Вы находитесь на странице: 1из 44

18th of May 2015

Operations Management For Competitive Advantage


Group 4
Azis Rizky Prawira
Camelia Indah Murniwati
Jejen Nugraha
Muhammad Yuriansyah Putra
Nasrul Nabil Sangadji

1406513344
1406513376
1406589114
1406514100
1406589303

OUTLINE

Company Background of A-CAT Corp.


Problem Identification
Theory of MRP
Analysis
Conclusion & Lesson Learned

Company Background:
A-CAT Corp.

Mid-sized manufacturer and distributor of domestic electrical


appliances.
Operated two medium-sized facilities in Vidarbha region of
Maharashtra states of India.
Focus on the rural segment (low-income customers).
A-CATs manufacturing units had been in operation since 1986.
Annual sales of Rs6,000,000 US$120,000.
Had about 35 employees.
Manufactured electrical appliances for household use:
television signal boosters, transformers, FM radio kits,
electronic ballasts, battery chargers, voltage regulators, etc.

Problem Identification

Sunita Menon was assigned the task of preparing


the operation plan for the next eight weeks for the
product P0110.
The basic problem Menon Faced was deciding how
to produce economically.
After collecting the data (Bill of Materials, Product
Structure Diagram, Master Schedule, On Hand
Inventory, Costs Associated), Menon reached a
different answer for every lot-sizing technique that
she applied.

Theory of MRP

MRP is a planning approach to material / material


that ignoring the past, but look to the demands or
needs of future production.
MRP can be applied for planning materials / parts /
components or sub-assemblies that depend on the
product or inventory.
MRP is a computerized information system is built
specifically to help manufacturers manage inventory
and schedule of reservations / reception material /
materials.

MRP Input

Authorized
master production
schedule

Inventory
transactions

Inventory
records

MRP
explosion

Material
requirements
plan

Other
sources
of demand

Bills of
materials

Engineering
and process
designs

Information for MRP


Bill of Materials (BOM) of all products for certain that consists of several
levels (level).
Number parts / components are unique and permanent.
The existence of Master Production Schedule (MPS) of production. The
final result contains the time and amount.
The amount of material requirements / Notes Inventory (Inventory Record)
for each part / component products.
Stock code number.
Lead time for each part / component in an exact figure.
The required amount equal to that of the production schedule.

BOM Sample

Master Production Scheduling

Master production schedule (MPS): Total aggregate production for all types
of "family" seats

Inventory Record

Supply Notes : A record that shows an items lot-size policy,


lead time, and various time-phased data.
Gross requirements : The total demand derived from all parent
production plans.
Scheduled receipts are orders that have been placed but not yet
completed.
projected on-hand inventory: An estimate of the amount of
inventory available each week after gross requirements have
been satisfied.
planned receipts : Orders that are not yet released to the shop
or supplier.
planned order releases : An indication of when an order for a
specified quantity of an item is to be issued.

Lot Sizing in MRP Systems


Lot sizes the part quantities issued in the planned order receipt and
planned order release sections of an MRP schedule.

Analysis

Based on the data (Bill of Materials, Product


Structure Diagram, Master Schedule, On Hand
Inventory, Costs Associated), Lot Sizes will be
determined by using Lot Sizing Strategies below:
1.
2.
3.
4.

Lot for Lot (L4L)


Economic Order Quantity (EOQ)
Least Total Cost (LTC)
Least Unit Cost (LUC)

Bill of Material (BOM)

Level
0

(Quantity)

Independent
Demand

(1)

(2)

(2)

Dependent
Demand

(4)

(3)

Master Production Schedule


The End Item: P0110

On Hand Inventory

Cost

1. Lot for Lot (L4L)

Lot-for-Lot (L4L) is the most commont technique. It


Sets planned orders to exactly match the net
requirements
Produces exactly what is needed each week with no
inventory carroed over into future periods.
Minimizes carrying cost.
Does not take into account setup costs or capacity
limitations.

