Академический Документы
Профессиональный Документы
Культура Документы
1406513344
1406513376
1406589114
1406514100
1406589303
OUTLINE
Company Background:
A-CAT Corp.
Problem Identification
Theory of MRP
MRP Input
Authorized
master production
schedule
Inventory
transactions
Inventory
records
MRP
explosion
Material
requirements
plan
Other
sources
of demand
Bills of
materials
Engineering
and process
designs
BOM Sample
Master production schedule (MPS): Total aggregate production for all types
of "family" seats
Inventory Record
Analysis
Level
0
(Quantity)
Independent
Demand
(1)
(2)
(2)
Dependent
Demand
(4)
(3)
On Hand Inventory
Cost
Week
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release
L4L
1
500
0
-4
-3
-2
-1
1
400
2
350
3
300
4
450
5
300
6
450
7
225
8
525
240
240
240
240
0
300
300
300
0
450
450
450
0
300
300
225
0
450
450
525
0
525
525
350
0
350
350
450
0
225
225
160
0
160
160
300
-2
-1
320
700
600
900
600
900
450
1050
180
0
0
520
0
520
520
600
0
600
600
900
0
900
900
600
0
600
600
900
0
900
900
450
0
450
450
1050
0
1050
1050
Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release
500
-3
500
L4L
1
340
0
Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release
L4L
1
500
0
L4L
1
600
0
340
-2
-1
320
700
600
900
600
900
450
1050
20
0
0
680
0
680
680
600
0
600
600
900
0
900
900
600
0
600
600
900
0
900
900
450
0
450
450
1050
0
1050
1050
Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release
340
-3
500
-3
500
1580
-2
-1
2080
2400
3600
2400
3600
1800
4200
0
1580
1580
2400
0
2400
2400
3600
0
3600
3600
2400
0
2400
2400
3600
0
3600
3600
1800
0
1800
1800
4200
0
4200
4200
Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release
600
-3
600
960
-2
-1
1560
1800
2700
1800
2700
1350
3150
0
960
960
1800
0
1800
1800
2700
0
2700
2700
1800
0
1800
1800
2700
0
2700
2700
1350
0
1350
1350
3150
0
3150
3150
P0X
Week
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
1
160
160
0
0
500
500
2
350
350
0
0
500
1000
3
300
300
0
0
500
1500
4
450
450
0
0
500
2000
5
300
300
0
0
500
2500
6
450
450
0
0
500
3000
7
225
225
0
0
500
3500
8
525
525
0
0
500
4000
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-1
520
520
0
0
400
400
1
600
600
0
0
400
800
2
900
900
0
0
400
1200
3
600
600
0
0
400
1600
4
900
900
0
0
400
2000
5
450
450
0
0
400
2400
6
1050
1050
0
0
400
2800
POY
Week
-1
1
2
3
4
5
6
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
680
680
0
0
350
350
600
600
0
0
350
700
900
900
0
0
350
1050
600
600
0
0
350
1400
900
900
0
0
350
1750
450
450
0
0
350
2100
1050
1050
0
0
350
2450
P1X1
Week
P1X2
Week
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
1580
1580
0
0
430
430
-1
2400
2400
0
0
430
860
1
3600
3600
0
0
430
1290
2
2400
2400
0
0
430
1720
3
3600
3600
0
0
430
2150
4
1800
1800
0
0
430
2580
5
4200
4200
0
0
430
3010
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
960
960
0
0
400
400
-1
1800
1800
0
0
400
800
1
2700
2700
0
0
400
1200
2
1800
1800
0
0
400
1600
3
2700
2700
0
0
400
2000
4
1350
1350
0
0
400
2400
5
3150
3150
0
0
400
2800
Cost
4,000
2,800
2,450
3,010
2,800
15,060
D = Annual Demand
