Involves and cooperates with other disciplines on process requirements, design interference check
and design changes. Resolve fabrication, integration and testing interface issues and technical
queries, in conjunction with other disciplines engineers.
Managing competency database for engineers staff. Tracking performance and progress against
targets to ensure team is in place and competent to do the job. Evaluating the performance of
engineers and provide counseling and guidance to members of the project.
Worked with high-profile clients and international contractors to execute numbers of Engineering,
Procurement and Construction projects
Having good knowledge in Interface engineering between discipline in a project team, business
development and planning.
Work experience(s)
Name and address Daewoo Shipbuilding and Marine Engineering
Tempo Scan Tower 31 Floor, Jl. HR Rasuna Said Kav. 3-4 Jakarta 12950
of employer Indonesia
Date
Position held
Type of business
Project(s) execution
Project name
Date
Role
Responsibilities
Description
Project name
Develop, coordinate, and complete the interface M40 module between each group to achieve
zero defect and on time delivery target
Determines project specifications by studying product design, customer requirements, and
performance standards; completing technical studies; preparing cost estimates.
Ensure accurate and timely reporting standards are maintained throughout the project.
Monitor engineering progress against budget and forecasted schedule
Coordinate piping design and engineering effort with other area Lead Engineers and disciplines of
the project.
Prepare project estimates, budget, schedules and execution plans.
Establish the working relationship with operations management needed to facilitate the
coordination and execution of project work, such that the operational impact is minimized.
Perform other project engineering and project management related duties.
The Mariner Project is a heavy oil field development on the UK continental shelf. The concept consist
of a large PDQ platform (Process, Drilling and Living Quarter), topside weight approximately 31.000
tonne, a jacket substructure, a ship shaped Floating Storage Unit (FSU) for storage and offloading and
infield pipelines and cables. Gas for power generation and a light oil for dilution of the heavy oil will be
imported.
The Mariner oilfield is located in the United Kingdom sector of the North Sea, about 150 kilometres
(93 mi) east of the Shetland Islands, Scotland, block 9/11A. It was discovered in 1981 at a depth of
about 1,200 metres (3,900 ft) below sea level. Water depth in the area is about 100 metres (330 ft).
Estimated recovery is at least 250 million barrels (40106 m3) of oil.
Ichthys Gas Field Development - FPSO Project, Australia
Date
Role
Responsibilities
Description
Develop, coordinate, and complete the interface M04, L03, and L04 module between each group
to achieve zero defect and on time delivery target
Determines project responsibilities by identifying project phases and elements; assigning
personnel to phases and elements.
Determines project specifications by studying product design, customer requirements, and
performance standards; completing technical studies; preparing cost estimates.
Ensure accurate and timely reporting standards are maintained throughout the project.
Monitor engineering progress against budget and forecasted schedule
Coordinate piping design and engineering effort with other area Lead Engineers and disciplines of
the project.
Prepare project estimates, budget, schedules and execution plans.
Establish the working relationship with operations management needed to facilitate the
coordination and execution of project work, such that the operational impact is minimized.
Perform other project engineering and project management related duties.
Gas from the Ichthys Field will undergo preliminary processing at the offshore central processing
facility (CPF) to remove water and raw liquids, including a large proportion of the condensate. This
condensate will be pumped to a floating production, storage and offloading (FPSO) facility anchored
nearby, from which it will be transferred to tankers for delivery to markets. The gas will be transported
from the CPF through a subsea pipeline more than 885 kilometers to the onshore LNG processing
plant proposed for Blaydin Point on Middle Arm Peninsula, Darwin, Northern Territory.
The FPSO function is to act as an offshore production facilities that house both processing equipment
and storage for produced hydrocarbons. It has processing equipment or topsides, aboard the vessel's
deck and hydrocarbon storage below in the double hull. After processing, the FPSO stores
oil/condensate before offloading periodically to a shuttle tanker which transports the product to a
refinery.
Project(s) execution
Project name
Date
Role
Responsibilities
Description
The scope is research on potential application use for LNG distribution and gas demand in South East
Asia espesially in Indonesia, and also preparation for prepare design of LNG mini plant in Gresik
Surabaya for supply gas in central java.
Name and address Pondok Pinang Center Block A8-12 Ciputat Raya Street South Jakarta
of employer
Date
Position held
Type of business
Projects execution
Project name
Date
Role
Description
Semarang Terminal LPG is one of three terminal facility that planning will be build on 2007 by
Pertamina Persero. Indonesia government plan to switch Karesol to LPG to decrease subsidy of fuel.
For easy distribution of LPG, Pertamina plan to make interconection between Terminal LPG and
SPPBG/SPBG.
Responsibilities
Ensure that project management plan, project start up check list and standard operating
procedure are complied with
Take particular responsibility to ensure that Company policy for quality, safety, and environment
is adhered to
Monitoring for installation equipment : LPG pump, Fire pump, Gas Compressor, Marine Loading
Arm, etc.
Control and monitor the progress and performance of all functional areas of the Project Team as
per design.
Collect, review and coordinate all engineering division document such as Specification,
calculation sheet, data sheet, drawing and technical review
Commisioning all process and equipment on Terminal LPG Semarang
Formal education
Name of University
Date
Qualification Awarded
Field Study
Name of University
Date
Qualification Awarded
Field Study
Profesional training
Date
Name and type of organisation
providing education and training
Principal subjects /
occupational skills covered
2010 2014
DSME In House Training
Personal skills
and competences
Mother tongue
Other language(s)
Self-assessment
Bahasa Indonesia
English
Understanding
Speaking
Writing
Listening
Reading
Spoken interaction
Spoken production
English
Excellent
Excellent
Excellent
Excellent
Excellent
Computer skills
and competences
Personality Traits
Effective communication skills both verbally and in writing with superiors, colleagues, and
individuals inside and outside the company
Have potential to adjust to any work environment independently, and can also handle my
assignment confidently
Ability to work in a team environment
Creative, quick learner and result oriented
Effective analytical and problem-solving skills
AVEVA Marine
Reviewing Software: Navisworks Simulate
AutoCAD 2D.
MS Office: MS Word, MS Excel, MS Power Point and MS Outlook
Ms Project
Year
Client
Project Name
Project
Location
Project
Type
Project Scope
Project Role
April 2014
to date
Statoil, Norway
United Kingdom
Offshore
Detailed Engineering
Sept 2013
to date
INPEX Operations
Australia Pty., Ltd.
Australia
FPSO
Detailed Engineering
Jan 2011
Dec 2012
Gresik (Indonesia)
Onshore
Research Engineering
Detailed Engineering,
Semarang
(Indonesia)
Onshore
Detailed Engineering+
Procurement+
Construction
April 2008
Dec 2010
PT. Pertamina