Step 1: MRP Explosion Calculations


MRP Explosion Calculations
Item
P0110
Q
L4L
LT
2
OH
240
SS
0

Week
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release

MRP Explosion Calculations


Item
POX
Q
LT
OH
SS

L4L
1
500
0

-4

-3

-2

-1

1
400

2
350

3
300

4
450

5
300

6
450

7
225

8
525

240

240

240

240

0
300
300
300

0
450
450
450

0
300
300
225

0
450
450
525

0
525
525

350

0
350
350
450

0
225
225

160

0
160
160
300

-2

-1

320

700

600

900

600

900

450

1050

180
0
0
520

0
520
520
600

0
600
600
900

0
900
900
600

0
600
600
900

0
900
900
450

0
450
450
1050

0
1050
1050

Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release

500

-3

500

MRP Explosion Calculations


Item
POY
Q
LT
OH
SS

L4L
1
340
0

Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release

MRP Explosion Calculations


Item
P1X1
Q
LT
OH
SS

L4L
1
500
0

L4L
1
600
0

340

-2

-1

320

700

600

900

600

900

450

1050

20
0
0
680

0
680
680
600

0
600
600
900

0
900
900
600

0
600
600
900

0
900
900
450

0
450
450
1050

0
1050
1050

Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release

MRP Explosion Calculations


Item
P1X2
Q
LT
OH
SS

340

-3

500

-3

500

1580

-2

-1

2080

2400

3600

2400

3600

1800

4200

0
1580
1580
2400

0
2400
2400
3600

0
3600
3600
2400

0
2400
2400
3600

0
3600
3600
1800

0
1800
1800
4200

0
4200
4200

Week
-4
Gross requirement
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order release

600

-3

600

960

-2

-1

1560

1800

2700

1800

2700

1350

3150

0
960
960
1800

0
1800
1800
2700

0
2700
2700
1800

0
1800
1800
2700

0
2700
2700
1350

0
1350
1350
3150

0
3150
3150

Step 2: Lot-for-Lot Run Size for an MRP Schedule


P0110
Week

P0X
Week

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
1
160
160
0
0
500
500
2
350
350
0
0
500
1000
3
300
300
0
0
500
1500
4
450
450
0
0
500
2000
5
300
300
0
0
500
2500
6
450
450
0
0
500
3000
7
225
225
0
0
500
3500
8
525
525
0
0
500
4000

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-1
520
520
0
0
400
400
1
600
600
0
0
400
800
2
900
900
0
0
400
1200
3
600
600
0
0
400
1600
4
900
900
0
0
400
2000
5
450
450
0
0
400
2400
6
1050
1050
0
0
400
2800

POY
Week
-1
1
2
3
4
5
6

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
680
680
0
0
350
350
600
600
0
0
350
700
900
900
0
0
350
1050
600
600
0
0
350
1400
900
900
0
0
350
1750
450
450
0
0
350
2100
1050
1050
0
0
350
2450

P1X1
Week

P1X2
Week

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
1580
1580
0
0
430
430
-1
2400
2400
0
0
430
860
1
3600
3600
0
0
430
1290
2
2400
2400
0
0
430
1720
3
3600
3600
0
0
430
2150
4
1800
1800
0
0
430
2580
5
4200
4200
0
0
430
3010

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
960
960
0
0
400
400
-1
1800
1800
0
0
400
800
1
2700
2700
0
0
400
1200
2
1800
1800
0
0
400
1600
3
2700
2700
0
0
400
2000
4
1350
1350
0
0
400
2400
5
3150
3150
0
0
400
2800

Step 3: Total Cost Calculation for L4L


Item
P0110
P0X
P0Y
P1X1
P1X2
Total Cost L4L

Cost
4,000
2,800
2,450
3,010
2,800
15,060

2. Economic Order Quantity (EOQ)

Economic order quantity (EOQ) is the order quantity that


minimizes total inventory holding costs and ordering costs. It is one
of the oldest classical production scheduling models.
Step 1: EOQ Calculations

D = Annual Demand
H = Annual Holding Cost
S = Setup Cost

Step 2: MRP Explosion Calculations


Lv 0 (P0110)
EOQ = 588
LT :2
Gross requirement
schedule receipts
projected on hand
net requirements
Planned order receipts
Planned Ending Inventory
Planned order releases
Lv 1 (POX)
EOQ = 1287
LT :1
-3
Gross requirement
schedule receipts
projected on hand
net requirements
Planned order receipts
Planned Ending Inventory
Planned order releases
1287

Lv 1 (POY)
LT :1
Gross requirement
schedule receipts
projected on hand
net requirements
Planned order receipts
Planned Ending Inventory
Planned order releases

