Академический Документы
Профессиональный Документы
Культура Документы
MR
Vision
Vision plus
Register 8
Print No.: M2-050.031.01.09.02
Replaces: M2-050.031.01.08.02
S ie me ns A G 1 99 8
The reproduction, transmission or
use of this document or its contents
is not permitted without express
written authority. Offenders will be
liable for damages. All rights,
including rights created by patent
grant or registration of a utility
model _or_ design,_are_ reserved.
English
Doc. Gen. Date: 04/99
0-2
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 4
TD SD 23
Siemens AG
Medical Engineering
Contents
0-3
Page
1 _______General _______________________________________________________ 1 - 1
Read this first . . . . . . . . . . . . . . . . . . . .
Safety Note . . . . . . . . . . . . . . . . . . . . .
Magnet Overview . . . . . . . . . . . . . . . . . .
Transport dimensions . . . . . . . . . . . . . .
Floor Loading . . . . . . . . . . . . . . . . . . . .
Magnet environment. . . . . . . . . . . . . . . . .
Availability of LHe when the magnet is shipped cold
Issuing orders and transport procedures . . . . . .
Transport routes . . . . . . . . . . . . . . . . .
Issuing the order . . . . . . . . . . . . . . . . .
Inspecting the magnet shock indicators . . . . . . .
Checking the shock indicators . . . . . . . . . .
Damage during system transport . . . . . . . . . .
Important notes for the operation of the magnet . .
Component Overview . . . . . . . . . . . . . . . .
System components . . . . . . . . . . . . . . .
Explanation of the abbreviations used. . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.1-1
.1-2
.1-4
.1-4
.1-5
.1-5
.1-5
.1-6
.1-6
.1-6
.1-7
.1-8
.1-8
.1-9
1 - 10
1 - 10
1 - 11
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Page 3 of 6
TD SD 23
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.3-1
.3-1
.3-2
.3-3
.3-4
.3-4
.3-4
.3-5
.3-5
.3 - 6
.3-6
.3-6
3 - 11
3 - 13
3 - 14
MAGNETOM
Planning & Installation
0-4
Contents
Page
Positioning the magnet . . . . . . . . . . . . . . . . . .
Positioning the magnet within the markings . . . . .
Levelling the magnet . . . . . . . . . . . . . . . . .
Adding the aluminium shim plates . . . . . . . . . .
Setting the center height of the magnet . . . . . . .
Checking the galvanic separation of the magnet . . . . .
Removing the shipping brackets . . . . . . . . . . . . .
At the gradient coil . . . . . . . . . . . . . . . . . .
Between magnet and gradient coil . . . . . . . . . .
Sea Ship Kit Removal Instructions . . . . . . . . . . . .
Introduction . . . . . . . . . . . . . . . . . . . . . .
Procedure. . . . . . . . . . . . . . . . . . . . . . .
Air Ship Kit Removal instructions . . . . . . . . . . . . .
Instruction. . . . . . . . . . . . . . . . . . . . . . .
Procedure. . . . . . . . . . . . . . . . . . . . . . .
Determining the temperature . . . . . . . . . . . . . . .
General . . . . . . . . . . . . . . . . . . . . . . . .
Position of the carbon temperature sensors . . . . .
Flowchart for magnet installation . . . . . . . . . . .
Measuring the cryogenic linear temperature sensors
Connecting the quench tube . . . . . . . . . . . . . . .
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.3 - 15
.3 - 15
.3 - 16
.3 - 18
.3 - 19
.3 - 19
.3 - 20
.3 - 20
.3 - 21
.3 - 22
.3 - 22
.3 - 23
.3 - 24
.3 - 24
.3 - 25
.3 - 26
.3 - 26
.3 - 26
.3 - 27
.3 - 28
.3 - 30
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 6
TD SD 23
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 4-1
. 4-2
. 4-3
. 4-4
. 4-6
. 4-6
. 4-7
. 4-8
.4 - 13
.4 - 13
.4 - 14
.4 - 15
.4 - 16
.4 - 17
.4 - 18
.4 - 19
.4 - 19
.4 - 20
.4 - 21
.4 - 22
.4 - 24
Siemens AG
Medical Engineering
Contents
0-5
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.5-1
.5-1
.5-1
.5-2
.5-2
.5-2
.5-3
.5-3
.5-4
.5-4
.5-6
.5-7
.5-7
.5-8
5 - 10
5 - 11
5 - 12
5 - 12
5 - 13
5 - 15
5 - 17
5 - 18
5 - 23
5 - 24
5 - 25
5 - 25
5 - 26
Siemens AG
Medical Engineering
Register 8
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
M2-050.031.01
Rev. 09
04/99
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
Page 5 of 6
TD SD 23
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.6-1
.6-2
.6-4
.6-5
MAGNETOM
Planning & Installation
0-6
Contents
Page
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
. 7-1
. 7-1
. 7-1
. 7-1
. 7-2
. 7-3
. 7-3
. 7-3
. 7-3
. 7-3
. 7-4
. 7-4
. 7-6
. 7-8
. 7-8
.7 - 11
.7 - 12
.7 - 13
.7 - 14
.7 - 15
.7 - 16
.7 - 17
.7 - 18
.7 - 19
.7 - 19
.7 - 20
.7 - 21
.7 - 21
.7 - 22
.7 - 22
.7 - 24
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 6
TD SD 23
Siemens AG
Medical Engineering
General
1-1
The separate installation guide provided previously with the system documentation has been eliminated. Register 8 of the Planning Guide is the reference guide for the MR installation. The individual
installation steps are described in detail in the respective chapters of this manual.
Information regarding site-planning is contained in the Planning Guide.
The flowchart below provides you with an overview of the complete installation.
Install2
InstallationStart
Preliminary steps
chapter 1 (this chapter)
RF-room
refer to chapter 2
MagnetOR35
refer to chapter 3
Rem.systemcomp.
refer to chapter 4
Computer room
refer to chapter 5
Control room
refer to chapter 6
Cabling
Magnetcovers
refer to chapter 7
Start-up
Fig. 1
Installation flowchart
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 12
TD SD 23
MAGNETOM
Planning & Installation
1-2
General
Safety Note
The superconducting magnet described in this document is designed for use with whole body Magnetic
Resonance Imaging (MRI) systems. The magnet is designed for stationary use.
CAUTION
CAUTION
safety shoes
face mask
gloves (cryogenics)
leather gloves (RF-room)
Always
secure the transport device and load before moving the load
report defects to supervisors immediately
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 12
TD SD 23
Siemens AG
Medical Engineering
General
1-3
Never
NOTICE
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 3 of 12
TD SD 23
MAGNETOM
Planning & Installation
1-4
General
Magnet Overview
M-or35
Fig. 2
Transport dimensions
2508 mm
Minimum height
2411 mm
Width
2150 mm
Length
2264 mm
8000 kg
1500 kg
NOTICE
You have to add the diamensions of the transport tools which will be used.
NOTICE
For detailed smallest possible transport dimensions refer to register 5, chapter 1 of this manual.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 12
TD SD 23
Siemens AG
Medical Engineering
General
1-5
Floor Loading
Magnet environment
NOTICE
NOTICE
Just like the Impact magnet, the OR 35 magnet is usually shipped cold. No
time will be lost to precooling the magnet. Instead it can be filled with helium
immediately after it has been moved into the building. For that purpose you
should have at least 450 liters of liquid helium on-site.
NOTICE
Refer to chapter 3 in this register for checking the temperature and/or the liquid helium level of the magnet.
