' and F".
During the construction of the Genevilliers Bridge, the stability of the balanced
cantilevers had to be assured by a cable-staying system (fig. 3.42). The overturn
ing moment, which could have been created by the fall of a mobile concreting
carriage, was very large (M = 128000 kNm = 12800 tm).
The results of the above calculations, in the case of Gennevilliers are compiled
in.a simplified form in Fig. 3.43. They correspond to the case of a pier, where the
prestressing used for temporary fIXing, comprises four cables (12 T 15 cables),
and where the pier is cable-stayed by four cables; each cable stay is made of one
,
'0/
175
12 T 15; the cables arc symmetrically placed in pairs on either side of the pier, at a
distance 22 m from the pier's axis.
The diagram shown in Fig. 3.43 represents the variation of the tensile forces in
the temporary fixing cables F and in the cable stays F I and F", when P increases
(d is assumed to be 80 m). The temporary fixing cables are initially stressed b)' a
force of 165 t (1650 kN), and the cable stays by 100 t (1000 kN).
The load P = 160 t corresponds to the fall of a mobile concreting carriage
(weight, 80 t, dynamic coefficient, 2). It can be noted that, up to P = Po 03 185 T,
the comprOilive forco. do not decrease in the wedges. When P> Po, the tensile
force. increase in cable llay. H' and decrease in cable-stays H". When P
reaches approximately 250 t, the tensile forces become nil in cable stays H" and
increase more rapidly In cable stays H'. The increase in tensile forces in the
temporary ftxing cable. is small and thus can be neglected in a rapid calculation.
The random and known site loadings being taken into account, if a mobile con
creting carriage [clI. the maximum overturning moment would be 176000 kNm,
i.e. P,.. 220 t. The tensile forces would reach 370 t in the cable stays H', that is
185 T pcr 12 TIS oablo. lbil value is well below the cable ultimate strengtn.
F-F'-F"
670T
\~.
\\
.," "
.\
\
,,"
,,"
",,550 T
--------~~~;
\,
. \
'.\
.\.\
'. .
.100
117 1051
129O~
~ .....
Po
Cable slays' tenSIle fortes F'ond F"
..........,
__
90 .320'
160 185
PT
'
176
177
LOnqitudinal section
$o/lC101
N.E.obulmlnl
Mud
__
.
i
67.76
_.
77.00
7700'
77.00
T.. _--'f'f~--t.,"'"-,
77.00' 67.76
.U I '34.00 ><t::{::~
1!l''!UjP=4\
93.2\
473.32
21.30
I.
lrid9t on lilt
Main structure
~quay
Pier element
t
11201
~--::==~
Colferd
Vorioble
'forced concrete
.-.
.-
-------
,
I . >
3.00'
.
. _!__ I
Moss concrele
I
I.
Fig. 3.45
l.tp5.60
900
.1
.1
'
9.00
.1
Can
--e
~~.~,-.
Bordeaux~antilever
supports
178
179
~"---~ ......<';;:'
........
The two bridges of Pierre-Benite over the river Rhone each comprise a continuous
deck fixed on river piers. Deck and piers form a portal frame. The decks are made
of assembled precast segments (fig. 3.48). The river piers have a 2 m diameter
i:
5600..
1960C
84.0C,. 5600 I
r- -
79.00
173.~2
BoCkfil~ ~50.oo,
75.00
250.00
I I'
75.00
3.60
50.00.
pier foundations are pneumatic caissons (fig. 3.50). Because of thcir small dimen.
liions. it was impossible to usc the piers for cantilever construction (If the tied.
without udding a large amount of temporary reinforcement. This reinforcement.
for each pier, was made offour columns each consisting of a 760 mOl 9 steel tube
filled with concrete. The tubes were placed in pairs on either side of each pier. At
their top wu placed a cradle incorporated in the form work of the deck section
which was cut in silU. Some means' of adjustment was necessary at each support;
because the permanent pier was. rigidly connected to the deck. no vertical move.
ment was po&Sible here. Flat jacks were used to free each temporary support of
the load accumulated during construction of the deck. In their lower part, the
tubes could transmit their reactions to the foundation caissons.
In the case of the bridge over the flood gates, this transfer of load was made
through two transverse webs, covered by a stiffening slab ensuring the transition
with the metallic tubes. Two 12 T 13 prestressing cables, placed vertically, held
the' system toaetbcr. The cables were looped in the foundation caissons, and
anchored in the deck.
.
In tbe case of the bridge over the flood canal, the solution adopted was similar
to that used in the construction of the Saint-Jean bridge in Bordeaux. The lower
end of the tubes relted on the reinforced concrete colTer dam collars used for the
foundation coastruction. Each pier was vertically prestressed by two 12 T 13
cables. They wa'e used mainly to increase the normal force in the support.
180
181
312,58
67.47
92,00
-
:~l--
J.c:.~n
81.46
-~I~
+"AA'
J.
71.65
.;
0,.
'SI!
etlV
II::
~ti
~
~
Fig. 3.5 I
..
'
'l'l
l
:.:.:' '~1~
8':
'. A,
Transverse section
iTJ
:
.'
I'
. t.. '. .
'.
~---;~-~--,
Section AA
,.. ,_ ~.!O
I
Pier.
"'I
Sf
~,.
:3 20
oi
~:::=T;:::SS==:::~--I
.~
Z
Beom
~~
['.
: P~d"lol
....
1 .~
oN
~ ..: . '
"
0'
~~;,...;
ChQlt
,/
F"I')V"'1""';."
fl)r"",.,;
,Moss
fO\i'\dohon
.. .
640
,
_,_~~10
.n
22~~fj~
... :~?,..~
Shoft
o
26 39 ~~.
._------ ! ~
(1)
.'
. ' --Column
)..
Pion
.,'
68.
t{ .
~I
5.3 The downstream bridge or the Boulevard Perfpherlque o,tr the R'ver Seine
In Paris
The downstream bridge of the Boulevard Peripherique comprises twin decks with
four continuous spans each resting on two river piers. one ground pier and hvo
abutments. The decks rest on neoprene bearings (fig. 3.51). The decks are com
pletely prefabricated. The river piers are com posed of tapered columns placed
over a' hollow pedestal comprising two pillars of polygonal section. linked by
cross-bracing webs (fig. 3.52). The piers are founded on mass concrete footings.
cast inside steel coffer danls.
Because of the small dimensions of the top of the pier. it was not possible to
ensure the stability of the balanced cantilevers during construction by fixing them
at the supports. It was necessary to use, for each pier, a single temporary support
Pion section
fJrJ)"
~
~oo"
-.~:hiir
-s~
-:
~~.-:.'" .~.
J~.
::
~t
~""':..':~~I.".'~
~: ...._ ,_14 5Q._----..ij
,-,
~- _!520
Fig. 3.52
.4
~~?.,
.- - _,.
.,
"~r
4.-~--'.
~. (':L:lJ .~ ~
~: "',
'~
~'-',:",'''~''::':~''~~
:..J-~...1
,.-!?~,
40
,0
,-,
placed inside coffer dams. This layout had the advantage of decreasing the
amount of material needed, but the placing of the segments always had to start
from the same side of the pier. Each temporary support comprised a metallic tube
1020 mm +filled with concrete and resting on the pier footing. On top of this tube
was placed a reinforced concrete trestle. The trestle was 0.8 m thick and the deck
rested on top of it (fig. 3.53). The V-shaped trestle directed the vertical loads con
centrated in the box girder flanges towards the steel tube. The head of the tube
had been reinforced to aJlow a better distribution of the forces.
182
183
88.25
2.405
i. ..~:~.~~.:_~~~~=-~.I=Ql
j r ._ :._~L:.-_~._L.~
Wee;e-shoped jOlnt-- ::::-80
Reinforce: concrete treslle Column
......_.. !
,\Too
f2 ~7
~~
;-;:O;-lr,' r-~;;;";~enclO$u(e
Steel !ube
filled with concrele
1,
~I;: it ~f
Fool
8 'I
~. ~
"'9
J~
'!
o~
:a
&U
The distance between the axis oC the pier and the axis oCthe temporary'support
\vas dictated by the size of the colTer dam. It was small in comparison to the length
of the cantilever beam._ The lever arm was 2.4 m Cor 2/44.1 m long cantilevers
(fig. 3.54). The reactions in the temporary supports wero very lar,e. Tho Itatie
maximum reaction dwing construction was 1060 t. The valuo thi. reaction
increased to 1280 t, if one applied a load factor of 1.2. ThII factor could represent
a dynamic effect either durinathe placiDa of the segments or due to the
eccentricity of the wind pressures. The support reaction. of the right bank pier
reached 1380 t during the tensioning of the continuity cables of the 92 m long
central span. But at that time, the deck was a redundant structure and its stability
\vas assured. To avoid the risk of uplift of the temporary support during certain
periods of the construction, the tube-trestle system wu linked to the deck by
12 T 13 prestressing cables looped in the picr's footing, these cables having a
breaking load of 640 t. To ob~ain a similar result. some prestressing bars flXed the
deck to the piers. During the statically determinate phase of the construction, the
decks were supported on the piers through steel wedges.
The maximum concrete stress in the trestle was 13 MPa, while the stress in the
concrete of the tube reached 14 MPa, this value being calculated on a transformed
section with a modular ratio of 10 for the surrounding steel.
Because of the high value of the vertical reaction in the temporary support, a
high shear force \vas created in the sections near the support. The shear force \vas
directed upwards. The effect of this shear force was increased by prestressing
cables placed in the deck at an acute angle. The ve~ica1 component was added to
the above..mentioned shear force. Added to these forces was the Resal effect
created by the depth variation of the beams. This effect acted in the same direc..
tion. In these conditions, the nlaximum static shear force. \vas equal to J 000 t,
corresponding to a shear stress of 4.8 MPa.
To ensure the strength of the joint components of the temporary support and
the pier, it \vas necessary to placc, inside and outside the box girder, temporary
12 T 13 prestressing cables. Their inclined path created a vertical component,
!
:J
0
C
oU
-a
"-r;
or
-;t
>::
~ 1~
_J
I#=: .,~
u
1:1=
c8~
.81
... ;
'0:3
~
C'I
....
i
~~
~
..
~~ ..o
2
..,
..,.
v~
~.
184
185
'///.
Lonqitudinol seetion
'11
,/
'/
",.:;'
, ,0
,.lf~~it-JOint
Fig.3.S5
...
support-detaiJs
j ~.
-~.
:':::~""";
all
;.
reducing the shear force (fig. 3.SS). There were two temporary cables per support.
The interior cables were looped, into the lower slab of the box beam and the
exterior ones into the main column. The exterior cables were guided by two pre
fabricated saddles held against the beam by prestressing. These saddles controlled
the deflection of the cable profile. All the cables were anchored on a steel joist
resting on the upper flange of the box beam. In figure 3.54 the two guide saddles
can be seen illustrating the above description. It is cleart from this example, that
the use of a single temporary support t even though it is more economical, can
create complex situations when the temporary support is positioned a short
distance from the pier. Similar temporary supports were used during the construc
tion of the Joinville bridge over the River Seine (fig. 3.57).
5.4
Fig. 3.56
This structure comprises a continuous three-span deck, rlXed on two sloping piers
articulated at their foot. The distance between the hinges was 186 m (fig. J.S 8). To
avoid the use of an expensive and complicated centring system t the bridge was
built by cantilever construction, inside mobile concreting carriages, from the tops
of the sloping piers. During the cantilever construction, the sta bili ty of the
balanced cantilevers was ensured by temporary tower supports, placed in the river
186
i
28260,
~679~
'46.70
29.50 4 '
29.5721
'Q
. ~~
:Y~2.568 ~
17.70-
+0.66)
,..
29.291,
.... ;,...
. :+2.~..-
67.9~---r
.~ '~?&66'
~8~
,..:
./
#:0.:
.. ~r_2~__ ",
;-------- N:'9.10---- _.... ;
./
--~ -~--~---l
I
I
'"''
187
I~
d!?764
t-"~---~
~:;, ~E:~~~~-
G;a~-;-'~-"W'"
Fig.3.58
near the banks. The tower supports also supported the formwork for the sloping
piers. These piers transmit vertical loads approximately equal to 4000 t down to
foundation rock. They are founded on driven steel piles. The system formed by
the temporary tower support and the slopinl pier was a riptanaled trianpe, in
which each el~mont had its own specific role (fiss. 3.59 and 3.60).
(a) The 'lertical side of the right angle \vas constituted by the temporary to\ver
~~~
'., . . ~
.....
_I'~_I
';
Fig. 3.59
I'
1.....,
4.00
Gronite
~J
4.10
support consisting of fOUl 900 mm ., tubes. The tubes were infilled with con
crete, crO$l-braccd and assembled in two gem-high sections bolted together,
The tubes were linked at tho top by reinforced' concrete which formed a
support cap on which the deck rested via a pseudo-hinged joint under the
whole widtla of the box airder. This pseudo-hinge was to eliminate the
transmission of flexural forces to the tower during the deck construction. It
was made of six, 6O()..mm ftatjacks, that would cvcntuaUy be used to adjust
the level of the QantiJcvcr beams, to compensate for the settlement and elastic
shortening of tho temporarY tower support during loading.
The Oat jacks were associated with sand boxes that would allow, alter the
connection of the cantilever beams, the removal of the centring of the "arch
and the temporary tower supports (tia. 3,,61).
(b) The horizontal side of the right angle triangle comprised a decking placed at
high tide level and supported by PH 360 beams anchored at both ends, in the
sloping pier rootin& and in the pile cap. This cross..bracina stopped any
longitudinal movement of the top ofthe pier during construction.
(c) The falsework, upon which rested the rormwork for the sloping pier, was
placed along the hypotenuse of the right angled triangle. This falsework was
composed of HEB SOO beams anchored in the pier footing and in the tower
support cap" Itcrcated a rigid link between these two clements.
188
189
-::-=======
i
i
'WllI
.
. la,l JOCks
F
o
N
.n
.600
...
,
t
::.~.~~?
.
I
".
'-----.
-.A _
'
J
(a )
(b)
(d )
(e )
---.---_""Y_.. . . . . . . --.--..--
I'
Temporory support
The temporary tower support and the falsework thus formed a triangulated
system of permanent shape. stopping all movement of the temporary tower
support in the longitudinal direction of the bridge. The construction stages for the
sloping pier and commencement of the deck are shown in fig. 3.62. The deck was
then constructed by the cantilever method (fig. 3.63).
,,
,
,
r. ..
r___ --1
II
Fig. 3.63
_Tempotory
support cop
Fig. 3.61
Temporary suppO';t
't
_'r~_
.too
deck
191
CANTILEVER CONSTRUCTION BY IN
The longitudinal beam" caIlcd main beams. are usually placed above the webs of
the seamcnt to be concreted. 1bc external forms, the base of the mould, working
deck ~d aanawIYI aro IUapclldcd from the main beams. The internal forms are
carried by I trlvelling carriqo, moviaa inside the deck.
During ~ncretin .. the ltabiJity of'the carriagcsis ensured by kentJedge on the
main beams. or by anchorlP to the lCCood last seament. When they are moving,
the weight of the carrilaCl is balanced by I rear counterweipt (ball1st or wlter
It is made of formwork hanging from a steel frame, carried by the portion of the
deck already built. The mobile carriage actually consists of the two sets of
form work necessary for the construction of a pair of segments.
Fig. 4.1
Steel beam
~TIQ"I~n9
~Jse_k
Lateral fOl'mwork
Internal fOl'mwOrk
itt 1Q-.,
192
~~-:-.~
"'~.-..-=-'"
"
--~~,
"," .
193
bags). The main beams, during concreting, often sustain significant deformations
which could lead -to transverse cracks in the joints between the segments. These
cracks appear on the upper side of the lower flange because of deformations of the
carriages due to the weight of the concrete in the webs and upper flange.
This problem can be avoided if one uses sufficiently rigid mobile carriages. But
these carriages can be very heavy, and their dead weight leads to an increase in
prestressing in the cantilever beams and}he stabilizing system. For example, the
Oisse! bridge carriage, weighing 110 t can be counted as a heavy carriage
..
.J
(fig. 4.3).
