Академический Документы
Профессиональный Документы
Культура Документы
STANDARD DOCUMENTS
FOR
ELECTRICAL AND MECHANICAL WORKS
(INCLUDING ERECTION ON SITE)
First Edition
April 1987
TABLE OF CONTENTS
20
- STANDARD CONDITIONS .. 28
ANNEXURE A
FORM OF TENDER BOND .
107
ANNEXURE B
FORM OF ADVANCE PAYMENT BOND .
108
ANNEXURE C
FORM OF PERFORMANCE BOND
109
Gentlemen,
1. After having examined the Instructions to Tenderers, Outline Drawings,
Standard Conditions of Contract, Outline Specification and Bill of
Quantities/Schedule of Rates* and Prices for the execution of the above
named Works, we, the undersigned, offer to execute, complete and
maintain the whole of the said Works in conformity with the said
Instructions, Outline Drawings, Standard Conditions of Contract, Outline
Specification, and Bill of Quantities/Schedules of Rates* and Prices for
the
sum
of
Rials
Omani
_________________________________________________________________________
_______________________________________________________________________
(RO.
______________________________)
and/or
the
sum
of
_________________________________________________________________________
____________________________________________ [___________________]
or such other sum as may be ascertained in accordance with the said
Conditions.
2. We undertake, if our Tender is accepted, to commence the Works within
_________ days of receipt of the Engineers order to commence, and to
complete and deliver the whole of the Works comprised in the Contract
within ________ days calculated from the last day of the aforesaid period
in which the Works are to be commenced/or by the ______________ day of
_____ 20__.
3. If our Tender is accepted, we will obtain the undertaking of a locally
registered Bank (as required in the Sultanate of Oman Standard
Conditions of Contract for Electrical and Mechanical Works, 1 st Edition) to
be jointly and severally bound with us in the sum of 10 per cent of the
Contract Sum for the due performance of the Contract under the terms
of a Performance Bond as attached and to be approved by you.
4. We agree to abide by this Tender for a period of 90 days from the date
fixed for receiving the same and it shall remain binding upon us and
may be accepted at any time before the expiration of that period.
5. In the event of our Tender being accepted and until a formal Agreement
is prepared and executed, this Tender together with your written
acceptance thereof, shall constitute a binding obligation upon us.
______________________________________________________________________________
*delete where not applicable
6. We understand that you are not bound to accept the lowest or any
Tender you may receive.
7. We acknowledge receipt of the following circular letters:
Reference number of letter
Date
_____________________________
_____________________________
_____________________________
_____________________________
_____________________________
_____________________________
___________________
___________________
___________________
___________________
___________________
___________________
Interest
________________________________
_______________________________
________________________________
_______________________________
________________________________
_______________________________
________________________________
_______________________________
________________________________
_______________________________
________________________________
_______________________________
________________________________
_______________________________
______________________________________________________________________________
*delete where not applicable
APPENDIX TO THE FORM OF TENDER
CLAUSE
Number of Drawings
5.2.2(b)
_________________________
5.7
7.1
_____________
and or by the day of
_______
________________________
Amount of Performance Bond
9.1
RO. _____________________
_______________being5% of
the Contract Sum.
Programme to be Furnished
following
12.1
____
days/months*
Engineers
order
to
commence
the Works.
Advance Detailed Progress
following
of Plant Schedule
commence
12.4
____
days/months*
Engineers
order
to
the Works.
Indirect or Consequential Damage
16.1
RO. _____________________
17.1
RO. _____________________
17.2(b)
RO. _____________________
31.1
RO.
_______________
per
31.2
RO.
_______________
per
31.3
RO.
_______________
per
33.1
___________
39.4(b)
Signature
___________________________________
in
capacity
of
________________________
Duly
authorized
to
sign
Tenders
for
and
on
behalf
of
_____________________________________
_______________________________________________________________________________
Address _______________________________________
Witness
____________________
______________________________________________
____________________
____________________
______________________________________________
Occupation
_________________
FORM OF AGREEMENT
THIS AGREEMENT made this _____________ day of __________________ 20
.
BETWEEN
_____________________________________________________________________________
of ________________________________________________________________(hereinafter
called
the
Employer)
of
the
one
part
and
___________________________________________
_______________________________________________________________________________
____________________________________________________________________________
(Company
Registration
Number)
___________________________________________________
(hereinafter called the Contractor) of the other part.
WHEREAS the Employer is desirous that certain works should be executed viz:
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
7
_________________________________________________________________________
and
has
accepted a Tender by the Contractor as summarized at Appendix B Summary
of Contract Sum for the execution, completion and maintenance of such
Works.
NOW THIS AGREEMENT WITNESSETH as follows:
1. In this Agreement, words and expressions shall have the same meanings
as are respectively assigned to them in the Standard Conditions of
Contract hereinafter referred to.
2. The following documents shall be deemed to form and be read and
construed as part of this Agreement viz:
The said Tender
The Standard Conditions of Contract
The Outline Drawings
The Outline Specification
The Bill of Quantities*
The Schedule of Rates and Prices*
The Tender Board/Ministry Letter of Acceptance*
______________________________**
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
______________________________
3. In consideration of the payments to be made by the Employer to the
Contractor as hereinafter mentioned the Contractor hereby covenants
with the Employer to execute and complete the Works and to remedy
defects therein in conformity in all respects with the provisions of the
Contract.
______________________________________________________________________________
*delete where not applicable
**other additional documents as required
4. The Employer hereby covenants to pay the Contractor in consideration
of the execution, completion of the Works and the remedying of defects
therein the Contract Price at the times and in the manner prescribed by
the Contract and limited by the Cash Flow contained in the Appendix to
the Form of Tender.
IN WITNESS whereof the parties hereto have hereunder set their
respective hands and seals on the day and year first above written.
______________________________
Signed by a duly authorized Signatory
for and on behalf of the Government
of the Sultanate of Oman
______________________________
Witness
______________________________
Signed by a duly authorized Signatory
for and on behalf of the Contractor
______________________________
Witness
Ratified in accordance with the Sultani Decree No. 48/76, as amended,
on the ____ day of ________ 20____.
_____________________________________
THE DEPUTY PRIME MINISTER
FOR FINANCIAL & ECONOMIC AFFAIRS
_______________________
UNDERSECRETARY FOR
FINANCIAL AFFAIRS
MINISTRY OF FINANCE
AND ECONOMY
10
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
RO
____________________
- Value of Plant
- Value of Shipping/Insurance
- Value of Erection/Installation
- Value of Building and Civil
Engineering Works
- Value of Provisional Sums*
- Value of Contingencies*
____________________
____________________
____________________
____________________
____________________
____________________
____________________
TOTAL
RO
____________________
____________________
____________________
TOTAL
____________________
RO
____________________
11
______________________________________________________________________________
*delete where not applicable
APPENDIX B TO FORM OF AGREEMENT
SUMMARY OF CONTRACT SUM
(FOR USE WITH VALUES IN RIALS OMANI AND/OR OTHER CURRENCIES)
DESCRIPTION
R.O.
BILL NO. 1
\
2
3
4
5
6
7
8
9
10
11
12
13
..
..
..
..
..