NOTICE
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 5 of 12
TD SD 23
MAGNETOM
Planning & Installation
1-6
General
All transport activities, including delivery into the RF room, should be performed by a licensed carrier
only.
Transport of the magnet or any other heavy components by SIEMENS employees is prohibited.
Transport routes
Before issuing orders to the carrier, the project manager and the architect/construction engineer must
determine the weight capacity of the floor along the transport route and in the temporary storage
areas. The architect/construction engineer must certify in writing that the route can withstand the
expected load.
It is the responsibility of the carrier to obtain information concerning the various transport routes
before the actual transport. Copies of the transport plans and certification must be provided by the
carrier upon receipt of the order.
The order for transport by a licensed carrier must be issued in writing. In addition to general
information (e.g., a list of parts, etc.), the order must contain the following data and documentation:
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 12
TD SD 23
Siemens AG
Medical Engineering
General
1-7
The shock indicators are located at the back of the magnet (right side, middle section) as seen from the
patient table. One is configured for 2 g, the other one is for 6 g.
Shock_3
Fig. 3
Inspect the shock recorders immediately on the truck when the magnet arrives at the installation site
(refer to the figure on the next page).
Check the condition of the shock indicators again after final positioning of the magnet in the magnet
room.
NOTICE
Siemens AG
Medical Engineering
Report the shock indicator status to OMT, Oxford, using the form and envelope enclosed with the shipment.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 7 of 12
TD SD 23
MAGNETOM
Planning & Installation
1-8
General
Shocki_1
Fig. 4
NOTICE
Inform the carrier immediately if you detect damage to the packing or the product.
After you have informed the carrier, send a FAX to the Oxford Shipping Department and to
TD MR in Erlangen. Indicate the nature or extent of damage in the fax. If at all possible, include
photographs of the damaged items.
NOTICE
MAGNETOM
Planning & Installation
Check all items against the packing list supplied with each magnet and notify
the Oxford Quality Department and TD MR in Erlangen by FAX of any shortage or damage.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 8 of 12
TD SD 23
Siemens AG
Medical Engineering
General
1-9
Important
Notes
Installation engineer/operator
Please read this first.
(Text is also listed below).
Fig. 5
It is essential that the installation/operators manual be read and understood before commencing any operation on the system.
Always wear protective clothing when handling cryogens and heed all warnings and safety
notices associated with cryogens and magnetic fields.
Before energizing the magnet, ensure that the ERDU is connected to the magnet and in full
working order.
Always ensure that the helium vessel is fully depressurized before removing any blanking
plug buffle set or fitting from the turret.
Always check that the current probe is connected for the correct magnet polarity before running current into or out of the magnet and ensure that gas is venting through the probe with
adequate flow.
Never leave a running magnet power supply unattended while it is in operation. Before removing the current probe, ensure the power supply is in standby and no fault lights are illuminated.
Always keep a log of any operation performed and record cryogen levels on a daily basis.
Never allow the helium level to fall below the recommended minimum.
10
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 9 of 12
TD SD 23
MAGNETOM
Planning & Installation
1 - 10
General
Component Overview
System components
ACCU
RF-Power
MR-ElectronicsCabinet
CCA
PCA
GPS
MagnetOR35
RFfilterplate&RFCC
Alarmbox
MRC
19"
15"
Patienttable
compon_1
Fig. 6
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 10 of 12
TD SD 23
Siemens AG
Medical Engineering
General
1 - 11
The installation instructions contain certain abbreviations which are explained below:
CCA
Control Cabinet
PCA
Power Cabinet
GPS
RFPA
ACCU
RFCC
RFAS
MRC
MR Console
MRSC
MR Satellite Console
SMI
CCU
RFSU
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 11 of 12
TD SD 23
MAGNETOM
Planning & Installation
1 - 12
General
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 12 of 12
TD SD 23
Siemens AG
Medical Engineering
2-1
2
Most of the modular RF-rooms used in Germany and Europe are manufactured by Siemens Matsushita GmbH & Co. KG in Heidenheim and installed by a team of Simon Hegele employees. In view of Siemens Med minimal involvement in these areas and the separate, detailed documentation available on
the subject, we are only providing General Notes for the RF-room installation.
NOTICE
However, you can always contact Siemens Med, TD MR 7, in Erlangen, if you have questions regarding the installation of the RF-room. The telephone numbers to call are ..-9131-84-3791 or 6201.
Safety
NOTICE
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 2
TD SD 23
MAGNETOM
Planning & Installation
2-2
General Notes
The RF-room and floor have to be completed before the magnet arrives at the site. Ensure that the
opening in the RF-room wall allows for easy transportation of the magnet into the room.
The contact surfaces of the RF-gaskets (used with particular designs) should be free of grease.
The nuts should be tightened with the torque specified by the manufacturer.
The RF-integrity of the RF-room must be measured (attenuation 90 dB).
The door contacts cannot be damaged.
The protocols must be filled out and filed with the other protocols (register 9 of the system manual).
NOTICE
The spectroscopy retrofit requires a second filter plate which includes the RF
wave guides for the gradient cables.
Depending on the location of the second filter plate, the gradient cables may
not be long enough. For this reason install the second filter plate in a way,
which allows you to reuse the gradient cables.
CAUTION
MAGNETOM
Planning & Installation
Dont forget the RF-gaskets while installing the filter plate for the copper-clad
or steel-clad RF-room.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 2
TD SD 23
Siemens AG
Medical Engineering
3-1
Additional information
NOTICE
Depending on the space available and the layout of the facilities, the cabinets
may have to be moved into the computer room before transporting the patient
table, magnet cover, and magnet into the MR suite.
Refer to the examples on the next two pages for further details.
The order of bringing in the system components depends on the location of
the opening for magnet transport plus the space available for magnet positioning.
If there is very little room between the sides of the magnet and the wall, move in the rear magnet
covers before positioning the magnet on its location.
Fig. 1
Handling of the rear magnet covers when the installation is from the front
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 30
TD SD 23
MAGNETOM
Planning & Installation
3-2
Move in the patient table and the front magnet cover before positioning the magnet on its location.
Patient table
Front magnet
cover frame
Raump_2
Fig. 2
Handling of the front magnet covers and the patient table when the installation is from the back
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 30
TD SD 23
Siemens AG
Medical Engineering
3-3
Checklist
This checklist ranges from the preliminary steps to moving/installing the magnet
Yes
Rooms completed
No
RF-room installed
Waterinstallation for
ACCU prepared
Final location of
magnet marked
Finalized transport
route
Required L-Helium
on site or ordered
Licensed carrier
informed/crane
ACCU
ACCU positioned
Magnet
Coldhead connected
checkl
Fig. 3
Magnet moved in
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 3 of 30
TD SD 23
MAGNETOM
Planning & Installation
3-4
Safety instructions
CAUTION
NOTICE
To ensure maximum safety for the personnel and the system, the chains,
straps, or other lifting devices, as well as the hydraulic lifts and the steel rollers must be in good working condition.
Read through this chapter carefully. It lists all the items/steps that should
have been completed or prepared before the magnet arrives at the site.
Installation Prerequisites
Transport Requirements
Ensure that the magnet room is ready and the RF-shielding is installed.
Ensure that the opening to the RF-room is large enough (refer to the Planning Guide).
Verify dimensions of the RF-room opening (height, width; refer to the Planning Guide).
Provide temporary storage for the magnet with sufficient floor load capacity
(refer to the Planning Guide).
Ensure sufficient space for magnet installation (refer to the Planning Guide).
Take into account obstructions due to dropped ceilings, support beams, and columns.
Determine the final magnet location in the RF-room (refer to the Planning Guide).