~.
Fig. 4.3
Fig.4.4
Fig. 4.5
194
2.1.2
>
The main beams, when placed above the deck, obstruct the upper part of the
segment under construction, and thus hinder the construction process. For this
reason, some mobile carriages include main beams placed laterally alona the webs
external to the segments. This solution liberates the working area of the deck and
allows easier access when placing formwork or reinforcement, when concret
ing. It is then possible, when casting segments in Sllll, to apply procedures nor.
mally specific to precasting: such as the prcassembly of reinforcement and pre..
stressing cable ducts. This results in a speeding up of construction.
Mobile carriages with lateral main beams were used during the construction of
or
the Avignon bridge on the Rhone and the Moulins-les-Metz bridge (fi&. 4.6).
195
traditional carriagos;
conaestion afthe workinS swface.
This type of carriage was, at fir used for decks with a constant depth, as the
Kennedy Bridge in Dijon and Ute Canadicns Interchange in Paris (fig. 4.8).
Durinalhe concrctin. Phase, the cirriaici are linked by prestressing to the part
of the deck already built. Their positioning is determined by adjusring pins placed
at the rear of the carriages and slonina into holes made in the concrete of adjacent
aCanlcnls. TIu: movins of the carriages to their concreting position is made via a
mobile handling vehicle; moving along overhanging joists placed above the line of
the webs..
Puring cuntttruc;tiun ur the Clichy. Orlcnns
the self
supporting carriages were transformed; they were adapted to decks with ,ar;Clble
~:-
1- Concreting phose
~6Ch~;ij~~
Adlustjnl~ pins
l2\Olf
~ ~~Ii;~~~e
I
196
197
of and behind the carriage and braced together (fig. 4.10). The system fonns a
rigid trough linked by prestressing to the deck. The depth variation of the section
is obtained by vertical movement of the bottom of the mould \vhich is fixed, on
one side to the front joist and on the other side to the lower slab of the last con
creted segment. The internal formwork of the inside webs of the deck transverse
section is made of independent elements, resting on the front joist and suspended
at the rear from the previous segment.
During concreting of the Gennevilliers bridge, the stability of the self
supporting mobile carriage was er1sured by (fig. 4.11):
-
Fig. 4.8
hVo upper steel pins, linked to the outside shutter; they \vere slotted in holes
made in the upper chamfers of the external webs-Dywidag ~ 36 mm pre
stressing bars crossing each web made the connection;
hvo lo\ver steel pins) linked the base of the mould to the segment lo\\'er
fiange-Dywidng prestressing bars were also used for the connection.
The self \,eight P of the mobile carriage and of the segment concrete created an
overturning moment, balanced by two horizontal forces equal to F: a tension
applied to the upper pins and a compression on the )o\ver pins. The shear force
Mobile carrioge
Anchoroge
Rear
Front
~, ,j
I
.
"Ar~
IIi: :mf~
3if.1
Self.supporti~
external forms
Fig.4.10
198
199
Prestressinq bars
S~iel plns/
!
Pre$tr.ss;n~
Fig.4.11
bars
bridge
..::
,n.u.
IF-
Pre",."ing bot,
.36
12 T 15 beam cable
LocQtic:'\ of pin
Fig.4.12
j
was almost entirely applied to the upper pins. Because of the large forces applied
to the upper pins, they were anchored in precast concrete blocks. This avoided
large stresses in fresh concrete (fig. 4.12). The stress in the pins was transmitted to
the precast blocks by friction; this way, the magnitude of the required prestresling
force could be evaluated.
2.3
2.3.1
\_
Supporr sectiolls
Above each pier, a portion of the deck, called the support section, is concreted on
falsework. It can be used as the starting platform for the mobile carriages. When
the piers are tall, or in water, the falsework is often replaced by steel or concrete
corbels fIXed by prestressing on the top of the pier (fig. 4.13). The length of the
support sections is determined by the size of the mobile carriages and by their
Fig. 4.1 J
_..--~-~~~-~
200
(a) the two forms are placed side by side and move simultaneously; this is the
most common method for which the length of the support section is usually 7
to 10m;
(b) the same solution as (a), but the two forms are provisionally connected during
the construction of the fast standard segments-This reduces the deck space
requited by the forms;
(c) the second form is placed only after the construction of the first segment and
movement of the ftrst form;
(d) the support section is asymmetrical.
It takes a long time to build the support sections: usually severa/weeks. It is usual
not to include the support sections in the cantilever beam construction cycle. They
are usually built in advance.
ConnectiOn of truss.s
--+
.......
-If-
II
This cycle corresponds, in the case of 3-m long segments, to a travel speed of
(2 x 3)/6 = 1 m per day per mobile carriage (one pair of shutters). This is a rather
slow rate of progress and various techniques have been used to accelerate it:
(b)
(0)
.L:1SlZISJI
--l .
C1
(d)
Fig. 4.1~
I
Ic)
201
~.,
--@
202
constTucnon of lhe cross section in two slages. In the first stage, the lower
flange and the webs (with a part of the Qpper flange to form a table and to
permit the positioning of the cables) are concreted by means of the mobile
carriage. A U- or W-shaped beam is thus constituted (fig. 4.16), After
tensioning of the cables and travelling of the carriage, the upper slab is con..
creted over a simple travelling formwork.
The second stage is usually carried out wit~ a delay of two or three sea"
ments after the first stage. This technique has the advantage of decreasing
the volume of concrete to be placed by the mobile carriage, and conse
quently of decreasing the weight of these carriages. Furthermore, the cons
truction of the second stage is independent of the first and thus is removed
from the critical path.
The decks of the Saint..Isidore and Magnan viaducts and the AS Nice
ring road ,vere concreted in this way; the Saint-Isidore viaduct had 40-m
spans. Concreting of the second stage was carried out after the connection
of the candJever beams, by means of rormwork travelling on the lower
flange from one abutment to the next. For the Magnan viaduct. to take
n,,~uunt ~)r the si~nifiennt spnns. the secund Nlngc fuUu\Vcd the IinH \~'ith ..
three segments delay. The same happened at the Cliehy, JoinviJlc and
Puteaux bridges. Their deck cross-section had three and two webs
respecti\'ely (fig. 4. 18).
These methods lead to a notable reduction of the cycle, allowing the construc
tion, per week and per carriage, of either two pairs of standard segments, or a pair
9f double length segments. The speed of travel reaches approximately 2 m a day.
The major obstacles to any further improvement of the travel speed arc the
203
MOBILE CARRIAGE
.1s' sl.
~I'tc"ono~
movemen'
:,\!.-;
').64
"
'r-e mould
of 'he mould
1"'''01 10'1101 'orm
..... !!~
Front MYOtion
9.10
7.tO
~C)"
:.
~'GGI'.
F"on t
ho,.,
t:P\;,
t
....i
J!: S
lU'lI,UI
"cu".
RIot onC"Ot9'
ROll O"~"'~'o9'
,,,,,at """Jer .
Riot
U,,5"""'f.IC$
hontIf
lOWlr .itrod
Bo'tom of
'--_ ...
FiJ. 4.11
.h. mould
t~
..
"
204
205
by bonded \vires (fig. 4.19). The deck was built by the cantilever method. with 3m
long segments built in t\VO stages.. During the first stage, the precast \\'ebs.
maximum ,,'eight 16 t, \vere placed 'on cradles inside the mobile carriages. These
carriages followed the longitudinal prortle of the bridge, the predicted deforma
tions being taken into account (fig. 4.20).
During the second stage, the webs were, rigidly connected with the adjacent seg
ments by means of a dowel joint and temporary prestressing bars (fig. 4.21). The
other parts or the cross-section were then concreted inside mobile carriages, which
were suspended from the webs. This method, using the partial prefabrication of
19.20
t-I
so O
6.50
mm
1.60. 1.60.
i
Carriageway
6.50
1.50
Carriageway
2%
..-
To avoid heat losses, the forms are generally insulated and a space heater
(radiator or infrared heater) is often placed inside the segment.
In the second case, the concrete is heated in its mould inside an enclosure
(steal1t chamber) where steam circulates at low pressure. In this way, within two
or three days, even in winter, it is possible to attain the compressive strength
required for prestressing (about 25 MPa). However, if it is desired to start pre..
stressing earlier, for example after 24 hours, it is advisable to act locally, at
anchorage level. One can then use embedded electric heating, as in the Candes
bridge. over the river Vienne. One can also use precast end blocks as in the Issy..
les-Moulineaux. Clichy and Gennevilliers, bridges. Durina construction of the
Gennevilliers bridge, despite the large dimensions
the deck, it was possible to
concrete two segments per week, thanks to early prestressml.
The h'tbs can also be precast. This method was fli'st tried during the construc
tion of the access viaduct and of the main structure of the BrotoMe bridge. The
webs, which \vere thin and sloping. were precast in pairs on a bed and prestressed
! ./"
I,
~.
,/
,."
..
,i
5.60
Tendon strc~:S
Adjustable brackeTs
,",'
",
18
4.00
Tensiontn9 Jocks
.d-l
.,<>,
,",,~
.1
20'
.~ /
/>
20
5.60
4.00
Connec.tlon bef'lle-en
Presfress.:-<; le"'ldoi"ls
tendons
ct> 36
,
.n" .~
~ .Jr,:-:.:11:
~r
"t2
.. : . ] ~::::'i""'" .. -.-<--~ -1. 1 11"
b
~
1m .. ~~----\.
~
."'\04 _
OywidQq cr.:"oroq8
Fig.4.19
11
_ .
'~z==i. C-
brackets
.
i
Mob,'e carrloge
Fig. 4'.20
or
I .
AdluSlo~le
Oywldoq onCl'\0t'0ge
Bast of mould
32 O,wida9 bars
OfSfrtbu',on
beams
206
Prefabricated web
~I--,,~
1-.-1
d!\
. f
207
the seaments to use liahter elements, simplified the mobile concreting carriages
and reduced their wcisht (3S 0. The length of the construction cycle was reduced:
even for the cable-stayed bridge it was possible to concrete four segments per
week per mobile carriage, Le.' 12 m ofdcck per week (fig. 4.22). The positioning of
the prcc:ast weill was c,:a,rried out, on the banks, by a tower crane travelling
parallel to the bridge. and over the Seine by a self-propelled gantry.
A crossin. of tho Seine by the Metro line was another example of the use of
precast web This structure had a maximum span of as m. The deck is a three
web box beam without .ide clPtilevm. The upper flan&e, which carries the trains,
wa. lowered In order to decrease, U much as poSliblc, the slope of the bridge
ramps. Bcc:ause of the relative weight of the superstructure, the length of the seg
ments waa limited to 2.S m and the seaments were built in two stllges (lig. 4.23).
'.':'~~riI
Fig.4.23
108
The precast webs, with glued joints. were first placed by a gantry travelJing on the'
existing webs, and then were integrated by prestressing to the adjacent segments.
The upper and lower flanges were then concreted. two segments at a time.
209
2.4
(a) the prestressing bars connecting 'the upper pins and the prefabricated ele.
ments were doubled up. Had o(1e bar failed, the' mobile carriage would notl
have fallen;
(b) the link between the prefabricated elements and segments was ensured by:
Safety 1
Had the tendon failed, the precast element would have remained connected to
the segment;
(c) the joint between segments. at the rear or the mobile carnage, was traversed
by reinforcement designed to ensure the joint strength, in the case of failure of
the cantilever beam tendons, which were holding the precast element and the
segment carrying it.
Prestressing
bars doubled
---
Safety I
Safety 2
Safety 2
Nominel reinforcement
Precast .Iemen,s
Safety 3
Precast elements
Prestressing bars
Prestress ing
tendons
Prestressino bar.
3.1
Safety 3
Lonoitudinol reinforcement
c
Fig.4.24
In the rdatively rare case ofa low deck crossing horizontal and accessible ground,
one can build the deck by resting the forms on falsework travelling on the ground.
This construction technique has been used for bridges crossing canals in
hydroelectric schemes, before filling of the can~ls. The segments can be 6 to 8 m
long, as was the case in the Channas and Bourg-Ies-Valence bridges (fig. 4.25).
The falsework can also rest, not on the ground, but in 8 river on a jetty structure
founded on piles. The contractors Polensky and Zollner have used this method for
the construction of several structures.
3.2 Construction with Cormwork luspended from a lona gantry beam
In the case of a viaduct with many equal spans. it can be economical to use a steel
gantry resting on the top bf the piers of the bridge. This gantry would be capable
210
211
of $Upportina the weight oI'the segment during concreting. The formwork is hung
from the steel lantry and moved after construction of each segment.
The Jcnath of the segments can reach 10m, which leads to an average progress
of (2 x 10)/6 - 3.3 m per day, as durina the Siegtalbriicke construction
(fig. 4.26).
CHAPTER FIVE
We have seen in the previous chapter that In situ concreting or deck sections
generally limits the rate of construction to about J mptr day per shutter (2 m per
day per mobile carriage). 'Vith that in mind, it certainly seems advantageous to
use precastlng, \vhich usuall)' allows the construction of one section per
Fig. 5.1
Stockpiling or segments
or
212
213
214
usually coated with a polymer glue, with an epoxy-resin base, hardening quickly
and not sensitive to temperature or moisture. The use of such joints is possible
only if the adjoining faces are perfectly matched. To fulfil this condition, the seg
ments are made one after the other, in the same sequence as in the structure-by
casting each segment against the segment previously made. The front face of each
clement is then used as shutter for the rear face of the next. Joints made in this
way arc called match-cast joints.
The epoxy resins are thermosetting materials with high strength characteristics.
They adhere easily to the concrete, as long as the faces to be glued are clean and
dry; they polymerize at a temperature higher than SoC. At 18C, they harden in
less than 24 h.
2.1
2.1.J
In structures built in recent ye'ars, epoxy glue has played a fourfold role:
215
Elevation AA ~
(v)
It.)
<D Glued joint
ollehorCl\l'
.
k1\:4'r
S,etion 88
T
f;@
I
I
II
I
216
217
of the temporary prestressing forces F. and F2 are chosen such that the normal
force N is close to the centroid of the section; this allows an almost uniform
distribution of normal stresses over the depth of the joint, thus entailing a uniform
glue thickness.
J
2.1 J
(J )
of the segment at the joint which had just been glued. These forces, combined with
the weight P of the segment, create a resulting force R acting at an angle to the
joint. Because of the low friction coefficient of the glue, the sliding force in the
joint produced by P, can be balanced only by the vertical component of the
sloping reaction C applied perpendicularly to the lower face or the web key
(fig. S.5). The resultant R can then be divided into a reaction C carried by the key
and a horizontal reaction N contributing to the closing of the joint. The distribu
tion of lIorn,al stresses in the joint area is different from the one reached by usual
calculations. In particular, N is smaller than the sum E of the temporary prestress
ing forces. If a is the angle with the horizontal of the supporting face of the keys,
(F - N) is equal to P tan a and in the usual case where Ian a equal to P12.
For a 50-t segment. temporarily attached to the preceding segments by a pre
stressing force of 100 t, at the level of the upper flange, the normal force is
decreased b)- 25 t. i.e. a quarter of the applied prestressina force. U' the segments
are placed rapidly enough in the structure, so that fOUf 5elmentl are placed berore
the setting of the glue in the first joint, the normal force in this joint will decrease
by lOOt; this roughly represents the elimination of one 12 T 13 prestreslinl cable.
The same apPlies in the case where, ir temporary usembly devices are not used,
the segment is secured by permanent prestressing cables.
Consequently, it is advisable, durin. checks or strenllh of cantilevers during
construction, to take into account the reduction or the effective prestressing force,
otherwise some joints may open up. It is recommended that the position and value
tt
,.1
F2
-.-otL
Regarding the cable layout for permanent prestressing, one knows that the beam
strength is provided by a rarst system of tendons, inclined or not, with anchorages
usually positioned at the face of the' segment; prestressing operations are then
integrated in the construction cycle, as a new pair of segments cannot be placed
until the tendons or the previous pair hav.e been stressed (fig. S.6).