EOQ = 1665
-3

-2

588

-2
1176
500
676
1287
611

-2
1176
340
836
1665
829

1665

-1

1
2
3
400 350 300

4
450

5
6 7 8
300 450 225 525

240
160 350 300
588
588
428 78 366
588 588

450
588
504
588

300 450 225 525


588
588
204 342 117 180
588

-1
1
2
0 1176 1176

3
4
0 1176

5
6
0 1176

3
4
0 1176

5
6
0 1176

0 1176 1176
0 1176
0 1176
1665
1665
1665
1318 142
631
1120
1665
1665
1665

Total Cost :

D=
H=
S=
2DS/H =
EOQ =
Total Cost :

17940
52
500
345000
588
4719

1176 1176
1176
1176
1287 1287
1287
1287
722 833
944
1055
1287 1287
1287
1287

-1
1
2
0 1176 1176

D=
H=
S=
2DS/H =
EOQ =

34970
16.9
400
1655385
1287
3354

8
D=
H=
S=
2DS/H =
EOQ =
Total Cost :

36010
9.1
350
2770000
1665
2107

Lv 2 (P1X1)
EOQ = 10418
LT :1
-4
-3
Gross requirement
5148
schedule receipts
projected on hand
500
net requirements
4648
Planned order receipts
10418
Planned Ending Inventory
5770
Planned order releases
10418

-2
-1
1
0 5148 5148

2
3
0 5148

0 5148 5148
10418
622 5892
10418

0 5148

Lv 2 (P1X2)
EOQ = 4994
LT :1
-4
-3 -2
Gross requirement
3861
0
schedule receipts
projected on hand
600
net requirements
3261
0
Planned order receipts
4994
Planned Ending Inventory
1733
Planned order releases
4994
4994

4
5
0 5148

8
D=
H=
S=
2DS/H =
EOQ =

0 5148
10418
744
6014
10418

-1
1
3861 3861

2
3
0 3861

3861 3861
4994 4994
2866 3999
4994

0 3861

4
5
0 3861

0 3861
4994
138
1271
4994

Total Cost :

164060
1.3
430
108532000
10418
1766

8
D=
H=
S=
2DS/H =
EOQ =
Total Cost :

121582.5
3.9
400
24940000
4994
2351

Step 3: EOQ Run Size for an MRP Schedule


P0110
Week

P0X
Week

POY
Week

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
1
160
588
428
428
500
928
2
350
0
78
78
0
1006
3
300
588
366
366
500
1872
4
450
588
504
504
500
2876
5
300
0
204
204
0
3080
6
450
588
342
342
500
3922
7
225
0
117
117
0
4039
8
525
588
180
180
500
4719

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
676
1287
611
199
400
599
-1
0
0
0
0
0
599
1
1176
1287
722
235
400
1233
2
1176
1287
833
271
400
1904
3
0
0
0
0
0
1904
4
1176
1287
944
307
400
2611
5
0
0
0
0
0
2611
6
1176
1287
1055
343
400
3354
Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-2
836
1665
829
145
350
495
-1
0
0
0
0
0
495
1
1176
1665
1318
231
350
1076
2
1176
0
142
25
0
1101
3
0
0
0
0
0
1101
4
1176
1665
631
110
350
1561
5
0
0
0
0
0
1561
6
1176
1665
1120
196
350
2107

P1X1
Week

P1X2
Week

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-3
4648
10418
5770
144
430
574
-2
0
0
0
0
0
574
-1
5148
0
622
16
0
590
1
5148
10418
5892
147
430
1167
2
0
0
0
0
0
1167
3
5148
0
744
19
0
1186
4
0
0
0
0
0
1186
5
3861
10418
6014
150
430
1766

Net Requirements Production Quantity Ending Inventory Holding Cost Setup Cost Total Cost
-3
3261
4994
1733
130
400
530
-2
0
0
0
0
0
530
-1
3861
4994
2866
215
400
1145
1
3861
4994
3999
300
400
1845
2
0
0
0
0
0
1845
3
3861
0
138
10
0
1855
4
0
0
0
0
0
1855
5
3861
4994
1271
95
400
2351

Step 4: Total Cost Calculation for EOQ


Total EOQ Cost
ITEM
COST (In Rs)
P0110
4719
POX
3354
POY
2107
P1X1
1766
P1X2
2351
TOTAL
14296

3. Least Total Cost (LTC)

Least Total Cost (LTC) is a dynamic lot-sizing technique that


calculates the order quantity by comparing the carrying cost and the
setup (or ordering) cost for various lot sizes and then selects the lot in
which these are most nearly equal.

