Академический Документы
Профессиональный Документы
Культура Документы
(b)
Introduction
IIL
A TRENCH
(c)
Previous work
of
method
empirical
An
predicting
Strain gauges
To datum 20m
A major research
0
E
0
30
a'
Strain gauges
Taping/levelling
Inclinometer/settlement
ct.
point
gauges
Piezometer
5 metres
*Geotechnics
Fig.
f. Detailed
trench experiment
typical
0.5
2
t
I
I
I
I
I
I
I
I
10
10
movement
0
10
(mm)
10
0
10
10
0
I
I
II
-3
o.
aCL 4
I
I
I
28
Ground
Engineering
j
I
6.5
I
(mm)
10
5
I
I
I
I
tube profiles
movement
0
10
4.5
I
t
I
I
Horizontal
Horizontal
-0
plan layout
Fig.
profiles
15
04
I
I
I
I
I
0.5
I
I
Lv
Horizontal
movement
10
0
0
10
Horizontal
(mm)
0-
I
I
oC
20
10
20
0
10
I
1.9
1
4.2
movement
7.1
(mm)
0
20
10
20
10
4
E
vo.
Cl
I
I
I
I
I
I
I
I
4
E
II
II
I
I
I
I
I
I
I
10-
10
Fig. 4. Site 3;inclinometer tube profiles
tion of pipe strain adjacent to a trench.
Both methods have yet to be checked
against field measurements.
Records of ground movements available
to date are limited to those published by
TRRL (Symons, 1980) and British Gas
(Howe et al, 1980) from which the figures presented in Table I have been ex-
tracted.
Movement due to trench excavation on
any one contract can vary over small distances along the length of the trench even
where the factors controlling the movement
are apparently similar. Hence in practice,
statistical analysis of a large sample of
field data, and development of an empirical
model of ground movement, may provide
the best approach to a practical method
of prediction.
Field experiments
In order to substantially
increase the
available data on ground movements induced by current trenching practice, measurements
of surface and subsurface
movement are currently being carried out
at a large number of Water Authority sites
throughout England and Wales. The field
experiments take two forms; simple experiments in which horizontal and vertical
are recorded
ground surface movement
along a line perpendicular to the direction
of a passing trench, and more detailed experiments in which ground movements at
depth are monitored using inclinometers
and settlement gauges, and pipe strain is
measured
by means of strain gauges
mounted on adjacent mains (Fig. 1). In
both cases the instruments are read prior
to, during, and, where possible, for a long
period (up to 2 years) after excavation.
The results of up to 50 simple experiments are expected to be available by the
end of the programme. A total of six or
more detailed experiments in a variety of
ground conditions will be carried out. Four
of the latter have been carried out to date,
the results of which are summarised
Fig.
below.
Site 1
At this site a sewer was under construction in a rural area. The trench was 4.5m
deep by a nominal 1.5m wide. Ground
conditions comprised silty sands and gravels to a depth of 3m and silty sandy clay
below 3m. Groundwater level was about
2m below ground level. The trench support
system consisted of 3m long by 2.4m high
trench boxes.
Maximum horizontal and vertical movements of the order of 7mm and Smm
respectively were recorded immediately
excavation and reinstatement.
following
Movement
during Sq months
following
reinstatement has been very small (1-2mm
or less).
The maximum recorded change in strain
on a 100mm dia. main parallel to the trench
and 1.8m distant was 75 microstrain. This
strain has decreased significantly (possibly as a result of seasonal temperature
variation) since trench reinstatement.
Profiles of inclinometer
tubes located
along a line perpendicular
to the trench
wali, nearly six months after excavation
and reinstatement
of the trench, are presented in Fig. 2.
Site 2
A 3.7m deep
profiles
Site 3
Excavation of a 4.3m deep by 1.2m
wide trench, supported by close sheeting,
was carried out in a dense sand in a minor
urban road. Groundwater level was about
3.5m below ground level.
Maximum horizontal and vertical movements were very small (about 1mm) during excavation and up to one month after
reinstatement.