The attachment cables of the variou~ beams-forming the second family-are
anchored either in the lower nange, in bosses, or in the chamfers joining web and
top nange. after having been positioned at these points. Under working loads, the
sllear forces in the joints vary greatly according to the characteristics of the
structure. In structures with variable depth, with inclined prestressing tendons in
the webs, the shear stresses in the joint are small; they a~~aJIYJ)~gU~der
permanent loads, and their values usually ~e between 1 and 2.5 MPa, (N/mm 2)
undef imfSOiJlciads. However, in a deck of constant depth, with long spans, and
with horizontal prestressing cables, shear stresses, under imposed load, can reach
4 MPa (N/mm2 ) in the joints; this happened in the Connans bridge over the Seine
and in the approach spans of the Rio NiteroI bridge in Brazil, where each web had
three keys. Both the selection and correct use of the glue are critical for shear
resistance; a close control 0/ glued joints is required. Generally, available glues
have a final strength higher than is 'required, on condition that polymerization is
sufficiently complete. This entails:
-
(5)
Detail A
---
(J)
Fig. 5.5
Fig. 5.6
218
Concerning this last point, the trealment of lhe laces to be glued is most
important. Comparative tests have shown that sandblasting of the surface gives
the best results; the faces must be kept dry and clean at the time of placing. free of
any oil or grease. In case of rain, the joints must be burnt with alcohol to dry off
any superficial humidity. However, the presence of water in the concrete does not
affect the properties of the glue.
1t has also been found that the rapid placing of successive segments haa had a
fa vourable effect on glue be~aviour. If during setting, additional compressive
stress is applied, by placing the subsequent segments, the ultimate strength of the
resin is increased substantially. One can also note that, in structures with variable
depth, the plane of the joint is not perpendicular to the forces, especially at the
level of the lower flange. In this case, the glued joint is submitted to local shear
forces. which can be very high; in the case of nonpolymerization of the glue, the
shear forces can lead to a crack in the lower slab, as this is subjected, ncar the
joint, to vertical forces, which on one side act upwards and on the other side
downwards (fig,S ,6).
Further to the usual care given to ensure the normal polymeri~ntion of the glue,
such problems can be avoided by placing additional keys in the lower. slab, or by
lining the shutter to obtain a face perpendicular to the forcCt
2.2
2.2.1
Segnlents
...
2~
219
Elevotion AA
2--S!!
t)
;::>
A
Section B8
( 4 )Anchorov, bos.e,
( 5 ) Hole, fOt liftinv equipmtn.
( 6 ) HOj" 10t ttmPOfOlroncl)qrQ9"
( 7 ) Ducts for p'..tr."i~ tendons
220
come down
to t\VO
basic methods:
(a) concreting on a precasting bed (or slip form) of the whole length-of a balanced
cantilever system: pier segment and segments of the two adjoining
cantilevers;
(b) concreting of all the deck segments in one or several raxed moulds, called
precasting cells.
In the first case, the form work moves, but it is flXed in the second case.
3.1
On a precasting bed which reproduces on the ground the exact shape of the deck
initial compensating hog being taken into account, the segments are cast
one next to the other, preferably in the order that will be used during assembling in
the structure. The Internal and external shutters, usually made in steel and
mechanized. are moved from one casting position to the next, ensuring the COn
tinuity of the outside edges and of the geometrical form. If the bed represents the
\vhole length of a balanced two-beam system, the pier segment is at the middle of
the bed. and construction moves towards the outside in a symmetrical way on
each side (fig. 5.9). This method guarantees the integrity at the soffit line;
however, it requires some fixed installations, which take up more and more rOom
as spans increase; it does not permit, without intermediary adjustments, the
achievement of profiles varying from one beam to the nexl Furthermore, the (orms
somt~
..-Ji.,Ll I
I I I I
I I IIIlJ II I
I I I I I
JOi.
must be specially designed so that they can move over the whole length of the pre
casting bed.
The precasting bed method was first used for the bridges of Choisy..le..Roi
(fig. 5.10) and Courbevoie (decks with constant depth, with webs respectively
vertical and sloping). The technique was' then extended to the case of decks with
variable depth for the Oleron viaduct; part of the structure was curved in plan.
Some arrangements were made to temove the pier segment from the bed by
lowering the bottom of the mould between adjacent segments, before completion
of the whole of the balanced two-beam system; the space was then freed to start
the next segment. In fact, four forms were working simultaneously over the whole
length of the bed for the fabrication of two or even three consecutive balanced
beam systems (see sketch in fig. 5.9).
Other structures ~ere built in France in this way: in particular, the bridge over
the Ardour River in Bayonne, the Tours bridge over the Loire and, more recently,
the Calix bridge in Caen.
In cases where there is not enough space, or if the size of the structure justifies
only a small installation, the precasting bed can represent only the length
...-l.I .
I I - , ~kk::. I 1 I I
build the symmetrical part of the rarst cantilever, the pier segment is turned around
so that the first segment or the second cantilever is match-cast against it.
The typical cross section of a mobile form is' shown in figure S.1 I. It can be
seen that the external forms move on rails; the jacks for striking the formwork and
the telescopic internal shutters also move on rails. The segments are removed and
carried to the stockpiling area by a mobile gantry astride the precasting bed or by
a crane travelling either on the ground (as in the Calix ~iaduct) or floating (as in
14-,.
I T ~ 1111-I4
Flnl,hed st9"'ent,
or half
of a balanced ltl'o-canri/ever system, the pier segment being built at one end. To
-f.'.!IIIIII.IIIIIII~
-1.\1
221
~,.
222
Choisy-le-Roi and Courbevoie. where the precasting bed was on the bank of the
Seine).
Coner.dng in precasting ceDs
In the second method, the segments are precast inside c,lIulQr /0111JS at a fixed
pi ace. It is then necessary t as shown in figure oS .12, to transport each hardened
segment to a position where it can play the role of form for the next SClment.
Up Lo now. horizontal preoutin. cells have been the most commonly used. These
cells arc usually made of onc rUled part and two mobile parts. The fixed part com
prises the lateral outside shutter, the soffit shutter-which is adjustable-and one
of the end shutters. The fltat mobile part, called the core, carries the shutter for the
inside void. The second mobile part, called the counlermould, is formed by the
selmont previouiJy concret'ed, which when placed against the fixed pan becomes
the shutter for this end oCtile sesment, and makes match-cast joints (fig. 5.13).
Each "Imene nrst occupies its cutina place, then moves to an adjacent position.
where it is used as a match-cast counter mould for the next segment, before being
carried to stockpiJe~,: The mo.ment of the segment from one place to the next is
most important for the accuracy of the seomctric shape qfthe deck; the bottom of
the mould on which each "Imcnt is built is provided witli friction rollers or sliding
skates moving on guide raits. As each 5Cgment stays on ~ts own mould bottom. till
stockpiling, this requires at least three mould bottoms for catch casting cell.
The. eXlernai ,hullen are usually hinged to allow striking of the segment
formwork. A jlxed{ace ,hutter forms the shutter for the end face of the sesment
opposite the countcrmould. The Internal shutters are hinged and adjustable; some
removable panel. ean bo placed in the lower part, to anow for variations in
scamcnt hciaht. Tho internal shutters arc moved through the fixcdfacc shutter on
an auxiliary carrialcmovinllo~&itudinaUy. The casting po~ition of a segment can
Form design and utilization are easier than in the first method, but the successive
movement of the segments creates some adjustment problems. The cellular forms
belong to t\VO families: horizontal precasting cells, where the segments are placed
next to each other, and vertical precasting cells, where the segments are placed on
top of each other.
To 510ekpile
[J
I
223
3.2
I
Pi&- 5.13
224
then be cleared in this way for placing the bottom of the mould, the prefabricated
reinforcement cage and prestressing ducts.
The main cycle of operations during precasting of a segment in a cell is as
follows:
225
The first horizontally precast segment was used in the construction of the Pierre
Benite bridges on the Rhone, whose decks were a constant height. This method of
precasting a cell has since been extended to structures with variable height
(bridges on the Boulevard Peripherique in Paris (fig. 5.14), Aramon and
Bourg-Saint-Andeol bridges, Saint-Andre-de-Cubzac bridge and others). But it
can also be easily applied to the construction of,more complex geolnetrical/orllls,
such as are met in cun'ed bridges and in bridges with a variable crossfall. The
Chillon viaducts were amongst the first characteristic examples: in plan, they have
an S shape \vith a curvature radius of 700 m and a constantly varying cross-fall.
Cross-foil adjustment
e-
"ttY
Alignment adjustment
The precasting cellular forms had superimposed trays carrying the bottom of the
mould t which would be independently adjusted for the three components of the
There are to date only a few examples of segment precasting in a cell with a
l'ertictllcLt;S. In France, lhe Saint-Denis curved viaduct (fig. 5. J6) and the Noir
moutier bridge were built in this way t but in both cases, the segments had
concreted joints, in which case the match-casting and adjustment problems did
not exist. However, more recently the segments forming the cantilevers of the roof
226
Canlil~er
227
P~tdge$)
I
-,
L ~ d'1i 25 N""'bt'o'DtICf9"IO~.bu.ft
RemoYobitcore
~---.1.'
1---'" ';
~
.''-'
~t
LV "
Upper shuttet
0"'1""
NumOtf 01 ..
A.,__,""l'o'_
PrOduct"", " .....".. '
,.,
2100
60 kin
2~,o30b<ICl9t..
)'ICl'
10m
of Parc-des-Princes and the decks of the Vienne bridges over the Rhone were cast
in vertical ceUs, with malch-east joints.
Recently, several thousands of segments for the upper carriageways of the
Rhone-Alpes motorways were fabricated in this way (fig. 5.17). In this variant,
the segments are cast on their side, the countermould segment and tho cast
segment being on top of each other, no longer side by side.
This type of cellular form has the advantage of greatly facilitating concreting:
the prestressing ducts do not interfere with the flow of the concrete and conse
quently are themselves well surrounded with concrete. Furthermore, concreting is
done \\'ithout construction joints in planes perpendicular to the neutral axis of the
deck. On the other hand, a disadvantage of this method is that tilti"g of the seg
ments, before placing in the structure, requires a handling frame more com
plicated than a simple truck (fig. 5.18).
Pia- $.18
Tiltinl of a segment
._.~-",.~",.,:;j,
228
14.60
54
3.45
_t_~-'V'....
6.62
54
3.45
0.26
I.
04
Cell
Jilint
0.26100.34
0.84 to 0.10
Joint
7.~o
Fig. 5.19
.I
.,.
Cella
to
c;j
Cell C lreorn2/
i Teeml,
I
.
! t'
Cell AI
aI
Tlom2
14ft
. Cu,in ft 19n
I
I
f--r-~-----'
~eom': I
.
m2,
I' tjTeol
I.
I
14
23
~.9"'~1~.
.
I
.
:
I
Cell A ~1~;'iITeotn2 __ ~l't..~
':
~4.~hIl4 .. n~41/2nl
Cell B i
.
rr......,
.._..!Teom2
.......-.., wI
.
.
,
~_
CeIlC~
.
I
iT.
Cell 0 .
Teorn3
,'~
Shill 1
'
'!~L
,
~
I
.
I
Shill 2
This type of cell was employed in Russia for the construction of several
structures, including the Chelepikhinsky bridge in Moscow (fig. 5.19).
J.3
13
'6n~
o
o
Ce" 0
14
"~T
1018
vv...
18
229
The usual precasting cycle, on a bed or in fIXed cells, corresponds to the construc
tion of one segment per day per shutter, i.e. about 3 m of deck per day, the seg
ments being cured overnight for 14 hours. This cycle was eastly reached, even for
the first structures, both for the ChoisyleRoi and the Pierre-Bernte bridges.
The precasting cycle was then shortened, first by improving the conditions of
segment construction: reinforcement and cabling, and then by mechanising the
shutlers. These improvements led, at the Connans bridge on the Seine, to an
output cycle of four segments a day with two pairs of shutten and two teams of
labourers: each team was fabricating its second segment while the first segment
WQS curing. The construction time of I segment WII then broulht down to about
live hours and the curing period for the segment could then reach nineteen hours.
If the weather is cold, the concrete is slightly heated to 30135C (preheating of
the concrete) and the shutters are heat insulated. Concrete can then be pumped
from the mixer to the prefabrication mould; this method proved very satisfactory
.,
The cantilever construcllon o[prestressed concr.:le bridges
230
231
removed at the ninth hour. This result can be achieved only if an adequate
is applied to the concrete.
I henna/ treatment
3.4
In the case of segment precasting, concrete thermal treatment must achieve two
seemingly contradictory effects:
accelerated hardening to allow rapid form striking;
a final compressive strength as close as possible to the S\I'cngth of the con
crete cubes.
SeveraJ treatment methods can be used:
-
traditional steamina;
direct heating of the forms by electric heating elements;
direct heating of the forms by low pressure steam.
The use of a traditional steam enclosure has several drawbacks. First, it is difficult
to keep a uniform temperature inside the steam enclosure. Secondly). the parts
with different thicknesses in one segment are heated at the same temperature.
\vhich is damaging. Also, the treated unit can get a thermal shock, creating
thermal cracks, when the difference in temperature between the ambient
atmosphere and the steam enclosure reaches JOoC. Steaming can, however, be
acceptable for long-curing cycles, i.e. lasting 10to 14 hours.
Heating the forms by electric healing elemenl! is suitable for IOlZgcuring
cycles. This system allows a great flexibility for regulation from one area to the
next, and is very $imply adjusted by means of cyclic measurements. It is then
possible to give uniformity to the thermal tre~tment oftbick and thin parts of the
segment; this limits the thermal gradients, th\lS preventing damage from adverse
condhions in the concrete at the start of its solid state.
Heating the shutters by low-pressure sleam is preferable in the case of short
curing cycles lasting less than five hours: it introduces a lot of heat in a short time,
thus increasing the internal temperature of concrete by 10 to 15C per hour. But
this system requires complex regulation w~ch must ensure an equal temperature
at any time during the treatment in all the shutters, whatever their thermal con
ductivity, and the external conditions, (fig. 5.21). These different systems of treat
ment: steam enclosure, electric heating elements a~d low-pressure steam, have
been successfully applied to bridges with precast segments. The segment$ in
Choisy-le..Roi and Courbevoie bridges \\'ere placed in steam enclosures. For the
construction of the upstream and downstream bridges of the Boulevard Peri
pherique and for the Blois bridge, electric heating was chosen. Self-steaming
,shutters with low-pressure steam were used at the Pierre-Benite bridges, at the
:' Oleron viaduct and on the B3 motorway structures. Whether the shuttcrs arc
Faa, 5.21
chose a ",nenl whose performances can cope with rapid heating of con.
crete (preferably with ClA <; 1196 and C)S/CzS ~ 3);
produce concr,te with regular characteristics, minimal water content and a
temperature of 35C at placing time;
use lormwork stV! enough to resist the expansion of concrete durinl its
plastic stale when it is heated.
.
"."tl.
a
period or two to three; hours when concrete is kept at the sur
roun_ tompcraturc;
a slow ',mpertll",., Increase of less than 20 0 C per hour;
a level of treatment with constant temperature, less than 80 C, lasting suf
ficient time to achieve designed strength;
a cooll", down period made at a rate similar to the temperature increase.
..
...._
232
8e
SC
100
Short cycle
65C
6501
80
Preheating cose
60
____
I
35~
.400,
eoac
CJ\'t
t-re:~
It
'h
18.lQr
~I
--.A
"t'
T
Presettino Temperature
increase
--~--~-
Level of
treatment
'N
J
CoofincJ down
Long cycle
35
.~
I
J
'2h30~
4h
~
*.
I.
5h
19h
Healing lOh
'h
:~.
~l~
~ :~
!~
We also show on the same figure an example of a long cycle: at the Connans
bridge, corresponding to a treatment duration or 19 hours.
SOC
60
233
This first method is the most simple and the most economical. whenever it can be
used. It was used for the Choisy-Ie-Roi, Courbevoie, Juvisy and Connans bridges
on the Seine. where a navigable waterway enabled a floating crane to bring the
segments from the precasting yard and place them in the structure (fig. 5.26). A
234
235
Placing equipment,
,Pontoon
-------~
(Ex:
Lounchin9 gird...