Step 1

Step 2

Week Quantity Ordered


1
160
1-2
510
1-3
810
1-4
1260
1-5
1560
1-6
2010
1-7
2235
1-8
2760

Carrying Cost Setup Cost Total Cost Different


0
500
500
500
350
500
850
150
950
500
1450
450
2300
500
2800
1800
3500
500
4000
3000
5750
500
6250
5250
7100
500
7600
6600
10775
500
11275
10275

Week Quantity Ordered


3
300
3-4
750
3-5
1050
3-6
1500
3-7
1725
3-8
2250

Carrying Cost Setup Cost Total Cost Different


0
500
500
500
450
500
950
50
1050
500
1550
550
2400
500
2900
1900
3300
500
3800
2800
5925
500
6425
5425

Week Quantity Ordered


5
300
5-6
750
5-7
975
5-8
1500

Carrying Cost Setup Cost Total Cost Different


0
500
500
500
450
500
950
50
900
500
1400
400
2475
500
2975
1975

Week Quantity Ordered


7
225
7-8
750

Carrying Cost Setup Cost Total Cost Different


0
500
500
500
525
500
1025
25

Week
1
2
3
4
5
6
7
8

Net Requirement Prod. Qty Ending Inv.


160
510
350
350
0
0
300
750
450
450
0
0
300
750
450
450
0
0
225
750
525
525
0
0

Holding Cost
350
0
450
0
450
0
525
0

Setup Cost Total Cost


500
850
0
850
500
1800
0
1800
500
2750
0
2750
500
3775
0
3775

LTC
Level 0
P0110
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8

Item
P0110
POX
POY
P1X1
PIX2

Inventory
240
500
340
500
600

Net Requirement
400
350
300
450
300
450
225
525

Cost/Unit Set Up Cost


200
500
65
400
35
350
5
430
15
400

Step 1

Step 2

Week Quantity Ordered


1
520
1-2
520
1-3
2020
1-4
2020
1-5
3520
1-6
3520
1-7
5020
1-8
5020

Carrying Cost Setup Cost Total Cost Different


0
400
400
400
0
400
400
400
975
400
1375
575
975
400
1375
575
2925
400
3325
2525
2925
400
3325
2525
5850
400
6250
5450
5850
400
6250
5450

Week Quantity Ordered


3
1500
3-4
1500
3-5
3000
3-6
3000
3-7
4500
3-8
4500

Carrying Cost Setup Cost Total Cost Different


0
400
400
400
0
400
400
400
975
400
1375
575
975
400
1375
575
2925
400
3325
2525
2925
400
3325
2525

Week Quantity Ordered


5
1500
5-6
1500
5-7
3000
5-8
3000

Carrying Cost Setup Cost Total Cost Different


0
400
400
400
0
400
400
400
975
400
1375
575
975
400
1375
575

Week Quantity Ordered


7
1500
7-8
1500

Carrying Cost Setup Cost Total Cost Different


0
400
400
400
0
400
400
400

Week
1
2
3
4
5
6
7
8

Net Requirement Prod. Qty Ending Inv.


520
520
0
0
0
0
1500
1500
0
0
0
0
1500
1500
0
0
0
0
1500
1500
0
0
0
0

Holding Cost
0
0
0
0
0
0
0
0

Setup Cost Total Cost


400
400
0
400
400
800
0
800
400
1200
0
1200
400
1600
0
1600

LTC
Level 1
P0X
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8

Item
P0110
POX
POY
P1X1
PIX2

Inventory
240
500
340
500
600

Qty
1
2
2
4
3

Net Requirement
510
0
750
0
750
0
750
0

Tot. Req
1020
0
1500
0
1500
0
1500
0

Cost/Unit Set Up Cost


200
500
65
400
35
350
5
430
15
400

Step 1

Step 2

Week Quantity Ordered


1
680
1-2
680
1-3
2180
1-4
2180
1-5
3680
1-6
3680
1-7
5180
1-8
5180

Carrying Cost Setup Cost Total Cost Different


0
350
350
350
0
350
350
350
525
350
875
175
525
350
875
175
1575
350
1925
1225
1575
350
1925
1225
3150
350
3500
2800
3150
350
3500
2800

Week Quantity Ordered


5
1500
5-6
1500
5-7
3000
5-8
3000

Carrying Cost Setup Cost Total Cost Different


0
350
350
350
0
350
350
350
525
350
875
175
525
350
875
175

Week
1
2
3
4
5
6
7
8

Net Requirement Prod. Qty Ending Inv.