**
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
____________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
_________________
____________________
_________________
RO
____________________
**
_________________
- Value of Plant
____________________
_________________
- Value of Shipping/Insurance
____________________
_________________
- Value of Erection/Installation
____________________
_________________
- Value of Building and Civil
Engineering Works
____________________
_________________
- Value of Provisional Sums*
____________________
_________________
- Value of Contingencies* ____________________
_________________
TOTAL
____________________
_________________
RO
____________________
**
_________________
____________________
12
____________________
_________________
____________________
_________________
RO
**
____________________
_________________
______________________________________________________________________________
*delete where not applicable
**insert type of currency as applicable
TOTAL
13
1.1
Definitions............................................................................................... 28
1.2
Interpretation.......................................................................................... 33
1.3
1.4
Headings or Notes..................................................................................33
1.5
Cost........................................................................................................ 33
2.0
2.1
Engineers Duties....................................................................................33
2.2
Engineers Representative......................................................................33
2.3
2.4
3.0
3.1
Assignment............................................................................................. 34
3.2
Sub-letting.............................................................................................. 35
4.0
CONTRACT DOCUMENTS.........................................................................35
4.1
Languages.............................................................................................. 35
4.2
4.3
5.0
5.1
5.2
5.3
Approved Drawings.................................................................................38
5.4
Inspection of Drawings...........................................................................38
5.5
Foundation Drawings.............................................................................. 39
5.6
Errors in Drawings...................................................................................39
5.7
6.0
6.1
6.2
Errors by Contractor................................................................................40
6.3
Errors by Engineer..................................................................................41
14
7.0
7.1
General Obligations................................................................................41
7.2
Setting Out............................................................................................. 42
7.3
7.4
Operation of Plant................................................................................... 43
8.0
AGREEMENT ANDPROCEDURES..............................................................43
8.1
Form of Agreement................................................................................. 43
8.2
Government Procedure...........................................................................43
8.3
Fixed Price............................................................................................... 43
9.0
BONDS.................................................................................................... 44
9.1
Performance Bond..................................................................................44
9.2
10.0
CONTRACT DATA.................................................................................. 44
10.1
Site Data.............................................................................................. 44
10.2
Sufficiency of Tender............................................................................45
10.3
PROGRAMME........................................................................................ 46
12.1
Programme to be Furnished.................................................................46
12.2
12.3
Progress of Works................................................................................46
12.4
13.0
CONTRACTORS SUPERINTENDENCE.....................................................48
Contractors Employees.......................................................................48
13.3
Notice of Objection..............................................................................48
13.4
Proficiency of Languages.....................................................................49
14.0
14.3
14.4
Employer's Equipment.........................................................................50
14.5
15.0
15.1
15.2
15.3
15.4
15.5
Over
15.6
15.9
Urgent Repairs..................................................................................... 54
16.2
Mitigation of Loss.................................................................................55
17.3
17.4
17.5
Notification by Contractor....................................................................58
17.6
18.1
18.2
Returns of Labour................................................................................65
26.1 Delivery.................................................................................................. 68
26.2 Packing and Marking...............................................................................68
26.3 Shipping Documents...............................................................................70
26.5 Overseas Transport.................................................................................71
26.6 Local Transport........................................................................................ 71
26.7 Receiving and Damage Reports..............................................................72
26.8 Unloading and Storage at Site................................................................72
27.0 SUSPENSION OF WORKS.........................................................................73
27.1 Order to Suspend Progress.....................................................................73
27.2 Payment for Plant when Progress Suspended.........................................73
27.3 Resumption of Work................................................................................74
28.0 DEFECTS BEFORE TAKING OVER.............................................................74
29.0 TESTS ON COMPLETION..........................................................................75
29.1 Notice of Tests......................................................................................... 75
29.2 Time for Tests.......................................................................................... 75
29.3 Delayed Tests.......................................................................................... 75
29.4 Facilities for Tests on Completion............................................................75
29.5 Repeat Tests............................................................................................ 76
29.6 Consequences of Failure to Pass Tests on Completion............................76
30.0 EXTENSION OF TIME FOR COMPLETION..................................................77
31.0 DELAYS IN COMPLETION.........................................................................77
31.1 Penalty for Delay in Completion..............................................................77
31.2 Prolonged Delay...................................................................................... 78
31.3 Engineering Services.............................................................................. 78
32.0
TAKING OVER....................................................................................... 79
Contractor to Search............................................................................82
33.11
33.12
Misconduct.......................................................................................... 83
33.13
34
VARIATIONS............................................................................................. 83
37.11
37.12
37.13
37.14
Adjustment to Certificates...................................................................92
37.15
Corrections to Certificates...................................................................92
38.0
PROVISIONAL SUMS.............................................................................92
38.1
Provisional sums.................................................................................. 92
38.2
38.3
39.0
NOMINATED SUB-CONTRACTORS.........................................................93
39.1
Nominated Sub-Contractors................................................................93
39.2
Objections to Nominations...................................................................93
39.3
39.4
39.5
39.6
40.0
PAYMENT CONDITIONS.........................................................................95
40.1
Terms of payment................................................................................ 95
40.2
Provision of Plant.................................................................................95
40.3
Installation of Plant.............................................................................. 96
40.4
41.0
42.0
CURRENT FLUCTUATION......................................................................97
43.0
FOREIGN CURRENCY............................................................................97
43.1
43.2
43.3
Currency Conversion...........................................................................98
43.4
44.0
44.1
Contractor's Default.............................................................................98
44.2
44.3
44.4
45.0
BANKRUPTCY....................................................................................... 99
46.0
OUTBREAK OF WAR...........................................................................100
46.1
Outbreak of War.................................................................................100
46.2
46.3
47.0
47.3
47.4
47.5
48.0
FRUSTRATION.................................................................................... 102
49.0
SETTLEMENT OF DISPUTES................................................................103
50.0
NOTICES............................................................................................ 104
50.1
Notices to Contractor.........................................................................104
50.2
50.3
Change of address.............................................................................104
51.0
TERMINATION OF CONTRACT.............................................................104
52.0
21
INDEX
Clause
20.3
20.4
33.9
20.1
15.7
15.0
17.4
34.8
50.3
37.14
12.4
9.2
37.7
24
8.0
22.3
22.4
37.2
37.9
5.2
22.4
5.3
3.1
18.2
20.3
3.0
45
9.2
9.1
9.0
34.9
15.1
37.13
37.10
25.4
32.1
37.12
37.14
22
Page
61
82
50
85
104
46
64
36
44
44
92
91
79
91
92
Clause
37.2
37.6
37.15
37.8
37.3
37.0
50.3
52
34.8
15.6
33.11
19.2
21.5
53
21.5
30
33.7
31.1
4.2
18.1
10.3
33.8
22.7
34.6
20.5
29.6
16.1
40.4
39.6
10
4
6.2
50.1
17.5
7
44.1
13.2
36
23
Page
87
89
92
90
88
63
77
82
77
45
64
85
55
40
104
58
41
Clause
14.1
36.2
36.1
Page
Contractor's Equipment
Contractor's Equipment, Loss or Damage to
Contractor's Equipment, Removal of
Contractor's Equipment, Removal of on Termination in
case of War
Contractor's Failure to insure, Remedy on
Contractor's Representative
Contractor to Search
CONTRACTORS SUPERINTENDENCE
Correction and Withholding of Interim Certificates
Corrections to Certificates
Cost
Currency Conversion
Currency Conversion relating to Provisional Sums
CURRENT FLUCTUATION
Damage to Persons and Property
46.2
17.7
13.1
33.1
13
37.6
37.15
1.5
43.3
43.4
42
17.3
100
59
15.3
15.5
15.8
15.2
47.3
16
15.4
25.2
33
33.1
28
1.1
1
33.5
39.5
29.3
31
26.1
26
22.7
4.3
5.2
5
24
87
87
Clause
37.8
44.4
14.3
19.3
14.4
22.1
2
2.4
11
2.1
2.3
34.1
2.2
31.3
22.6
14
21.4
6.2
6.3
10.3
5.6
33.4
30
25.3
29.4
22.5
37.13
54
8.3
43
8.1
5.5
20.2
48
33.7
7.1
20
8.2
55.1
55
25
Page
Headings or Notes
Hours of Work
HOURS OF WORK AND RATE PROGRESS
Import Permits and Licenses
Increased Costs arising from Special Risks
Indirect or Consequential Damage
Inspection and Testing during Manufacture
Inspection Authority
Inspection of Drawings
Installation of Plant
Insurance of Works
Clause
1.4
21.1
21
20.6
47.5
16.1
25.1
25.6
5.4
40.3
17.1
17
41
32.4
1.2
38.3
37.1
37.3
22
4.1
18
33.13
15
26.6
36.2
33.2
23.1
35.2
33.12
6
6.1
16.2
47.1
21.2
25.7
39
39.1
34.6
33.3
13.3
29.1
26
Page
NOTICES
Notices to Contractor
Notices to Employer and Engineer
Notification by Contractor
Objections to Nominations
OBLIGATIONS OF THE CONTRACTOR
Observance by Sub-Contractors
Operating and Maintenance Instructions
Operation of Plant
Opportunities for other Contractors
Order to Suspend Progress
Ordering work against Provisional Sums
Orders for Variations to be in Writing
OUTBREAK OF WAR
Outbreak of War
Outline Drawings and Outline Specification
Overseas Transport
Ownership of Plant
Packing and Marking
PATENT RIGHTS
Patent Rights
PAYMENT CONDITIONS
Payment for Plant when Progress Suspended
Payment if Contract Terminated in Case of War
Payment in Rial Omani
Payments after Forfeiture
Payments against Provisional Sums
Penalty for Delay in Completion
Performance Bond
Performance Guarantees
Policies and Local insurances
Power of Engineer to Fix Rates
Procedure and Method
Proficiency of Languages
PROGRAMME
Programme to be Furnished
Progress of Works
Progress with Variation
Projectiles, Missiles etc
Prolonged Delay
Provision of Plant
PROVISIONAL SUMS
27
Clause
50
50.1
50.2
17.5
39.2
7
22.9
5.7
7.4
14.5
27.1
38.2
34.2
46
46.1
5.1
26.5
35.1
26.2
19
19.1
40
27.2
46.3
43.1
44.3
39.4
31.1
9.1
55.2
17.6
34.4
12.2
13.4
12
12.1
12.3
34.7
47.4
31.2
40.2
38
Page
Clause
38.1
23.2
21.3
43.2
26.7
25.5
44
17.7
36.1
Provisional sums
Quality of Materials
Rate of Progress
Rates of Exchange of Currency
Receiving and Damage Reports
Rejection
REMEDIES AND POWERS
Remedy on Contractor s Failure to Insure
Removal of Contractors Equipment
Removal of Contractor's Equipment on Termination in
Case of War
Removal of Defective Work
Repeat Tests
46.2
33.6
29.5
39.3
27.3
37.4
22.1
33.9
14.2
22.8
7.2
49
26.3
1.3
10.1
47
47.2
3.2
37.11
10.2
22.2
27
32
32.2
32.1
56
51
40.1
25
29
28
Page
Clause
17.2
29.2
7.3
26.8
15.9
32.3
44.2
34.3
37.12
37.5
34
34.5
35
23
1.0
1.1
Definitions
29
Page
means
approved
in
writing
including
subsequent
written
confirmation of previous verbal
approval and approval means
approval in writing including as
aforesaid.
(b) Contract
means
the
Instructions
to
Tenderers, Tender Documents,
Standard Conditions of Contract,
Outline
Specification,
Outline
Drawings,
Priced
Bill
of
Quantities*, Schedule of Rates
and Prices, if any*, Tender, the
Letter of Acceptance and the
Form of Agreement.
(c) Contractor
______________________________________________________________________________
*delete where not applicable
30
means
the
Contract
Sum
adjusted to give effect to such
additions or deductions as are
provided for in the contract.