Fig. 5.24
..
Fig. S.2S
,/
machine travelling on the ground was used for the Gardon, Bourg-Saint-Andeol
and Bonpas bridges; whereas the same crane travelling either on the ground or on
water was used for placing all the seamcnts of the Upst~eam and Downstream
bridges of the Boulevard PCripberique in Paris. On convenient sites, it is possible
to use the same mobil' ,anlry cran, for the precastina yard and for transponing
seamonti to their place in the bridle (Hartel bridle in Holland), This principle was
extended for the construction or the bridges over the Loire, in Tours (Motorway
bridgo and Mirabeau bridge). For these structures, the segments were placed by a
mobile gantry, straddling the deck and moving on two longitudinal tracks made
from Bailey bridges. These tracks, of a total length double that of a standard span,
are moved forward as construction progresses; they are supported by piles driven
in the river bed. The segments are brought along the deck, then taken by the
mobile lantry (figs. 5.21 and 5.28).
In the case of placing by a crane, one often meets problems when placing key
segmenu in t~e central part of the deck, as the part of -the deck already built
restricts the movements of the machine and does not allow front placing. To solve
this problem, for the B3 motorway viaducts, a 'keying bridge' was used (fig. 5.29).
This system, which weighed SO t, was made of two longitudinal sleel beams cross
236
237
:'''';'.,;~
Cron section
~.
"
Bog,e
~
=r'=JO:L
Fig. 5.27
"
",,<'
Conneclton~
'/
':
-\':
rronlcro~~bor "'1'(
. A
"
V)\
I:--EvtnlUCII
'i Itmpolory
.lJL
!i
"II "
~~
"
.~
~J1
r;ron~ r.'" 1~
L:Ii'J
braced to each other. It was supported at the front, by the pier head of the
balanced cantilever beam to be built, and in the rear, by the part of the deck
already built. It was equipped with a troUey, carrying a winch for 6fting the seg
ments, and a motorized bogie placed at the back. The supports for the
longitudinal beams comprised front and rear crossbars whicb could transmit
vertical loads, directly above the segment webs.
This machine allowed the placing of all the segments for the cantilever situated
on the side of the deck already built. while the symmetrical segments were more
easily placed by a crane. The same machine can be used for the stabilizing of the
cantilevers during construction, when the structurc'slUpporU may not be strong
enough to carry the asymmetrical loads imposed. In this case, the twin etntilevers
are rigidly linked to the longitudinal beams of the keying bridge by connections
which are moved as placing progresses, and which can resist tension and com
pression forces. When crane and keying bridge work in this combination, it is
possible to build a 40 mlong span in four working days.
The placing of segments by mobile crane has found a new application in the
construction of structUrfS with small spans, as in the case of motorway over
bridges with three spans. Segments, which have been precast in a casting yard, are
carried by road to the different sites and placed by a crane, as shown in figure
5.30. The method comprises:
-
use of two adjustable temporary props, which can easily be removed; they
238
239
CD
-Adjustoble prop
Temporory pr"lr"'inQ
...,
cv
Finol prntr."illQ
18lD30m ,pons
The overall construction of such an overbridge generally takes less than two
weeks, supports included: less than a week for the deck (fig. 5.31). This method
4.2
For the construction of the Pierre-BCoite bridps on the Rhone it was considered
advantascous to \IIC IIIOblk lifting ,qulp~nt, carried by the deck, to place the
segments. It nccdI relatively simple equipment, supported by the cantilevers
already built, and successively If/b, transports and places the segments. A
diagram reprcsentin, the system is shown in figure 5.32. It comprises a lifting
equipment B carried by a trolley C traveUulg on the deck on a track D. The
segment A is brought, on land or on water, to the pier, where it is taken by the
lifting equipment. This then carries it to two cantilevering launchinl Birders E, and
the segment is moved to its final place (lig. 5.33). The sySlCm can be simplified if
the segments ate brought diree:tJy under their fmal position in the structure.
In its initial form, this system is not eiltirely independent, as it requires the patt
of the deck situated above the pier to be constructed by another method.
This first element had been cast in situ in the case of the PierreBenite bridges.
It had been precast and placed by a crane moving on the ground in the Empel
Lounch,nq qirder
~-:-:-:-:-:-:-:-:-:-:-:-:-:-:-:
.A
Fig.5.34
Pollel
Temporory support
-Pier I
:-:7":-:-:-:-:-:-:-:-:-:-:-:-:-:-:-:::-":-:-:-:-:-:-:-:-:-:-~:-:-:-":~:-t~~:=:=~~:-:-:-:-:-:-:-:-:=:-:-:
....
j.
'.
-.
!.
,'. .
"~,,,,~~,~,
..........:
<
242"
4J.J
243
Let us rust review the method of deck construction at the O/eron viaduct
(fig. 5.37).
Segments were carried fllong the deck itself and placed by a launching girder
which is. overall, slightly longer than the bridge spalls. The launching girder \\'as
an E24 Iteel (highly ductile mild steeI)' lattice girder, of ree/QlZgular sec/ion.
entirely welded, with a total weisht of 113 t and a length of 95 m (maximum deck
span: 79 m). It included two fIXed legs, called the IUllnel legs. which allow the
ments to come through, placed one at the rear and the other about the middle of
the prder, plus a foldable front lea called the guide leg. The bottom chords of the
girder were used u tracks for the carriases, which could mo\'c the segments
vertically and rotate them by 90 horizontally.
Three distinct phases occurred during construction of the cantilevers (fig. 5.38).
seg-.
bridge in Holland. and by a.floating crane at the Bayonne bridge on Adour. This
system was improved at the Saint-Andre..de-Cubzac bridges where the pier scg
ments were placed by the same equipment as the standard $Cgments (fig. 5.34).
One of the two mobile carriages is temporarily hunS by cable stays, to an
auxiliary tower fixed on one side of the pier. The pier segment is brought on the
other side, lifted and placed by the winches the mobile camage. In this lame
position, the', next segment is placed, then tho auxiliary tower is removed
(fig. 5.35). Then, simple operations allow the placing of the two mobile carriages
", in a position convenient for lifting the standard segments (fig. 5.36).'
or
4.3
By this most elegant method, the segments are placed by a sleel girder launched
over the cantilevers. This method was first used at the Dleron viaduct; it'has since
been frequently employed. By reviewing the different structures built by this
method. \ve \vill try to show how launching girders have developed over the last
few years.
244
245
The principle was as follows. During placing of the pier segment, the central leg
is on the end of the cantilever, at the same place as the rear leg during placing of
the standard segment The placing of a standard segment was done as a statically
determinate beam supported at two points as it is not possible to modify the reac
tion under the rear leg which applies well defined forces to the deck.
During placing of the pier segment, certain fottes must not be exceeded. The
reaction under the central leg must not be higher than the one under the rear leg
during placing of a standard segment, increased by the weight of the truck carry
ing the segment.
Several other structures were built with launching girders similar to the one
used on the Oleron viaduct.
CD
Guide
",leg
-f:'
support
TeMpotory
brae.,
Chi/Ion viaduct (figs. 5.39 and 5.40) overlook-jng Lake Geneva; a 122-m
long girder weighing 230 t (maximum deck span: 104 m) was used. The
girder, of constant rectangular section, was cable stayed; its adjustable
legs.. equipped with hydraulic mechanisms, allowed it to follow the slope
variations of the deck (fig. 5.41). To folJow the curve of the structure. the
girder pivoted around its rear leg, by travelling transversely on its central
leg. The girder had three adjusting mechanisms (fig. 5.42):
~
'I
36.00
I_
79.00
43.00
The girder was rolling on its back leg and on the carriage which was connected to
an auxiliary steel frame, or temporary tower, placed on top or the pier segment.
During the travelling of the girder, the rear and central legs were rolling on rail.
A support atQuslment was made when the girder was supported by the rear Ie
the central leg and 'the guide lea, before placing the pier segmeftt. This adjustment
was made by jacks. to distribute correctly the weight of the &irder on ita three
supports.
"-li iI .
III
nil . ~
'w
...... 1
.'
..
246
122.50
Guidi 1t9
9 n
Phase2;Ofpierse me ls I i
!!!!!..!!!
--------~-~~~~-
~~~~~~~~~~
G:fUlF
"I
---- ....
~--.--..
~_!e~O..!.!.t!~!r
Guide1et-
$UP",'
Phose :
~1~;~~:lIin9
""W"'
Fig. 5.41
The guide leg was designed as the other legs, letting the segment come
through.
- Blois bridge over the Loire. A 112-m long girder, weighing 123 t, wq used.
(maximum deck span: 91 m). The su'der had a constant triangular "ellon,
and could be entirely taken to pieces, so that it could be transported by
road (ftg.5.43). AD the components of the Sirder were connected by high
strength' friction grip bolts (fig. S.44).
The usc of a lightweight frame in E36 steel (high strCDlth weldable steel) could
create larsc deflections in the girder. To reduce and control these deflections, two
-... -~-
~3l
=:::!~ ~:~~~~pe
5.6-/.
247
248
","
249
. ~-;...
1,
~rLII~~.~:,~~~~Jf{4f4i~,
k,:; .~", ~ j"t"""\I'~.~
'1".,.,.O~j'n"li\I~J~j',~J~j~I~J~~~~~I~"j~~_.!
~~y -~/tj ~At'. .,.~ ~,~! ~~::
.
:
~
.
.l.,._,.~-,-"
;k~~d~:~': .....;. ;: .~., :;'~i" ~~~~~~;,-:-~~;"':::;"':-'~\~~4'A
~!!~
rp/"-::~
"I
i'
t,jl..t", -,..
"
' ',:..-'
\
Fig. 5.43
1'"." ''''
,.r
",-.'
Fig. 5.45
I'
. ,'; ,
..... / ....,:
.'
. : -
_.:'
",
..0\
.,:
- ,-
r'
. ,',-
11~\,,$~~~;~~;!{.~~:~~~: .~' ~
e--,-,
/'
'
"
~;;~
(It
.
;-""1'" ". :
.....
types of cable stays were used; untcnsioned or tensioned, which were successively
working during the segment placing phase (untensioned upper cable stays) then
dwing the girder travelling phase (lower tensioned cable stays).
The girder of the Blois bridge was then used for the construction of two other
structures: the A ramon bridge on the Rhone (fig. 5.45) and the 900 m long Seudre
viaduci.
Elevation.
i.
(
Section A
250
-Guide le~
I..
55,49
...l..
52.22
.1
This is the most recent example of a largc launching girder, capable ofplacina scg
Illments weighing 130 t on a bridge with maximum spans of 102 m and a minimum
1IIIcurvature radius of 330 m (fig. 5.47). The girder weighed 23' t and wu 122 m
"long.
Placing of pier segment
Guide leg
251
252
Cantil~'er
253
In the range of smaller and tighter spans, the launching girder designed for the
construction of the viaducts is a ~haracterjstic example of a versatile machine,
which could be dismantled and reused for several structures (fig. 5.50). This girder
was used for placing segments of a maximum weight SO t on spans not exceeding
60 m. The study of these launching girders shows an evolution on two main
points: structure andjoinrs.
The structure involves an increase in the external variable forces according to
the loading case. The external forces are transmitted by activt cable stays which
allow the structure to be placed in the most favourable condition for the applied
..~ . j;.!.~
"i
U:
loadings, and lead to an optimal use of the constant section and to an economy in
the \veight of the frame.
At the same time, a constant section, identical from one end of the girder to the
other. led the contractors to stop using welded joints and to replace them by joints
which could be dismantled, thus building the girder in standardized and
interchangeable panels. The length can then be altered according to the span and
to the \veight of the segments. Some prestressed joints, making the bolts work in
tension-thus reducing the number of bolts and shortening the time necessary to
assemble and dismantle the frame-were recently substituted by joints of plates
and high strength bolts (fig. 5..5 1). These prestressed couplings were used at the
Deventer bridge and subsequently on the B3 viaducts.
At the same time, the operation method had also changed. The deck need no
longer be submitted to forces transmitted by the supports of the launching girder
as these can now be placed above or near the structure's piers.
Some new schemes for launching girders have been designed: their total length
is slightly more than twice the standard span of the deck and this allows the
standard segments of cantilever N and the pier segment of cantilever N + 1 to be
placed at the same time.
Fig. ~.50
The rarst examples of such launching girders were used on the Rio Niteroi" bridge
in Brazil, .:>n the Devenler bridge in Holland and on the B3 South Motorway.
viaduct, east of Paris.
'
The Rio Nlteroi bridge, linking Rio de Janeiro to Niteroi, has a 16-km-long
deck (fig. 5.52) which was built by fOUf identical launching girders. Each
launching girder, which could be completely dismantled, had a constant triangular
254
,~.~i::!:.;:.:; . .
>'.t~
.. '~ ",.,o\1~
0
0
00
. . . .. :
":
::.
:::~~o~:.o~~:!
..... .. ;.
. '..
.;.,
...
255
section and was 166 m Ions and weighed 400 t (maximum deck span: 80 m). The
joints were basically similar to the Blois bridge joints. The girder had three legs,
which did not form a tunnel; with one leg being fIXed and the other two moveable.
The operation was as follows (ti.. 5.53):
..
The launcml11 airdcr rested on three supports, each placed above a pier. It placed
simultaneously two seam-ts onto the cantilever, one on either side of the central
leg, and could alio place tho'pier alament ofthe next cantilever.
.
/",,"
of'' '
,1,.,
Phcu, J: TraNlIInI
1aJUtC1U",
The lauachia. airder w rollin. on two auxiliary temporary towers, placed one
above tho pier of tho ftDiabod cantilever and the other 'one above the next pier.
Theso ~poruy tow. . wert connected to curiaacs which allowed them to lift
the launchiDI pdet and rclc_ tho lop. As the deck was partially curv~ in plan,
tho two tempOrary cowon , equipped with tranlyerse mechanism which
allowed tho beam to mo" OIl curved path.
Tho Iaunchin. a1Jder a110 comprised three systems of active cable stays: lateral,
central and Jaunchins cables. The lateral cable stays, placed in the lower part of
the two spans, and permanentJy in tension. played an important role when the
load wu pauing at the airder's midspan. The central cable stays were tensioned
only durina the travellin& operations or the launching girder, and transferred the
reactions of the front and rear legs to the central lea. As the deck was very long,
and because of the water under the structure, the seaments were brought by sea
on Pontoons. The stability of the cantilever was ensured by the launching girder
itself, as some intermediate IUpports could be moved is segment placing
progressed.
~~::~3:~~~~~~~~~~~~~~~~~~
The girder uacd on tho Deveater bridae in HoUand (file 5.54) could also be
completely, dilmantled; it had constant trill1&ular section and was 156 m lona
and ~d 180 t (maximum deck span '074 m).
The jointa were made by prcstnssina rods placed perpendicularly to the plane
of the joint (4 5.5 1). Tho lauricbing girder had three fiXed legs, the rear and
CCJltral lep forming a tunnel, and' two cable stay systems: the central and
launchinl cable stays. The operation was the same as for the Rio Niteroi' bridge,
but tho launching girder could place only one segment at a time, with the segments
being broupt along the deck.
Its main feature was that it could lift IlseV: the girder, assembled at ground
level, could 6ft itself to its working level by means of the central tower which was
used as a lifting jack.
In the case of the BJ South Motorway viaducts (fig. 5.55) a highly mechanized
launchiDa girder was used for the construction of a deck with constantly changing
geometrical shapes which was resting on 200 piers and crossed five railway
tracks, the Ourcq canal and several urban roads. The laWlching girder allowed the
"';.'~"~
256
257
~~e'''''''''l''"''!J .... ~. -.
C'OSIltchOft
..
~
-l.J
Sysllmfo,_
lIlIoodincj
Ihllt-aAtlJ i i Vi,.~ i H! -i
ii
"'Y"-'
Ro1hn9 trock
Fig. S.56 Launching girder of the 83 South motorway viaduct- general arrange
ment
V''11
~.
,----
c..
PO
PI
lr
c..
P2
P3
PO
258
~
,.
..
... . '
",'
..
.....
;,~
-~"-.;;.,"O:""'"
...;
,.-=--'..