680
2180
1500
0
0
1500
1500
0
0
0
0
0
1500
3000
1500
0
0
1500
1500
0
0
0
0
0

Holding Cost
263
263
0
0
263
263
0
0

Setup Cost Total Cost


350
613
0
875
0
875
0
875
350
1487.5
0
1750
0
1750
0
1750

LTC
Level 1
P0Y
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8

Item
P0110
POX
POY
P1X1
PIX2

Inventory
240
500
340
500
600
Net Requirement
510
0
750
0
750
0
750
0

Qty
1
2
2
4
3
Tot. Req
1020
0
1500
0
1500
0
1500
0

Cost/Unit Set Up Cost


200
500
65
400
35
350
5
430
15
400

Step 1

Step 2

Week Quantity Ordered


1
1580
1-2
1580
1-3
7580
1-4
7580
1-5
13580
1-6
13580
1-7
19580
1-8
19580

Carrying Cost Setup Cost Total Cost Different


0
430
430
430
0
430
430
430
300
430
730
130
300
430
730
130
900
430
1330
470
900
430
1330
470
1800
430
2230
1370
1800
430
2230
1370

Week Quantity Ordered


5
6000
5-6
6000
5-7
12000
5-8
12000

Carrying Cost Setup Cost Total Cost Different


0
430
430
430
0
430
430
430
300
430
730
130
300
430
730
130

Week
1
2
3
4
5
6
7
8

Net Requirement Prod. Qty Ending Inv.


1580
7580
6000
0
0
6000
6000
0
0
0
0
0
6000
12000
6000
0
0
6000
6000
0
0
0
0
0

Holding Cost
150
150
0
0
150
150
0
0

Setup Cost Total Cost


430
580
0
730
0
730
0
730
430
1310
0
1460
0
1460
0
1460

LTC
Level 2
P1X1
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8

Item
P0110
POX
POY
P1X1
PIX2

Inventory
240
500
340
500
600
Net Requirement
520
0
1500
0
1500
0
1500
0

Qty
1
2
2
4
3
Tot. Req
2080
0
6000
0
6000
0
6000
0

Cost/Unit Set Up Cost


200
500
65
400
35
350
5
430
15
400

Step 1

Step 2

Week Quantity Ordered


1
960
1-2
960
1-3
5460
1-4
5460
1-5
9960
1-6
9960
1-7
14460
1-8
14460

Carrying Cost Setup Cost Total Cost Different


0
400
400
400
0
400
400
400
675
400
1075
275
675
400
1075
275
2025
400
2425
1625
2025
400
2425
1625
4050
400
4450
3650
4050
400
4450
3650

Week Quantity Ordered


5
4500
5-6
4500
5-7
9000
5-8
9000

Carrying Cost Setup Cost Total Cost Different


0
400
400
400
0
400
400
400
675
400
1075
275
675
400
1075
275

Week
1
2
3
4
5
6
7
8

Net Requirement Prod. Qty Ending Inv.


960
5460
4500
0
0
4500
4500
0
0
0
0
0
4500
9000
4500
0
0
4500
4500
0
0
0
0
0

Holding Cost
338
338
0
0
338
338
0
0

Setup Cost Total Cost


400
738
0
1075
0
1075
0
1075
400
1813
0
2150
0
2150
0
2150

LTC
Level 2
P1X2
Item
P0110
POX
POY
P1X1
P1X2
Week
1
2
3
4
5
6
7
8

Inventory
240
500
340
500
600

Net Requirement
520
0
1500
0
1500
0
1500
0

Item
P0110
POX
POY
P1X1
PIX2

Qty
1
2
2
4
3
Tot. Req
1560
0
4500
0
4500
0
4500
0

Cost/Unit Set Up Cost


200
500
65
400
35
350
5
430
15
400

Step 3: Total Cost Calculation for LTC

Item
P0110
P0X
P0Y
P1X1
P1X2
Total Cost

Cost
3,775
1,600
1,750
1,460
2,150
10,735

4. Least Unit Cost (LUC)

Least unit cost method a dynamic lot-sizing


technique that adds ordering and inventory carrying
cost for each trial lot size and divides by the number
of units in each lot size, picking the lot size with the
lowest unit cost.