(g) Day
(i) Drawings
(j) Employer
(k) Engineer
means___________________________
_
_________________________________
__________________________________
or other person, persons or firm
appointed from time to time by
the Employer and notified in
writing to the Contractor to act
as the Engineer for the purposes
of the Contract in place of the
said Engineer whose full address
31
32
(o) Month
33
(s) Plant
(v) Site
(w) Specification
(x) Sub-Contractor
means
Nominated
SubContractor (as defined in Clause
39.1) or any person, firm or
company
(other
than
the
Contractor)
named
in
the
Contract for any part of the
Works or any person to whom
any part of the Contract has been
sub-let with the consent in
writing of the Employer, and the
Sub-Contractors legal personal
representatives, successors and
permitted assigns.
34
35
(ab)Works
(ac) Writing
36
1.2
Interpretation
Words importing persons or parties shall include firms and corporations.
1.3
1.4
Headings or Notes
The headings and marginal notes in these Standard Conditions of
Contract shall not be deemed to be part thereof or be taken into
consideration in the interpretation or construction of the Contract.
1.5
Cost
The word Cost shall be deemed to include overhead costs whether
incurred on or off the Site.
2.0
2.1
Engineers Duties
The Engineer shall carry out such duties in issuing decisions and orders
as are specified in the Contract provided that before the issue of orders
which either increase the Contract Price to an amount greater than the
Contract Sum or cause further increase in the Contract Price the
Engineer shall have obtained the specific approval of the Employer as
required by Sultani Decrees No. 48 of 1976 as amended unless such
orders are issued pursuant to Clause 15.9 (Urgent Repairs) hereafter.
The Contractor upon receipt of such an order from the Engineer shall
copy such order to the Employer.
2.2
Engineers Representative
The Engineers Representative shall be responsible to the Engineer and
his duties are to watch and supervise the Works and to test and
examine any Plant or workmanship employed in connection with the
Works. The Engineers Representative shall have no authority to relieve
the Contractor of any of his obligations under the Contract nor, except
as expressly provided in Clause 15.9 to order any work involving delay
in completion or any extra payment by the Employer, nor to make any
variation to the Works.
Where the Employer directly appoints a separate Consultant the
Consulting Engineer may be required to appoint such Consultant to act
as Engineers Representative in pursuance of Clause 2.3 of the
Conditions of Contract.
37
2.3
2.4
3.0
3.1
Assignment
The Contractor shall not assign the Contract or any part thereof or any
benefit, obligation or interest therein or thereunder, otherwise than by a
charge in favour of the Contractors Bankers of any Monies due or to
become due under the Contract, without the prior written consent of the
Employer.
38
3.2
Sub-letting
The Contractor shall not sub-let the whole of the Works. Except where
otherwise provided by the Contract, the Contractor shall not sub-let any
part of the Works without the prior written consent of the Engineer
which shall not be unreasonably withheld. Any such consent, if given,
shall not relieve the Contractor from any liability or obligation under the
Contract and he shall be responsible for the acts, defaults and neglects
of any Sub-Contractor, his agents, servants or workmen as fully as if
they were the acts defaults or neglects of the Contractor his agents
servants or workmen.
4.0
CONTRACT DOCUMENTS
4.1
Languages
4.2
(a)
(b)
All correspondence between the Employer, Engineer and the Contractor shall be in
English.
(c)
The Contractor shall, in the manufacture of the Plant, observe and comply with and
be bound by the laws of the country of manufacture. In the execution of work on
Site and in the erection and operation of the Works the Contractor shall comply
with laws of the Sultanate of Oman,
(b)
The Contractor shall comply fully with the Laws concerning the appointment of
agents, the provision of the regular maintenance and repair facilities together with
the establishment in the Sultanate of Oman of a sufficient amount of spare parts to
ensure the same,
(c)
The Contract shall be governed by and construed in accordance with the Laws of
the Sultanate of Oman,
39
(d)
The Contractor and his Sub-Contractors shall strictly observe the Boycott of Israel
law and no materials shall be supplied which have been manufactured by any firm
which is on the Boycott list nor shall any materials be shipped in any vessel which
is on the said list.
Each delivery of materials shall be accompanied by:
i) a certificate of origin countersigned by the Chamber of Commerce in the
country of origin,
ii) a manufacturers certificate stating that his goods do not include any materials
manufactured or made in Israel; the certificate shall be countersigned by the
nearest Sultanate of Oman Embassy. In countries where the Sultanate of Oman
has no diplomatic representation counter-signatures by any acceptable Arabian
Embassy.
4.3
5.0
5.1
5.2
5.2.1
(a) Strictly within the times stated in the Specification or in the programme to be provided
under Clause 12.0 (Programme), such Drawings, calculations, samples, patterns, models
and information as may be called for therein, and in the numbers therein required or as the
Engineer may reasonably require in order to properly consider the design of the Works.
40
(b) During the progress of the Works and within such times as the Engineer reasonably
may require such Drawings of the general arrangement and details of the Works provided
that the Contractor shall not be under any obligation to supply copies of shop drawings.
5.2.2
(a)
(b)
(c)
(d)
All Drawings shall be in metric and have a title, serial number, issue
record and scale together with the name of the Employer, the Project, the
Engineer and the subject matter.
(e)
The Contractor shall submit Drawings and full particulars of all Temporary
Works to the Engineer before commencing the same. The Engineer may
require modifications to be made if he considers them to be insufficient
and the Contractor shall give effect to such modification but shall not be
relieved of his responsibility for the sufficiency thereof.
41
5.2.3
As far as Drawings, calculations, Specification, data sheets, lists reports or any other
documents are subject to the Engineers approval or comments, the Engineers approval
will be given within twenty eight (28) days of receipt of such documents. If documents
submitted by the Contractor are incomplete and the Engineer is not in a position to check
the documents then the Engineer will inform the Contractor and the above mentioned
twenty eight (28) days period shall start after receipt of the required complementary
information. The same applies if any documents cannot be approved owing to the fact that
mistakes, discrepancies, deviations from the Contract Documents or other inconsistencies
are found and the Contractor is requested to submit the documents after rectification.
If the Engineer shall not approve any Drawing, calculations, sample, patterns or models so
provided the same shall be forthwith modified to meet the requirements of the Engineer
and shall be re-submitted. Approved Drawings shall be signed or otherwise identified by
the Engineer.
All documents submitted for approval shall be accompanied by a transmittal letter, listing
the said documents. The transmittal letters shall be serially numbered, with the relevant
number to be entered on each submitted document.
5.3
Approved Drawings
Drawings approved as above described shall not be departed from except as provided in
Clause 34.0 (Variations). In such case the Contractor shall submit new or amended
Drawings for approval which state clearly the revised reference number together with the
date of the amendment thereto. When approval has been given all copies of the superseded
Approved Drawings shall be clearly marked Superseded.
5.4
Inspection of Drawings
The Engineer shall have the right at all reasonable times to inspect all Drawings
comprising of the works at the premises of the Contractor and that of his Sub-Contractors.
42
5.5
Foundation Drawings
The Contractor shall, as required by the Engineer, within the times stated, provide
Drawings showing the manner in which the Plant is to be affixed together with all
information relating to the Works, required for preparing suitable foundations, for
providing suitable access for the Plant and any necessary equipment to the point on Site
where the Plant is to be erected and for making all necessary connections to the plant
(whether such connections are to be made by the Contractor under the Contract or not).
Such Drawings shall be submitted in due time to allow for incorporation of such
information within the programme for the Works.
5.6
Errors in Drawings
Subject to Clause 6.1 (Mistakes in Information) any and all expenses resulting from an
error or omission in or from delay in delivery of the Drawings and information required in
accordance with this Clause shall be borne by the Contractor.
5.7
5.7.1
The Contractor shall furnish to the Employer as soon as possible and not later than the
period stated in the Appendix to the Form of Tender, before the Works are taken over,
Operating and Maintenance Instructions together with Drawings (other than shop
drawings) of the Works as completed, in sufficient detail to enable the Employer to allow
training of the Employers personnel and to operate, maintain, dismantle, reassemble and
adjust all parts of the Works. Unless otherwise agreed, the Works shall not be considered to
be completed for the purposes of taking over under the terms of Clause 32.0 (Taking Over)
until such Instructions and Drawings have been supplied to the Employer.
5.7.2
Two copies of the final Drawings of the Works as completed As Built Drawings shall be
prepared by the Contractor and forwarded to the Employer. These Drawings shall contain
sufficient detail to enable the Employer to maintain, dismantle, reassemble and adjust all
parts of the Works.
5.7.3
All Drawings incorporated in the operations, instructions and maintenance manuals as well
as all key drawings, i.e., general arrangement drawings, system diagrams, flow diagrams,
single line diagrams, control diagrams, if applicable, and all others considered by the
Engineer to be necessary, shall in addition to the original dimension of the Drawings be
supplied in a reduced size for easy handling.
43
5.7.4
All instruction sheets shall be bound in booklet form and be in the Arabic and English
language containing all information, description of equipment, diagrams, etc., necessary to
enable the Employer to properly operate and maintain the whole of the Works. Such
booklet shall include all possible operating procedures such as star-up, shut-down as well
as operating forms and operators log sheets for all mechanical and electrical plant and
equipment. The various instructions shall be written in a style easily intelligible for the
operating and maintenance personnel explaining, for various situations, what is to be done
and why.
5.7.5
The Contractor shall during the Defects Liability Period revise and/or update the operating
and maintenance instructions and introduce such modifications in the finally bound copies.
5.7.6
The Contractor shall prepare, assemble and submit spare parts lists in accordance with the
Contract Documents for all Plant supplied by him or by his Sub-Contractors.