259
........ :.
11:~~:""""
~~ .
.:~fi~! ;~
::;':~~~::f~t:::
. _
. ..~ ..~,"'~~'
lew. . . .
A'
x'
Fig. S.S8
'rot.-ll
._cCbeb
I}JaL.L:l:.."
. WI
length' was two-and-a-haV times the length of a standard span; it rested, in its
working position, on four legs, three of which were placed above the piers, while
the fourth leg was at tho CrId 0{ the last built cantilever (fig. 5.61). It weighed 500 t
and was about ZSO m 1001 (maximum deck span 95 m). Each deck span was
made of seven prefabricated subunits. The pier subunit weighed 600 t Ilnd WIlS
1_
2~O.00
~;'O'jjljj'~""j"''Icr
~~""")t""""~
'II'
~H~8Ii~B""II~
If
4~DY''''iC~
1l'
~ .~~"i:HZ:P""'~
err
2 c::e:'
fig. S.S9
a week, i.e. four to six segments a day. The average construction speed was 60 m
a week, including travelling of the launching girder. The B3 South launching
girder was used again recently for the erection of the Marne-la-Vallee viaduct.
4.JJ
This category includes the launching girder used for the construction of the bridge
on the East Escaut in Holland (Ocstershelde Brug) (fig. 5,60). The girder's overall
~"8iir
ca::x:::::ct '
I.
Fig. S.6J
I!
Rollers
"W'If""""'i
----.
11
..
rUT:C~l[ru(l~rrttrtUti
"'00
.1,
95.00
.1.
95.00
.1.
9~OO
.1
.:.,~~~,.,..-r:;:
260
I 0<
17.S m long; it was placed at high tide by pontoons; the pontoons carried two
lifting towers equipped with jacks which had a I-m lift. The standard subunits,
weighing 190 to 275 t (13 m long), were placed symmetrically and simultaneously
by the launching girder. They were placed alternately on one cantilever. then on
the next, to allow the concrete joints between the subunits to harden.
4.3.4
26]
18.00
I ot(
..
Trovel 14.5
J- .
~ ..
II
I
:
A launching girder with a different desilft, WU used Cor the construction of the
Vienne bridges over the Rh6ne (maximum span 98.4 m). This aitder was slightly
longer than the span and allowed ,'multanlOUl plad1l, qf"""",11' Cor each ofthe
two boxts formln, the deck (fl,. 5.62). It wu formed by two steel frames
(triangular section, 120 m long) placed paraUel to the 18-m centre line; the
frames were used as a rolling track by a self-pro~lled gantry (fig. 5.63). Each
frame rested on fOUf supports (fig. 5.64):
-
I:ig. 5.63
The steel frames were launched over the intermediate supports which were
equipped with sliding bearings. The movement wu ensured by electric winches
incorporated in the frames which pulled them from a faxed point located at the
end of the completed cantilever. The segments were "brought OD an auxilia,,'
' ..
SJ
..
-r
."'
,,-~~;
i.-=-~~.:.5.=~~,,-~,::
.' f,'"
fl.l~~.~~:~~':~:~1
Fig. 5.62
.-.
H
--~.~ -V':~~i~.:_.~ ~
I
1----".... -'.'-98.40
.-.- ..- _..- -'.- _. -----:
.~ I':; ~.".~.
:~
;MM)\MMtw
-r.,
~~ ..,~ .
;T~V"1}{Tj.i~~
,_~::'1':~
. -
~~~~,
-....-
.J"
.~
12000
~.'f: 1:111~.111..nlll}.,.lilo
~ ~. "'1"'I"A~~~'
'
' .'Io".h~:.~ .
:.;:-. , ~ .. ' ~_ {<!"r.r,.~~ '1,11,1
~ ~,
_., .....,,:.c,t,:i t. ~ ..._'~ '";'Vi r, r, ;':: /' ~,~,r ..,rf~.r~:}......~
1:;2~
~~;~
' .,. ".,,,.
.
I
~y
J
P:
p-u
c==:::r
I
~'
Fig. 5.64
Vie~ne
bridges-operation method
262
gantry moving on tyres, drawn by a tractor and could be loaded and unloaded
independently. This machine completely separated the. precasting and placing
operations.
The launching girder of the VieMe bridges could build structures of IOSm
spans with segments ~ighing up to SS t.
The development of cantilever construction by the usembly of precast seg
ments led some companies, which were already specialized in handling and lifting
gear, to design equipment for segment placing and to hire it to construction
companies. These girders belong to the same category u the one used during con
struction of the VieMe bridges. They usually comprise two steel frames, made
of standard clements which can euily be dismantled and transported, and a
mobile truck (fig. S.65). As they easily deflect, these girders must rest on the deck
in several places and occupy different positions during placing of the segments of
one cantilever. Figure 5.66 shows the different positions occupied by one of these
g
~
:1tl
G
'6
~
:I
~
..f i
I
'is
:1
J1J
b
tl
It
I;
101
II. I
Q
.-.
-,.;1n\
.! : \\ ~,
.. 1~JI;
I ..
i .\ \~
II \\ n:
:{=r:ti>
'1
Ie;
!
"
...
f1.
I;
Mr--V'I
~
o-~-o-o-t'l""""OClOO
"'0""""
t'l
r--_O\ ..........
0
.~
c:
.~Ba
e
~~u
tl
G
.c:
'
.;
.
a
b
'0
t'l
:a
.!:a:;
:a
aaljOllOll
"'3 "'3
tl!i;
"'3
011
.3
....
:a
:a
1.l!
li
t=~ ....
"'3"'3
~~t=
... III
.c:
...
.:/ ~
~
"..0.,..
~~:q~:::l8
8~:::l~
N
00
.... 80 ....
:l~::l
....
""N
...."" 8..,
0>0
00>0
--
--
N
N
00>0
CON >0
.,.. 0
>0 ....
.,..0N
.c II
~'o
'il
~
-5
coo
c:
""NN
m'i
~o
aZ
"_
--
o-N
~]
.Dcoo
-- _ _
-N
-oS
t'l t'l
t'l
i-a ~a .!!c
-3"
~~j 88 :!!
88
8
u u
c:
u
ffi~
~oS
-'i
'!~
.APPul mobil,
~ooO\\OO\ao
i ~.
>8
~DC""
::l.1S
~F~ ..,. ~~
~:::l"""'2:::l:l~:q2:~
--- -
S
..
'5
'!
~~~~~~~~ O~~
.... CIOt'l
7.10
263
'i i ,- 'M'
f3
Ii.a
g .. ii < ~ ~ -5 1I > .!
e! 0
C:'-':'~ Ii J; ~ 0
'0
c: c:
.2.!!I
:!t :E ~:!
OU
'0
.:.
bIOI
DO. 5
...
<~t~~~>~~~m~i
.
"'Nf'II"'a,
III
..,
III
DC
~~
""IQ ....
::r ~
00 0
-...
_....------.
264
ITransport of segments)
9600
~'::J
( (kIXXXXiXXkikXkAXA
2~
..
~n9~om \~;::eom
<D
Gantry
A&
(l.
--rr.
:':
:'280
.
..
s.,,~ W
14~440;
. :'1 ~400
- - - - -I'
I
11'
\::!3.
PIOCifMJ oI~ts 5 to 8
A~
r
: ..
C!
2240
.,
::.
II
27.20::m:=
.
gUO
I -,
: . 1920 .:
~ of Mc)tnlftts 9 to 11
@,
or
5
5.1
Sf Cfoud bridge
B
1I I I lIZ
3Q40
:
265
Some precautions must be taken, so that the joint's match-caatinais still effective
despite the deformation. occurring in the segments dwina tll,tlng, Itoc1cplllng and
transporting.
During the precastlng stage. it is necessary, if higlt-ttmpll'aturf curing is
applied, that it is applied homogeneously t~ each segment, in ita concreting posi
tion and in its countermoukl position.
.
During stockpiling, it is necessary to avoid crtep deformations and warping or
Fig. 5.67
Handling of segments
the segments by, for example, supporting it on three points. The same applies if
the segments are transported when the concrete is very young. At the Saint-Cloud
bridge, ror example, because of the large size of the segments, it was necessary to
use sloping tie-rods to ensure the stability of the shape during transport and
placing.
Lifting and handling of a two-webbed segment is usually done by a slngle
lifting beam. For a three-webbed segment, it is advisable to use a triple lifting
beam (fig. 5.67).
5.2
The longitudinal cables will be grouped in distinct transverse grouPSt which can be
isolated from each other by waler slOps, made during precasting, at the joints in
the webs and in the flanges (fig. 5.69). Despite these measures, cables grouting is
still a difficult operation and some research was undertaken on how to keep the
duets tight at the joints. and thus, how -to grout the tendons separately. Different
. methods have been studied.
266
267
Section AA
Expandable
sleeve
Polymerizab1e
resin
Expansion
system --""-;=~;;"'.-61-IFlliii:T~~.
Duct
Pi pes for expansion
fluid
Grout
Col/ar joinls, placed at the duct jW1ction, y,'ere tried~ but this system was
inefficient \yhen tendons were close to each other. Today, the most satisfactory
solution is the use of expandable connecting sleeves glued with epoxy. These
sleeves arc made of a cylindrical folded envelope threaded inside the duct by an
inflatable tube, until it is across the joint. The expansion system at the end of the
tube causes a plastic dilation of the tube, thus pressing this against the internal
walls of the ducts, where the sleeve fits tightly (fig. 5.70). "This joint is made
watertight by a preglueing of the sleeve: a rapid hardening resin is placed inside
the longitudinal folds of the sleeve, before introduction in the duct. Such sleeves
were successfullr used at the Saint-Andre-de-Cubzac bridges.
Groups of tendons
Detail A
Water 'stop
Glued joint
The values must, of course, be u,ed with care, as they can vary considerably with
the availability of cquipment:within the contracting company. The development of
bridge construction by preCast segments with match-cast glued joints, and
technological advances allow rapid Construction speeds; the field of application of
this method has been extended to structures with very variable spans and con
stantly changing geometrical shapes. In the following chart is shown a general
review of precast bridges finished or under construction in France, since the cons
truction ~ the Choisy-lc-Roi bridge.
It is interesting to Dote that, during the last IS years, a steady evolution in the
268
Start or
Area
Prccasting
Chois)'JeRoi
Pierre- Benile
Oltron
Courbevoie
Juvisy
Pont a\'al
Pont amont
Bonpas
Blois
Bayonne
1962
1962
1964
1965
3600
16400
Aramon
Bourg..Saint-Andeol
1968
1970
Tours
1969
Structure
1966
1966
1967
1968
1968
1968
...
30300
4800
B
B
C
3200
10100
10900
16200
C
C
26800
5000
6900
B
C
B
C
C
B
C
C
7900
4700
4200
3300
Platina
EM
PL
G
0
GandBM
o and EM
G
PL
B
Coignet
(CD)
(CD)
1970
1970
1971
10200
PL
73600
Saint-Cloud
CaUx
St-Andre-de-Cubzac
1972
22500
1972
1972
1972
19500
C
C
B
GandEM
Coignet
(Cn) J\rc:\
PL
(CB) Arc:a
EM
Coignet
PL
BOUYJUfS
aM
1972
Angers
Pont Leon Bureau a
Nantes
Viaduc RATP
Marne.. la..Vallee
Le Scorff et Le Blavet
Beauregard
Saint.. Brieuc
Echangeur Saint..
J974
13800
PL
1974
2600
(ETPO)
1975
18000
PL
(CD)
1975
1976
1977
C
B
EM
7000
C
C
PL
Coignet
BouYlues
BouYlues
C
B
PL
M
1977
1977
~faurice
Oumarsheim
7800
16600
29400
15700
C'
PL
(C)
(MB)
(WO)
(LO)
83 South Y10ducts
~_
I
I
I
I..
Coignet
!o
'N
_I
I. 650 .:
13.00
204C
.. __
I:
-.,
!
I
Ch,1I0ft vkJducts
I~
(CD)
Bouygues
9.50
1525
-0
i\:!-'==D ~l
(CD)
1972
r j
j
1660--...,
St Cloud vloduct
, (CB)
Corbeil et Evry
Vieone
i.i..J...Q.Q
718
:.
(Ca)
(Ca)
77100
25300
7900
19800
1972
~t ~1
(CD)
1970
C'
Ballot
. ;:._. !
(CB)
Connans
28100
14.00
r~~
~'. ~;
:-
Stud,e bridge
(CB)
Gardon
Seudre
Viaduc B3 Sud
P.S. Rhone-Alpes
Viaducs Rhone.. Alp~s
I.
(CD)
(CD)
(CB)
PL
PL
Lj-M
! :~Il!il ~.66.1 I
(CD)
(CD)
(CD)
(CD)
Coignet
~~
! U
Contractor
EM
PL
construction
269
Fig. 5.71
~.OO
I.....
tJOO"
2ft
Ntj'
,i-.
t
."
,I)
the Choisy-Ie-Roi bridge, built in 1962~ the 14-m-wide deck comprises two
parallel box beams at 6.6-m centres, made of 2S t segments;
the St-Cloud bridget built in 1972; its 20.4 m wide deck consists of a single
spine beam, with three cells, made of segments of 130 t maximum weight.
Some contractors, however, prefer using sInall segments. precast by
traditional methods (precasting bed ) and placed with equipment com
monly available (crane, gantry ...). The Calix viaduct is a typical example;
it was built with segments of maximum weight 43 t, which were placed by a
tower crane and liftina equipment.
~
271
However, over 200 m span, 'this type of structure has several drawbacks, which
soon become prohibitive:
-
CHAPTER SIX
CANTILEVER CONSTRUCTION OF
CABLE-STAVED BRIDGES
However, some cantilever bridges have been built with spans greater than 200 m:.
the Bendorf bridge in Germany (208 m span), the bridge over the Urado bay
(230 m span) and the Hamana bridge (240 m span) in Japan.
In some cues, specific st~ were taken to limit the drawbacks which we just
mentioned:
,tronatboning of the lower flange by introduction of continuous passive
reinforcement at the Beadcd' bridge;
use of li&btweiabt all1C.lte to reduce the self-weight in the Ottmarsheim
bridaO over the Rhine.
p'ET..g"""r",.. ,. .-,
I
E;,='"
LodltOIed cables
Preslressed cables
A.. ,oqnt
_ _ '0'
I
-~Ol
101
,~t~ ..
__.i~~
coase lob<es
-t.
POCklflQ
. envelope
Prestre~~d' :
Wlfe~
270
-;
....
_-......
~~~
272
First, the variations in tension are higher under working loads than for cables
placed inside the concrete and made integral by grouting. Then, it is necessary to
protect the cable stays against strain phenomena (fig. 6.3):
-
or
fr 1800
1000
0.50fr
273
- nonstij]inlng
by the structure of the cable: lock-coiled ropes;
by the Corm of steel treatment: stainless steel or galvanized wires;
by sheathing of the cables: grease, paint. epoxy-based or not, resin.
watertight sheath in plastic or steel;
by the medium where the cables are placed: nitrogen or inert gas;
. - stiffening, when the covering of the cables contributes to their strength.
This is the case of prestressing cables, threaded in metal ducts and grouted
with resin or cement.
The ducts can be either of stainless steel or of steel with paint protection.
However, one must note that, because of the low stres'sing force in the cable, the
risk of stress corrosion is negligible (it is usually assumed that the risk appears
only when stresses are higher than 0.4 UTS). The best absolute guarantee against
corrosion seems to be the possibility of rep/acing the stay cable if it deteriorates.
tr sup
(MPo)
0.65 fr
t---.. . . .
2.3
The stay cables, which are submitted to wind loads, can be the cause of vibration
phenomena, which could flead to fatigue failures. The risk of this happening is
increased if:
'"
750
- the stay cables are round and have a smooth surface, thus having a high
lin;
100
200
300
"'et(MPa)
Fig. 6.3 Maximum permissible stress value of the stay cables in accordance with
the variations of stress to which they are submiJted
274
have a rough surface which stops air flows separating from the structure; their
structure allows them, by internal friction, to dissipate the vibratory energy. One
can alleviate these drawbacks by giving some antivibration mechanisms to the
stay cables; these mechanisms can be of two sorts:
275
./
i~d';::"'"
/~L..