LUC

Step 1
Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

160

500

500

1-2

510

350

500

850

1-3

810

950

500

1450

1-4

1260

2300

500

2800

1-5

1560

3500

500

4000

1-6

1200

5750

500

6250

1-7

2235

7100

500

7600

1-8

2760

10775

500

11275

3.13
1.67
1.79
2.22
2.56
5.21
3.40
4.09

Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

300

500

500

3-4

750

450

500

950

3-5

1050

1050

500

1550

3-6

1500

2400

500

2900

3-7

1725

3300

500

3800

3-8

2250

5925

500

6425

1.7
1.3
1.5
1.9
2.2
2.9

Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

300

500

500

5-6

750

450

500

950

5-7

975

900

500

1400

5-8

1500

2475

500

2975

1.7
1.3
1.4
2.0

Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

225

500

500

7-8

750

525

500

1025

2.2
1.4

Step 2

Level 0
P0110

Week

Net Requirement

Prod. Qty

Ending Inv.

Holding Cost

Setup Cost

Total Cost

160

510

350

350

500

850

350

850

300

750

450

450

500

1800

450

1800

300

750

450

450

500

2750

450

2750

225

750

525

525

500

3775

525

3775

LUC

Step 1
Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

-1

-1-0

520

400

400

-1-1

1120

195

400

595

-1-2

2020

780

400

1180

-1-3

2620

1365

400

1765

-1-4

3520

2535

400

2935

-1-5

3970

3266.25

400

3666.25

-1-6

5020

5313.75

400

5713.75

0
0.77
0.53
0.58
0.67
0.83
0.92
1.14

Week
2

Quantity Ordered
900

Carrying Cost
0

Setup Cost
400

Total Cost
400

2-3

1500

195

400

595

2-4

2400

780

400

1180

2-5

2850

1218.75

400

1618.75

2-6

3900

2583.75

400

2983.75

Week
4

Quantity Ordered
900

Carrying Cost
0

Setup Cost
400

Total Cost
400

4-5

1350

146.25

400

546.25

4-6

2400

828.75

400

1228.75

Week
6

Quantity Ordered
1050

Carrying Cost
0

Setup Cost
400

Total Cost
400

Step 2

Level 1
P0X

Unit Cost

0.44
0.40
0.49
0.57
0.77

Unit Cost

0.44
0.40
0.51

Unit Cost

0.38

Week

Net Requirement

Prod. Qty

Ending Inv.

Holding Cost

Setup Cost

Total Cost

-1

180

58.5

58.5

520

1120

600

195

400

653.5

600

653.5

900

1500

600

195

400

1248.5

600

1248.5

900

1350

450

146.25

400

1794.75

450

1794.75

1050

1050

400

2194.75

Step 1

Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

-1

-1-0

680

350

350

-1-1

1280

105

350

455

-1-2

2180

420

350

770

-1-3

2780

735

350

1085

-1-4

3680

1365

350

1715

-1-5

4130

1758.75

350

2108.75

-1-6

5180

2861.25

350

3211.25

0
0.51
0.36
0.35
0.39
0.47
0.51
0.62

Week
3

Quantity Ordered
600

Carrying Cost
0

Setup Cost
350

Total Cost
350

3-4

1500

157.5

350

507.5

3-5

1950

315

350

665

3-6

3000

866.25

350

1216.25

Week
5

Quantity Ordered
450

Carrying Cost
0

Setup Cost
350

Total Cost
350

5-6

1500

183.75

350

533.75

Step 2

LUC
Level 1
P0Y

Unit Cost

0.58
0.338
0.341
0.41
Unit Cost

0.78
0.36

Week

Net Requirement

Prod. Qty

Ending Inv.