Verify that the water for the ACCU has been routed to the final location of the ACCU. In this way you
will be able to quickly connect the compressor. This is an important advantage when the magnet has
been shipped cold, and the cold head has to be connected immediately to reduce the boil-off rate.
NOTICE
MAGNETOM
Planning & Installation
The distance of the truck to the unloading zone determines the size and
capacity of the crane.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 30
TD SD 23
Siemens AG
Medical Engineering
3-5
The rooms have been completed. This means that the RF-room has been installed including
the opening for moving in the magnet. In addition, the room should have sufficient light and the
floor should be level and clean for easy transportation of the system.
The four corners of the magnet have been drawn on the floor of the RF-room (refer to Fig. 3-28
on page 22 of this register).
The floor from the unloading zone to the final location of the magnet in the examination room
has been covered with steel plates (min. 5 mm thick).
The tools and auxiliary tools must be on-site (steel rollers, hydraulic lifts, etc.)
Tools
Manruverable in
every direction
Fig. 4
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 5 of 30
TD SD 23
MAGNETOM
Planning & Installation
3-6
Tools required
NOTICE
Ensure that the measurement devices and tools are in good working condition.
Unloading
Fig. 5
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 30
TD SD 23
Siemens AG
Medical Engineering
3-7
Fig. 6
Fig. 7
Fig. 8
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 7 of 30
TD SD 23
MAGNETOM
Planning & Installation
3-8
Fig. 9
Location of screwss
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 8 of 30
TD SD 23
Siemens AG
Medical Engineering
3-9
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 9 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 10
NOTICE
Mag_1
Fig. 15 Attachment points of the chains
NOTICE
CAUTION
Attach the chains to the magnet as described under Domestic transport without crate (page 12 and up).
Lift up the magnet carefully out of the lower container and position it on the
four transport rollers.
Proceed with the transportation of the magnet into the building as described on the next pages.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 10 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 11
Fig. 16
Use four ropes or chains with a capacity of at least 3000 kg per rope/chain (length of rope/
chain is approx. 4 m).
Diameter
25 mm
Lifting eye
30mm
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 11 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 12
Shackle
NOTICE
Do not damage or tear off the connections on the turret or other pipes at the
magnet.
The transport rollers should be positioned on the steel plates by now (refer to
Fig. 20 on page 13).
CAUTION
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 12 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 13
Identify the front and the back of the magnet. Position the magnet correctly
on the steel rollers so that you do not have to turn it around in the RF-room.
NOTICE
Maneuverable
steelrollers
Aluminium
beams
Magnet
ANORD_1
Fig. 20 Configuration of the four sets of transport rollers
NOTICE
CAUTION
Siemens AG
Medical Engineering
Verify that the magnet and the steel rollers are balanced.
The steel rollers must not shift when you move the magnet. If they do, the
magnet may be damaged when it slides off the rollers.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 13 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 14
NOTICE
Mag_3
To facilitate moving the magnet, a manual or electrical cable winch can be used.
CAUTION
Ensure that the ropes attached to the magnet do not damage the magnet or
the gradient coil.
When using the cable winch, ensure that the magnet does not pick up speed
(especially when the floor runs slightly downhill).
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 14 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 15
NOTICE
Adhere to the distances required for the side panels. They may vary according to the size and layout of the room.
Position the magnet exactly above the markings on the floor (refer to the Register 3, chapter
1-6 of this manual). It is not necessary to draw the markings for the insulation and shim plates.
However, just before positioning the magnet, verify that insulation and shim plates are handy.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 15 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 16
Patient End
Service End
Magnet
supportbeams
Mark_2
NOTICE
Leave the hydraulic lifts at the magnet. You will need them again.
The objective is to align the magnet in the horizontal and to set the center height of the magnet.
For that purpose, you need the following tools:
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 16 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 17
Procedure
Use the water level hose to level A with B and C with D (in the x direction).
Raise the magnet with the hydraulic lifts and slide the insulation plate and the aluminium shim plates
between the magnet support beam and the floor (refer to Fig. 27 as well).
Lower the magnet and verify that A,B and C,D are aligned with one another. If they are not , add more
shim plates until the markings match the water level.
Subsequently, check whether A is level with C (on the left side of the magnet) and B is level with D (on
the right side of the magnet). Align the magnet referring to the markings on the flor in the z direction
(as described in Fig. 25).
Finally, check the alignment of all four points, A,B,C, and D, to one another. The markings must be on
the same level according to the water hose level. Acceptable tolerance is 3 mm.
C
Patient
End
B
X
leveling hose
Centrpu1
CAUTION
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 17 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 18
Slide the insulation plates and the aluminium shim plates underneath the magnet support beam
(the number and the thickness of the aluminium shim plates depend on how much the magnet
alignment deviates from the values of the water hose level).
Insulation plate
Shimplates
Shimpl_1
Fig. 27
For each corner of the magnet you are provided with the following amount of plates:
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 18 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 19
Either add or take away the same number of aluminium plates at each corner of the magnet until the
center height of the magnet is 1100 mm.
Centrpu3
1100
+/-5 mm
Patient
End
NOTICE
CAUTION
Check once more the horizontal alignment of the magnet, the distance to the
walls on either side, as well as the center height.
When the magnet is aligned correctly, remove the hydraulic lifts. Store the remaining aluminium shim
plates in a safe place.
CAUTION
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 19 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 20
NOTICE
Each end of the magnet support beams includes a hole for bolting the magnet
to the floor in areas prone to earthquakes.
To ensure safe transport, the gradient coil is secured on each side by two brackets and four screws.
Brackets
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 20 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 21
Lock nut
Lock nut
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 21 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 22
Introduction
If the magnet system has been sea freighted with liquid helium contained in the helium vessels, the
venting system will be equipped with a relief valve and bursting disk, regulating the pressure in the system to 2 bar absolute (see figure below.)
The magnet system can be left safely venting through the relief valve, until depressurizing is required.
When depressurization is required, carefully follow the procedure described below.
Blank
1/3 PSI
non return valve
Helium syphon
ventline
Pressure gauge
Autofill
Helium syphon
30 psia relief valve
Depressurisation
valve (shown closed)
SEASHIP1
CAUTION
MAGNETOM
Planning & Installation
Ensure that the system includes the DCL Baffle and 1/3 psi pressure gauge
before you perform this procedure.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 22 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 23
Procedure
NOTICE
This procedure should be performed only by trained personnel, wearing protective clothing.
Check that the shut-off valve at the quench valve is in the closed position (handle is at right angles to
the valve axis.)
Remove the VW25KF blank from the end of the shut-off valve and connect the valve to the site
venting.
Ensure that the pipes used are supported and not left to hang on the connections alone. If the site
venting is not installed, run the pipes to atmosphere outside the MR suite.
NOTICE
Helium gas should not be allowed to vent into the MR suite or any other
closed room.
To minimize the amount of helium lost, open the shut-off valve slowly to approximately 15
degrees from the closed position and monitor the pressure gauge.
Helium gas should now be heard escaping. The vent line will cool in a few minutes until it
becomes very cold.
NOTICE
Do not come in contact with cold components. Do not smoke or use open
flames.
When the pressure indicated on the gauge has dropped to 5 psi, the valve opening should be
gradually increased until fully open.
NOTICE
Allow the system to depressurize until the vent line has thawed, indicating the system is now at
atmospheric pressure.
Remove the bursting disk assembly from the end of the quench valve and connect the site venting to
the quench valve.
Remove the 30 psia valve assembly and replace it with the stopper rod (baffle assembly) which is
packed in the accessories case.