At the BrotoMe bridge, where vibrations of high amplitudes (300 mm) were
noticed during medium velocity winds (15 mls) blowing at a 30 Mgle on the
horiz:ontal axis of the deck, this last solution was used (fig. 6.4). However, the
FiCo 6.S Neoprene shock absorbers
most simple apparatus i, better, such as the neoprene shock absorbers which are
placed insi~ metal d\U:ts to provide access for the stay cables through the deck
(lig.6.S).
At the Hocchst bridge, the stay cables, also made of prestressing tendons
grouted inside a plastic sheath, but placed transversely in pairs, began to vibrate in
pairs; they had to be linked to each other at several points. Despite all the preced
ing su8&eadonI, a rigid S1Up,nsion, i.e. made of prestressing tendons inside a
grouted steel sheath, with a roup surface, olTers an interesting solution to the
problems created by radaue strength and protection against corrosion.
For the same weight or steel, the stress variation under alternate loads, is
reduced significantly as the steel sheath contributes to the elTective section.
Furthermore, the prestressing steel, with an ultimate strength higher than the one
of lock-coiled cables, increases the range of stresses which can be applied to the
stay cables.
3
...::"
276
~~
(a)
fb
277
/. .'----- ""
?ayoables
~ro~
rn~
( b)
(c)
Deck
:
compression
/r
.< <,>'" '<'~:~~~<::,
The stay cables are then regularly spaced longitudinally along the deck and the
general arrangement is called multiple inclined cables. This type of cable-staying
has several advantages:
\,
Eros!,c Support
V reocliOn
~--. I
==.:sJ
I
N;
\,
.,
'N:~.
"".:
,
-
.,
Fig. fI,7
Fig. 6.8
278
279
INCLINED CABLES
Fia.6.12
Fi&. 6.9
Loscher's bridle
Harlley's bridle
the principle of their desian was severely criticised by Navier. Since 1940, the
development of cable-stayed bridges has revived, with.the construction of several
sleel structurea, especially in Germany. At the beginning, these structures had
only a limited nwnber of stay cables, even at times only one (fig. 6.13). Professor
Homberg was tho first to deep a sl,,1 structure with multiple-inclined cables. for
the construction of the Friedrich-Ebert bridge in Bonn over the Rhine (fig. 6.14).
Even tbouah a patent for cable-staycd concrete bridges had been registered in
1923 by Engineer Bousairon. it appears that no structure of this type with a con
crete deck was built before 1972.
Attar tho Mindin bridge in Saint-Nazaire, which has the longest steel span
(404 m), the BrotoMe bridge with a 32Q-m-Iong span, holds the record for cable
stayed bridges in prestressed concrete; its central span is much longer than the
Corrientes bridge built o~ Rio Parana in Argentina, which previously held the
record with a 24S-m-Iong span (fig. 6.16). Another structure, the Barrios de Luna
bridge, ICtually being built will have the longest concrete cable-stayed span. It will
be 400 m long (lig. 6.17).
Figure 6.15 gives a list of concrete bridges with multiple inclined cables
designed or built to this day.
_...
,-~.~~--
'
us~
1u04~;
.
i >119.00 l
Hoechst
(Germonyl
1972
14
"~
~~
Srotonne
2 (Ftoncel
1977
PlI!lCo-l<ennewick
(USA I
'l:l
'l:l
'C
.c
1:l
:25
III
..
'0
]
.~
:;
'0
RioEbro
(Spain)
.!I
.c
III
1980
Barriosd8Luno
(inconslruct1on(Spain))
-=
PosodasEncornocion
U;
'l:l
Easttbllongton
9 / inCQn$truction (USA))
..,
.0
10
~._,
/,nconstruCllon
Melico II
I
t1 ...1~00
haZ.10
q
I-I
33.20
Casado
Hi
1I~.00 I
~
0"?'
','
18530
40
.fl.'Z.60
I98.70'
330.00
.Z.10
146.30
440.00
274.30
SETEC
.'390I, ouGhorl
-"",
-:!!!.~
"(D.
lZl
l1.
I ~~.OO I
'C
.!P
50. zo
....
~ ~
~
.~
Bernard.
ha3.eo MathivOl,
Muller.
.~~ ~
~
~
~
.9
""
Campenon.
J.
~~
I91.70I
8
70.50
~ B
~.~
Kobejimo
(Japan I
11
:3u
.!!
.:~ :~
,,~
"""""t
.5
iWW/~
. .1. ~~,
;,,;
1980
'C
11
-0
00
l1.
Ul
>
,,__
'C
.c
I' I
Grant
Leonhardl
and
Andro
1978
Oyckerhoff
and
WidmaM
j50
-haZ:
"'_'
P,oject
tl:1
Ibl~
00
~J2O I
Cappon
I
Uo'Ihordl
and
.'Z.9O Andra
~jl20
-.!
- . -~
288.00
h'
112.35 6000
IG,onl.
Leonhardl
h1.~O
I~~!;'30
1-14
49.~ n23~
I CO\OOo
SOGELERG
3.401 Molhivol,
590
Paulik
282
OO
rr
if'~,-r~,-rOO ,-roo
::
.:::
1226~ 1~2.~ :
lliBS
it
163.70
"1"
..
t'
245.00
..
,::
'1'
..
163.70
..
,. 98.74 ~I~
22.50
I~
98.74
~I
~o~ o~~~
Fig.6.17 Barrios de Luna bridge
greater stiffness;
283
5.1
440.00
,.
The problem of aerodynamic stability is crucial for suspension bridges and cable
stayed bridges. When the deck of a bridge with a long span, belonging to a light
and flexible structure-as in the case of the suspension and cable-stayed
bridges-is placed in an air flow, it tends to be subjected to flexural and torsional
osciUatioDS, under the effcct of wall variations in the wind incidencc, which
modify the lin of the section (rll. 6.18).
For a critical wind velocity, the oscillations are not dampened and can lead to
failure of the structure. This pbcnomenon, called flutter, became evident when the
Tacoma bridge l:Ollapsed in 1940. Under a wind of 19 mls (68 kmlh), the deck
twisted by around 45 0 on the horizontal, alternately one way, and then the other
until it collapsed. The collapse wu filmed by a bystander and is very impressive
(f... 6.18(b. The car which can just be seen on the right-hand side or the picture
will rall in tho river a few seconds later; one can note the inclination of the lamp
posts: it aives an idea of the torsional warpina of the deck.
Flutter has been the subject of several analytical theories and or systematic
studies. Even though it is advisable to make tests in wind tUMels in the case of
large structures, it is, however, suffICient at the predesign stage, to make sure that
the torsional and bcndina frequencies are different from each other to avoid the
creation of flutf" phenomenon. A value of the ratio of frequencies higher than 2.5
seems to be adequate.
.
This result can be obtained by giving to the deck a box section with high
torsional stiffness. One can note that the risk of flutter is higher for steel cable
stayed bridges which have a dock lipter than concrete bridges. Similarly wide
bridges are less sensitivo than narrow bridges.
Decks of cable-stayed bridges and or suspension bridges are subjcct to Karman
vortices, which can lead to resonance, thus making the bridge very uncomfortable
for its users.
The $Olutions are simple and generally consist of improving the deck pr0)7le
either by the design of the leading edges of the cross section (as on the Severn
bridge in the UK) or by adding deflectors (as on the cable-stayed bridge in Saint
Nazaire)(fig. 6.19).
The vortices can initiate nutter by initiating the first torsional movements of the
deck.
284
Cantile~'er
(~
. . . . , . . ,",""",OO"
--=
?.
285
Defleclors
( SI NOlOi" b,idge )
( Severn brodge)
.!L
Ir ~ 2.5
6
The stiffness is a function of the tensile stress and of the length and depends upon
the denection of the cables, which varies as a third power of the tensile stress
(lig. 6.20).
./
C Co
82 {2
1+
Fig. 6.18 (a) The phenomenon of nutter; (b) Failure by nutter of the Tacoma
bridge
12 cr 3
Co
286
0 (1
)
E = Eo/ ( 1 + --) Eo
12CJ
Eo:
A:
1= Acos a:
o(y):
0:
In figure 6.21, the C!Jl'VCI show the primary importance of the stress in the cables.
For a stress of 100 MPa, the stay cable stiffness. for a horizontal span of
100 m, is equal to one half that of a straight cable. This explains why the first
IT
IGpo)
Eo'
200
180
1- 400 m
Tension
750
700
~650
-600
~ S::550
.~~
o
50
100
150
zoo 250 300 (m)
Vmarion of the apparent modulus of elasticity of a stay cable with
length and stress
CJ =400 MPa
CJ =500 MPa
E= 0.94 Eo
E=0.96Eo
In concrete cable-stayed bridges with medium length spans, where the dead
weight is usually a significant proportion of the total load, the permanent stress in
the stay cables is sufficiently high, so that the variations in apparent modulus of
elasticity, due to variablo loads, can be neaJected.
~
This no 1011l0r applies to bridges with long spans; the efficiency of a stay cable
decreases rapidly, as its length increases:
(Mpo)
" 350
400
30
Fig. 6.21
cable stayed bridps--cven with small spans-did not possess adequate stiffness,
because of the low permissible streases in the cables. However, for cables with a
horilontal span of 200 m, stressed beyond 400 MPa, the value of E remains close
toEo:
1= 200 m
287
CJ 400 MPa
CJ = 500 MPa
E=0.80Eo
E=0.93 Eo
In that case, it is necessary to use stay cables capable of supporting high stresses;
the same applies at the anchorages.
6.2
.... "~;
.&3.
A .P. ...
288
289
7.1
16100
r.
~~.-:."
16100.
<0
~~,
384.00
The study of existing or projected cable-stayed bridges, shOWI three main ty~s of
structure, as a function of span. When the gap is asymmetrical, designers
generally tend to use cable-stayed bridges with an tectntrlc tOWlr. The balancing
span usually includes intermediate supports at small intervals, which contribute to
the anchorage of stay cables and increase the stilTness of the suspension. One can
quote two interesting examples of such structures (fig. 6.22):
-
~~~
for concrete bridges, the Hoechst bridge over the river Main;
for steel bridges, the Kniebriicke in Dusseldorf.
If the structure has to span two gaps close to each other and of approximately the
same length, one might choose a symmetrical tll'O-Spall cable'sta~d bridge. The
Ludwigshafen bridge (steel bridge) in Germany and the Ottmarsheim bridge
(concrete bridge at design stage) in France, are examples of this type of structure
(fig. 6.23).
Three-spall cable-stayl!d bridges (with two towers) form the third group of
structures. If the Opening is nearly symmetrical-which is the most frequent
case-these structures can have a very long central span. This type or structure is
the most common; the BrotoMe bridge (fig. 6.24(a and the Pasce>-Kennewick
bridge belong to this group; the Mindin bridge in Saint-Nazaire, Is an example of
such a structure in steeL
the section over the side support, because of the continuity of the cablestayed bridge and of the access viaduct;
the section under the tower;
the section at midspan of the central span;
the section at 0.4 I in the side span; the value of the variation of moments in
this section usually determines the size of the cross section.
We will examine the influence of the main geometric and structural parameters
on the stress distribution in the bridge:
300.31
Fig. 6.22 Example of a cable-stayed brid&e with eccentric tower: the Hoeehst
bridle
290
.~~
291
--rt
--; i
.-4 !
'>I_I1
I
.
I
I
I
~0~l4000i
... .....39401
iii
:g
11
1'
I.
.&J
Fig. 6.25
g
2
j ~
a.l
j
1I
I, I,
oS
:9
...
I~-r
r
.q .
,..
1l>.
.; I ~! i
~--P-l
.: i, : i
.,....
jj
.&J
![
~
:,
,"
;.
~:i I
II
-5
....
o'"
c.."
n:~ i .
ij
U!
M
<
;'
iT
I
1
~jl
~t
'-'
'It
N
.Q
.~
LI.
119.40
-JI
g
c
Illr!t
. I.
,...-----~---.
280.00
I
I
WI 40 __...
All example of a side span with closely spaced supports (Rio Caroni
bridge)
Qsg
6730
Heovlly slressed sections
,.......--:
'.
1l
i;'
1il
U
i U:0
'"
'"'
O--I-~
r!t
e
-
Iii
t-~
I
_I
.Q
-8910
Side span
Fig. 6.26
eenhol SIlO"
The ratio IlL usually ranges between 0.4 and 0.5. The curves in figure 6.27
show that small variation in this ratio leads to large changes of bending moment
in the highly stressed sections.
The shorter the side spans, the more limited wiJI be the variations of moments
there: to the obviolls effects due to span shortening, can be added the increase of
number of stay cables, whose efficiency is increased by a more rigid anchorage
near the side piers. It is tempting to bring the IlL ratio to below 0.4 but, if the
shortening of the side span improves the behaviollr of the deck, the corresponding
292
293
-1375
I
Imposed load: 1t1m run over
centrol span
1t/ml
t
t t t
t t"
,,'~FU"Y fixed
I
I
~800
1250"
I
Loaded side span
~
~ddltloflol
IJ..'
T
f
-1390
-1040
. 'I
1tlml
.4~
~rITIl"I-I.r-....- .. /l-n
\.
"
"'-__
--=
~
----~ -75
50
,'-'660
Simply supported
Fig. 6.28
1314
increase of the lifting reactions under the side supports creates new technical
problems.
It seems advisable, whenever possible, to ensure conti""lty between the cable
stayed structure and its access viaducts. By rlXing the tide .pans at theit ends. the
variation of moments is reduced (by about 25%) while an eJeaant solution is then
fOWld for the problem of deck uplift on the side supports (rll. 6.28). Furthermore,
during construction. this system decreases the 1eDlth or cantilever beams to be
built from the main pier-this point will be further discussed in paragraph t 1.
Regarding the deck support conditions over the main piers, figure 6.23 shows
that simple support and fixed supports lead to extremely different results.
In the first case, the bending moments over the supports remain small, but
those created in the side span are relatively high, as the forces are acting on this
span. On the contrary, in the second case, the bending moments over su pports
become significant, whereas the bending moments in the side span are effectively
reduced. But the strength of the deck can easily be improved with little cost by an
increase in the dimensions of the sections near the supports. Also, jf the main piers
are sufficiently high and flexible, it is essential to have full fixity of the piers. In
practice, partial fixity of the deck to the main piers will often be beneficial: it
brings a compromise between the extreme solutions. The BrotoMe bridge deck is
partially faxed on the main piers by a ~rown of neoprene bearings (fig. 6.30).
294
295
2.60
.~
~~~9;6
I
i
I
-1200
~-146
Loyout of bearings
350
Pig. 6.29
8 SUSPENSION
From a construction point of vicw,Jzxing the tower is the most simple solution;
the tower stability is then achieved even before positioning of stay cables. The
ratio hiL depends only on the type of cable-staying, as we wiU see in the next
paragraph. However, hIL is normally close to 0.2, except for structures with small
spans when the ratio can be considerably higher.
If previous choices seem obvious, this is not the situation for the respective
stiffnesses 0/ deck and lowers. However, it seems that there is an equivalence for
"the ~tresses induced in the structure, between a bridge with a stiff deck and flexible
"towers (e.g. the Brotonne bridge) and a bridge with a flexible deck and stiff towers
{e.g. the Pasco-Kennewick bridge).
To demonstrate the importance of this part of the structure on the cost, it can be
said that the coat of suspcDlion at the Brotonne bridge was 29% of the total cost
of the main structure, whereas the tower was only 496 of the same figure.
8.1
8.1.1
Cable-staying arranaements
296
Radial layout
297
F~I
h;
Si
.!!.:...!!
A,
(T
_x,_o_
cos a,.
28qux;
8qulj
Pi. as;A;
Hor
tu
.I~
sin ai
(T
Fig. 6.31
III
1 .