6.0
6.1
6.2
Errors by Contractor
The Contractor shall at his own expense carry out any alterations or remedial work
necessitated by reason of such discrepancies, errors or omissions for which the is
responsible and modify the Drawings and information accordingly, or if the same be done
by or on behalf of the Employer shall bear all costs reasonably incurred thereby. The
performance of his obligations under this sub-clause shall not relieve the Contractor from
his liability under Clause 5.6 (Errors in Drawings) together with Clause 6.1 (Mistakes in
Information) and under Clause 31.1 (Penalty for Delay in Completion) insofar as that
liability arises as a result of such discrepancies, errors or omissions.
44
45
6.3
Errors by Engineer
The Engineers approval of the Contractors and Sub-Contractors Drawings shall not
relieve the Contractor from his responsibility for errors or omissions which may exist, even
though Works are executed in accordance with such approved Drawings. Where such
errors or omissions are discovered later, they shall be made good by the Contractor at his
own expense irrespective of any approval of the Engineer. Any work executed according to
the decisions, instructions or orders received from the Engineer shall not in any way relieve
the Contractor from his responsibilities for supplying the Plant and executing the Works in
accordance with the Contract unless the Contractor has informed the Engineer upon receipt
and in writing that decision, instruction or order will result in the Contractors breach of
Contract and the Contractor has initiated a query or dispute in accordance with Clause
11.0(b) (Engineers Decisions) and has commenced an action under Clause 49.2 (Notice
for Arbitration).
7.0
7.1
46
7.2
Setting Out
The Contractor shall be responsible for the accurate setting out of the Works in relation to
original points, lines and levels of reference given by the Engineer in writing and for the
correctness, subject as above mentioned, of the positions, levels, dimensions and alignment
of all parts of the Works and for the provision of all necessary instruments, appliances and
labour in connection therewith. If, at any time during the progress of the Works, any error
shall appear or arise in the positions, levels, dimensions or alignment of any part of the
Works, the Contractor on being required so to do by the Engineer shall at his own cost,
rectify such error to the satisfaction of the Engineer, unless such error is based on incorrect
data supplied in writing by the Engineer in which case the Contractor should inform the
Engineer in writing and the cost of rectifying the same shall be borne by the Employer. The
checking of any setting out or of any line or level by the Engineer shall not in any way
relieve the Contractor of his responsibility for the accuracy thereof. The Contractor shall
carefully protect and preserve bench marks, sight rails, pegs and other things used in
setting out the Works.
The Contractor shall give to the Engineer not less than 24 hours notice of his intention to
set out or give levels for any part of the Works so that arrangements may be made for
checking or issuing instructions.
7.3
47
7.4
Operation of Plant
The Contractor shall, if required by the Tender Documents, give a breakdown of prices for
the operation of the Plant for such period or periods stated therein. In the absence of such a
requirement or should the Employer not approve the offer than the obligations of the
Contractor save for Clause 33.0 (Defects after Taking Over) and Clause 15.4 (Damages to
Persons and Property after Taking Over)shall cease upon the issue of the Taking Over
Certificate. In the event that the Employer approves the offer than this shall be subject to a
separate Agreement with its own specific terms and conditions, however, without limiting
the liability of the Contractor under the terms and Conditions contained herein.
8.0
AGREEMENT ANDPROCEDURES
8.1
Form of Agreement
The Contractor shall when called upon so to do enter into and execute a Farm of
Agreement to be prepared and completed at the cost of the Employer in the form annexed
with such modification as may be necessary.
8.2
Government Procedure
The proposed Contract will, if the Contract Sum exceedsR0.500,000.000, be subject to
review by the Cabinet of the Deputy Prime Minister of Legal Affairs of the Sultanate of
Oman, after which the Contract will be signed by the authorised signatory of the Employer
and the Contractor and will then be subject to ratification in accordance with Sultani
Decree No. 48/76 as amended.
8.3
Fixed Price
That Contractor shall not be eligible for any increase in the Contract Sum due to the time
taken by the Employer for the finalisation of the Form of Agreement as stated in Clause 8.2
hereof.
Subject to Clause 52.0 (Changes in Cost and Legislation) this Contract is a Fixed Price
Contract and there shall be no amendment or adjustment of the Contract Sum unless due to
Clause 34.0 (Variations) hereof.
48
9.0
BONDS
9.1
Performance Bond
For the due performance of the contract, the Tender shall contain an undertaking by the
Contractor to obtain, within either 10 days for a local company or 20 days for an
International Company from the date of the Letter of Acceptance, a bond of a bank
registered in the Sultanate of Oman to be jointly and severally bound with the Contractor to
the Employer, in the sum of 5% of the Contract Sum. The said bank shall be approved by
the Employer. The terms of the said bond shall be in accordance with Annexure C and the
cost of obtaining such bond shall be at the expense of the Contractor. Such bond should be
valid until the expiry of the Defects Liability Period. If an increase of the Contract Sum is
mutually agreed upon owing to any changes and/or modifications and/or amendments as
per Clause 34.0 (Variations) the Performance Bond shall be adjusted accordingly.
9.2
10.0
CONTRACT DATA
10.1
Site Data
The Employer shall make available to the Contractor with the Tender Documents such data
on climatic, hydrological and general conditions for the operation of the Works which shall
have been obtained by or on behalf of the Employer from investigations undertaken
relevant to the Works together with information relating to access to the Site. The Tender
shall be deemed to have been based on such data, but the Contractor shall be fully
responsible for his own interpretation thereof.
49
10.2
Sufficiency of Tender
The Contractor by tendering shall be deemed to have satisfied himself as to all the
conditions and circumstances affecting his Tender, including but not limited to the nature
and character of the Works to be executed, the prevailing environmental and ambient
conditions, local uses, codes and conditions, the existing installations (if any), the
possibility of executing the Works as required by the Contract, the general circumstances at
the Site of the Works, and as to the general labour position at the Site, and to have
determined his prices accordingly. The Contractor shall be responsible for all errors made
and for any misunderstanding or incorrect information subject to Clause 6.0 (Mistakes and
Error) hereof. Any information received from the Employer or the Engineer shall not
relieve the Contractor from his responsibility for executing the Works in accordance with
the Contract, including details and apparatus which may not have been specifically
mentioned in the contract but are necessary for ensuring the safe and efficient execution of
the Works.
10.3
11.0
ENGINEERS DECISIONS
The Contractor shall proceed with the Works in accordance with the decisions, instructions
and orders given by the Engineer in accordance with these Standard Conditions of
Contract, provided always that:
(a) If the Contractor shall, within 7 days after being given any decision, instruction or
order otherwise than in writing, require it to be confirmed in writing, such decision,
instruction or order shall not be effective until written confirmation thereof has been
received by the Contractor; and
(b) If the Contractor shall, by written notice to the Engineer within 21 days after receiving
any decision, instruction or order of the Engineer in writing or written confirmation
thereof, dispute or question the decision, instruction or order, giving his reasons for so
doing, the matter shall be referred to the Engineer who shall within a further period of
21 days by notice in writing, with reasons there for, to the Contractor and the
Employer, either confirm, reverse or vary such decision.
50
12.0
PROGRAMME
12.1
Programme to be Furnished
Within the time stated in the Appendix to the Form of Tender following ratification of the
Form of Agreement the Contractor shall submit to the Engineer for his approval a detailed
programme showing, in such form as may be required by the Engineer, the order of
procedure in which he proposes to carry out the Works including the design, manufacture,
delivery to Site, erection and commissioning thereof. The submission to and approval by
the Engineer of such programme shall not relieve the Contractor of any of his duties or
responsibilities under the Contract.
12.2
12.3
Progress of Works
If at any time it should appear to the Engineer that the actual progress of the Works does
not conform to the approved programme, the Contractor shall produce, at the written
request of the Engineer, a revised programme showing the modifications to the approved
programme necessary to ensure completion of the Works within the Time for Completion.
12.4
51
Sub-Contractor's Plant:
-
Other information:
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
____________________________________________________________________________
Such progress information shall be brought up to date every month and shall form the basis for the
follow-up and expediting services to be performed by the Engineer.
(b)
(i)
The Contractor shall submit to the Engineer any and all reasonable information
required by him at any time during manufacture. This information shall clearly and
accurately show the progress of work and the actual state of affairs.
(ii)
During the period of shop fabrication, the Contractor shall submit monthly reports
in conformity with the Engineer's request. Such reports shall show the actual
progress as of the date of the report plotted against the progress schedule as given
in the Contract and shall be broken down to indicate the state of purchased
material, detailed shop fabrication schedule, shipping dates, etc.
(iii)
The inspections and expediting work carried out by the Engineer shall not release
the Contractor from any of his obligations under this Contract.
(iv)
(v)
Travelling expenses (transportation and hotel costs only) incurred by the Engineer
outside of the Sultanate of Oman in connection with co-ordination meetings,
checking the progress of work, expediting of work, necessary routine visits, etc., to
the Contractor's/Sub-Contractors offices and/or premises shall be borne by the
Employer.
52
13.0
CONTRACTORS SUPERINTENDENCE
13.1
Contractor's Representative
The Contractor shall give or provide all necessary superintendence during the execution of
the Works and as long thereafter as the Engineer may consider necessary for the proper
fulfillment of the Contractor's obligations under the Contract. The Contractor, or a
competent and authorised agent or representative approved of in writing by the Engineer,
which approval may at any time be withdrawn, is to be present on the Site during all hours
worked by the Contractor and shall give his whole time to the superintendence of the same.
If such approval shall be withdrawn by the Engineer, the Contractor shall, as soon as is
practicable, having regard to the requirements for a replacement as hereinafter mentioned,
after receiving written notice of such withdrawal, remove the agent from the Works and
shall not thereafter employ him again on the Works in any capacity and shall replace him
by another agent approved by the Engineer. Such authorised agent or representative shall
receive, on behalf of the Contractor, directions and instructions from the Engineer, or,
subject to the limitations of Clause 2.0 hereof, the Engineer's Representative.