Replace the 2 bar pressure gauge with the 1/3 psi gauge which is packed in the accessories case.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 23 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 24
Remove the shut-off valve from the quench valve and blank the outlet with an NW25KF blank and
check the depressurization valve. The system will now pressurize to its normal operating pressure,
1/3 psi (approx. 20 mbar).
Pack the removed parts and return them to the Oxford Service Department for reuse.
Adress:
Oxford Magnet Technology Ltd.
Wharf Road, Eynsham
Witney, Oxon OX8 1BP, England
Telephone:
0044 (1865) 880 880
Fax:
0044 (1865) 880 872
Instruction
If the magnet system has been air freighted with liquid helium contained in the helium vessel, the venting system will be fitted with relief valve which ensure that the pressure within the helium vessel is kept
above atmospheric pressure.
The magnet system can be left safely venting through the relief valves until depressurisation is
required.
AIRSHIP2.AI
Quench valve with integral
10 psi bursting disc
depressurisation
line
Blank
16 psia relief
valve D
Blank
B
Helium syphon
ventile
E
Blank A
Pressure gauge
Smart
Helium Syphon
C
Depressurisation
valve (shown closed)
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 24 of 30
TD SD 23
Siemens AG
Medical Engineering
CAUTION
3 - 25
Procedure
NOTICE
This procedure should only be carried out by trained personnel, wearing protective clothing.
Ensure DCL Baffle is on hand prior to carrying out this procedure.
Remove the blanking plug (A) from the end of the depressurisation line. There may be a small release
of gas, but there should not be a continuous flow. If there is, cap off the tube and call the Oxford
Service Department, since there may be a fault with the quench valve. Do not proceed further since
this might allow air to enter the system.
Assuming there is no flow refit blank (A) and remove the large blanking flange (B) from the end of the
quench valve and connect the site venting to the quench valve.
NOTICE
Helium gas should not be allowed to vent into the imaging suite or any closed
room.
NOTICE
Do not touch the cold parts. Smoking and naked lights are forbidden.
Allow the system to depressurise until the depressurisation line has thawed, indicating that the
system is now at atmospheric pressure.
NOTICE
The following operation should be done quickly to prevent air entering the
system.
Remove the 13 psig valve (F) assembly and and replace it with the current lead baffle assembly
which is packed in the accessories case.
Remove the 16 psia valve (D) from the 1/3 psig valve (E), remove blank (A) from the Tee, connect the
Tee to the 1/3 psig valve and close the depressurisation valve (C). The system will now pressurise to
its normal operating pressure, 1/3 psi.
Pack the remove parts and return them to the Oxford Service Department for re-use.
(Address for the return parts on page 24)
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 25 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 26
General
The magnet is usually shipped cold. However, the magnet may warm when it is shipped to certain
countries or when it is in transport or storage for an extended period of time.
For that reason, the temperature of the helium vessel should be determined as quickly as possible
after the magnet arrives at the customer site.
The temperature of the helium vessel is measured via the three carbon temperature sensors in the
helium vessel.
If the magnet is still cold, that is, the vessel contains liquid helium, the temperature can be maintained
if you refill the magnet immediately with liquid helium. You will not only save time, you will also save a
great deal of money.
However, should the magnet have warmed, you have to pump down the vacuum and fill it with helium
again.
Refer to the next page for instructions on how to measure the temperature as well as on how to determine the threshold between a warm and a cold magnet.
Sensor
temperature sensors.
Heliumvessel
R-Middle
R-Bottom
Fig. 34
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 26 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 27
The course of the magnet installation is illustrated in the flowchart shown below.
The diagram on the next page helps you in determining whether the magnet is warm or cold.
Magnet warm =
Temperature is between
nitrogen and room
temperature
Flolw_2
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 27 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 28
Use a digital voltmeter and measure the resistance (in ohm) of every CTLS at plug C on the magnet
service turret.
Plug C
R-Bottom
c
R-Middle
A
C
e
Common
a
R-Top
C-plug
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 28 of 30
TD SD 23
Siemens AG
Medical Engineering
3 - 29
Enter the actual values measured at the sensors into the tabl.
R-Bottom
c
R-Middle
e
Common
a
R-Top
A - E (top)
B - E (middle)
C - E (bottom)
C_plug_2
Fig. 37 Pin configuration of plug C
Enter the values from the Oxford Magnet Acceptance Protokol into Table 1 (for room-,nitrogen-,
and helium temperature).
Points
A - E (top)
B - E (middle)
C - E (bottom)
Compare the actual values with the resistance values from the OMT Magnet Acceptance Protocol.
If the temperature ranges between a room temperature of 293 K and a nitrogen temperature of
77 K, precool and fill the magnet as described in chapter 15 of Register 1 in the Start-up
Manual.
If the temperature ranges between 77 K (liquid nitrogen) and 4.2 K (liquid helium), refill the cryostat with LHE only as described in chapter 1 of register 8 in the System Manual.
CAUTION
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 29 of 30
TD SD 23
MAGNETOM
Planning & Installation
3 - 30
CAUTION
Prior to refilling liquid helium, install the quench tube or an equivalent so that
escaping gas can be exhausted to the outside.
adaption flange
Fig. 38
CAUTION
MAGNETOM
Planning & Installation
Verify that the magnet is galvanically separated from the quench tube.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 30 of 30
TD SD 23
Siemens AG
Medical Engineering
4-1
The chart provides you with an overview of the components to be installed in the RF-room.
RF-room
Magnet covers
Tunnel lighting
Videocamera, microphone
Filterplate
RFCC
Patient table
Intercom
Cabling
refer to chapter 7
Fig. 1
hfroom
NOTICE
Siemens AG
Medical Engineering
The RF-shielding of the RF-room must not be damaged when installing the
magnet stop or the cable ducts.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 24
TD SD 23
MAGNETOM
Planning & Installation
4-2
ACCU
Filterplate
RFCC
GPS
PCA
CCA
RFPA
RFAS
raumplan
Fig. 2
The example is showing the installation of the filterplate and the RFCC
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 24
TD SD 23
Siemens AG
Medical Engineering
4-3
CAUTION
Install the remote control for the Magnet Stop at an easily accessable location in the examination
room (see Fig. 3)
Cable inlet
120
80
80
Magnet stop
~ 1600
~ 200
Emergency
shut-down
button
magstop
Fig. 3
Fig. 4
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 3 of 24
TD SD 23
MAGNETOM
Planning & Installation
4-4
The table guide is aligned via four adjustable bolts to the table guide supports.
The following drawing is valid for the front and rear support of the table guide.
frontview
front support
adjustment bolts
locknut
M10x16
Fig. 5
Mount the front and back support to the magnet flange using the allen screws M10x16.
Use the allen screws M10x50 and lock nuts to stabilize the supports in the vertical direction
(refer to Fig. 6 on the next page). Do not forget the washers.
NOTICE
MAGNETOM
Planning & Installation
Do not forget to connect the grounding cable from the AS 25 coil to the
magnet (page 6, Fig.7)
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 24
TD SD 23
Siemens AG
Medical Engineering
4-5
Front support
Front
Magnet flange
Screw M10x16
Adjustment screw
locknut
90 degrees
support2
Fig. 6
Attach the adjustment bolts to the table guide. Do not forget the lock nuts.
Attach the table guide with the four adjustment bolts to the table supports.
Since you need the funnel to set the vertical distance of the table guide, this procedure will be
described later on pages 10-14 (Installing the front and back panel) in this chapter.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 5 of 24
TD SD 23
MAGNETOM
Planning & Installation
4-6
The two grounding cables are locatet at the rear side of the magnet nearby the tuning boxes.
