Академический Документы
Профессиональный Документы
Культура Документы
management
consultant and designer
Mass rapid
transit
mecca metro
saudi arabia
transport masterplanning
feasibility studies
tender preparation and analysis
detailed design
With Meccas first metro line now in operation, the city is developing a network of four further lines. SYSTRAs experience
gained during the design and construction of the first line is
now being employed on the planning and design of the larger
network.
The Challenge
The city of Mecca, which lies in the Western area of Hejaz in Saudi
Arabia, has a population of around 1.6 million people which is
expected to grow to 2.2 million by the year 2029. In addition,
Meccas religious significance as the birthplace of Prophet Muhammed and the centre of pilgrimage, prayer, and scholarship for
the worldwide Muslim community, means that over 15 million
people visit the city every year, with several million visiting during the Muslim season of Hajj.
Given the number of visitors, it is not surprising that the first metro
line to be built was the Southern Line in the Al Mashaaer Al
Mugaddassah area, to serve the citys pilgrims. The line, which
began operation with limited capacity in 2010, reaching full capacity in 2011, runs only for around one week of the year and
has helped ease heavy congestion during this important event.
As well as being delivered within a very tight timescale, this line
has achieved the highest capacity of any metro line in the world:
72,000 people per hour (pph). This brought its own technical
challenges.
The city now plans to build four further metro lines, which will
run both over- and underground for a total distance of 114 km
with 62 stations for the medium-term network, and about 180
km with 88 stations for the longer-term network. The first phase
will see the construction of the central sections of Lines B and C,
with future phases seeing the addition of part of Line A followed
by Line D and extensions to Lines A, B and C.
In detail
The 18 km Al Mashaaer Al Mugadassah metro links the pilgrimage sites of Mina, Muzdalifa and Arafat near Mecca. The whole
line is elevated, running on precast concrete viaducts with nine
stations and a depot.
www.systra.com
mecca metro
saudi arabia
SYSTRA was employed by the Ministry of Municipalities and Rural Affairs (MOMRA) in 2008 to produce preliminary designs for
the Southern Line, including civil works, stations, tracks, other
buildings, electrical, mechanical and drainage. This contract also
involved setting the performance and functional specifications for
equipment and making initial cost estimates.
Finding a solution to meet the unique operational requirements
was the biggest challenge during the design phase, according to
Mohammad K.. He credits the success of the design to the fact
that SYSTRA employs people who have actually operated metro
systems. We have experts who know metro operation from the
inside, because they have done it, says Mohammad K.. Thats
different from having operation theorists. Its part of our DNA.
MOMRA awarded the contract to deliver the Southern Line to
contractor China Railways Construction Company (CRCC), with
CRCC later approaching SYSTRA to produce detailed designs for
the civil works. The timeframe here was extremely tight less
than two years for the line to be operational. We had to deliver
the whole design in 14 months, which was quite amazing, says
Mohammad K..
The speed of construction meant that SYSTRAs designs had to
be shovel-ready from the moment that they were complete; there
was no time in the programme for the contractor to look at
issues of buildability or detail. Here, the time spent out on site
by SYSTRAs people was crucial to getting the design right, says
Mohammad K.: Our key designers dont just have experience
in designing things that work in theory, they are people who
have constructed things, so they know what works and what
doesnt.
Following on from SYSTRAs success in two separate roles on the
Southern Line, AlBalad AlAmeen Company (ABC) which is the Municipality of Meccas investment arm, employed SYSTRA to carry
out a feasibility study of a Mass Rail Transit network for Mecca.
SYSTRAs tasks included preparing studies on operation, technical
feasibility, environmental impact, defining investment and operation costs, and construction phasing.
www.systra.com
at a glance
facts and figures
finance
stakeholders
Southern Line
Client: Development
Commission of Makkah, Madinah
and Al Mashaaer through
the Ministry of Municipalities
and Rural Affairs
Clients consultant: SYSTRA
Contractor: China Railways
Construction Company
Contractors designer (civils):
SYSTRA
finance
Public finding: 100%
key dates
2010: Southern Line Al Mashaaer
Al Mugaddassah begins operation
(reduced capacity)
2011: Southern Line Al Mashaaer Al
Mugaddassah begins operation (full
capacity)
2018: phase 1, Lines B and C
(central sections) expected to open
2021: phase 2, Line A
(central section) expected to open
2024: phase 3, Line D
expected to open
2026/28: phase 4 and 5, extensions
of the 4 lines expected to open
December 2013
SYSTRAs role