STRUCTURE
Table of Contents
Scope/Objectives
References
Health and Safety Hazards
Responsibilities
Procedures /Method to be Employed
Manpower Requirements
Material Requirements
Equipment Requirements
Health and Safety Provisions
Q.C Approvals and other Documentation
Site Safety Engineers Approval
Coordination with the Safety Engineer to ensure that the works are carried
.out in a safe working atmosphere
Coordination with the QC Engineer for tests to be carried out and initiate for
.the inspection for the finished works
.The implementation of any request that might be raised by the Consultant
Efficient daily progress has been obtained from all the equipment and
manpower engaged in the work and check the same against the daily report
.received from the Foremen
The passage of all the revised information to the Foremen and ensure that its
.being carried out properly
Coordination with the surveyor and plan the survey works in advance as per
.the work sequence
SA 21/2 cleaned and painted with one coat - 50 microns DFT of Epoxy primer
.(Sigma 7412) at Steel Factory
Secondary Surface Preparation at Site
o Degrease the structural member surface with suitable alkali degreaser if
.necessary
.o Clean the surface by the use of fresh water jet
.o Roughen the surface with emery paper for better adhesion
.rafter pieces together and the painting crew will apply final touch up
.Erection procedure shall be as per this sequence up to completion of building
Two mobile cranes of 30T capacity each shall be engaged in lifting the
.assembled rafter pieces
SHEETING FOR ROOF 6.5
Prepare the roof panels by segregating by lengths shown on roof sheeting
.plan
.Place the first sheet (with the given dimension) for the eave overhang
Use a string line projected away (by 65mm) from the eave strut to establish
.the correct distance and line
Start at the eave and work up the roof towards the ridge from both sides of
.the building and both slopes finishing with the ridge panel
.Provide bead mastic over the panel corrugations along panel end laps
.Make sure that the panel ribs are kept in a straight line from eave to ridge
.Install gable trims after completing the roofing
Eave gutters shall be spliced using two runs of mastic and pop-rivets. The
gutter is then hung by means of gutter straps which are screwed through the roof
.panel
Down spouts connections are cut with aviation snips at locations shown on the
.roof plan
FINAL CHECKING / INSPECTION 6.6
Engineer shall ensure after erection of the structural steel members and
:accessories are checked and inspected as mentioned here below
.All bracings are in position and tightened
.All bolts are in place and high strength bolts are tightened properly
.All damaged paint is touched-upped and made good
.Check that roof and gutters are clear of debris and ferrous metals
.Check all roof penetrations for weather tightness
Engineer shall Issue Application for Inspection (AFI) for each of the above
.activities when it completed
:MANPOWER REQUIREMENTS 7.0
Foremen
Welders
Steel Painters
Helpers
Driver
:MATERIAL REQUIREMENTS 8.0
Generator
Welding Rods
Cutting Sets with gas cylinder
Steel Pipes, angles, beams and columns
Approved Paint
:EQUIPMENT REQUIREMENT 9.0
.Welding Machine 2 Nos
.Gas Cutting Set 1 No
.Maniscope 1 No
.Hand Tools L.S
Pick up 3T 1 No