Fig. 7
The magnet covers consist of one front panel, one back panel, as well as three right and three left side
panels. The following panel components are already integrated and adjusted in the factory:
Front panel:
Light localizer, the DCU with touchscreen, and the coil connector at the right side.
Back panel:
Patient air, light box for tunnel lighting.
NOTICE
The two bolts which are holding the front-funnel to the front-panel are locked
with nuts. These nuts have to be removed. They are just for transportation!
CAUTION
The front panel is top heavy. Ensure that it does not tip over when you remove
it from the pallet.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 24
TD SD 23
Siemens AG
Medical Engineering
4-7
Bracket
Bracket
Bracket
frontv_1
Levelling feet
Fig. 8
Levelling feet
Installing the adaption plate for the cable duct of the patient table
Attach the distance plate to the front panel frame using screws M16X30 as shown in Fig.9.
frontpanel frame
frontpanel
M16x30
magnet
distance plate
bolts
levelling feet
tischfla
Fig. 9
bolts M12
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 7 of 24
TD SD 23
MAGNETOM
Planning & Installation
4-8
Insert the twelve bolts M16 into the holes (detail "X") at the patient and service end of the magnet.
Tighten the bolts with lock nuts.
Attach a second nut and a washer onto the bolt.
Attach the front panel onto the support bolts and fix it with washers and nuts.
back viev
Rear
Front
bolts
Detail "X"
bracket
lock nuts
B
magnet_3
Use nut A and B (Fig. 10, detail "X") to set the distance .
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 8 of 24
TD SD 23
Siemens AG
Medical Engineering
4-9
Adjust the distance of 245 mm +/-5mm between the outside surface of the front panel and the front
flange of the magnet refer to Fig.11.
flange
Click the front funnel into the holders of the front panel.
Adjust the front panel. Use for the adjustment the levelling feet and the nuts shown in Fig. 8 and Fig. 9
The adjustment has to be done with the front funnel installed! The front panel with the front funnel
must be in align with the guide rails of the gradient coil (Fig.13).
front
A
guide rails
cover_1
Fig. 12 Magnet with front and back panel and guide rails
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 9 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 10
NOTICE
Ensure that the guide rails (Fig.12) are levelled out horizontal.
This is important for the adjustment of the side cover panels.
If the guide rails are not levelled horizontal readjust the front or/and the rear panel in the height.
CAUTION
Check the adjustment of the front funnel the rear funnel and the table guide
during readjustment of the panels.
coveradj
Front panel
Guide rails
Funnel
Guide rails
Position of the funnel
must be centered with
the guide rails
Funnel
approx.
3mm
CAUTION
MAGNETOM
Planning & Installation
Affix the Laser Warning Labels on the front panel (refer to Register 2,
chapter 1, page 7).
Register 8
M2-050.031.01
Rev. 09
04/99
Page 10 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 11
guideadj
Front panel
Levelling feet
Guide rail
Funnel
Levelling feet
Guide rail
Position of funnel
must be centered with
the guide rails
Funnel
Table guide
up
down
Place the table guide (with the adjustment bolts already installed) onto the front and rear
table support. Use the M10X20mm allen screws with the large brass washers to fix the
table guide to the supports. Align the table guide as shown in Fig.14 .
In the vertical, the upper platform of the table guide has to be completely flush with the
triangular surface of the funnel. In the x-direction, the table guide has to be positioned
symmetrically to the gradient coil (guide rails). In the z-direction, the front of the table guide
has to lie against the front panel.
The guide rails define the upper distance from the front panel to the back panel. The exact
position of the back panel is determined by the back funnel. Ensure that the funnel is symmetric with the gradient coil in the x-direction.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 11 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 12
CAUTION
Don t forget to attach the connector ( Wire W26, see also wiring diagrams in
the Planing Guide, Reg.10 ) of the Display-box (part number: 31 04 077) in the
opening 1 (see Fig.15) of the back funnel.
connector
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 12 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 13
NOTICE
Side panels
Attach the side panels on both sides and adjust them as required.
fine adjustment
front
sidecov
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 13 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 14
DCU adjustments
The DCU is factory adjusted. In case additional adjustments are required, refer to the functions
of the screws described in Fig. 17.
1 - Mounting screws
2 - Height adjustment
3 - Distance to funnel
4 - Height adjustment including tilt angle
NOTICE
MAGNETOM
Planning & Installation
The mounting hardware shown in Fig.17 is the same for both sides of the
DCU.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 14 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 15
The tunnel lighting consists of a light bar which is part of the inside covering for the AS 25 coil. The light
generated in the light box by the Halogen lamp (at the back panel of the magnet) is distributed via a
large number of individual fiber optic cables.
CAUTION
Handle the black corrugated hose with care during the installation process.
The hose contains the highly fragile fiber optic cables.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 15 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 16
Video camera
The video camera and the microphone for patient monitoring are contained in the same housing.
CAUTION
Handle the camera and the microphone with care. Like any other electronic
device, they are highly sensitive to shock or other impacts.
Take off the back cover of the camera housing by removing the two screws.
Route the video and audio cable through the opening in the back panel, up through the swivel arm
into the camera housing which also contains the sockets. Connect the cables to the sockets.
Attach the swivel arm to the back panel using the four supplied screws.
Attach the back cover of the camera housing.
Attach the support arm using the five supplied Allen screws.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 16 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 17
To provide the service engineer with enough room, the RF filter plate together with the RFCC should
not be installed in the immediate vicinity of the magnet. In addition, a more cost-effective cover can be
selected for the RFCC.
In a modular RF-room, the filter plate can be installed directly in the recess provided for that purpose.
In a conventional RF-room the filter plate can be installed directly as well, as long as the RF integrity is
maintained. However, we recommend the use of a filter frame (refer to chapter 3 Components in Register 1 and to chapter 1 'RF-shielding' in Register 4 of this manual).
Interior of
RF-room
RF filter plate
RF filter frame
filterpl
Fig. 20 Installation of the filter plate
NOTICE
Siemens AG
Medical Engineering
The RF integrity can now be measured if the transport opening of the RFroom has been closed.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 17 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 18
Attach the two mounting brackets for the RFCC (8 washers, lock washers, nuts M6 each)
interior of
RF-room
mounting
bracket
brackets
CAUTION
The RFCC is very heavy. You either need a lifting device or three people for
the installation.
Lift up the RFCC, guide the support bolts through the elonguated holes in the mounting brackets.
Secure the RFCC to the brackets using 10 washers, lock washers, and nuts M6.
Shift the RFCC in the elonguated holes until it is flush with the RF-room wall. Tighten the nuts.
Interiorof
RF-room
RFCC
RFCC
rfccin
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 18 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 19
Protect the tabletop against damage by covering it with corrugated paper or packing material.
connectorplates
liege1
vertical motor
screws
Fig. 23 Patient table
gear bolt
1 of 4
levelling
feets
mechanical endstop
limit switch
S2
S4
transport
roller
liegedet
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 19 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 20
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 20 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 21
transport brackets
mounting screws
transich
Fig. 30
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 21 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 22
Attach the cable duct to the two bolts sitting on the mounting plate refer to Fig.32 (tighten by hand
only).
Installation frame
Front panel
ductmon
M16
mounting plate
85mm
Bolts M12
Cable duct
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 22 of 24
TD SD 23
Siemens AG
Medical Engineering
4 - 23
Align the patient table with the cable duct to the magnet, table guide and front funnel refer to Fig. 33.