H = Annual Holding Cost
S = Setup Cost
Lv 1 (POY)
LT :1
Gross requirement
schedule receipts
projected on hand
net requirements
Planned order receipts
Planned Ending Inventory
Planned order releases
EOQ = 1665
-3
-2
588
-2
1176
500
676
1287
611
-2
1176
340
836
1665
829
1665
-1
1
2
3
400 350 300
4
450
5
6 7 8
300 450 225 525
240
160 350 300
588
588
428 78 366
588 588
450
588
504
588
-1
1
2
0 1176 1176
3
4
0 1176
5
6
0 1176
3
4
0 1176
5
6
0 1176
0 1176 1176
0 1176
0 1176
1665
1665
1665
1318 142
631
1120
1665
1665
1665
Total Cost :
D=
H=
S=
2DS/H =
EOQ =
Total Cost :
17940
52
500
345000
588
4719
1176 1176
1176
1176
1287 1287
1287
1287
722 833
944
1055
1287 1287
1287
1287
-1
1
2
0 1176 1176
D=
H=
S=
2DS/H =
EOQ =
34970
16.9
400
1655385
1287
3354
8
D=
H=
S=
2DS/H =
EOQ =
Total Cost :
36010
9.1
350
2770000
1665
2107
Lv 2 (P1X1)
EOQ = 10418
LT :1
-4
-3
Gross requirement
5148
schedule receipts
projected on hand
500
net requirements
4648
Planned order receipts
10418
Planned Ending Inventory
5770
Planned order releases
10418
-2
-1
1
0 5148 5148
2
3
0 5148
0 5148 5148
10418
622 5892
10418
0 5148
Lv 2 (P1X2)
EOQ = 4994
LT :1
-4
-3 -2
Gross requirement
3861
0
schedule receipts
projected on hand
600
net requirements
3261
0
Planned order receipts
4994
Planned Ending Inventory
1733
Planned order releases
4994
4994
4
5
0 5148
8
D=
H=
S=
2DS/H =
EOQ =
0 5148
10418
744
6014
10418
-1
1
3861 3861
2
3
0 3861
3861 3861
4994 4994
2866 3999
4994
0 3861
4
5
0 3861
0 3861
4994
138
1271
4994
Total Cost :
164060
1.3
430
108532000
10418
1766
8
D=
H=
S=
2DS/H =
EOQ =
Total Cost :
121582.5
3.9
400
24940000
4994
2351
P0X
Week
POY
Week
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
1
160
588
428
428
500
928
2
350
0
78
78
0
1006
3
300
588
366
366
500
1872
4
450
588
504
504
500
2876
5
300
0
204
204
0
3080
6
450
588
342
342
500
3922
7
225
0
117
117
0
4039
8
525
588
180
180
500
4719
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
676
1287
611
199
400
599
-1
0
0
0
0
0
599
1
1176
1287
722
235
400
1233
2
1176
1287
833
271
400
1904
3
0
0
0
0
0
1904
4
1176
1287
944
307
400
2611
5
0
0
0
0
0
2611
6
1176
1287
1055
343
400
3354
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
836
1665
829
145
350
495
-1
0
0
0
0
0
495
1
1176
1665
1318
231
350
1076
2
1176
0
142
25
0
1101
3
0
0
0
0
0
1101
4
1176
1665
631
110
350
1561
5
0
0
0
0
0
1561
6
1176
1665
1120
196
350
2107
P1X1
Week
P1X2
Week
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-3
4648
10418
5770
144
430
574
-2
0
0
0
0
0
574
-1
5148
0
622
16
0
590
1
5148
10418
5892
147
430
1167
2
0
0
0
0
0
1167
3
5148
0
744
19
0
1186
4
0
0
0
0
0
1186
5
3861
10418
6014
150
430
1766
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-3
3261
4994
1733
130
400
530
-2
0
0
0
0
0
530
-1
3861
4994
2866
215
400
1145
1
3861
4994
3999
300
400
1845
2
0
0
0
0
0
1845
3
3861
0
138
10
0
1855
4
0
0
0
0
0
1855
5
3861
4994
1271
95
400
2351
Step 1
Step 2
Week
1
2
3
4
5
6
7
8
Holding Cost
350
0
450
0
450
0
525
0
LTC
Level 0
P0110
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8
Item
P0110
POX
POY
P1X1
PIX2
Inventory
240