Fan layout
sin ai cos OJ
t:f
sin 2a;
Ai
- fan layout, where cables are regularly spread along the top part of the tower
does not differ much from the previous one, and has the advantage ofeasier
anchoring, because the cables are further apart;
- harp layout, where the cables are parallel to ca~h other, reduces the risk of
tower instability, as the pAssage points through the tower 4te spread alOftg
the whole height of the tower; this allows simpler construction procedures
as the incidence angle of the cables is constant. From the aesthetic point or
view, this is the most elegant solution for cablestayina with two parallel
planes: the cables remain parallel whatever the angle of vision.
Genera]~Yt the deck suspension is stopped over a certain lenlth on eithtt side or
the towers and of the central span (partial suspension, as in tht Brotonne bridge);
but in some projects stay-cable anchorages are spread continuously alona the
deck~ the deck is no longer supported by the piers (total suapenslon ,,& in the
Pasco-Kennewick bridge). However, it is advisable to reduce as much as possible
the length of the main span which is not suspende~ as this area would then
require important internal prestressing, with adverse redundant effects. The three
fI,.
~v
!iF
!if'''tna;
~Yi
~u ~.
'Ai
tierS;
!:lX,
&
sin aj
~v
tiy;
P; -
Fig. 6.32
~)..iCOS
Xi
Qi
298
over the horizontal, is an inverse proportion of sin m,. This weight will then be
minimal when llt = 45 0.
In the same way, if the efficiency of stay cable A,B, is the ratio P, of the
reaction at deck level over the vertical deflection Q, at this point, it appear. that
the efficiency is proportional to sin 2 Q, cos llt and maximum for a value of Q, near
55 .
If the weights P, of all the stay cables is added, the steel weight R in each ofthc
three suspension types can be compared by a graphical representation of their
variations in relation to hlL (fig. 6.33).
By studying the corresponding curves in the case of total deck suspension, one
cnn notc that:
the minimum value of steel weight is achieved when hlL is equal to 0.29
with a radial system, or 0.50 with a harp system (in this case, this is the
absolute minimum value as all the stay cables are at 45 with the
horizontal);
the radial system is more economical than the harp system when
hlL <0.30. In the usual case of h/L =0.2, the steel saving i. 18%. Beyond
hlL =0.3, it is the reverse, as the decrease in cable length is compensated
by an increase in the cross section area due to a smaller angle of incidence;
the fan system gives similar results as the radial system when
.-
<h/L
system.
0.15
hl~ROdio'(R)
I
L
I
When h/L
>0.2
A comparative mady can be made in the case of partial suspension o/the deck.
The above comments are still qualitatively valid, but the weight of sted is
decmmd: a. the deck is partially supported on the main piers, some of the
vertical load. are directly transmitted by bending over a length nearly equal to bo
(fiS. 6.24(b.
Finally, if' the length near the tower without stay cables (bo) is equal to one
tenth of the length of the CCIltral span L(bo = 0.10 L}, the saving in steel due to
partiallUlpal.ion can reich 20%.
Tho following chart alvo" for an /tIL valuo of 0.20, the values of no/96Ll
corresponding to different cabling systems.
Partial suspension
Total suspension
Radial
Fan
(R)
(F)
Harp
(H)
Radial
(R)
Fan
(F)
Harp
(H)
1.23
1.29
1.45
1.01
1.05
1.19
Radial cabling
In .... q8LI/... 1
~Horp(H)
n = 2(b _ bo}
~Fon(F)
1.4
L- 2b
4q6 1
n= 2(b -b o} -0 -k
o
1.0
I
-----j-
?ol
--: II
0.1 0.15 0.2 0.25 03
0.4
h2(b - bo})
I .
-(I + k 2Xb 2 (2'
L-)
h
h
Harp cablina
--:1
0.5
b-bo
lVith k =- - and k';: kho - bo
h-ho
~!j--- ~1-1---.11
0.2
_bt)
Fan cablin&
1.2
<0.25.
...
0.8
0.6
0.4
299
0.6
h/L
Fig. 6.33 Weight of suspension steel for different stay cabling systems (total
suspension)
n..
-b~}
..
300
Transversely, the stay cables can be placed either in a single plane in the deck axis
8.2
The
02
~atetol
03
suspension
I
!
!
b1
Fig. 6.34
II
.,.I
b2
b3
Sl,l Y en hies
per tower,
placed ill a fan layout, anchored at both ends in the deck and crossing the lower
on saddles which form a fixed point.
The stay cables are made of stranded prestressing cables. threaded in steel
ducts and grouted with cement. The number of strands ranges from 39 to 60 from
the shortest to the longest cable. The steel duct has a standard external diameter
of 165 m and a wall thickness of 4.5 mm. Continuity and water tightness of the
ducts are ensured by welding, and the protection against corrosion by two coats
of paint.
The ducts are strengthened at sections where the cables are fiXed into the tower
or the deck so that they can resist ~he flexural forces induced by cross winds or by
the structural deflections under imposed loads. The anchorages of the stay cables
into the deck have two main purposes:
AXIal suspension
01
301
b4
The stay cables are not fixed to the deck so that their positioning can be changed;
302
Ii
Section B.B
...
r;
~
~ .,ffJ>;'\
.
~
II
IA.
303
they can also be replaced in cue of ~amage. Stay-cable tensioning is done by four
12 T 13 parallel jacks. A hydraulic jack, designed for this project, allows varia
tions in positioning by acting on the screw which locks- the anchorages (fig. 6.3 S).
Pigure 6.36 shows the changes in tension in the shortest, the middle and the
longest cablC$ during construction. It can be observed that the maximum force in
a stay cable, under permanent load, is sustained just before tensioning of the next
cable, and that this value i. seldom equalled under working load (except for the
longest cable).
In terms of construction, the BrotoMe bridge presented two problems: the
positioning of the stay cables and the bVcction of grout.
A lightweiaht carriage system, supported from the cabla above the one under
consideration, allowed placJns of the ducts in 12-m IDng sections (fig. 6.37). More
difficult wu the threading of the last strands of the last stay cables, not only
600
500
:: 4
End plole
!
.5
'"
~~OO
8
'0
c
0
'ilI
200
100
'0
.....:.J.Tl.TJT.l.TJ:;.t;i-LTa..;:J.:rfr~ttrT.-!:T:!:T:'-ir5-5*ij
~tj
I! ~
VOllable
Imposed klods
"'-'."'J~:":C;'~
304
305
9 TOWERS
9.1
The towers are concrete elements submitted to high compressive forces because of
the vertical components of the tensile forces in the stay cables; and in conse
quence they pose a significant risk of geometrical instability. Their longitudinal
arrangement can be of the flexible type and have a single vertical element; or be of
the rigid type with an Aframe tower (for example: the Maracaibo bridge)
(fig. 6.38). Their transverse arrangement depends on the type of suspension, axial
or lateral; it can take different forms (fig. 6.34):
one or two vertical towers;
Aframe towers;
portal towers.
Bending of the towers can happen in both longitudinal and transverse direc
tions. The longitudinal flexural forces are caused by permanent and imposed
loads. To reduce these forces, the adjustment bfthe cables under permanent loads
attempts to eliminate the bending moment at the foot of the tower, by balancing
out the horizontal components of the tensions in the stay cables placed at that
level.
The only longitudinal bending moments induced in the tower in service come
Fig. 6.37
because oftheit length (340 m), but also because the ducts had a eonstant section
for aU the stay cables, while the number of strands increased.
Grouting was done in good conditions, despite the proportion of the ducts
occupied by strands, the length of the cables, the difference of level between the
base poinfwhere grout was introduced and the saddles on the towers, and the fact
that the total volume of grout, taking the duct diameter into account, could have
led to clogging and segregating problems, which required some complicated
adjustments.
,
The pressures requited for grouting rarely exceeded 35 MPa because 01' the
thixotropic role of the additive.
II ~
306
307
from the highway vehicle loading and the effects of temperature and moisture.
The transverse bending moments come mainly Crom "'ind effects; the wind pres
sure can be very significant as the towers can be very tall. The bending oC the
towers and geometrical stability are conditioned by:
-
9.2
For construction reasons, in concrete structures. the towers are usually fIXed at
the base, either in the deck or in the main pier. The flexural forces in towers are
much higher in the case of harp systems than in the case of fan systems; this is
shown on the bending moment diagram for the two cases (fig. 6.39).
In the example under study, the towers are fully fIXed at thcirbaso and the stay
cables are fixed to the towers. The more favourable behaviour oC fan systems is
explained by the specific role played by the cables near the abutments or the bank
piers: they act as holding cables, restraining the movements oC the top of the
tower. In the fan system, where the cables converge near the top ofthe tower, and
load ploccd on the centrol span is directly trunsmlued to the holding cable, and the
only flexural forces applied to the tower are the ones due to the lengthening of the
cables. On the other hand, in the harp system, loads placed near the quarter point of .
the central span can be transmitted to the holding cables only by the combined effects
of extr~ tensioning ofthe nearest cable andofflexureofthe tower.
The stfffness of the tower has only a small effect on the flexural forces as is
shown in figure 6.40(a).
__
Fig.
~I
101
(b)
Pia. 6.40 Lonaltudlul bendina of the towers: (a) Influence of the tower stiffness;
(b) Influence of stay cable connection to the towers
In the case oC a bod aupport, the stay cables can be tenninated at the tower
and attached to it, or colllilUlOlU through the tower; they would then pass over a
saddle or throuah an encaled stccJ duet. The support fixity is ensured by cable
friction or by special flxinl s)'Item (iii. 6.41).
AI the toworl aro usually .ufficiently braced by the stay cables which alway.
includo ono or more fixed polnta, deformations under the applied loads remain
small; these second order dTects can be neglected when checking for longitudinal
bendin&
9.3 Transverse bendial of the tower
Because oC the extreme beiaht or the towers, it seems advisable to estimate the
wind effect. according to the French 'Snow and wind regulations 1967' rather
than according to the 'Ministerial circular' which gives a constant pressure of
2 kN per square mctrc of exposed area. It is best, whenever possible, to refer to
the maximum speeds recorded on site.
The distribution of the tower drag coefficient by the 'Snow and wind regulations'
is not very accurate; it is therefore advisable to check the value of this coefficient
experimentally in a wind tunnel; but most often, this experimental valuc is lower
than the 'Snow and wind relulalions' estimate. In the case of cablestayed bridges,
the forces applied by the wind on the stay cables cannot be neglected. The drag
force on the stay cable is a function of Reynolds number R. and therefore, for a
wind velocity V and a diameter d oCthc stay cables (fig. 6.42):
Vd
dVq
::: 4.04
v
,
R, ::: -
-.,
....
< .
,~.
308
309
'Snow and wind regulations' distinguish three different fields, each corresponding
to different values of the drag C,.
When V == 45 mIs, the minimal value ofthe drag coefficient is reached when
dyq > 1.5, i.e. when d) 135 Mm.
It can be noted that the dotted curve in figure 6.45, which has been drawn from
measured values of the drag coefficients, has an absolute minimum when
d == 1SO Mm. A siightly larger diameter of the stay cable i.e. d = 160 mm, is then
the optimum in the case of a wind velocity of 45 mls. Fot maximum wind
(I)
(0 )
(b)
Fig. 6.41
v
~
----..
Ct
12
.....
..... ~.~r~:-:J:..-t:
".:,
II
10
0.7
0.5
_.+._.
(c )
O.Z
(d )
~t~- ~=:_=t--"'~-----'J~'.r;.1- i :
00
jl 1
~---_,...----
,~.
Expertmentol
1'\..;.....;..-......
4 6 8
I4
6 8
meo~uremer"s
-.1---1- ~ I---J . tJ i
:.. . ...
-- 'I r--- \,' -------r.::--
//.
..
I ':.
==
! '
t\ I;
1\ .~ .
- - ---'1-- - _.-' --
04
'-J~
'I
0.8 - .
=E
=::
6 8
Re: Vd/,..
13.5
Fig. 6.42
L__ ~l Ll , J J
VaJue
10
20 30 50
100 200
d ( em )
310
velocities encountered on site, between 30 and SO mis, the diameter of stay varies
between 120 and 200 mm.
If the stay cables are close to each other, the velocity of the airflow is increased;
this leads to higher pressures than in the case of isolated c~bles; this phenomenon
must be taken into account-When the transverse structure of the tower consists of
one or two isolated masts, one must take the second order deformation. into
account when checking for bending caused by wind pressure. On the contrary,
these deformations can be neglected if the towers arc of the portal or rigid
Aframe types.
9.4
The problem of geometric stability of towers is critical mainly if the towers com
prise one or two Isolated masls; the transverse stability is the most critical.
Before occurrence of any transverse de/orlnatlon of the tower, the stay. cables
are situated in a vertical plane detcnnined by their anchorage points in the deck
and the points of passage through the tower. For each cable, this plane becomes
inclined in the case of tower deformation, but its projection on the plane or the
deck always crosses the centre of the tower foot; this creates a recoil moment
(fig. 6.43).
- loadlnl combination.
Tho second order deformations are evaluated, taking into account concrete
cracks, 'the effect of reWorcement on the stiffness and creep correspondini to
service loads. They arc determined by neglecting the concrete in tension and by
aivinl to the coner", In compression a stress-strain diagram of the rectan&1e
parabola type.
Checkin. of the limit atate can be done according to the 'General Directives
relatina to calculation of structures dated 13.12.71' which is compatible with the
new .omiprobabUistic theories on safety. It consists of showing that there is a state
or strOSI whorl the calculated forces arc compatible with the calculated material
strenatb.
Tho loads applied to the towers will be introduced with specified i1Jit;al
eccentricities (flS. 6.44).
N,
Construction errors
Error in verticolity
N2
lmm/m
.
<
Inilial
/
ec:c:enlric:iliel
11
311
~/OO.035m
Error in strO;9htneu
R 200h
\1'
7~=-
85\
9
Hin
I
I
, * 50C
~
II
,* 3O"C
..c:
20r;::\
.... /
... ,.~
c
Fig. 6.43
10
Fig. 6.44
312
thermal effects:
to high axial forces, nearly 9000 t of permanent loading and 10 000 t maximum
imposed load; this leads to a mean permanent compressive stress of 9 MPa.
Because of the small cross section of th,e tower, the reinforcement is very dense:
it can reach Soo kg/m J at the level of the ,tower foot; it is on average 300 kg/m J
At first it was planned to use HEB steel joists, which could give a high concentra
tion of steel in a small area. After further study. it appeared preferable to use steel
bars of 56 mm diameter. which are less cumbersome and avoid the use of con
necting plates. The last problem concerned the continuity of reinforcement. The
usual overlap of such bars could not be envisaged near the face of the tower; nor
could continuity by welding be contempla'ted. Eventually the continuity of these
steel bars was ensured by mechanical sleeve connectors.
The process consisted in mounting at the end of the lower bar a sleeve inside
which the upper bar was sealed by a resin. The cOMection of the sleeve to the
lower bar was done on the ground which caused little difficulty; had this operation
A temperature difference of 10C between deck and stay cables will also be con
sidered.
F or checking of the ultimate limit statet the concrete and tower reinforcement
are usually highly compressed; the tensile stresses in the reinforcement remain
small. even under limited wind effects. It is advisable, for tower construction. to
use well-compacted cOlfcrete placed inside sllp-[orm shuttlrlng (sliding shutters
must be avoided). The tower reinforcement will preferably be or high tensile steel
of large diameter \vith continuity ensured by mechanical connectors (threaded
sleeves, mounted sleeves, smooth sleeves with injections of cement grout or resin).
,
J
..
stCT~"
{jH i
! ~
-.
~i
............,..."....
.....
.. .
0 ': .
IfCflONCC
'I'
..... ..,....
' ..
_ It.
-.
StClI~OO
A1
~(
..
I
I.
! c=
JIt4 t\
,It
~.
."..'"
( ~,.
. ,,:
...
~l
Fig. 6.45
313
314
been made in the air on the upper bar, amidst all the reinforcement, it would have
been almost impossible (fig. 6.46).
Complete continuity in compression is ensured by direct contact of the bars,
while tbe continuity in tension (the tensile forces arc small) is ensured by the resin.
The towers arc built in slip-form formwork, with 3m lifts. The error in verticality
at the top did not exceed 40 mm, and the average compressive strength of the con
/.
I
1"1300
Ib)
Ie)
~~
'<:Zb~
Id)u
r----- ._ _. __..