13.2
Contractors Employees
The Contractor shall provide and employ on the Site in connection with the execution,
completion and remedying of defects of the Works:
(a) Only such technical assistants as are skilled and experienced in their respective callings
and such sub-agents, foreman and leading hands as are competent to give proper
supervision to the work they are required to supervise; and
(b) Such skilled, semi-skilled and unskilled labour as is necessary for the proper and
timely execution, completion and remedying of defects of the Works.
13.3
Notice of Objection
The Engineer shall be at liberty to object: to and require in writing the Contractor to
remove forthwith from the Works any person employed by the Contractor in or about the
execution, completion and remedying of defects of the Works who, in the opinion of the
Engineer, misconducts himself, or is incompetent or negligent in the proper performance of
his duties, or whose employment is otherwise considered by the Engineer to be undesirable
and such person shall not be again employed upon the Works without the written
permission of the Engineer. Any person so removed from the Works shall be replaced as
soon as possible by a competent substitute approved by the Engineer.
53
13.4
Proficiency of Languages
The Contractor's agent and a reasonable proportion of his technical
assistants shall be capable of speaking, writing and understanding the
language(s} of the Contract Documents. A sufficient number of the
foreman shall have a working knowledge of the language(s) spoken by
the labour employed on the site.
14.0
14.1
Contractor's Equipment
The Contractor shall, at his own expense, provide all Contractor's
Equipment, haulage and power necessary to execute and complete the
Works.
14.2
14.3
15.0
15.1
(i)
Force Majeure
- insofar as they occur within the Sultanate of Oman, war,
hostilities (whether war be declared or not), invasion,
act of foreign enemies, rebellion, revolution, insurrection
or military or usurped power, civil war, riot, commotion
or disorder of persons other than employees of the
Contractor or of his Sub-Contractor or use or occupation
by the Employer of any part of the Works; or
15.2
(ii)
(iii)
15.3
15.4
15.5
Damage to Persons and Property from a cause occurring before Taking Over
57
15.6
If the Employer has to pay or elects to pay any money in respect of any
such claims or demands as aforesaid, the amount so paid and the cost
incurred by the Employer shall be charged to and paid by the
Contractor, provided always that the Employer shall, if circumstances
permit. give to the Contractor reasonable opportunity of examining such
claims or demands before payment. In the event of the Contractor
disputing the amount of any payment (except payments made in
accordance with the legal obligations or after approval of the
Contractor} then the Contractor shall have the right to refer
the matter to arbitration in accordance with Clause 49.2 (Notice for
Arbitration).
59
15.8
15.9
Urgent Repairs
(a)
60
(b)
16.0
16.1
16.2
Mitigation of Loss
In all cases the party establishing a breach of contract shall be under a
duty ta take all reasonable measures to mitigate the loss which has
occurred provided that he can do so without unreasonable
inconvenience or cost. Should he fail so to do, the party in breach of the
Contract may claim a reduction in the damages.
17.0
17.1
Insurance of Works
(a)
The Contractor shall insure the Works to the value of the Contract Sum
plus such other additional sum which in the opinion of the Contractor is
sufficient to cover these additional expenses of a nature incidental to
the Contractors responsibilities under Clause 15.1(Care of Works) which
additional sum shall in any event not be less than 15 per cent of the
Contract Sum and shall be stated in the Appendix to the Form of Tender.
Such insurance shall be effected prior to commencement of the Works in
accordance with Clause 17.6 (Policies and Local Insurance}.
(b)
17.2
17.3
(b)
(c)
17.4
(ii)
(iii)
(iv)
(b)
(c)
(b)
17.5
17.6
Notification by Contractor
(a)
(b)
(b)
65
17.7
18.0
18.1
18.2
19.0
PATENT RIGHTS
19.1
Patent Rights
The Contractor shall fully indemnify the Employer against all claims and
proceedings for or on account of infringement of any letters patent,
66
19.3
20.0
20.1
Foundations
The Contractor if required by the Tender Documents shall give sufficient
information as required by the Engineer to complete the design for the
foundations of all Civil Works for the Project and shall safeguard any
building structure, foundation or approach provided by the Employer in
the existing Plant (if any) for transport, reception, installation and
remedying of defects of the Works covered by this Contract and the
Contractor shall be responsible for the repair at his own expense of any
damage caused by him to these constructions, building structures,
roads, etc.
20.3
20.4
20.5
Consents Wayleaves
The Contractor shall, before the time specified for delivery of any Plant
to the Site, obtain all consents, wayleaves and approvals required in
connection with the Regulations and By-Laws of local or other
authorities which shall be applicable to the Works. The Employer shall, if
so required by the Contractor, provide assistance as is practicable.
20.6
69
21.0
21.1
Hours of Work
Unless otherwise provided in the Outline Specification the Employer
shall five the Contractor facilities for carrying out the Works on the Site
continuously during the normal working hours. The Engineer may, after
consulting with the Contractor, direct that work shall be done at other
times if it shall be practicable in the circumstances for work to be so
done.
21.2
21.3
Rate of Progress
(a)
(b)
21.4
21.5
(b)
(c)
(d)
71
22.0
LABOUR
22.1
Engagement of Labour
The Contractor shall make his own arrangements for the engagement of
all labour local or otherwise and, save in so far as the Contract
otherwise provides, for the transport, housing, feeding and payment
thereof.
22.2
Supply of Water
The Contractor shall, provide on the Site, to the satisfaction of the
Engineer, an adequate supply of drinking and other water for the use of
the Contractors staff and workpeople.
72
22.3
22.4
22.5
22.6
The Contractor shall, in all dealings with labour in his employment, have
due regard to all recognized festivals, days of rest and religious or other
customs.
Epidemics
In the event of any outbreak of illness of an epidemic nature the
Contractor shall cmply with and carry out such regulations, order and
requirements as may be made by the Government of the local medical
or sanitary authorities for the purpose of dealing with and overcoming
the same.
22.7
Disorderly Conduct
The Contractor shall at all times take all responsible precautions to
prevent any unlawful, riotous or disorderly conduct by or amongst his
employees and for the preservation of peace and protection of persons
and property in the neighborhood of the Works against the same.
22.8
(c)
(d)
74
22.9
Observance by Sub-Contractors
The Contractor shall be responsible for observance by his SubContractors of the foregoing provisions.
22.10
Returns of Labour
The Contractor shall deliver to the Engineer at monthly intervals a
return in detail, in such form as the Engineer may prescribe, showing the
supervisory staff and the numbers of the several classes of labour
employed and the Constructional Plant used from time to time by the
Contractor on the Site and such other information as the Engineer may
require.
23.0
23.1
Manner of Execution
23.2
(a)
All Plant to be supplied and all work to be done under the Contract
shall be manufactured and executed in the manner set out in the
approved Drawings and Specifications and other Contract
Documents or where not so set our, all work on Site shall be carried
out to the satisfaction of the Engineer in accordance with such
directions as the Engineer may give.
(b)
(c)
Quality of Materials
(a)
(b)
All equipment and material shall be unused and the best in quality
of their respective kinds.
All Plant shall be treated to resist deterioration due to the severe
prevailing local conditions. Such treatment shall include but not be
restricted to extra coatings of protective materials, insulations, etc.
75
(c)
76
24.0
(a)
(b)
25.0
TESTING OF PLANT
25.1
25.2
25.3
25.4
Certificate of Testing
As and when the Plant shall have passed the tests referred to in this
Clause the Engineer shall furnish to the Contractor a certificate in
writing to that effect.
The Contractor shall furnish copies of the relevant test data relating to
the test carried out to be distributed in accordance with the Outline
Specifications.
25.5
Rejection
(a)
(b)
78
(c)
79
25.6
25.7
Inspection Authority
(a)
(b)
No Reduction of Liability
Any decision, instruction, rejection or approval by the Engineer or the
Inspection Authority shall not release the Contractor from his obligations
to execute the Works in accordance with the Contract.
26.0
DELIVERY OF PLANT
26.1
Delivery
Unless the Engineer shall otherwise direct, no Plant shall be delivered to
Site until the Engineer shall have issued, in respect of such Plant, a
certificate under Clause 25.4 (Certificate of Testing). Such Plant shall be
delivered to Site only upon an authorization in writing applied for and
obtained by the Contractor from the Engineer.
The Contractor shall be responsible for the reception on Site of all Plant
delivered for the purposes of the Contract.
26.2
(b)
80
(c)
(d)
(e)
(f)
(g)
The markings on the box, case and/or bundle shall be carried out
by means of block letters not less than 30mm high to be stenciled
to the box, case and/or bundle with black indelible paint with the
following information:
1.
EMPLOYER
: GOVERNMENT OF SULTANATE OF
OMAN MINISTRY OF________________
2.
3.
4.
5.
6.
7.
8.
9.
10
PROJECT
:
CONTRACT REFERENCE NO. :
CONTRACTOR*
:
SUB-CONTRACTOR*
:
PORT OF DESTINATION
:
CONSIGNMENT SERIAL NO. :
GROSS WEIGHT
:
NET WEIGHT
:
SIZE OF BOX
(LENGTH X WIDTH X HEIGHT):
11. BRIEF INDICATION
OF CONTENTS*
:
81
______________________________________________________________________________
*delete where not applicable
26.3
Shipping Documents
(a) The Contractor shall submit complete and full shipping documents
soonest after shipping, in order to reach the Employer and the
Engineer before the arrival of the ship. Responsibility for delays, loss
or damages of shipping documents shall rest with the Contractor.