Strain was recorded at three locations
in a 100mm diameter cast iron water main
running
parallel to the trench at a distance of 1m. The maximum
measured
change in strain immediately following excavation was 65 microstrain. Each set of
gauges showed a strain "wave" travelling
along the pipe with the advance of the
trench head, the effects of which appeared
to dissipate after reinstatement.
Profiles of inclinometer tubes, one month
after excavation and reinstatement,
are
presented in Fig. 4.
Site 4
A 3.8m deep by 1.2m wide trench was
excavated in firm to stiff sandy silty clay
in a minor rural road. The trench was supported by a 3m long by 2m high trench
box. Groundwater level was about 1.5m
below ground level.
Maximum
movements
towards
the
trench recorded by inclinometers at distances of 0.5m, 1.9m, 4.2m and 7.1m from
the trench wall were 17mm, 8.5mm, 5mm
and 1.5mm (horizontal) and 6mm, Omm,
1mm and 1mm (vertical) respectively,
three weeks after excavation and reinstatement.
Strain gauges were installed some distance from the inclinometer line on an
80mm diameter cast iron main running
March, 1982
29
Discussion
Published data on ground movements
and pipe strain associated with trench
excavation are summarised in Table I.
There is at present no general agreement on allowable strains in cast and ductile iron pipes due to trenching taking
into account such factors as installation,
environment
changes and traffic loading,
nor on the relationship
between movement and pipe strain. Hence no attempt
will be made to draw conclusions from
the records of measured strain presented
in Table I, and elsewhere
in this Paper.
However, work currently being carried out
at the WRC Engineering Centre suggests
that the measured strain associated with
the installation of new pipes, and, indeed,
the strain resulting from instrumentation
of a buried pipe for experimental
purposes, may well be of the same order as,
or more than, the pipe strain resulting from
trench excavation.
Ground movements
measured at Sites
1 to 4 are generally
significantly less than
but...
solution
to providing
information
for
industry.
In current practice, large ground movements causing significant damage to structures are the exception rather than the
rule where workmanship
is of a high standard. The evaluation of a large number of
field experiments will highlight those areas
where damaging
movements
may occur
and enable special precautions to be formulated and applied, reducing the frequency and extent of damage to adjacent
services.
References
I. F. (1978): Discussion of "Lateral
displacement of shallow burled pipelines due
to adjacent deep trench excavations", (Crofts,
J, E., Msnzies, 8, K. & Tarzi, A. I.) Geotech-
1. Symons,
J.
TABLE I.
RECENT PUBLISHED RECORDS OF GROUND MOVEMENT AND PIPE STRAIN NEAR TRENCHES
Source
Trench/geometry
Main'round
Site 1t
5.5m deep
3.5m wide
230mm (4.7m)
Parallel to trench
'Max measured
Soft sandy
clay
Trench support
movement
Hydraulic
shoring (failed)
120mm H
230mm V
Max measured
strain in main
(1.5m)
Site
2'.0m
deep
3.6m wide
305mm
Stiff sandy
clay
(2.7m) Parallel to
trench
Site
3'.0m
deep
0.76m wide
Site
4'nknown
depth
Site
deep
4.0m wide
A'm3.3m
100mm
Ductile iron crossing
trench
Firm clay
Nil
Unknown
Unknown
minimal" )
Unknown
Unknown
("minimal" )
Unknown
Unknown
Nil
Unknown
Clay over
gravel
Steel plates
deep
1.5m wide
43mm H
115mm V
("close" )
("
B'.3m
deep
1.9m wide
1.5m fill
over sand
Steel sheets
C'm
50mm H
25mm V
100mm V
(0.5m)
deep
Nil
London
clay
Hydraulic
units
Nil
London
clay
Steel sheets
1m wide
Site Ds
5m deep
1m wide
shoring
30+mm
(1.3m)
30
Horizontal
vertica
given
Ground
Engineering
distance
of measurement
point
or main
from
edge
of trench
30mm H
20mm V
(0.5m)
000jzs
Main fractured
with gravel
Site
175p,s
22mm H
(1.5m)
Site
230jts
(1.5m)
(supported)
Site 5t
70mm H
170mm V