Holding Cost

Setup Cost

Total Cost

-1

20

3.5

3.5

680

2180

1500

262.5

350

616

600

900

157.5

773.5

900

773.5

600

1500

900

157.5

350

1281

900

1281

450

1500

1050

183.75

350

1814.75

1050

1814.75

LUC
Step 1
Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

-1

780

430

430

-1-0

3580

70

430

500

-1-1

5980

190

430

620

-1-2

9580

460

430

890

-1-3

11980

700

430

1130

-1-4

15580

1150

430

1580

-1-5

17380

1420

430

1850

-1-6

21580

2155

430

2585

0.55
0.14
0.10
0.093
0.094
0.10
0.11
0.12

Week
3

Quantity Ordered
2400

Carrying Cost
0

Setup Cost
430

Total Cost
430

3-4

3600

90

430

520

3-5

7800

180

430

610

3-6

11400

495

430

925

Week
6

Quantity Ordered
4200

Carrying Cost
0

Setup Cost
430

Total Cost
430

Step 2

Level 2
P1X1

Unit Cost

0.18
0.14
0.078
0.081
Unit Cost

0.10

Week

Net Requirement

Prod. Qty

Ending Inv.

Holding Cost

Setup Cost

Total Cost

-1

780

9580

8800

220

430

220

2800

6000

150

370

2400

3600

90

460

3600

460

2400

7800

5400

135

430

1025

3600

1800

45

1070

1800

1070

4200

4200

430

1500

LUC
Step 1
Week

Quantity Ordered

Carrying Cost

Setup Cost

Total Cost

Unit Cost

-1

360

400

400

-1-0

2460

157.5

400

557.5

-1-1

4260

427.5

400

827.5

-1-2

6960

1035

400

1435

-1-3

8760

1575

400

1975

-1-4

11460

2587.5

400

2987.5

-1-5

12810

3195

400

3595

-1-6

15960

4848.75

400

5248.75

1.11
0.23
0.19
0.21
0.23
0.26
0.28
0.33

Week
2

Quantity Ordered
2700

Carrying Cost
0

Setup Cost
400

Total Cost
400

2-3

4500

135

400

535

2-4

7200

540

400

940

2-5

8550

843.75

400

1243.75

2-6

11700

1788.75

400

2188.75

Week
4

Quantity Ordered
2700

Carrying Cost
0

Setup Cost
400

Total Cost
400

4-5

4050

101.25

400

501.25

4-6

7200

573.75

400

973.75

Week
6

Quantity Ordered
3150

Carrying Cost
0

Setup Cost
400

Total Cost
400

Step 2

Level 2
P1X2

Unit Cost

0.15
0.12
0.13
0.15
0.19
Unit Cost

0.15
0.12
0.14
Unit Cost

0.13

Week

Net Requirement

Prod. Qty

Ending Inv.

Holding Cost

Setup Cost

Total Cost

-1

360

4260

3900

97.5

400

97.5

2100

1800

45

142.5

1800

142.5

2700

4500

1800

45

400

587.5

1800

587.5

2700

4050

1350

33.75

400

1021.25

1350

1021.25

3150

3150

400

1421.25

Step 3: Total Cost Calculation for LUC

Item
P0110
P0X
P0Y
P1X1
P1X2
TOTAL

Cost (Rs)
3,775
2,195
1,815
1,500
1,421
10,706

Conclusion

Based on calculations, Total Cost for every lot-sizing


Method as follows
Lot-Sizing Method

Total Cost (Rs)

Lot-for-Lot (L4L)

15,060

Economic Order Quantity (EOQ)

14,296

Least Total Cost (LTC)

10,735

Least Unit Cost (LUC)

10,706

The lowest cost was obtained using the Least Unit Cost
Method of Rs10,706.
Sunita Menon should choose the Least Unit Cost Method
as Lot Sizing Strategy at A-Cat Corp.

Lesson Learned

MRP system determines detailed schedules that show exactly what


is needed over time.
MRP is most useful in industries where standard products are
made in batches from common components and parts.
The systems effectiveness depended on the inventory position and
policies, the bill of materials and the demand requirements for
finished goods and components.
Lot sizes are the production (or purchasing quantities) that are
used by the MRP system. The simplest case is when the system
schedules exactly what is needed each period (known as lot-forlot), but when there are significant cost (set up cost & carrying cost)
lot-for-lot might not be the least costly method.
The advantage of the least unit cost method is that it is more
complete analysis and would take into account ordering or setup
costs that might change as the order sizes increases.
The lowest cost from the alternatives method of Lot Sizing can be a
consideration for Lot Sizing.

References

Jacobs, F. Robert, and Richard B. Chase. Operations


and Supply Chain Management. 14th. Global Ed.
New York: McGraw-Hill Companies Inc. 2014.
Material Requirements Planning at A-Cat Corp.
2012. Richard Ivey School of Business Foundation.

Вам также может понравиться