CAUTION
To prevent potential injuries, the distance between the table guide and the
patient table cover at the head end must not exceed 5 mm (see Fig. 33)
magnet cover
allign
magnet
cable duct
patient table
max.5 mm distance
Fig. 33 Align the patient table with the cable duct to magnet, table guide and front funnel
NOTICE
Siemens AG
Medical Engineering
The patient table will be aligned and bolted to the floor during system start-up
(Start up manual, register 1, chapter 9).
Register 8
M2-050.031.01
Rev. 09
04/99
Page 23 of 24
TD SD 23
MAGNETOM
Planning & Installation
4 - 24
Intercom
The intercom system is integrated into the CCA cabinet K2120. A loudspeaker has to be installed
inside the RF-room. A second loudspeaker (piezo) is already installed the rear table guid support.
CAUTION
The RF-shielding of the RF-room must not be damaged when installing the
loudspeaker.
lautspr
Fig. 34 Loudspeeker
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 24 of 24
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5-1
General
To keep the helium boil-off to a minimum, install the ACCU cabinet (ACCU = Air Compressor Chiller
Unit) first so that the cold head can be connected as quickly as possible.
Install the three-in-one cabinet (CCA, PCA, gradient) and the RFPA in parallel or immediately after
completion of the ACCU cabinet. Route the cables after you finished installing the cabinets.
After the ACCU has been connected to the PCA, switch on the refrigerator immediately (naturally only
if the helium vessel contains liquid helium).
Flowchart
The flowchart provides you with an overview of the components to be installed in the computer room.
Magnet unloading,
transport,set-up
Installation in
computer room
Installation of
ACCU to
reduce boil off
Set up the
cabinet
Connect the water
hoses
Installation of
the other
cabinets
Cabling / refer
to chapter 7
Installation in
RF-room
Fig. 1
Start-up
refrigerator
equippm
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 26
TD SD 23
MAGNETOM
Planning & Installation
5-2
Computer Room
Prerequisites
Tools
Safety
NOTICE
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5-3
CAUTION
710
holes
450
Fig. 2
710
holes_3
1650
Fig. 3
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 3 of 26
TD SD 23
MAGNETOM
Planning & Installation
5-4
Computer Room
Service End
magnet
magnet
support beams
Patient End
Fig. 4
holemag
Move cabinet unit on the transport pallet in the immediate vicinity of its final location.
Remove the screw connections between the cabinet unit and the pallet.
1
3
Fig. 5
CAUTION
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5-5
5
6
Fig. 6
Fig. 7
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 5 of 26
TD SD 23
MAGNETOM
Planning & Installation
5-6
Computer Room
10
Fig. 8
Move cabinet unit on the transport pallet in the immediate vicinity of its final location.
Remove the screw connections between the cabinet unit and the pallet. (The four mounting bolts are
located at the corners of the cabinets).
position of the
transport lock screws
Fig. 9
Transport pallet
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5-7
General Description/Subsystems
The ACCU cabinet is an essential component for the operation of the high performance gradient
system within the MAGNETOM magnetic resonance imaging system. Because of the heavy heat
dissipation of the gradient coil, the currently used air cooling had to be substituted by water cooling. In
addition to the water cooler, the cabinet also contains the helium compressor for the cold head of the
magnet and an air compressor for driving the pneumatic RF switches within the system.
Accu_1.ai
SIEMENS
SIEMENS
Front view
Back view
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 7 of 26
TD SD 23
MAGNETOM
Planning & Installation
5-8
Computer Room
Preliminary steps
The synthetic hoses for supplying the ACCU with water should have been routed up to the final
location of the cabinet
Ensure that the water inlet hoses include a flow rate meter
One shut-off valve each should be provided for the chilled water inlet and outlet hoses
One temperature indicator should be provided for the chilled water inlet
Overview/General
Figure 12 provides you with an overview of the water connection for the ACCU cabinet. For a more
detailed description of the on-site water connection, refer to chapter 4 of Register 4 of this manual.
Overvwat
Water outlet
SIEMENS
Water inlet
Pressure gauge
Flow meter
Temperature indicator
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 8 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
CAUTION
5-9
When you connect the hoses on top of the cabinet, do not mix up the water
inlet with the water outlet connection!
X 130
X 110
X 111
Pressurized air
Primary
circuit
Low
High
pressure pressure
Mag.
in
Grad.
in
Water
in
Water
out
Magnet
out
Grad.
out
Gradient Gradient
cabinet
coil
Gradient Gradient
cabinet
coil
Topview1
The various connections on top of the ACCU cabinet are shown in figure 13.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 9 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 10
Computer Room
Valves closed
Hose barbs
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 10 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 11
NOTICE
After you have installed the hoses check them for leaks.
Open
Proceed slowly.
NOTICE
For further information, refer to chapter 2-2, in Register 2, and chapter 4-3 in
Register 4 of this manual.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 11 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 12
Computer Room
General / Overview
The cold head is connected to refrigerator RW 6000 which is located in the lower part of the ACCU
cabinet. The cables are routed from the cold head to the ACCU. Connections are established in two
steps via the filter plate, first the semirigid lines, and then the power cable.
Semirigid lines
Cold head
SIEMENS
Power cable
Filter plate
5/100
Refrigerator
RW 6000
Accu_an
Fig. 19
CAUTION
MAGNETOM
Planning & Installation
Do not mix up the HP and LP lines when you connect the semirigid pressure
lines.
marked red = high pressure; marked green = low pressure!
Register 8
M2-050.031.01
Rev. 09
04/99
Page 12 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 13
Start at the cold head with the routing and installing of the semirigid pressure lines and connect
them via the filter plate to the ACCU.
Connect the pressure lines in the right order: marked red = high pressure,
marked green = low pressure!
Ensure that the flange has been installed. If not, attach it with M6X12 mm Allen screws before routing
the semirigid pressure lines through the filter plate (refer to Fig. 20 and Fig.24).
Filter Plate
High
Press
Semirigid Pressure Lines
flexible part
SIEMENS
Power
Cable
Computer Room
Magnet Room
Cold Head
Sericoo1
Fig. 20 Overview
NOTICE
Connect the semirigid pressure lines to the filters at the cold head.
Carefully route the semirigid pressure lines through the filter plate to the ACCU cabinet.
Connect the semirigid pressure lines to the connectors on top of the ACCU cabinet.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 13 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 14
Computer Room
Do not bend or twist the semirigid pressure lines. Connect them carefully.
CAUTION
Follow the instructions shown below and hold or turn the components only as indicated.
Adapter
Hold
Turn
Hold
Turn
Hold
semiri_3
Connection to
Hold
Turn
Hold
semiri_4
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 14 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 15
The set of the RF feed-through for the high-pressure and low-pressure line is shown
in Fig. 23. The set consists of:
Clean the pressure lines at the area where they will be fed through to the filter plate with
sand paper. Cover this area with the supplied contact grease.
Mount the two half flanges at this area around the pressure lines and fix them with the
mounting screws.
mounting screws
This side will be attached to the
Filterplate (computer room)!
2 half flanges
hfdurchf
RF-cord
Fig. 24 HF feed through installation
CAUTION
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 15 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 16
Computer Room
mounting screws
Insulation
Insulation
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 16 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 17
Connecting the cold head power cable via the filter plate
X 111
X 111
X 111
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 17 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 18
Computer Room
Overview/General
The water hoses are connected on top of the ACCU cabinet. They are then routed through the filter
plate and connected to the valves of the gradient coil. A water filter must be integrated into the secondary water circulation system before the GPS. The water cooler for the hoses is located in the center
section of the ACCU cabinet. For the technical data of the water cooler, refer to chapter 4 of Register 4
in this manual.