(b) The shipping documents shall be distributed as follows:
________________________________________________________________________
FOR THE
FOR THE
Documents
EMPLOYER
ENGINEER
_________________________________________________________________________
Shipping Invoice for the consignment
-
Original
Copy
Packing List
1
3
2
1
1
1
1
1
Bill of Lading
-
Original
Copy
Certificate of Origin
-
Original
Copy
Manufacturers Certificate as
per Boycott Status (Clause 4.2(d)
Compliance with Laws)
-
Original
Copy
_________________________________________________________________________
82
26.4
26.5
Overseas Transport
When carrying out overseas transport either by sea by air the special
provisions, laws and regulations concerning transportation shall be
taken into consideration.
26.6
(a)
(b)
(c)
Local Transport
(a)
The Contractor shall arrange and carry out under his own
responsibility and supervision the local transport from the port of
disembarkation to the Site.
(b)
83
highways and bridges. The Contractor shall bear every and all
expenses related herewith.
(c)
84
26.7
26.8
(b)
The Contractor shall carefully unload all imported Plant at the Site
from trucks and trailers and delivery vehicles including barges if
any, as the case may be. Items of permanent installation shall be
properly and neatly stored in areas designated by the Engineer
and shall be protected to prevent damage or deterioration of any
type. Storage methods shall be such as the cause minimum
inconvenience to others and shall be arranged to facilitate
inspection and withdrawing from stores. All facilities for Plant
storage shall be subject to the approval of the Engineer.
(b)
86
27.0
SUSPENSION OF WORKS
27.1
(b)
(c)
(d)
Necessary for the proper execution of the Works or for the safety
of the Works or any part thereof in so far as such necessity does
not arise from any act or default by the Engineer or form any of
the excepted risks.
Provided that the Contractor shall not be entitled to recover any such
extra cost unless within 28 days after receipt of the order to suspend
progress of the Works he gives to the Engineer notice in writing of his
intention to make such claim.
27.2
three months or (if later) at the time when, but for such suspensions,
the Plant or such Portion thereof would have been delivered; provided
this Sub-Clause shall not apply if the suspension is within paragraphs
(a), (b) or (c) of Sub-Clause 1 of this Clause; and further provide that the
Contract Price of any Plant that according to the decision of the Engineer
is defective or not in accordance with the Contract shall not be include
in such Certificate.
88
27.3
Resumption of Work
If the progress of the Works or any Section thereof is suspended
pursuant to Sub-Clause 1 of this Clause and if permission to resume
work is not given by the Engineer within 90 days after the date of
suspension, then unless the suspension is within paragraphs (a), (b), (c)
or (d) of that Sub-Clause, the Contractor may serve notice in writing on
the Engineer requiring permission within 28 days after receipt thereof to
proceed with the Works or the Section in regard to which progress is
suspended and, if such permission is not granted within that time, the
Contractor may by a further notice in writing to the Engineer elect or
treat the suspension where it affects a Section of the Works as an
omission of such Section under Clause 34 (Variations) or where the
suspension affects the whole of the Works as an abandonment of the
Contract by the Employer.
28.0
(b)
(c)
then the Contractor shall with all speed and, at his own expense, make
good the defects so specified. In case the Contractor shall fail so to do
the Employer may, provided he does so without undue delay, take at the
cost of the Contractor such steps as may in all the circumstances be
reasonable to make good such defects. All Plant provided by the
Employer to replace defective Plant shall comply with the Contract and
shall be obtained at reasonable to make good such defects. All Plant
provide by the Employer to replace defective Plant shall comply with the
contract and shall be obtained at reasonable prices and where
reasonably practicable under competitive conditions. The Contractor
shall be entitled to remove and retain all defective Plant that the
Employer may have replaced at the Contractors cost. Nothing
contained in this Clause shall affect any claim by the employer under
Clause 31.0 (Delays in Completion).
89
29.0
TESTS ON COMPLETION
29.1
Notice of Tests
The Contractor shall give to the Engineer, with a copy to the Employer,
21 days notice in writing of the date after which he will be ready to
make the tests on Completion. Unless otherwise agreed the tests shall
take place within 10 days after the said date on such day or days as the
Engineer shall notify the Contractor in writing.
29.2
29.3
Delayed Tests
If in the opinion of the Engineer the tests are being unduly delayed he
may, by notice in writing, call upon the Contractor to make such tests
within 21 days from the receipt for the said notice, and the Contractor
shall make the said tests on such days within the said 21 days as the
Contractor may fix and for which he shall give advance notice to the
Engineer. If the Contractor fails to make such tests within the time
aforesaid the Engineer may himself proceed to make the tests. All tests
so made by the Engineer shall be at the risk and expense of the
Contractor unless the Contractor shall establish that the tests were not
being unduly delayed in which case tests so made shall be at the risk
and expense of the Employer.
29.4
90
29.5
Repeat Tests
If any Portion of the Works fails to pass the tests, then test of the said
Portion shall, if required by the Engineer or by the Contractor, be
repeated within a reasonable time upon the same terms and conditions,
save that all reasonable expenses to which the Employer may be put by
the repetition of the tests shall be deducted from the Contract Sum.
29.6
(b)
(c)
91
30.0
(b)
(c)
(d)
(e)
(f)
31.0
DELAYS IN COMPLETION
31.1
93
31.2
Prolonged Delay
If the Works or any Portion of the Works in respect of which the
Employer has become entitled to the maximum amount of the penalty
under Sub-Clause 1 of this Clause remains uncompleted the Engineer
may by notice in writing to the Contractor require him to complete and
by such notice fix a final time for completion which shall be reasonable
having regard to such delay as has already occurred. If for any reason,
other than for which the Employer or some other Contractor employed
by his is responsible, the Contractor fails to complete within such time,
the Engineer may by further written notice to the Contractor elect
either:
(a)
(b)
or
(c)
and recover a penalty from the Contractor by reason of the said failure
the total amount stated in the Appendix to the Form of Tender for the
prolonged delay or in the event of a termination concerning the whole of
the Works then the Employer shall recover from the Contractor in
addition to the Penalty for the prolonged delay the whole of the Contract
Price for that part relating to the said Portion.
The Employer may without prejudice to any other method of recovery
deduct the amount of such penalties from any monies in his hands due
or which may become due to the Contractor. The payment or deduction
or such penalties shall not relieve the Contractor from his obligation to
complete the Works or form any other of his obligations and liabilities
under the Contract.
31.3
Engineering Services
If the Contractor shall fail to achieve completion of the Works within the
time prescribed by Clause 7.1 (General Obligations) hereof, then the
Contractor shall pay to the employer the sum stated in the Appendix to
the Form of Tender as a payment for extended Engineering Services for
every day or part of a day which shall elapse between the time
prescribed by Clause 7.1 hereof and the date of certified completion of
the whole Works. The Employer may, without prejudice to any other
method of recover, deduct the amount of such compensation form any
monies in his hands, due or which may become due to the Contractor.
94
95
32.0
TAKING OVER
32.1
32.2
32.3
(Care of the Works) shall not apply to any Portion of the Works while
being so used by the Employer.
32.4
(b)
(c)
33.1
98
33.2
(b)
From any act or omission of the Contractor done or omitted
during the said period.
33.3
Notice of Defects
If any such defect shall appear or damage occur the Employer or the
Engineer shall forthwith inform the Contractor thereof stating in writing
the nature of the defect or damage. The provisions of this Clause shall
apply to all replacements or renewals carried out by the Contractor to
remedy defects and damage as if the said replacements and renewals
had been taken over on the date they were completed to the
satisfaction of the Engineer but not so as to extend the Defects Liability
Period in respect thereof beyond two years from the date of taking over
or such other greater period as may be stated in the Appendix to the
Form of Tender.
33.4
33.5
33.6
99
33.7
33.8
Conditions Applicable
These Standard Conditions of Contract shall apply to all inspections,
adjustments, replacements and renewals and to all tests occasioned
thereby, carried out the Contractor pursuant to this Clause.
33.9
Right of Access
Until the final certificate of payment shall have been issued, the
Contractor shall have the right of access to all parts of the Works for the
purpose of inspecting the working thereof and to records of the working
and performance thereof for the purpose of inspecting the same and
taking notes therefrom during normal working hours, at his own risk and
expense, for himself or his duly authorized representatives, whose
names shall have previously been communicated in writing to the
Engineer. The Contractor may at his own risk and expense make any
test which he considers desirable subject to the Engineers approval,
which shall not be unreasonable withheld.
33.10
Contractor to Search
The Contractor shall, if required by the Engineer in writing, search for
the cause of any defect, imperfection or fault under the direction of the
Engineer. Unless such defect, imperfection or fault shall be one for
which the Contractor is liable under the Contract, the cost of the work
carried out shall be borne by the Employer. But if such defect,
imperfection or fault shall be shown to be one for which the Contractor
is liable as aforesaid the cost of the work carried out in searching
aforesaid shall be borne by the Contractor.
33.11
property not forming part of the Works arising after the expiration
of the Defects Liability Period nor for loss of profit unless it is
shown form the circumstances of the case that the Contractor has
been guilty of misconduct and the circumstances giving rise to
the claim occur within four years after the date of taking over. The
Contractor shall have no liability under this Sub-Clause in respect
of any claim unless notice thereof has been given by the
Employer to the Contractor within 90 days after the event giving
rise to the claim.
101
(b)
33.12
Misconduct
Misconduct comprises any and every lack of care or skill, and means
an act or omission on the part of the Contractor resulting from either a
failure to pay due regard to the serious consequences of an cat or
omission which a conscientious and reasonable Contractor would
foresee as likely to ensure, or a deliberate disregard of any
consequences of such act or omission.