500
340
500
600
Net Requirement
400
350
300
450
300
450
225
525
Step 1
Step 2
Week
1
2
3
4
5
6
7
8
Holding Cost
0
0
0
0
0
0
0
0
LTC
Level 1
P0X
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8
Item
P0110
POX
POY
P1X1
PIX2
Inventory
240
500
340
500
600
Qty
1
2
2
4
3
Net Requirement
510
0
750
0
750
0
750
0
Tot. Req
1020
0
1500
0
1500
0
1500
0
Step 1
Step 2
Week
1
2
3
4
5
6
7
8
Holding Cost
263
263
0
0
263
263
0
0
LTC
Level 1
P0Y
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8
Item
P0110
POX
POY
P1X1
PIX2
Inventory
240
500
340
500
600
Net Requirement
510
0
750
0
750
0
750
0
Qty
1
2
2
4
3
Tot. Req
1020
0
1500
0
1500
0
1500
0
Step 1
Step 2
Week
1
2
3
4
5
6
7
8
Holding Cost
150
150
0
0
150
150
0
0
LTC
Level 2
P1X1
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8
Item
P0110
POX
POY
P1X1
PIX2
Inventory
240
500
340
500
600
Net Requirement
520
0
1500
0
1500
0
1500
0
Qty
1
2
2
4
3
Tot. Req
2080
0
6000
0
6000
0
6000
0
Step 1
Step 2
Week
1
2
3
4
5
6
7
8
Holding Cost
338
338
0
0
338
338
0
0
LTC
Level 2
P1X2
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8
Inventory
240
500
340
500
600
Net Requirement
520
0
1500
0
1500
0
1500
0
Item
P0110
POX
POY
P1X1
PIX2
Qty
1
2
2
4
3
Tot. Req
1560
0
4500
0
4500
0
4500
0
Item
P0110
P0X
P0Y
P1X1
P1X2
Total Cost
Cost
3,775
1,600
1,750
1,460
2,150
10,735
LUC
Step 1
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
160
500
500
1-2
510
350
500
850
1-3
810
950
500
1450
1-4
1260
2300
500
2800
1-5
1560
3500
500
4000
1-6
1200
5750
500
6250
1-7
2235
7100
500
7600
1-8
2760
10775
500
11275
3.13
1.67
1.79
2.22
2.56
5.21
3.40
4.09
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
300
500
500
3-4
750
450
500
950
3-5
1050
1050
500
1550
3-6
1500
2400
500
2900
3-7
1725
3300
500
3800
3-8
2250
5925
500
6425
1.7
1.3
1.5
1.9
2.2
2.9
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
300
500
500
5-6
750
450
500
950
5-7
975
900
500
1400
5-8
1500
2475
500
2975
1.7
1.3
1.4
2.0
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
225
500
500
7-8
750
525
500
1025
2.2
1.4
Step 2
Level 0
P0110
Week
Net Requirement
Prod. Qty
Ending Inv.
Holding Cost
Setup Cost
Total Cost
160
510
350
350
500
850
350
850
300
750
450
450
500
1800
450
1800
300
750
450
450
500
2750
450
2750
225
750
525
525
500
3775
525
3775
LUC
Step 1
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
-1
-1-0
520
400
400
-1-1
1120
195
400
595
-1-2
2020
780
400
1180
-1-3
2620
1365
400
1765
-1-4
3520
2535
400
2935
-1-5
3970
3266.25
400
3666.25
-1-6
5020
5313.75
400
5713.75
0
0.77
0.53
0.58
0.67
0.83
0.92
1.14
Week
2
Quantity Ordered
900
Carrying Cost
0
Setup Cost
400
Total Cost
400
2-3
1500
195
400
595
2-4
2400
780
400
1180
2-5
2850
1218.75
400
1618.75
2-6
3900
2583.75
400
2983.75
Week
4
Quantity Ordered
900
Carrying Cost
0
Setup Cost
400
Total Cost
400
4-5
1350
146.25
400
546.25
4-6
2400
828.75
400
1228.75
Week
6
Quantity Ordered
1050
Carrying Cost
0
Setup Cost
400
Total Cost
400
Step 2
Level 1
P0X
Unit Cost
0.44
0.40
0.49
0.57
0.77
Unit Cost
0.44
0.40
0.51
Unit Cost
0.38
Week
Net Requirement
Prod. Qty
Ending Inv.
