1. SCOPE
The scope of this procedure covers the control of installation of in-situ concrete paving
surfaces including finishes to ensure compliance with the contract specifications.
2. PROCEDURE
.1All activities connected with concrete pavings will be carried out in accordance with the
contract specifications. In any circumstances where specifications are not provided or
unclear, clarification will be sought from the Consultants representative.
.2 Where necessary a method statement shall be prepared and approved by the Project
Director/Manager. It shall include:
i)
ii)
iii)
iv)
v)
Method of curing.
ii)
Curing and drying of the base concrete before the flooring is laid.
iii)
iv)
Period of protection of the completed floor from damage by other trades, including
restriction of access.
.5Special care while laying concrete finishes and wearing surfaces:
i) Where a structural concrete slab itself forms the flooring or where a topping is laid
monolithically or bonded to a hardened base, the wearing surface shall be adequately
protected against damage during subsequent building operations.
ii) In hot or drying conditions, care shall be taken that the concrete mixes do not stiffen or
dry out to an extent that prevents full compaction. After compaction and finishing, the
surface shall not be allowed to dry out quickly and this may be achieved by protection by
plastic sheeting or other suitable means. In addition where concrete is laid in the open, its
surface shall be protected from the effects of the sun and wind to limit the risk of
cracking.
iii) Compaction of concrete shall be carried out in such a way that an excess of `laitance
is not brought to the surface.
For the highest abrasion resistance, the final trowelling shall be made when considerable
pressure is required to make any impression on the surface. However, excessive
trowelling should be avoided to prevent the production of a polished or slippery finish.
Water shall not be applied between trowelling operations as this may cause surface
weakness.
iv) Curing shall be done as specified.
v) When topping is laid separately and bonded, the surface of the base shall be
thoroughly prepared as specified to ensure proper bond between the topping and the
base concrete.
SITE NO.:
Sheet
No.
SUBCONTRACTOR:
CLIENT
Checke
d
STAGE
ITEM
Date
by
PREPARATION
PE
aggregate) to specification.
CONCRETE
LAYING
GF
APPROVAL TO PROCEED.
QA/QC
GF
surface
against
adhesion
topping
between
and
GF
SE
base by tapping for hollowness.
APPROVAL TO PROCEED
QA/QC