33.13
34
VARIATIONS
34.1
(c)
(d)
Change the levels, lines, position and dimensions of any part of
the Works; and
(e)
Execute additional work of any kind necessary for the completion
of the Works.
102
and no such variation shall in any way vitiate or invalidate the Contract,
but the value, if any, of all such variations shall be taken into account in
ascertaining the amount of the Contract Price.
103
34.2
34.3
Valuation of Variations
All extra or additional work done or work omitted by order of the
Engineer shall be valued at those rates and prices set out in the
Contract id, in the opinion of the Engineer, the same shall be applicable.
If the Contract does not contain any rates or prices applicable to the
extra or additional work then suitable rates or prices shall be agreed
upon between the Engineer and the Contractor.
34.4
(b)
104
34.5
34.6
34.7
34.8
105
106
34.9
35.0
35.1
Ownership of Plant
Plant supplied or to be supplied pursuant to the Contract shall become
the property of the Employer at whichever is the earlier of the following
times:
35.2
(a)
(b)
(c)
Marking of Plant
Where the property in Plant passes to the Employer prior to the delivery
to the Site of such Plant the Contractor shall so far as is practicable and
to the reasonable satisfaction of the Engineer set the Plant aside and
mark the Plant as the property of the Employer. In the event of the
Contractor failing so to set aside and mark the Plant as aforesaid the
Engineer shall be entitled to withhold any interim certificate for that
Portion to which the Contractor may otherwise be entitled.
Such Plant shall be in the care and possession of the Contractor solely
for the purposes of the Contract and shall not be within the ownership of
disposition of the Contractor and any interim certificate issued by the
Engineer shall be without prejudice to the exercise of any power of the
Engineer contained in the Contract to reject Plant which is not
accordance with the Contract and upon any such rejection the property
in the rejected Plant shall immediately revert to the Contractor.
107
36.0
CONTRACTORS EQUIPMENT
36.1
36.2
37.0
37.1
Certificate of Payment
The Contractor may at the times and in the manner following apply for
interim and final certificates as referred to in Clause 40.0 (Payment
Conditions) for Plant shipped and en route to the Site and for work
executed on the Site.
37.2
108
______________________________________________________________________________
*delete where not applicable
(c)
Arrival on Site
Each such application in respect of arrival of the Plant on Site shall be
accompanied by a receiving report and if applicable a damage report in
accordance with Clause 26.7 (Receiving and Damage Reports).
(d)
Installation and Erection
Each such application in respect of installation or erection of the Plant
forming part of the Permanent Works shall state the stage reached as
set out in the detailed progress schedule.
(e)
Taking Over
Each such application in respect of Plant which has satisfactorily passed
the tests on completion shall be accompanied by the Taking Over
Certificate.
(f)
Civil Works
Each such application in respect of the Civil Works associated with the
Works shall be accompanied by a statement by the Contractor detailing
the stage reached as set out in the detailed progress schedule.
In each such application the Contractor shall state the amount claimed
and shall set forth in detail, in the order of the schedule of prices,
particulars of the work executed as set out in Clause 12.4 (Advanced
Detailed Progress of Plant Schedule) pursuant to the Contract to a date
named in the application and since the period covered by the last
preceding certificate, if any, which includes work on Site.
37.3
37.4
Retention Money
(a)
The Engineer shall make a deduction of a sum equal to 10
percent of the amount due to the Contractor under Sub-Clause 5 (Value
of Interim Certificates) related to interim certificates only until a reserve
shall have accumulated in the hands of the Employer up to the limit of
5% of the Contract Sum.
109
b)
Upon issue of the Taking Over Certificate with respect to the
whole of the Works 50 per cent of the retention money (or where a
Taking Over Certificate is issued with respect to such Section of the
Works only such proportion of 50 per cent of the retention money as the
Engineer shall determine have regard to the relative value of such
Section of the Works) shall become due and payable to the Contractor.
(c)
Upon expiration of the Defects Liability Period for the whole of the
Works the Outstanding retention money shall become due and payable.
(d)
Provided that if, at such time, there shall remain to be executed
by the Contractor any outstanding defects referred to under Clause 32.1
(Taking Over Certificate) or any works ordered during such period
pursuant to Clause 33.2 (Making Good Defects) the Employer shall be
entitled to withhold payment until the completion of such works of as
much money as shall in the opinion of the Engineer represent the costs
of the Works outstanding.
37.5
(b)
(c)
Any sums which are due and payable to the Employer by the
Contractor under the terms of the Contract,
(d)
Any previous payments made by the Employer to the Contractor
under the terms of the Contract.
Provided that no sum shall be included in any interim certificate in
respect of any Works that, according to the decision of the Engineer,
does not comply with the Contract, or Plant has been brought and is at
the date of the certificate prematurely upon the Site.
37.6
him and the Engineer shall have the power to withhold any interim
certificate:
(a)
If the Works or any part thereof are not being carried out, to his
satisfaction in accordance with the Contract, or
(b)
(c)
Because of a requirement in writing for necessary additional
supporting documents or details, or
(d)
Where the Contract expressly gives the Employer the right to
deduct monies form sums due under the Contract.
37.7
Advance Payments
(a)
Unless stated otherwise the Contract provides for a payment in
advance, for Plant and Civil Works, [Clause 40.2 (a) (Provision of Plant),
40.3 (Installation of Plant) and 40.4 (Construction of Building, Civil
Engineering Works) refers] and any amounts becoming due to the
Contractor in respect thereof shall be included in interim certificates.
(b)
On signing the Form of Agreement and in exchange for the
Performance Bond and a separated bond for the amount of the Advance
Payment the Contractor shall receive from the Engineer an Advance
Payment Certificate for an amount equal to 10 per cent for the Contract
Sum less any sum for contingencies included in the Contract Sum.
Any Advance Payment made by the Employer shall be recovered by the
deduction, from each interim certificate, of 10 per cent of the gross
value of the certificate so that at the completion of the Works the
Contractor shall have repaid in full the total amount of the Advance
Payment.
In the event of the Contract being determined under Clause 44.1
(Contractors Default), Clause 46.0 (Outbreak of War), Clause 47.0
(Special Risks), the Employer may deduct the balance of the Advance
Payment outstanding from any monies due or which may become due to
the Contractor or the Contractor shall upon demand pay to the Employer
the amount of such balance and it shall be deemed a debt due form the
Contractor to the Employer and shall be recoverable accordingly from
the Contractor or from the Bank issuing the bond.
37.8
111
37.10
37.11
together with all further sums which the Contractor considers to be due
to him under the Contract. After receipt of this final account and of all
information reasonably required for its verification the Engineer shall
after the expiry of the Defects Liability Period issue a Final Account
Certificate stating:
37.12
(a)
The amount which in his opinion is finally due under the Contract
and (after giving credit to the Employer for all amounts previously
paid by the Employer and for all Sums to which the Employer is
entitled under the Contract),
(b)
37.13
37.14
Adjustment to Certificates
If any sum shall become payable to the Contractor under the Contract
otherwise than for work executed or Plant delivered the amount thereof
shell be included in the next certificate (interim or final) issued by the
Engineer, and if any sum shall become payable under the Contract by
113
the Contractor to the Employer, prior to the issue of the Final Account
Certificate, whether by deduction from the Contract Price or otherwise,
the amount thereof shall be deducted in the next certificate.
37.15
Corrections to Certificates
The Engineer may in any certificate give effect to any correction or
modification that should be made in respect of any previous certificate.
38.0
PROVISIONAL SUMS
38.1
Provisional sums
'Provisional Sum means a sum included in the Contract and so
designated therein for the execution of work or the supply of goods,
materials or services, or for contingencies, which sum may be used, in
whole or in part, or not at all, at the direction and discretion of the
Engineer who shall consult with the Employer prior to the issue of an
instruction in respect of the expenditure of such sum. The total sum paid
to the Contractor shall include only such amounts in respect of the work,
supply or services to which such Provisional Sums relate as the Engineer
shall approve or determine in accordance with this Clause.
38.2
(b)
114
(c)
38.3
39.0
NOMINATED SUB-CONTRACTORS
39.1
Nominated Sub-Contractors
All specialists, merchants, tradesmen and others executing any work or
supplying any goods, materials or services for which Provisional Sums
are included in the Contract, who may have been or he nominated or
selected or approved by the Employer and all persons to whom by virtue
of the provisions of the Contract the Contractor is required to sub-let any
work shall, in the execution of such work or the supply of such goods,
materials or services, be deemed to be Sub-Contractors employed by
the Contractor and are referred to in this Contract as Nominated subContractors.
39.2
Objections to Nominations
The Contractor shall not be required by the Employer or the Engineer or
be deemed to be under any obligation to employ any Nominated SubContractor whose performance warranties are not acceptable to the
Contractor or against whom the Contractor may raise reasonable
objection, or who shall decline to enter into a sub-contract with the
Contractor containing provisions that:
(a)
115
(b)
39.3
39.4
39.5
(a)
(b)
116
(a)
(b)
40.0
PAYMENT CONDITIONS
40.1
Terms of payment
Unless otherwise agreed the Employer shall pay to the Contractor in the
following manner the Contract Sum adjusted to give effect to such
additions thereto and such deductions therefrom as are provided in
these Standard Conditions of Contract.
40.2
Provision of Plant
(a)
(c)
_______________________________________________________________________________
*NOTE: The Employer shall complete this Sub-Clause prior to the issue of
Contract
** delete where not applicable.
*** inclusive of related value for Shipping and Insurance only.
40.3
(d)
(e)
(f)
Installation of Plant
(a)
(b)
118
40.4
(c)
(d)
(b)
(c)
10% within sixty (60) days from the date of issue of the Taking
Over Certificate of the whole of the Works.