Water
hoses
SIEMENS
Gradient coil
Filterplate
Water cooler
Water filter
CCA
PCA
GPS
accu_wf
Install the water filter (37 62 346) in the GPS intake line and open both valves.
Ensure that filter is installed such that the arrow on top corresponds to the flow direction.
NOTICE
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 18 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 19
The connection at the top of the ACCU is coned. Therefore only the coned hose barbs, as the counterpart, will fit and guarantee a tight connection (1 Fig. 32).
At the water connection of the gradient and the external water filter the connection is made with a seal
between the flat surfaces (2 Fig. 32)
ACCU-Cabinet
Gradient-Cabinet
Seal
ACCUGRAD
Fig. 32 Water connection ACCU
NOTICE
Please pay attention during the system installation that the correct hose
barbs are used and all water connections are fitting properly.
NOTICE
The valves for the gradient coil water distribution are connected with brackets
to the gradient frame during transport.
Shipping brackets
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 19 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 20
Computer Room
screws to remove
Primary
circuit
High
Low
pressure pressure
Mag.
in
Grad.
in
Water
in
Water
out
Magnet
out
Grad.
out
Gradient Gradient
cabinet
coil
Gradient Gradient
cabinet
coil
Topview2
Fig. 35
Clambs
Fig. 36
NOTICE
MAGNETOM
Planning & Installation
Tighten all clamps and check the water hoses for leaks.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 20 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 21
Mount the valves to the frame with Allen screws M6 x 50 mmm, washers and nuts.
Connect the water hoses to the inlet and outlet valve.
Open the inlet and outlet valve before switch on the ACCU-cabinet.
brhi_2
water outlet
water inlet
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 21 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 22
Computer Room
Mount the water hoses with the aluminium bar to the frame.
Use M6 x 30 mm Allen screws.
brhi_3
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 22 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 23
Minus pole
(black cables)
Plus pole
(red cables)
PCA cabinet.
cable holder
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 23 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 24
Computer Room
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 24 of 26
TD SD 23
Siemens AG
Medical Engineering
Computer Room
5 - 25
NOTICE
The system has to meet all requirements regarding service and remote diagnostics. This means that all available error messages from the subsystems
have to be transferred to the host computer system.
For the implementation of the supervision concept, a SIEMENS standard
SLAVE D5 SNr.: 8962300 K2079 has to be used to connect the ACCU with the
system control electronics. The messages are transferred via the serial USP
(Universal Serial Protocol) interface.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 25 of 26
TD SD 23
MAGNETOM
Planning & Installation
5 - 26
Computer Room
Room thermostat
The room temperature is monitored via the room thermostat. If the temperature exceeds 22 C, a message is displayed at the alarm box and the MRC monitor. Simultaneously, the program writes a code
into the error log file.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 26 of 26
TD SD 23
Siemens AG
Medical Engineering
Control room
6-1
Flowchart
The chart below shows the components to be installed in the control room.
Control room
MRC onsole
Monitors
Keyboard
Alarm Box
Cabling
refer to chapter 7
Fig. 1
flowch
CAUTION
Siemens AG
Medical Engineering
The RF-shielding of the RF-room must not be damaged when installing the
alarm box and the cable ducts.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 6
TD SD 23
MAGNETOM
Planning & Installation
6-2
Control room
MR-console
Fig. 2
Fig. 3
The monitors (MRC and video) will be positioned on the computer base.
Fig. 4
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 6
TD SD 23
Siemens AG
Medical Engineering
Control room
6-3
Monitor cable
Keyboard cable
Fig. 5
Fig. 6
Fig. 7
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 3 of 6
TD SD 23
MAGNETOM
Planning & Installation
6-4
Control room
Several of the key caps have to be replaced. The new key caps and key function strip are included in
the shipment.
MRCTAST
Functionkey labels
MRC keyboard
4
1
3
2
Fig. 8
MRC keyboard
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 6
TD SD 23
Siemens AG
Medical Engineering
Control room
6-5
Alarm box
The alarm box contains the ON/OFF switch for the magnet as well as one of the Magnet Stops
(the remote control Magnet Stop is located in the magnet room).
NOTICE
Considering its contents, the alarm box has to be installed in an easily accessible area outside the 0.1 mT zone.
Magnet Stop
ON/OFF
70
25
Back view
Wall mounting
alarmbox
Fig. 9
NOTICE
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 5 of 6
TD SD 23
MAGNETOM
Planning & Installation
6-6
Control room
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 6
TD SD 23
Siemens AG
Medical Engineering
Component cabling
Prerequisites
7-1
7
You should have completed the following before installing the system cables:
All system components have been installed (chapter 2, page 7 in this register)
The on-site power connection has been isntalled
(refer to chapter 3 On-site electrical installations in Register 4 of this manual)
Additional information
Circuit diagrams
The diagrams for the individual system components are located in the separate
"Diagrams" manual.
The diagrams for component cabling are located in register 9 of this manual.
CAUTION
Observe the minimum bending radius for the cables listed below.
1. Gradient cable
RB
135 mm
2. Transmitter cable
RB
RB
RB
150 mm
NOTICE
Siemens AG
Medical Engineering
All cables for this system are connected on top of the cabinets.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 26
TD SD 23
MAGNETOM
Planning & Installation
7-2
Component cabling
Type numbers
The type number helps you allocate the diagrams to a particular component. Please note that the
same type number may be assigned to more than one component.
Type number
MAGNETOM
Planning & Installation
Components
K2079/C
GPS
K2110
RFPA
K2120
CCA
K2122
Magnet
K2121
ACCU
Gradient coil
K2124
RFCC
K2125
Local coils
K2126
PCA
Alarm box
K2127
RF-filter
RFAS
Resistor (Dummy) 2kW
K2130
Magnet stop
MRC/MRSC
RF-door switch
Humidity sensor
Room thermostat
DCU
Patient video camera
K2154
Patient table
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7-3
Ready, set, go
Install the cable ducts according to the project flowcharts (consult your project manager).
CAUTION
Ensure that the line voltage is switched off at the on-site power distribution
panel (remove fuses, lock switch) before you begin with the cable installation.
Switch the following circuit breakers in the power cabinet in downward (off) position
(F20, F19, F4, F12, F13, F14, F24).
Keep the line voltage and the protective conductor separate from the signal and control lines.
Route the gradient cables separate from the shim cable.
NOTICE
Route all Oxford cables separate from the signal lines, gradient cables, shim cables and line
voltage cables.
Have excess cable close to the filter plate meander across the ceiling and secure it with
cables ties.
WARNING
Route the line voltage and protective conductor cables separate from the signal and control lines.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 3 of 26
TD SD 23
MAGNETOM
Planning & Installation
7-4
Component cabling
The line voltage is connected on top of the PCA cabinet (PCA / X100).
PCA Back
L1
L2
L3
ground
power cable here
PE
PCAPOWER
Fig. 1
Central ground
PCA Front
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 4 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7-5
Braiding
Shrink tubing
Fig. 2
Strip the cable sheathing and remove part of the braiding. Cover the end of the cable with shrink
tubing such that approximate 4 cm cover the of the braiding remains exposed.
Route the cable through the clamp to the power connection box and connect it as shown in Fig.2.
Ground the cable with the strain relief clamp at the exposed braiding.
Connect the 3-phase line voltage and ground (refer to wiring diagram).