18.00
(0)
.:::_--1:
(0)
.,
c",
I
I
I
'" ~
jl_.-.-:.u," ~
18.00
(b)
18.00
(0)
The transverse cross section of the deck of a cable-stayed bridle must comply
with a certain number of requirements: lightweight, sativactory aerodynamic
stability, and ease of cable-stay anchorage. The design of the transverse structural
section differs according to the type of deck suspension: lateral or axial
suspension.
. In the case of lateral suspension, the plane of the cables can be placed outside
the deck working-area, or within the sidewalks, if any. An example of the first
solution is found on the Pasco-Kennewick bridge over the'Columbia river, Wash
ington State, USA, with a central span of 300 m.
The deck cross-section comprises two triangular section box beams, placed at
the sides and joined by a top slab with ribs positioned at 2.7 m interval (fig. 6.50).
The side box beams give anchorage points which are independent of the rib
distribution.
When the stay cables are placed inside the walkways, the cable anchorages can
directly transmit the forces to the webs of the deck. Such a solution was used on
315
200/2.50
-l
r;7i
I
(c)
( d)
the Hoechst bridge on the river Maine; this deck carries two roads and a railway
line (fig. 6.51).
In this case. al 'In the case of an axial suspension. a tubular section is most
appropriate, because of the high torsional stiffness. The projected cable-stayed
bridge at Ottmaraheirn. with an axial suspension, comprised a box girder with
three webs; the stay cables were anchored in the lower part of the central web (fig,
6.52). One of Ihe main features of this design is the top flange which, because of its
large span, was ribbed in both directions, the main ribs being placed transversely.
."i_.. . ~._. .~" JlC'aj_;;'~
316
317
Cross section
24.40
30];7 I
j~
:::
(,()
(Jt
~.10
15 to 20
6.00
.1..
12.40
..
I..
6.00
oo
",
'.
\,J
5241
. -.---- .J
"
~~~'---e.--.-._---. . ---.- . .
318
I:
"0
'75
,.
319
23.00
."
~,oE~r ~ J1
4
I.
Fig. 6.52
:!~
7.25
.1
7.25
j'
or lbe
23000
i.
9.75
..
_,
;.3.50.:.
"I
9.75
Fia 6.5$
113
I
Fig. 6.53
----
9.00
....
,/
Toptlonge 12~8cobles
K~V
./
_ .
L
"'..'
'.
'.
::~/
Precast web 4 ~ 8
tenSioned stirrups
'/
Y. .-
Props 12 T 15 coble
19.20
'j
II
11
. . . . - - . . . .VV
Fig. 6.54
i......
.""""
~,o'"
CONSTRUCTION PROBLEMS
.,,--,..-~
320
11.1
321
A symmetrical bridge with two spans is the most simple example. Such a structure
is, in fact, constituted of balanced cantilevers of total length equal to twice a span.
Because of these large dimensions, the stability of the balanced cantilevers from a
static or aerodynamic point of view, the deck must be fIXed at the top of the main
pier. The fixing mechanism must be capable of supporting very large forces.
"
In the case of the Oltmarshelm bridge, the balanced cantilevers would have
been 330 m lon&: these forces in the deck fixed at the very large and stiff pier
would have been much higher than the forces which would have occurred during
the service life of the decks. Because of this, the tendency is to design, whenever
possible, total or part/Qljlxlty of the deck at the piers; furthermore, this arrange
ment saves designing the most sensitive part of the structure for two different
systems of forces: during construction and in' service.
We can also observe that the continuity of a cable-stayed bridge with access
viaducts is advantageous from a construction point of view.
(2) Construction of the main balanced cantilevers to the junction with the lateral cantilever
(I)
322
323
11.2 Effect of inaccuracy in the weight of the segments and In the tension of the
stay cables
The fonns of the mobile concreting carriages, or the precasting formwork of the
segments, caMot be absolutely identical, or precisely adjusted during the con
struction of synunetrica1 clements of the balanced cantilever system. Some varia- .
tions in the segment dead weight and in the tension of the stay cables are unavoid
able (taking into account the precision and accuracy of gauges used on site).
Despite the transfer of forces from one cantilever to the next through the tower
and the suspension, the. randomness of weight of the segments brings a severe
additionalloac1 The same applies, to a smaller extent, to the tension of the stay
cables.
Figure 6.58 sho\ys the distribution of bending moments induced towards the
end of the construction of the balanced cantilevers, in th~ deck and tower of the
Ottmarshcim bridge by a 196 accidental increase of the weight of ~he segments of
one cantilever. The additional stresses in the lower fibre, near the main pier arc
close to 1.2 MPa; because of this, during the design stage of a proj~t, some
important margins must be made in the limiting stresses and the weiaht~ of the
segments must be checked during construction (for example by checking the
su pport reaction at the ma~ pier).
730fm(leff deck)
Franoc.
Pulli1\9 rod
Sleel nose
mA
~J~I~!
~~j
n
n
r:===:~!riWi iF.&.:==
.
Fig. 6.58
P'et3
,.-.-
'c'.~
- ........
_"if"~~.",f;.J~~.
, .
324
325
th~ operations are continuous and are made from the part of the deck
which is already built. Access for staff and plant is then easier, without any
interference with the ground; this last point is of major interest in the case
of urban viaducts passing over numerous obstructions;
the supports carry only vertical reactions during construction and are not
subjected to asymmetrical bending moments; this avoids the need for
temporary supports;
this procedure is well suited to the building of structures with a constantly
changing shape (curved bridges, for example).
3
~c
:w
.~
I'd
Cl
, I
6
~
.0
It
._~
it cannot be directly applied to the construction of the first span, which then
presents a special problem (construction on falsework or cantilever con
struction from the abutment);
the forces applied to the deck during' construction are very different (in sign
and in value) from those applied during the service life of the structure.
Consequently, it is necessary to use a special system to maintain reasonable
internalltresses and to reduce the unproductive costs caused by temporary
prestreulng. Intermediate supports can be used, but the most common
Kolution is a tower supporting stuy cubil!~' as In the case of construction by
incremental launching. But in the case of progressive construction, the
tower and stay cables move from one pier to the next, instead of moving the
whole deck stayed by cables in the front portion.
Furthermore, It can be noted that during deck construction the supports arc
subjected to a maximum reaction under dead weight, which is double that
corresponding to the flnal system of forces. But this circumstance generally does
not have a critical consequence on pier and foundation design, as the efTect of the
dead weight is rarely more than half the total load including the inOuence of
horizontal forces.
When segments are concreted in situ, progressive construction is a slow
process, ns only one working position can be used instead of the two employed in
trnditional cantilever construction. The lack of speed can be counterbalanced by
an increase In the unit length of segments; but there is an obvious limitation due to
the weakness of fresh concrete. It is then preferable to use precast segments with
match-cast glued joints, as by this method one can reach speeds similar to those
achieved with launching girders.
Some conclusions can be drawn from the Rombas viaduct construction, which
was the first application of this method. Positioning was carried out by a swinging
jib lining the segment, which was conveyed to the finished part of the deck on a
truck. The jib positiqned the segment in its final position after application of the
glue (fig. 6.61).
--
.wau:_,
=4L4JG'.44i;~J
326
327
About one-third of each span was built following the cantilever method, with
final prestressing over the support. Beyond this point, a pair of temporary stay
cabloa wu placed at each scgmentj the tension in the stay cables (140 t) was
desipcd so that ita vertical component exactly balanced the weilht the ICl'
mentl (4' t): the deck wu then submitted to additional normal loads, as placing
progresses.
The only variable forces applied to the deck were the weight of the swinging jib
and the forces due to the movement of the segment along the deck. Figure 6.63
ShOWl, in tho cuo of a 33.5.m span, the portion of the loads which is taken by the .
stay cablos and by the deck when a segment is placed above the next pier; the
weight of the swinging jib is taken into account (total weight = 80 t). The deck
carries about three-quarters of the load, the rest is taken by the variation in
tension or the stay cables; this variation docs not exceed one tenth of the stay
cable initial stress.
Several other structures have since been built in this way: the Fontenoy viaduct
was one example.
Progressive constNetlon is of sroat interest for the span ranse 30 to 50 m,
where it compete. with construction by incremental launching and where
traditional cantilever construction is .tllJ not economical.
or
Trcnsport truck
~~PICCing
. lU- _
j;'
1000
Stressing
Staycabl. anchorages
80'
Fia. 6.63 Progressive construction-'forccs in the stay cables and in the deck
328
12.2
329
or arch bridges
PrincIpal pIer
~o
.__.1.
.~:~
25
i:i..__i....
::
l...
410.00
I ....
14
Fil.6.64 Construction of the CaraclS viaduct
26000
;)0
330
- ---_
~$~'
};:....
S~\~ ;,:~"l"l(l
--_.-
6700
..
' ......"",,,r-.':'-
..................._
331
"
.
mC'n
.j~~\.'
..
\1(1(1
;
:1
'.....'"
,.
V\.I
n' ! UIT11P.:=~~~Il7~'{Y.
~o~
.. ~
I
..... - - y l
I
'I
I
!..
26800
I:'
39000
~._
_
:!3 50500
1140
I~~
?44 00
pli-Jill9-~
500
1140
,~-,I
0
. - ;:400
635
. T
480 .
]650
..
'~.~
1'3.00'
800
252.00
~_J~7'
-;-:='7
flGllI ~
Fig. 6.67 Construction for the construction of an arch bridge
3750
190.00
115.00
~"'\ :;
.I~,
170.00
.1
c~bles
3750 ..
..
(0 )
I:
7360
33000
"2>0
..
T-!l'O -I
~
~30 ~=={lm
~
'Sta.. MWj 55
'i5';;;
(b)
Normal concrete
LiQh'wei9hl concre'e
Fig. 6.68
intenncdiate piers of which the taut diagonals are the temporary stay
cables.
This scheme was adopted for the Hokawazu bridge in Japan which has
span .of 170 m. The segments of the arch and the voided slab. which form
the upper deck were concreted into place from mobile carriages (fig. 6.67).
332
Finally, in the last scheme, the weight of the lattice structure is reduced by
setting up the upper framework from only temporary stay cables and not
BIBLIO'GRAPHY
BOOKS
GUYON,
(1968l.
2 ARTICLES
334
MATHIVAT
J MONOGRAPHS
La reconstruction en belon precontra;nt des ponts sur /a Marne, J.
CHAUDESAIGUES (Annales ITBTP, 1/1952).
La recolls/ructioll du viaduc de /a Vou/le, N. EsQUILLAN (Annales ITBTP. 7
8/1957).
Bibliography
335
L, vladuc de fa Ylosne, A.
GOUDEMANO,
Travaux, 12/1972).
LeI nouveaux POlltS sur fa Loire
12/1972).
Les viaducs de l'autoroute EJ, J.-F.
a Tours,
H.
GRELU,
R.
PERZO
(Revue
1978).
The Brolonlle Bridge, J. MATtllVAT (Proc. FIP Congress, Vol. 2 p. J 64, London,
1918).
The Colulnbia River Bridge al Pasco-Kennewick, F. LEONHARDT (Proe. FIP Con
gress Vol. 2, p. 144, London. 1978).
The Rip Bridge, A. FRIED (Pree. FIP, Congress, Vol. 2, p. 154, London, 1978).
Le ponl sur /e canal d'A/sace
Ottmarshe;m. B. GREZES, P. FA ESSEL, R.
JACQUES,
J.-P.
TEYSSANDIER,
M.
VUa.LOOEUX
crcss, London.
La reconslructioll du ponl de PUleaux sur /0 Seine, M. DUFRESNE, M.
FaoESTIER (French contributions, FIP Congress, London. 1978).
Le pont de Tricaslin sur Ie canal de Donzere-Mondragoll. M. PALCJO'
(French contributions FIP Congress, London, 1978).
Les viaducs du COIUournelnent QUlorOUlier de Nice, J. BUFFA (French contribu
tions FIP Congress, London, 1978).
337
INDEX
Accidents, 166
Aerodynamic stability, 283,301
Amsterdam-Rhine Canal, 20
Anchorage cables, 71
Anchorage plates, 82.84
Anchorages, 81, 87, 92, 273
mortise and tenon, 24, 2S, 26
prestress, 86
steel plate, 83
206.214,277,279,288,289.291.
293,295,296,301-4.309,312-314.
317-321
longitudinal stNcture-general
arrangement, 288-294
278-282
nomenclature. 290
336
two-span, 288
Chatey bridge, 7
224,245,246,247,25J
Choisyle-Roi bridge, II, 12,41, 78,85.
96, 134, 135, 160, 221, 222, 228.
230.233.259
Clichy hridgc.19S, 202. 204
Continuity of deflection, 33
Continuous structures. 41-46
Core, 223
Corrientes bridge, 282
Corrosion protection, 273
Countermould, 223
Counterweight. 22
Courbcvoic bridge, 138. 139, 221, 222,
230.233
Courbevois bridge, 78
Creep, stress distribution due to, 115-125
Creep deformations. 120
Creep effects, 42
Creep forces, 123
Creep stresses. 1'21
Croix- Luizet bridge. 22
Curved bridges, 53
338
Deck design, 21-125
ceU form, 57
cell number, 56, 57
constant depth, 85
depth effects, 77-79
equivalent thickness, 75-76
final adjustment to structure, 95-97
longitudinal section, 76-79
span distribution, 47-53
special problems, 102-125
stress distribution due to creep,
115-125
thermal gradients, 112-115
transverse cross section, 54-76
notation, 67
transverse stiffening, 102-111
variable depth, 84
variable width, 64-65
Deck stability during construction,
126-189
analysis of requirements. 16D-16S
applied loadings. 165-169
assessment principle, 169-170
cable staying, 171-175
normal loading, 166
random londing. 166-169
statemcnt of the problem, 159-160
Deck support, 126
Deck widening, 65. 66
Deflection curves, 41
Deflections
of balance bm, 97-102
statically determinate, \/9
Deformation variations of concrete, 119
Deformations
at mid-span, 42
long-term, 43
neoprene bearings, 143-146
under constant load. 47
under dead load and prestress, 42
under imposed load, 43. 46
Deventer bridge. 253. 255, 256
Diaphragms,l03-111
displacement characteristics. 131
flexible. 128, 129. 130-143
sloping. 109
vertical, 109. 129, 141
Donmere canal, 26
Donzere bridge, 4, 5
Drag coefficient, 308. 309
'--"'
Dynamic stability, 54
Eccentric prestressing, force, 1.60
Elastic stability, 54
Felsenaubnicke, 58
Flevieu bridge, 78
Fiihlingenlake, 19
~l
..
339
Intermediate supports, 75
/ssyles-Moulineaux bridge, 204
293
deformation, 143-146
doublelineof,146-152,157-159
58,59,65,67,78,110, J II,
11I0-185.2J5
316
228,230,239.240
J>loullaMcl bridge, 4
beds, 220-222
267-269
placing, 232-264
'
.."'.
340
341
deck,233-239
deck. 239-242.
264-267
horizontal, 223-225
vertical, 225-226
Prefabricated beams, 18
Prefabricated construttion, 2
Prestressing rods. 7
Prestressing tendons, S. 9
grouting, 265-26 ~
Ravensway bridge, 20
Reinforced conc:ret~, .:
:52,267
Rio Cuaiba, 22 .
253.254
~Ol
Roquemaure bridge, S5
Rosal correction, 70
T-beams, S5
Temporary cables, 34
Temponiry staging, 33
267
176,117
SaintJeande-Maurienne bridge. 40
164, 177-189
Tendons
longitudinal profile, 94
prestressin&~
Shear strength, 56
Sliding connections. 36
StaticaUy indeterminatemotnents, 93
bridges
Stc:l structures, 3
Stiffeners, 103-111
Symmetrical construction. 22
..........
Torsional strength. 54
Tricnstin bridge, 28
Web arrangement, 68
Web spacing. 56
Worms bridge. 7. 8
Ulthnutc strength. 54
Zero moment. 46
Zoolcn bridge. 20
Urnto bridge, 17
U:;sy bridge. 5
Somt shape, 77
.:
I:
8, 9, 265-267
Vertical deflections, 4 I
Voisne viaduct. 63