(d)
within sixty (60) days from the date of the issue of the Final
Acceptance Certificate or Final Account Certificate whichever is
later in respect of the entire Works, a payment equivalent to 15%
of the value of the entire executed Building and Civil Engineering
works as certified by the Engineer and approved by the Employer.
_________________________________________________________________________
*** inclusive of related value for Shipping and Insurance only.
41.0
42.0
CURRENT FLUCTUATION
Should the Contract provide for payment of either Part or the whole of
the Contract Sum in Rials Omani but that this sum is based on a foreign
currency rate then if after the opening of Tenders and prior to signature
of the Form of Agreement there should occur a change in the rates of
exchange as stated in Clauses 43.2 (Rates of Exchange of Currency) and
43.3 (Currency Conversion} hereby then the Employer reserves the right
119
FOREIGN CURRENCY
43.1
43.2
43.3
Currency Conversion
Where the Employer shall have required the Tender to be expressed in a
single currency but with payment to be made in more than one currency
and the Contractor has stated the proportions or amounts of other
currency or currencies in which he requires payment to be made, the
rate or rates of exchange applicable for calculating the payment of such
proportions or amounts shall be those prevailing, as determined by the
Central Bank of the Sultanate of Oman on the latest date for the
submission of tenders for the Works, as shall have been notified to the
Contractor by the Employer prior to the submission of tenders or as
provided for in the Tender Documents.
120
43.4
44.0
44.1
Contractor's Default
If the Contractor shall assign the Contract, without the consent in writing
of the Employer first obtained, or if the Engineer shall certify in writing
to the Employer that in his opinion the Contractor:
(a)
(b)
(c)
then the Employer may, after giving fourteen days notice in writing to
the Contractor, enter upon the Site and expel the Contractor therefrom
without thereby voiding the Contract, or releasing the Contractor from
any of his obligations or liabilities under the Contract, or affecting the
rights and powers conferred by the Contract on the Employer or the
Engineer and may himself Complete the Works or may employ any other
Contractor to complete the Works without prejudice to any other remedy
of the Employer. The Employer
or such other Contractor shall have free use for such completion of so
much of the Contractor's Equipment as may be on the Site in connection
with the Works without being responsible to the
Contractor for fair wear and tear thereof and to the exclusion of any
right of the Contractor over the same.
121
44.2
44.3
44.4
45.0
BANKRUPTCY
If the Contractor shall become bankrupt or insolvent, or have a receiving
order made against him, or compound with his creditors, or, being a
corporation commence to be wound up, not being a members voluntary
winding up for the purpose of amalgamation or reconstruction, or carry
on its business under a receiver for the benefit of its creditors or any of
them, the Employer shall be at liberty:
(a)
OUTBREAK OF WAR
46.1
Outbreak of War
If during the currency of the Contract there shall be an outbreak of war
(whether war is declared or not) in any part of the world which, whether
financially or otherwise, materially affects the execution of the Works
the Contractor shall, unless and until the Contract is terminated under
the provisions in this Clause contained, use his best endeavours to
complete the execution of the Works, provided always that either the
Employer or the Contractor shall be entitled, at any time after such
outbreak of war, to terminate this Contract by giving notice in writing
one to the other, and upon such notice being given this Contract shall
(save as to the rights of the parties under this Clause and to the
Operation of Clauses 47.0 [Special Risks] and 48.0 [Frustration)
terminate, but without prejudice to the rights of either party in respect
of any antecedent breach thereof.
46.2
46.3
SPECIAL RISKS
47.1
47.2
124
The special risks where these take place in the Sultanate of Oman are
the nuclear and pressure wave risks described in Clause 15.1 (b) (i)
(Care of Works), war, hostilities (whether war be declared or not),
invasion, act or foreign enemies, rebellion, revolution, insurrection,
military or usurped power, civil war or, riot, commotion or disorder of
persons other than the employees of the Contractor or his SubContractors.
47.3
47.5
FRUSTRATION
Should the Contractor be obstructed or delayed in the commencement,
execution or completion of his work by any necessary or unavoidable act
or delay of the Employer or by a cause in the Sultanate of Oman being a
riot, insurrection, war, blockade, revolution, civil commotion, pestilence,
acts of public authorities, fire, explosion, lightning, earthquake, cyclone,
tidal waves, typhoons, hurricanes, tornadoes, floods, plague, epidemics,
quarantine, strikes or other labour troubles or similar causes unforeseen,
not caused by and beyond the control of the Contractor; and if in the
opinion of the Engineer, the ultimate completion of the entire Works is
delayed thereby, then the Contract dates will be extended for a period
equivalent to the time the said work as a whole has been delayed for
said reason, provided that within seven (7) days the Contractor submits
to the Engineer for approval notice in writing stating in detail the reason
for each delay caused by frustration or Force Majeure.
49.0
SETTLEMENT OF DISPUTES
If any dispute or difference of any kind whatsoever shall arise between
the Employer and the Contractor or the Engineer and the Contractor in
connection wish, or arising out of the Contract, or the execution of the
Works, whether during the progress of the Works or after their
completion and whether before or after the termination, abandonment
or breach of the Contract, it shall be referred to and settled by the
Engineer who shall, within a period of ninety days after being requested
by either party to do so, give written notice of his decision to the
Employer and the Contractor. Such decision in respect of every matter
so referred shall be final and binding upon the Employer and the
Contractor, and shall forthwith be given effect to by the Employer and
by the Contractor, who shall proceed with execution of the Works with
all due diligence whether he or the Employer requires arbitration, as
hereinafter provided, or not. If the Engineer has given written notice of
his decision to the Employer and the Contractor and no Claim to
arbitration has been communicated to him by either the Employer or the
Contractor within a period of ninety days from receipt of such notice, the
said decision shall remain final and binding upon the Employer and the
126
50.0
NOTICES
50.1
Notices to Contractor
All certificates, notices or written orders to be given to the Contractor by
the Employer or the Engineer under the terms of the Contract shall be
served by sending the same by post, cable, telefax or telex or by leaving
the same at the Contractors principal place of business or to such other
address as the Contractor shall nominate for that purpose.
127
50.2
50.3
Change of address
Either party to the Contract or the Engineer may change its nominated
address by prior written notice to the others.
51.0
TERMINATION OF CONTRACT
The Employer shall have the right to terminate the Contract if it should
become necessary for the Employer to postpone or discontinue the
Works for any reason whatsoever. In the event of termination, the
Employer shall pay to the Contractor the relevant Contract Price in
accordance with criteria stated in Clause 46.3 (Payment of Contract
Terminated in Case of War) for the Works performed up to the date of
termination together with a reasonable allowance for profit and costs of
settlement.
52.0
(a)
53.0
54.0
FIRE PRECAUTIONS
The Contractor shall conform to the regulations of the Employer and any
other controlling authority in force at the Site of the Works with respect
to precautions to be taken against fire hazards.
55.0
GUARANTEES
55.1
129
55.2
Performance Guarantees
The Contractor shall comply with the performance and other guarantees
as stipulated in the Outline Specification, for Mechanical and Electrical
Works, the Civil and Building Works, the Schedules of Guarantees, the
Schedules of Technical Data, the Specifications and/or other Contract
Documents.*
56.0
(b)
130
ANNEXURE A
FORM OF TENDER BOND
H.E. The Chairman
Tender Board
P. O. Box 787
Muscat
Sultanate of Oman
Tender Bond NO.
By
this
bond
we
..
is
....
.
whose
address
..
hereby guarantee Messrs ....
..
of
..
and
hold
at
your
disposal
the
sum
of
RO
....
and/or
..
..
being
of
the
Tender
Sum
from
.until
Authorized Signature
(To be issued by a locally registered bank)
132
ANNEXURE B
FORM OF ADVANCE PAYMENT BOND
Ministry of Finance and Economy
P. O. Box 506
Muscat
Sultanate of Oman
Advance Payment Bond NO.
Whereas
(hereinafter called the Contractor) has been awarded a Contract dated
.. to execute, complete and remedy the defects of
the
.. for the
value of RO ( Rials
Omani
..and/or
.) to the Contractor
being 10% of the Contract Sum, less any sum for Contingencies included in the
Contract
Sum,
by
this
bond,
we
whose
address is .. guarantee to
pay
you
a
sum
not
exceeding
RO
.
and/or ..
.
on your first written demand without reference to or contestation on behalf of
the Contractor.
It is understood that our liability towards you will be progressively reduced by
the amount repaid to you by the Contractor as contained in the Certificates
and Payments against the said advance payment.
This bond should be returned to us upon its expiry or upon fulfilment of our
undertaking whichever is the earlier.
__________________
Authorized Signature
134
ANNEXURE C
FORM OF PERFORMANCE BOND
Ministry of Finance and Economy
P. O. Box 506
Muscat
Sultanate of Oman
Advance Payment Bond NO. ..
Whereas ....
whose address is .
.
are held and firmly bound unto the Government of the Sultanate of Oman
represented by the Ministry of Finance and Economy, Muscat in the sum of RO
..
and/
or
being 5% of the Contract Value.
We agree to make unconditional payment under this bond on your first written
demand without any reference to or contestation on behalf of the Contractor
provided the claim is received by us on or before.
The bond will be effective from .. and shall be
valid until the after which date our liability shall
automatically cease.
This bond should be returned to us upon its expiry or upon fulfillment of our
undertaking whichever is earlier.
__________________
135
Authorized Signature
136