Close the line power connection box.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 5 of 26
TD SD 23
MAGNETOM
Planning & Installation
7-6
Component cabling
NOTICE
The central ground is located right next to the line power box on top of the
PCA cabinet.
Route the protective conductors for the magnet and the RF-room according to the wiring diagram in
Register 9.
Connect all 16 mm2 ground straps to central ground of the magnet (refer to.
Fig. 3
Fig. 4
Fig. 5
Fig. 6
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 6 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7-7
Fig. 7
Grounding RF-room
Fig. 8
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 7 of 26
TD SD 23
MAGNETOM
Planning & Installation
7-8
Component cabling
Gradient cables
NOTICE
The gradient cables are routed through the top of the GPS cabnet.
gradcab
Fig. 9
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 8 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7-9
Heat gun
Shrink tubing
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 9 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 10
Register 8
MAGNETOM
Planning & Installation
M2-050.031.01
Rev. 09
04/99
Siemens AG
Medical Engineering
FIL-PLA
Component cabling
Page 10 of 26
TD SD 23
Component cabling
7 - 11
PCA Back
Back
X12
X133
X20
CCA
PCA
K2120
K2126
X53
X11
X13
X10
GPS
X134
K2079/C
X111
X51
X130
X135
+
Front
X110
X132
X50
X136
E25
X114
X54
X100
Ground
pcadach
PCA Front
Fig. 14 Top of PCA
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 11 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 12
Component cabling
CCA Back
X20
Back
X19
CCA
PCA
K2120
K2126
X29
X45
X6
X27
X30
X32
X50
X5
GPS
K2079/C
X18
X17
X15
X44
X7
X16
Front
X26
X23
X12
X11
X48
X24
X22
X10
X21
X3
X41
X2
X1
X42
X28
X8
X51
X4
X47
X46
X52
X36
X40
X35
X39
X34
X38
X31
X14
X33
X37
X13
X49
X9
ccadach
CCA Front
Fig. 15 Top of the CCA cabinet
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 12 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7 - 13
RFPA Front
Back
RFPA
K2110
Front
J100
J11
J10
RFPADACH
J15 RF out
J14
J35
RFPA Back
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 13 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 14
Component cabling
TABCABL
X14
X5
X12
X15
X13
X11
V3
X20
X24
Cable mounting plate
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 14 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7 - 15
X9
D10
X6 X3
X4
X7
X8
X9
3
2
X2
S10A
X1
front panel
X3 X4 X5
X6
D21A
X7
X1
X2
X5
S10B/C S10D
X10
RFAS
DECON
DETOFF
DETON DECOFF
X11
D53
S10E
RFASCONN
S10E
S10C
S10D
1
2
X11
X4
X9
X10
X8
D22A
X2
S10A
1
X5
X2
X3
D22B
X4
X4
X3
X6
X2
X7
S10B
X1
X1
X3
X1
D10
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 15 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 16
Component cabling
DET ON
to RFAS
NOTICE
MAGNETOM
Planning & Installation
To disconnect the hose from the T-piece, press against the metal ring and pull
off the hose at the same time.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 16 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7 - 17
RFCC_CON
DEC OFF
DET ON
X7
DET OFF
X5
X4
X3
X1
X1
X2
X9
X15
X5
hose
X6
X8
X100
X16
X7
X4
X10
Attach a piece of the thin blue pressurized hose for the automatic air/water separator.
Route the hose into a suitable container (preferably a 5 liter plastic container).
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 17 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 18
Component cabling
X 130
X 110
X 111
Pressurized air
Primary
circuit
Low
High
pressure pressure
Mag.
in
Topview1
Grad.
in
Water
in
Water
out
Magnet
out
Grad.
out
NOTICE
MAGNETOM
Planning & Installation
The air pressure hose is connected on top of the ACCU and fed through the
filter plate to the RFCC.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 18 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7 - 19
Cable routing
NOTICE
Cable numbers
The ends of the cables are identified with the item number, type number, and connector identification
as well as a running cable number. Allocate the cables via the cable number which is identified by a
W (wire) in the circuit diagrams.
Cable numbers
NOTICE
W 0...99
Standart cables
W 100...199
W 200...299
The circuit diagrams are included in Register 10 of this manual. They are identical with those in the Diagram manual.
To expedite system cabling, the cable overview has been categorized into cable groups. Register 10 includes the documents Component overview, Cable lists, Overview of cables and
individual cable groups.
Route the cables and lines in accordance with the cable lists and diagrams (refer to the lables at each
end of every cable).
Then continue with the Protective Conductor Test described on page 21 in this chapter.
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 19 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 20
Component cabling
The shim filter assembly is installed on the filterplate in the magnet room.
The following electrical connections have to be established.
X12
Top
Filter plate
C
OMTcable
618-190
X12C
1
Shim
inductor
unit
X12B
1
RAHMEN
Connect the shim cable coming from the magnet to the connector X12C at the shim inductor unit.
Connect the short shim cable (delivered with the filter plate) to the following connectors:
Use a cable tie to secure the cable shielding of the cable to the filter plate.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 20 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7 - 21
NOTICE
The entire system cabling must be installed, before this test can be performed.
Use the protective conductor meter and measure the ohmic resistance between the protective conductor connection on top of the line power distribution cabinet and an uncoated
metalic part of the:
ACCU
MR electronics cabinet
RFPA
RF-room
Filter plate and RFCC
Magnet OR35
Patient table
RFAS (front panel)
Housing MRC
Housing Monitors 19"and 15" (MRC)
Housing MRSC (if available)
Housing Monitor 19" (MRSC) (if available)
Digital camera
Should the resistance exceed in one instance 200m, test the protective conductor in question
for satisfactory galvanic connection.
If this is not successful for devices with inlet-connectors (for non-heating appliances), an
additional 16mm2 protective conductor should be connected to the respective housing. Do
not disconnect the protective conductor in the line voltage cable.
NOTICE
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 21 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 22
Component cabling
Computer room
NOTICE
Wait until the cabinets are positioned before you cut the feedthrough into the
cable tray.
NOTICE
MAGNETOM
Planning & Installation
After connecting the cables, secure the cables with cable ties.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 22 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
NOTICE
Siemens AG
Medical Engineering
Do not exceed the acceptable bending radius for the RF-cable (refer to the
first page of this chapter).
NOTICE
7 - 23
Insulate the water inlet and outlet hoses at the ACCU cabinet as well as the
high and low pressure lines of the cold head.
Register 8
M2-050.031.01
Rev. 09
04/99
Page 23 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 24
Component cabling
Magnet room
gradient bolts
CAUTION
Check the gradient-bolts Fig.33. They must be attached tight on the gradient
coil! In Oxford the gradient bolts have been tightened with a torqe of 25Nm.
Check if the gradient cables are tight together Fig.33.
Each pair ( X and X, Y and Y, Z and Z ) separately, see Fig.33.
In case of Vision Upgrade, dont forget to use tie wraps to tight the gradient
cables together.
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 24 of 26
TD SD 23
Siemens AG
Medical Engineering
Component cabling
7 - 25
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 25 of 26
TD SD 23
MAGNETOM
Planning & Installation
7 - 26
Component cabling
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 26 of 26
TD SD 23
Siemens AG
Medical Engineering
8-1
All Chapters:
Editorial changes
New layout
Siemens AG
Medical Engineering
Register 8
M2-050.031.01
Rev. 09
04/99
Page 1 of 2
TD SD 23
MAGNETOM
Planning & Installation
8-2
MAGNETOM
Planning & Installation
Register 8
M2-050.031.01
Rev. 09
04/99
Page 2 of 2
TD SD 23
Siemens AG
Medical Engineering