Академический Документы
Профессиональный Документы
Культура Документы
PROCEDURE FOR
PROJECT
CLIENT
CONSSULTANT
CONTRACTOR
PROCEDURE NUMBER
DOC. NO: HDOL/ETP/6907/JP/MECH-TANK- 2B /Rev-01
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
ABBREVIATIONS:
AFC
BM
Bench Mark
CI
Cast Iron
CPT
GI
Galvanized Iron
IBR
Id
Identification
IQI
IRC
JB
Junction Box
MS
Mild Steel
MT
NDT
OMC
PCC
P&ID
PQR
PT
Penetrant Testing
PVC
PWHT
RCC
RF
Reinforcement
RMC
SPT
U/G
Under Ground
WBM
WPS
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
CONTENTS
0.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 TERMS & DEFINITIONS
5.0 RESPONSIBILITIES
6.0 METHODOLOGY
7.0 HEALTH, SAFETY & ENVIRONMENT
8.0 QUALITY ASSURANCE & QUALITY CONTROL
9.0 DOCUMENTATION
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
1.0 PURPOSE
The need for PWHT is driven by code and application requirements, as well as the service environment.
In
general, when PWHT is required, the goal is to increase the resistance to brittle fracture and relaxing
residual stresses .Other desired results from PWHT may include hardness reduction, and material strength
enhancements
2.0 SCOPE
This procedure states explicitly in detail the minimum requirement for Post Weld Heat
Treatment (PWHT) by the electrical resistance method for nozzles, pipes & piping supports by
use of Microprocessor/computer controlled system.
This procedure covers description of the equipment, method of heating, location and type of
heating elements temperature measurement and thermocouple location.
Post Weld Heat Treatment (PWHT) shall be in accordance with ASME B31.3,&EIL
Specification/Standards.
3.0 REFERENCE DOCUMENTS
1 ) EIL Specification No : 6-77-0001 Rev-3, and 6-77-0005 Rev-1
2 ) ASME Sec. VIII, Div 1 : Boiler & Pressure Vessels code.
3) ASME B31.3
: Chemical Plant and Petroleum Refinery Piping
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
Project Manager
Site Engineer
Shall execute the work and report as per approved procedure and
quality plan.
QA/QC Engineer
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
6.0 METHODOLOGY
6.1 Person handling the PWHT activities
Qualification
The basic requirement for PWHT operator shall be that he should either be a science/technical graduate
or an electrical apprentice high school graduate with basic electrical knowledge to undertake the heat
treatment at the site.
6.2 Description of Required Equipment & Materials
Equipment The equipment shall be of a proper make & it should be bearing proper
electrical power input/output. Power distribution (supply) shall be of 380/440V Ph, with either single
phase secondary output or step down transformer secondary output (heat treatment unit) supplying low
voltage circuits. The temperature control equipment shall be operated manually or through regulators or
it shall be (made) operated automatically with the help of modular controls. The chart type temperature
recorder shall be used for recording temp. The frequency of calibration of temp recorder shall be three
months & a proper valid sticker shall be displayed on the temp recorder.
Materials
All the connection materials required for the heat treatment, shall be of standard quality & it shall be
selected free of defects.
6.3 Surface Conditions
The welds to be heat treated shall be prepared free of greases, lubricants dust and coatings to avoid
damage & short circuiting of accessories equipments. During heat treatment it shall be necessary to
protect from oxidation the mechanical surfaces line flange faces, threaded holes, threads by the
application of coating such as deoxaluminite or any other suitable coating material.
6.4 Method
The procedure for PWHT has to be followed for the various steel grades as mentioned
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
Compensating Cable
The cable recommended shall be twin type wore PVC coated copper/constantan connection to
thermocouple, with proper plug & socket. Copper constantan compensating cable shall be used for
connecting thermocouple wires & the temperature recorder.
The compensating cable specification should conform to international thermocouple reference tables
BSEN 60584 1 of 1996 and colour code as per BS 1843.