Holding Cost
Setup Cost
Total Cost
-1
180
58.5
58.5
520
1120
600
195
400
653.5
600
653.5
900
1500
600
195
400
1248.5
600
1248.5
900
1350
450
146.25
400
1794.75
450
1794.75
1050
1050
400
2194.75
Step 1
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
-1
-1-0
680
350
350
-1-1
1280
105
350
455
-1-2
2180
420
350
770
-1-3
2780
735
350
1085
-1-4
3680
1365
350
1715
-1-5
4130
1758.75
350
2108.75
-1-6
5180
2861.25
350
3211.25
0
0.51
0.36
0.35
0.39
0.47
0.51
0.62
Week
3
Quantity Ordered
600
Carrying Cost
0
Setup Cost
350
Total Cost
350
3-4
1500
157.5
350
507.5
3-5
1950
315
350
665
3-6
3000
866.25
350
1216.25
Week
5
Quantity Ordered
450
Carrying Cost
0
Setup Cost
350
Total Cost
350
5-6
1500
183.75
350
533.75
Step 2
LUC
Level 1
P0Y
Unit Cost
0.58
0.338
0.341
0.41
Unit Cost
0.78
0.36
Week
Net Requirement
Prod. Qty
Ending Inv.
Holding Cost
Setup Cost
Total Cost
-1
20
3.5
3.5
680
2180
1500
262.5
350
616
600
900
157.5
773.5
900
773.5
600
1500
900
157.5
350
1281
900
1281
450
1500
1050
183.75
350
1814.75
1050
1814.75
LUC
Step 1
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
-1
780
430
430
-1-0
3580
70
430
500
-1-1
5980
190
430
620
-1-2
9580
460
430
890
-1-3
11980
700
430
1130
-1-4
15580
1150
430
1580
-1-5
17380
1420
430
1850
-1-6
21580
2155
430
2585
0.55
0.14
0.10
0.093
0.094
0.10
0.11
0.12
Week
3
Quantity Ordered
2400
Carrying Cost
0
Setup Cost
430
Total Cost
430
3-4
3600
90
430
520
3-5
7800
180
430
610
3-6
11400
495
430
925
Week
6
Quantity Ordered
4200
Carrying Cost
0
Setup Cost
430
Total Cost
430
Step 2
Level 2
P1X1
Unit Cost
0.18
0.14
0.078
0.081
Unit Cost
0.10
Week
Net Requirement
Prod. Qty
Ending Inv.
Holding Cost
Setup Cost
Total Cost
-1
780
9580
8800
220
430
220
2800
6000
150
370
2400
3600
90
460
3600
460
2400
7800
5400
135
430
1025
3600
1800
45
1070
1800
1070
4200
4200
430
1500
LUC
Step 1
Week
Quantity Ordered
Carrying Cost
Setup Cost
Total Cost
Unit Cost
-1
360
400
400
-1-0
2460
157.5
400
557.5
-1-1
4260
427.5
400
827.5
-1-2
6960
1035
400
1435
-1-3
8760
1575
400
1975
-1-4
11460
2587.5
400
2987.5
-1-5
12810
3195
400
3595
-1-6
15960
4848.75
400
5248.75
1.11
0.23
0.19
0.21
0.23
0.26
0.28
0.33
Week
2
Quantity Ordered
2700
Carrying Cost
0
Setup Cost
400
Total Cost
400
2-3
4500
135
400
535
2-4
7200
540
400
940
2-5
8550
843.75
400
1243.75
2-6
11700
1788.75
400
2188.75
Week
4
Quantity Ordered
2700
Carrying Cost
0
Setup Cost
400
Total Cost
400
4-5
4050
101.25
400
501.25
4-6
7200
573.75
400
973.75
Week
6
Quantity Ordered
3150
Carrying Cost
0
Setup Cost
400
Total Cost
400
Step 2
Level 2
P1X2
Unit Cost
0.15
0.12
0.13
0.15
0.19
Unit Cost
0.15
0.12
0.14
Unit Cost
0.13
Week
Net Requirement
Prod. Qty
Ending Inv.
Holding Cost
Setup Cost
Total Cost
-1
360
4260
3900
97.5
400
97.5
2100
1800
45
142.5
1800
142.5
2700
4500
1800
45
400
587.5
1800
587.5
2700
4050
1350
33.75
400
1021.25
1350
1021.25
3150
3150
400
1421.25
Item
P0110
P0X
P0Y
P1X1
P1X2
TOTAL
Cost (Rs)
3,775
2,195
1,815
1,500
1,421
10,706
Conclusion
Lot-for-Lot (L4L)
15,060
14,296
10,735
10,706
The lowest cost was obtained using the Least Unit Cost
Method of Rs10,706.
Sunita Menon should choose the Least Unit Cost Method
as Lot Sizing Strategy at A-Cat Corp.
Lesson Learned
References