No. of Thermocouple
Minimum numbers of equally spaced recording thermocouple (T/C), which are required for any local
Post Weld Heat Treatment (PWHT) shall be as follows:
I. For pipes having diameter 6 or less;- 1 T/C.
II. For pipes having diameter up to 10 2 T/C.
III. For pipes having diameter greater than 12 3 T/C.
IV. . For pipes having diameter greater than 20 4 T/C
The thermocouples & positions shall be identified on the particular temperature recording
chart by number of colour / symbol of stamp
After the completion of PWHT remove the thermocouples & ground smoothly the area, to
clean & we thus achieve sound metal. As per the specification / instruction of the
inspector the areas are to be examined by MT or PT after grinding.
Insulation Cover
i)
The circumferential band width which has to be heated shall be minimum Six (6) times
the thickness of the shell material being welded from each edge of the weld, but not less
than25mm, whichever is greater.
ii)
The insulation distance shall be up to a minimum distance of 305mm beyond the edges
of the heating bands or up to a distance determined by the product of bore radius times
the maximum wall thickness whichever is less.
iii)
Through out the cycle of heat treatment the portion out side the heated band shall be suitably
Wrapped under insulation so as to avoid any harmful temperature gradient at the exposed surface of
pipe. For this purpose temperature at the exposed surface should not be allowed to exceed 50% of peak
temperature.
iv)
v)
Thermal insulation should be achieved by following means. Wool, mineral with minimum densit
of 80Kg /m3 With ceramic fiber, usually in stainless steel mesh as form of mat, minimum density
of 96Kg /m3
The number of layers & extent of insulated area shall be dependent on
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
* Wall thickness
* Pipe or fitting diameter
* Gradient requirement
* Site conditions
In all cases the minimum requirement shall be two (2) layers for densities (80Kg / m3 & 96Kg / m3)
vi)
Insulation shall be fixed using black annealed iron wire taking care, not damaging or
cutting into the insulation.
vii)
By following proper PWHT cycles, the item or the particular joint shall be completed & the
cooling rate should be controlled under insulation.
Temperature Recording
Temperature shall be measured using the thermocouples to be attached on the work piece during
the heat treatment proceedings.
i)
ii)
iii)
iv)
v)
Temperature recorders shall be calibrated after every three months or after repair. The
calibration
certificate should be kept & a sticker should be stuck on the instrument.
Control of temperature shall be done by using Microprocessor/Computer controlled system.
The
desired Time-Temperature cycle shall be entered into the Microprocessor/Computer. Automatic
Temperature Recorders, which have been suitably calibrated, shall be employed for measuring
and recording temperature. Both the actual Time-Temperature graph and designed time tempe
rapture graph shall be available on chart.
Manufacturer test certificate shall be submitted for thermo-couple materials and record shall
be
maintained by contractor.
Immediately on the completion of the heat treatment, the post weld heat treatment
charts/records
along with the Hardness test results on the weld, points where as required as per the welding
specification charts, shall be submitted to Engineer-in charge for his approval.
Each weld joint shall bear a unique identification number , which shall be maintained in the
piping
Sketch to be prepared by the contractor. The weld joint identification number should appear on
the corresponding post weld heat treatment chart. The chart containing the weld identification
number and piping sketch shall be submitted to the engineer-in charge.
Stress relieving time temperature shall be applicable over an area of min 6t inches (t = wall
thickness of pipe) on both sides of the weld but it should not be less than 2 on both sides.
ii)
Start the heat treatment cycle on an auto program where in heating rate shall not more
than 2000C per hour.
iii)
The cooling rates should not be more than 2000C / hr.
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
iv)
The soaking time shall be as per EIL Spec , 6-77-0005 & Established WPS.
Before start of actual PWHT work at site, a written procedure as per Exhibit-B of EIL
Specification is to demonstrated and documented.
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
9.0 DOCUMENTATION
ITP - as per PWHT procedure.
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL
Notes : In case of any conflict between the requirement of this procedure and EIL specification , the letter shall govern
U.PRAMANIK
D.CHATTERJEE
REV
DATE
PURPOSE
PREPARED
BY HDOL
CHECKED BY
HDOL
APPROVED BY
HDOL
CHECKED
BY EIL
APPROVED
BY EIL